Losses Reduction and Voltage Profile Improvement
Losses Reduction and Voltage Profile Improvement
PRESENTED
BY
AWAB ELWASILA
MOHAMMED MAHDI
AZZAM OMER
I
ACKNOWLEDGEMENT
At first our sincere appreciation goes to the different faculties and entire staff of
RECIPMT for the worthy knowledge they have shared with us in this six week’s
program. Special thanks to catering and cleaning staff whose continual support keeps
us healthy to participate wholeheartedly into the course as well.
The program coordinator, Aparup Paul, course director and the government of
“Republic of India” for the great endeavor and encouragement they are providing in
enlightening the developing states.
Finally, expressing gratitude to all the participants from different regions and
countries of the world who made accompany and sharing to me for their vast
experience and also helping me during writing my project.
I
ABSTRACT
Power losses in electrical system referred to the difference between the magnitude
of power generated and power consumed. Energy losses occur in the process of
supplying electricity to consumers due to technical and commercial losses. The
technical losses are due to energy dissipated in the conductors and equipment used
for transmission, transformation, sub transmission and distribution of power.
II
LIST OF ABBREVIATION
IT - Information Technology
III
TABLE OF CONTENTS
Table of Contents
ACKNOWLEDGEMENT ......................................................................................................................... I
ABSTRACT...................................................................................................................................................... II
LIST OF ABBREVIATION ................................................................................................................................ III
TABLE OF CONTENTS.................................................................................................................................... IV
CHAPTER ONE ............................................................................................................................................... 1
Introduction .................................................................................................................................................. 1
1.1 Overview ................................................................................................................................................. 1
1.2 Objectives................................................................................................................................................ 1
1.3 Problem statement ................................................................................................................................. 1
1.4 Motivation............................................................................................................................................... 2
1.5 Report layout .......................................................................................................................................... 2
CHAPTER TWO .............................................................................................................................................. 3
2.1 Introduction ............................................................................................................................................ 3
2.3 Type of losses .......................................................................................................................................... 3
2.3.1 Technical Losses ................................................................................................................................... 3
2.3.1.1 Reasons of high technical losses ....................................................................................................... 4
2.3.1.2 measurement of technical losses ..................................................................................................... 5
2.3.1.3 Measures for Reducing Technical Losses .......................................................................................... 5
1-Short Term Measures ................................................................................................................................ 5
2- Long Term Measures ................................................................................................................................ 6
2.3.2 Non-technical losses ............................................................................................................................ 7
2.3.2.1 Reasons of non-technical losses ....................................................................................................... 7
2.3.2.2 Measurement of non-technical losses .............................................................................................. 8
1-Estimation .................................................................................................................................................. 8
2- Monitoring ................................................................................................................................................ 8
3- Detection .................................................................................................................................................. 8
4- Recovery ................................................................................................................................................... 9
2.3.2.3 measures of reduction of non-technical method ............................................................................. 9
CHAPTER 3 .................................................................................................................................................. 10
A CASE STUDY ............................................................................................................................................. 10
3.1 Load Flow Using Electrical Transient Analyzer Program (ETAP) ........................................................... 10
3.2 Current Network Configuration: ........................................................................................................... 11
3.4 Proposed Scenario: ............................................................................................................................... 15
IV
CHAPTER FOUR ........................................................................................................................................... 20
4.1 Conclusion ............................................................................................................................................. 20
4.2 recommendations ................................................................................................................................. 21
REFRENCES .................................................................................................................................................. 22
V
CHAPTER ONE
Introduction
1.1 Overview
Nowadays Electricity became the most vital energy using in the whole world
since it considered as a clean source of energy that won’t affect on environment and
all current applications and devices depend on it. But losses in electrical supply
according to generation, transmission and distribution represented a vital problem
facing electrical utilities and cause damages to its infrastructures. These losses
studied in order to find efficient methods to fight it and provide acceptable
percentage of losses.
1.2 Objectives
The objective of this project is to define the main sources of electrical distribution
losses especially in Sudan. And to find out proper solutions to reduce or eliminate
these losses and provide electricity in the most sufficient way. Also, this project
come to shed light on some experiments carried out by the Sudanese company for
the distribution of electricity as seminars for lost cases, both technical and non-
technical so you can access a unified vision of how to reduce the loss.
Particular part of the network (case study) suffers from poor voltage regulation,
overloading and undesirable power losses.
1
1.4 Motivation
Interest in maintaining the electric power and reduce the loss of the most important
goals of the distribution company all over the world. So, distribution company
operate on the optimal use of electrical energy distribution and control of losses to
increase the stability of networks and technical competence and financial resources.
Chapter 1 (Introduction): it gives a review about power losses and their effect on
distribution power system as well as review of the case study and motivation of our
project.
