Ramagondanahalli CC Drain 5.00lakhs
Ramagondanahalli CC Drain 5.00lakhs
ESTIMATE
ಕಾಮಗಾರಿಯ ಹೆಸರು
ESTIMATED COST
Rs.5,00,000 -00
(Rupees Five Lakhs Only)
ESTIMATE
ESTIM
KARNATAKA RURAL INFRASTRUCTURE DEVELOPMENT LIMITED, MAYAKONDA , SUB -
DIVISION
GENERAL REPORT
Name of Work :
The Work of ದಾವಣಗೆರೆ ತಾಲ್ಲೂಕು ರಾಮಗೊಂಡನಹಳ್ಳಿ ಗ್ರಾಮದ ಕೆ.ಎಂ. ಶಿವರಾಜಪ್ಪನ ಮನೆಯಿಂದ ನೀರಿನ ಟ್ಯಾಂಕ್ ವರೆಗೆ ಸಿ.ಸಿ.ಚರಂಡಿ
ನಿರ್ಮಾಣ . has been entrusted to Karnataka Rural Infrastructure Development Limited
Vide Letter No.
Accordingly the plans and estimate prepared on the actual condition of work site & Rates Consider on the Basis
of the PWD CSR 2018-19 Shivamoga circle . The Following Provision are made in the estimate
Name of Work :
DETAILED ESTIMATE
Sl.
No. Items No L B D Qty Rate Amount Unit
RCC DRAIN
1 KSRRB 300-1. Earthwork excavation by manual means in Hard soil involving an average horizontal throw upto
2 meters and an average lift upto 0.5 m, excavated surface leveled and sides neatly dressed, the disposed earth to
be leveled neatly after breaking of clods complete as per specifications.( P.No.143, I.No.19.2)
2 KSRRB M2900-1 , Plain Cement Concrete M10 mix with Crushed Stone aggregate 40mm Nominal Size
Mechanically Mixed, Placed in Foundation & Compacted by Vibration including curing and cost of all
materials,labour,HOM Complete as per Specification(P.No.254, I.No-34.1)
3 Providing & Laying Plain / Reinforced Cement Concrete for Side Drains using M20 nominal Mix Concrete
with OPC cement at 300 Kgs.With 20mm & down Size granite Metal Course aggregetes at0.69 cum & fine
aggeregates at 0.43cum machine mixed ,well compacted for walls & bottom including centering , shuttering cost
of materials , HOM of machinery , curing etc., complete excluding cost of steel per MORTH specification NO
1550 , 1700, 2200(P.No.271, I.No-37.59.2)
RCC Drain
Side Walls 2 141.00 0.15 0.90 38.07
Bottom 1 141.00 1.52 0.15 32.15
Sl.
No. Items No L B D Qty Rate Amount Unit
12 KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of design mix M20 with OPC cement @ 320kgs,
with 20mm and down size graded granite metal coarse aggregates @0.878cum and fine aggregtes @ 0.459cum, with superplastisiser
@3lts confirming to IS9103-1999 Reaffirmed-2008, machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all
works in foundation plinth and ground floor level for roof slabs, staircase, lintles, retaining walls, return walls, walls ( any thickness )
including attached plasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed
blocks, anchor blocks, plain window cills, fillets etc., including cost of all materials, labour, HOM of machinery, curing, complete as
per specifications (P No. 13, Item No 4.11)
8 KKSRB 4-6.10 :Providing and removing centering, shuttering, strutting, propping etc., for and removal of form
work for flat surface such as suspended floors roofs landings balconies and likes thickness above 200 mm
including cost of all materials, labour complete as per specificaiton. Specification No. KBS 4.6.2 [ Page No. 16,
Item No. 4.30 ]
4 KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending,
hooking, placing in position, lapping and / or welding wherever required, tying with binding wire and
anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall
not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications (P.No.18,
I.No-4.46.2)
5 KSRB 2.3 : Filling available excavated earth ( excluding rock ) in sides of foundations upto plinth in layers not
exceeding 20 cms. in depth, compacting each deposited layer by ramming after watering with lead upto 50 m.
and lift upto 1.5 m. including cost of all labour complete as per specifications.(P.No.7, I.No-2.10)
TOTAL 3246065.00
Add 3% KRIDL Charges 97382.00
Sub-total-1 3343447.00
Add 1% for labour cess 33434.00
Sub-total-2 3376881.00
Add 12% GST 405226.00
Sub-total-3 3782107.00
Misc. and rounding off 7893.00
Total Estimated cost 3790000.00
2 Compaction of original ground by mechanical means 147 19.64 6.30 0.00 0.00 0.00 6.30 0.00 0.00 0.00 6.30 0.00 6.30 Sqm
6 P/L Un Reinforced PCC Pavement-M30 176 22.6.1 5366.00 7.20 1800.00 0.00 3566.00 7.20 2033.28 0.00 5599.28 0.00 5599.28 Cum
7 EWE in Ordinary Soil 143 19.2 179.00 0.00 0.00 0.00 179.00 0.00 0.00 0.00 179.00 0.00 179.00 Cum
8 P/L PCC M10 for RCC Drain 254 34.01 4635.00 4.40 1100.00 0.00 3535.00 4.40 1242.56 0.00 4777.56 0.00 4777.56 Cum
9 P/L RCC M20 for RCC Drain-For Wall Thickness 15cm 271 37.59.2 7474.00 6.00 1500.00 0.00 5974.00 6.00 1694.40 0.00 7668.40 0.00 7668.40 Cum
11 Providing and removing centering, shuttering, for deck slab. 16 4.3 440.00 0.00 0.00 0.00 440.00 0.00 0.00 0.00 440.00 0.00 440.00 Sqm
13 Cost of steel & fabrication charges(Fe 500) 18 4.46.2 6936.50 0.00 0.00 4491.53 2444.98 0.00 0.00 5356.82 7801.79 0.00 7801.79 Qtl
14 New Earth Filling 7 2.1 201.00 0.00 0.00 0.00 201.00 0.00 0.00 0.00 201.00 0.00 201.00 Cum
15 Providing and fixing name board 271 37.6 5500.00 0.00 0.00 0.00 5500.00 0.00 0.00 0.00 5500.00 0.00 5500.00 Each