Detailed Estimates: Construction of 1-Unit Multipurpose Building Brgy. San Jose, Borbon, Cebu
Detailed Estimates: Construction of 1-Unit Multipurpose Building Brgy. San Jose, Borbon, Cebu
DETAILED ESTIMATES
Materials
Reinforcing Steel Bars ( 4,920.00) kgs
# 16 G.I. Tie Wire ( 50.00) kgs
Hacksaw Blade ( 20.00) pcs
Sub-Total
Labor (80 kgs / day)
Carpenter/Steel man ( 16.00) day/s
Laborer ( 16.00) day/s
Sub-Total
STIMATES
RATE PER
No. of
DAY/ TOTAL
Crew/Unit
UNIT COST
Materials
12- 2'' x 4'' x 2mm THK C-PURLINS ( 16.00) pcs
12 mm sag rod ( 5.00) pcs
Welding Rod ( 40.00) kgs
1 1/2 x 1 1/2 x 1/4 thk angle bar ( 18.00) lengths
Sub-Total
Labor
Welder ( 6.00) day/s
Laborer ( 6.00) day/s
( 223,396.80)
( 22,339.68)
( 15,637.78)
( 22,339.68)
( 283,713.94)
57.67
20,000.00 20,000.00
( 20,000.00)
Materials
Materials
Pail Flush Type Toilet Bowl ( 1.00) sets
Wall hung lavatory with faucet and supply pipe
( 1.00) sets
4" x 4" PVC Floor Drain ( 2.00) sets
4" x 3.0m dia. PVC Pipe ( 10.00) lgth
3" x 3.0m dia. PVC Pipe ( 4.00) lgth
2" x 3.0m dia. PVC Pipe ( 6.00) lgth
2" dia. X 90° PVC Bend Elbow ( 6.00) pcs
4" dia. X 90° PVC Bend Elbow ( 4.00) pcs
4" dia. X 45° PVC Bend Elbow ( 4.00) pcs
2" dia. PVC P-Trap ( 2.00) pcs
4" dia. PVC Clean Out Plug ( 1.00) pcs
4" dia. x 4" dia. PVC Wye ( 2.00) pcs
3' dia. X 90° PVC elbow ( 4.00) pcs
Solvent Cement ( 1.00) pnt
1/2" x 3.0m HDPE pipe ( 10.00) lgth
1/2" dia. Gate valve ( 1.00) pcs
1/2" Coupling ( 1.00) pcs
1/2" x 90° Bend elbow ( 4.00) pcs
1/2" Tee ( 2.00) pcs
1/2" Female threaded adaptor ( 2.00) pcs
1/2" Faucet, hose bib, brass ( 2.00) pcs
Teflon Tape ( 3.00) rolls
Sub-Total
( 14,815.00)
( 10,370.50)
( 14,815.00)
( 188,150.50)
3,763.01
Materials
8" x 8" Glazed Tiles ( 230.00) Pcs.
8" x 8" Unglazed Tiles ( 70.00) Pcs.
Cement ( 3.00) bags
White cement / Tile Grout ( 3.00) kls.
Tile Trim ( 5.00) Pcs.
Sub-Total
Labor
Mason ( 3.00) Day/s
Laborer ( 3.00) Day/s
Sub-Total
Total Direct Cost
Indirect Cost(10% DC)
Tax(7% of DC)
Contractors profit(10% of DC)
TOTAL FOR TILEWORKS
Total Unit Cost
A. Materials
2" x 4" Utility Boxes Pvc ( 20.00) pcs
4" x 4" Junction Boxes PVC ( 12.00) pcs
3/4" dia. RSC Pipe ( 2.00) lgth
Screw Insulator ( 2.00) pc
3.5mm2 THW Stranded Wire ( 3.00) box
Service Drop Wire ( 80.00) m
PVC Clamp ( 15.00) pcs
Flexible tube 3/4" dia ( 100.00) m
Electrical Tape (Big) ( 5.00) pcs
600 mm T5, RECESSED TYPE BOX ( 9.00) set
CFL, DAYLIGHT PINLIGHT 6'' DIA. WHITE CASING ( 15.00) set
2 Gang Switch with Plate ( 5.00) pcs
Female Adaptor ( 5.00) pcs
KWHR meter w/Base ( 1.00) unit
Entrance Cap # 1" dia. ( 1.00) pcs
Safety Switch ( 1.00) set
Sub-Total
B. Labor
Electrician ( 4.00) day/s
Laborer ( 4.00) day/s
Sub-Total
Total Direct Cost
3.00 ( 350.00) ( 6,300.00)
3.00 ( 275.00) ( 4,950.00)
( 11,250.00)
( 28,090.00)
( 2,809.00)
( 1,966.30)
( 2,809.00)
( 35,674.30)
35,674.30
Materials
Boulders 6-8" diameter ( 3.00) cu.m
Portland Cement (Type 1) ( 10.00) bags
Washed Sand (Approved Source) ( 3.00) cu.m
2" diameter pvc pipe ( 1.00) length
Sub-Total
Labor
Ripraper ( 2.00) Day/s
Laborer ( 2.00) Day/s
Sub-Total
Total Direct Cost
Indirect Cost(10% DC)
Tax(7% of DC)
Contractors profit(10% of DC)
TOTAL FOR TILEWORKS
Total Unit Cost
TOTAL COST
( 2,501.50)
( 1,751.05)
( 2,501.50)
( 31,769.05)
31,769.05
20,000.00 20,000.00
( 20,000.00)