Project Charter - KMP
Project Charter - KMP
1
EXECUTIVE SUMMARY
For the past several Tata Power relied on external trainers and facilitators to
train their employees which increased its cost and dependency on the
availability of employees for the class rooms sessions. Now, the project KMP
aims to develop a knowledge management portal which integrates the
information & processes and will be an enabler of knowledge management in
the organization. The benefits expected from the project are improvement in
coordination & accountability, facilitating timely feedback & approval,
identifying the training needs.
PROJECT PURPOSE
Business Need
Business Objectives
The Business objectives for this project are in direct support of Tata
Power’s goals to improve coordination and collaboration among
employees in sharing knowledge through the online portal.
- Complete Design and development of the Tata Power- Virtual
University Internal Portal that strive to improve organizational
performance.
- Custom Validation of the software including Unit Testing, Integration
Testing, System Testing and UAT Testing.
- Implementation of the software developed at the client’s site.
2
PROJECT DESCRIPTION
Project Objectives
The KMP project will provide a fully developed Virtual University Software
for the online training and development of Tata Power employees. It will
include e-learning modules, tutorials, online forums and the online
assignments will be assessed, evaluated and e-certificates will be
provided to the employees. The main highlights of the project are as
follows:
Cost Effectiveness
The web-based instruction is viewed as cost effective for the
Company since the
information can be accessed at any time from any location.
The objectives which mutually support the milestones and deliverables for this project have
been identified. In order to achieve success on the KMP project, the following objectives
must be met within the designated time and budget allocations:
3
- Gathering the requirements of the client i.e. Tata Power and it freeze within the next 10
days.
- Work out the Detailed Design of the application to be developed including the prototypes
in 15 days.
- Develop the software in two phases with Unit as well as Integration Testing of the two
releases in 2 months.
- Validate the Software developed through system testing and User Acceptance Testing in
a time frame of 25 days.
- Implement the solution across Tata Power within 10 days of UAT testing completion
phase.
Constraints
Assumptions
4
The KMP project will include the design, testing, and implementation of an
online intranet KM portal throughout Tata Power for its employees. All
personnel, hardware and software resources will be managed by the
project team. All project work will be independent of daily and ongoing
operations. All project funding will be managed by the project manager
up to and including the allocated amounts in this document. Any
additional funding requires approval from the project sponsor. This
project will conclude when the final report is submitted within 30 days
after the Portal application is fully tested and deployed throughout the
organization, all technical documentation is complete and project closure
report is submitted.
RISKS
The following risks for the KMP project have been identified.
- Due to the time boxed approach for the development, it might not be
possible to accommodate any change requests without impacting the
project delivery timelines
- A failure in deployment can have severe financial repercussions for the
organization
- External threats breaching intranet security via new methods
In addition to the above risks, to deliver on the proposed dates, Pinnacle expects the following
commitments from Tata Power:
• Provide application design sign-off (for the scope considered for this proposal) before the
beginning of the project start. This can be approved by Tata Power PM.
• Ensure availability of Subject Matter Experts’ availability to review Component Designs
& Unit Test Plans.
• Ensure availability of Tata Power system analysts to provide timely inputs, issue
resolutions/clarifications & review comments during the entire period of offshore
development.
• Provide review comments on deliverables as planned.
• Tata Power PM to participate in weekly teleconferences with Pinnacle team to provide
issue resolutions/clarifications.
PROJECT DELIVERABLES
The following deliverables must be met during the project cycle of KMP. Any
changes to these deliverables must be approved by the project sponsor.
- Project Charter
5
- Statement of Work
- Training and Induction Plan
- Requirement Specification Document
- Requirement Traceability Matrix
- Detailed Design Plan
- Test Strategy Document
- Test Scenario/Case Document
- Defect Reports
- Status Reports
- Milestone Reports
- Configuration Management Plan
- Project Closure Report
SUMMARY BUDGET
The summary budget should contain general cost components and their
planned costs. As the project moves forward these costs may change as all
tasks and requirements become clearer. Any changes must be
communicated by the project manager.
6
The following table contains a summary budget based on the planned cost
components and estimated costs required for successful completion of the
project.
• Hardware $45,000
Total $245,000
Success for the KMP project will be achieved when a fully tested Tata Power
Virtual University Portal, and all technical documentation, is fully deployed
throughout the company within the time and cost constraints indicated in
this charter. Success will be determined by the Project Sponsor, Mr. Ranbir
Chakraborty, who will also authorize completion of the project.
PROJECT MANAGER
This section explicitly states who is assigned as the PM, their responsibility,
and authority level. Depending on the organization and scope of the project,
the project manager may have varying levels of responsibility and authority
for personnel, project expenditures, and scheduling.
John Doe is named Project Manager for the duration of the ISA Project. Mr.
Doe’s responsibility is to manage all project tasks, scheduling, and
communication regarding the ISA project. His team, consisting of two IT
specialists and one security specialist will be matrix support from the IT
department. Mr. Doe will coordinate all resource requirements through the
IT department manager, Jane Snow. Mr. Doe is authorized to approve all
budget expenditures up to, and including, the allocated budget amounts.
Any additional funding must be requested through the Project Sponsor, Jim
Thomas. Mr. Doe will provide weekly updates to the Project Sponsor.
7
AUTHORIZATION
___________________________________________ Date:___________________
Mr. Ranbir Chakrabarty
<Project Sponsor Title>