800 Change Control: Project Control System Manual
800 Change Control: Project Control System Manual
800
Change Control
- 71 -
Project Control System Manual
A. The Change Control process allows the project team to identify, evaluate,
approve, and document proposed changes to the project baseline. The process
- 72 -
Project Control System Manual
A. The Change Control process begins with the generation of a Change Request
form (Exhibit 25). Any project team member can initiate a change to the
project technical, schedule, and cost baselines by completing the Change
Request form in electronic format. (Project changes as a result of customer
direction, such as a change in funding levels or project scope, are called
directed changes. These directed changes will be initiated by the Project
Manager and approved by the Project Customer before implementation). The
originator fills out the Identification, and Description and Justification,
sections of the Change Request. The impacts of not approving the change are
also included in this section. The Change Request is then submitted to a
member of the project Change Control Board (normally the one most
affected) for consideration. Upon concurrence, the Change Control Board
member signs the Change Request and assigns an appropriate person(s) to
ensure the Change Impact Assessment is accomplished. The Change Impact
Assessment section records the potential impacts of the proposed change to
the project baseline and addresses safety/quality concerns. The assessment is
to be all-inclusive and thorough to ensure the consequences of implementing
(or not implementing) the proposed change are fully understood.
- 73 -
Project Control System Manual
B. After the Change Control Board member has concurred with the Change
Request, PM&IP enters the Change Request into the Change Request Log
(Exhibit 26). Change Requests are numbered sequentially (scheme: FY -
sequence #, e.g., 08-001) in order of receipt for tracking purposes. The
Change Request Log is updated each time there is a change to the status of a
Change Request. When the status of a Change Request is updated, PM&IP
will notify all Associate Project Managers and Control Account Managers
connected with that WBS level and send a notice to each member of the
project Change Control Board for informational purposes only. The affected
Control Account Manager will coordinate inputs to the Change Request form
and, if appropriate, draft a revised Control Account Plan reflecting impacts
due to the proposed change.
B. Class 1-2 Change Request: This classification of Change Request requires the
approval of the Project Customer. The Change Control Board evaluates the
Change Request and provides a recommendation to the Project Manager. The
Project Manager reviews the Change Request before forwarding to the
customer for approval which may include a Baseline Change Control Board
review. After receiving the customer approval, the Project Manager reviews
the action directed by the customer. PM&IP updates the Change Request Log
and the Change Request process enters into the Documentation Phase.
- 74 -
Project Control System Manual
F. During the review process, any disapproved Change Request is sent back to
the affected Control Account Manager who will consult with the originator to
determine any further action.
A. The Documentation Phase is where the project baseline is revised and the
approved change is implemented. Once the Change Request documents have
been signed by the proper level of authority, the Change Request becomes a
Change Order. For changes to the project’s technical design or scope, the
Associate Project Manager is responsible for ensuring the relevant technical
documentation is revised to reflect the change. PM&IP is responsible for
revising cost/schedule baseline documents for changes impacting these project
baselines. When appropriate, a new project baseline will be generated for
each approved Change Request. This action will improve traceability
between the Change Request and the Schedule and Cost Management
Systems.
B. Once the baseline documents are revised, PM&IP updates the Change Request
Log and the appropriate Control Account Manager(s) implements the Change
Order within his/her work scope. PM&IP also produces the Change Request
Summary Report (Exhibit 28).
802 Exhibits
- 75 -
Project Control System Manual
- 76 -
Project Control System Manual
- 77 -
Project Control System Manual
- 78 -
Project Control System Manual
- 79 -
Project Control System Manual
(Note: Use the Continuation Page on last page of the Change Request form if more space
is required. Label with section reference for any input to this page.)
Change Request #: This number will be filled in by PM&IP. The forms will be
numbered consecutively as they are received and will be entered into the Change Request
Log.
Date: Originator enters the date for the submission of the Change Request.
Date Required: Originator enters the estimated date approval is needed to avoid adverse
impacts on technical performance, schedule, cost or quality/safety.
Vendor Name: If the item has been purchased, or a subcontract issued, enter the
vendor's name(s) here.
Purchase Order #: If a purchase order(s) has been issued for the item, enter the
number(s) here.
Change Request Status: This field in the form lists the current status of the Change
Request: New / Open / Deferred / Duplicate / Approved / Disapproved / Withdrawn.
PM&IP will update the status of the Change Request as it progresses through the
procedure.
Description of Proposed Change: Describe the change requested. Use the continuation
page, as required.
- 80 -
Project Control System Manual
Justification for Proposed Change: Justify the proposed change. Describe the problem
or defect that will be corrected by the proposed change. Indicate the experience that
dictates the need for the change. Summarize the capability to make the change. Include
the impact if the change is not approved. Use the continuation page, as required.
Change Control Board Member Concurrence: The Change Control Board member
who concurs with the proposed change signs this block. Note: A Change Control Board
member may not concur on a Change Request originated by him/herself.
Impact Assessment Assigned To: The individual assigned to coordinate inputs to the
Change Impact Assessment section of the Change Request is identified in this block.
Name(s): Add the names of individual(s) who contributed and concurred to the pertinent
assessment section.
Classification Level: The Classification field in the Change Request form is a drop-
down list. Select Class 1, 2, 3, 4, or 5. The Control Account Manager, Associate Project
Manager, and PM&IP sign in the appropriate block.
Change Control Board Review: Names of the board members in attendance are
inserted in this block after review and recommendation by the board.
Final Approval: Based on the Change Request classification, the project customer or
appropriate project member will sign in the designated signature block.
- 81 -
as of: 1 Oct 09
FY10 Change Request Log
12 GeV Upgrade
CR Date Date CCB Contingency Mngmt Reserve Impact Approval Implementation
CR # Class WBS # Title Submitted Required Originator Concur (Burd. CY$K) (Burd. CY$K) Assessment Status Date Cost Sheet Cost Mgt P6
- 82 -
Exhibit 26. Change Request Log
Project Control System Manual
Project Control System Manual
- 83 -
Project Control System Manual
- 84 -