Chapter 3 (Foreword to ETAP & Technical losses case study): gives a brief
foreword to load flow using Electrical Transient Analyzer Program (ETAP)
software, its mainly concepts and features, and a case study of technical losses using
an unhealthy part of Sudan network as a model.
Chapter 4 (conclusions and future work): this chapter contains conclusions of the
knowledge gained by the project and recommended works to reduce technical
distribution losses in case study area.
2
CHAPTER TWO
2.1 Introduction
Electric power losses are wasteful energy caused by external factors or internal
factors, and energy dissipated in the system. They include losses due to resistance,
atmospheric conditions, theft, miscalculations, etc. and losses incurred between
sources of supply to load center (or consumers). Loss minimization and
quantification is very vital in all human Endeavors. In power system, it can lead to
more economic operation of the system. If we know how the losses occur, we can
take steps to limit and minimize the losses. Consequently, this will lead to effective
and efficient operation of the system. Therefore, the existing power generation and
transmission can be effectively used without having the need to build new
installations and at the same time save cost of losses.
Basically, losses in electrical power system can be identified as those losses caused
by internal factors known as technical losses and those cause by external factors are
called non-technical losses [3].
3
P loss = P source − P load
Where P source means the average power that the source is injecting into the
distribution line and P load is the power consumed by the load at the other end of
the distribution line. There are many sources of technical losses in distribution
system:
i. Overloaded transformers
ii. Cables undersized
iii. MT distribution lines too long
iv. Unbalanced network
v. Uncompensated reactive energy
vi. Connection of some great customer in low voltage
vii. Bad joints
4
2.3.1.2 measurement of technical losses
Losses in electrical system can be determined in different ways. Electric technical
losses occur as current flows through resistive materials and the magnetizing energy
in the line’s transformers and motors. However, the losses incurred in resistance
materials can be reduced by
i. the current
ii. Reducing the resistance and the impedance
iii. Maximizing voltages
5
iii. Reducing the length of LT lines by relocation of distribution sub
stations/ Installations of additional distribution transformers (DTs).
iv. Installation of lower capacity distribution transformers at each
consumer premises instead of cluster formation and substitution of DTs
with those having lower no load losses such as amorphous core
transformers.
v. Installation of shunt capacitors for improvement of power factor.
6
2.3.2 Non-technical losses
Non-technical losses are caused by actions external to the power system, or are
caused by loads and conditions that the technical losses computation failed to take
into account. NTL are more difficult to measure because these losses are often
unaccounted for by the system operators and thus have no recorded information. The
most probable causes of NTL are
7
2.3.2.2 Measurement of non-technical losses
1-Estimation
All utilities measures (top-down losses) as the difference between purchased
energy and energy sold. All estimates of non-technical losses are based on the
accuracy of the calculation of technical losses (assuming that administrative losses
are accurately known) subtracted from an estimate of total system losses. Some
utilities measure energy sent out at intermediate points in the distribution network,
e.g. at 33kV and 11kV substations and / or distribution feeders, and reconcile the
energy against consumption recorded by electricity meters that are downstream from
the meter location. The most common practice is to install metering at large
substations on the high or medium voltage side.
2- Monitoring
Monitoring is undertaken through summation reconciliation of Grid metering,
communal metering and metering at customer’s premises. Check or temporary
metering is used to detect electricity pilferage. Another important source of
monitoring data comes from the billing and collection system. However, it is not
generally reported by utilities that low consumption or sudden reductions in
consumption provide reliable indications of electricity pilferage. Utilities monitor
meter advances and meter readers are used to report obvious signs of occupancy and
/ or electricity use in premises that have been disconnected.
3- Detection
It is common to find that dedicated employees are deployed in order to check large
user metering and metering installations on a random but regular basis whenever
electricity pilferage is having a significant impact on revenue.
8
Meter reading staff may also be trained to detect the most obvious cases of meter
tampering and illegal connections, but this is not observed as a best practice or even
a widespread practice.
4- Recovery
Recovery involves the customer paying for stolen electricity along with a fine
commensurate with the amount of electricity stolen (as discussed under deterrence).
It is also generally seen that a utility is able to recover the full costs of repairing
meters, wiring, etc. The energy is estimated based on the customer’s end use profile
and the period of time over which it is believed that the energy has been stolen. The
time period is usually determined from the historical billing pattern.
2-administrative measures
i. Staff counseling
ii. Law & order
iii. Police and judiciary (special courts)
iv. Political support/ will
9
CHAPTER 3
A CASE STUDY
3.1 Load Flow Using Electrical Transient Analyzer Program
(ETAP)
ETAP Load Flow software performs power flow analysis and voltage drop
calculations with accurate and reliable results. Built-in features like automatic
equipment evaluation, alerts and warnings summary, load flow result analyzer, and
intelligent graphics make it the most efficient electrical power flow analysis tool
available today.
ETAP load flow calculation program calculates bus voltages, branch power factors,
currents, and power flows throughout the electrical system. ETAP allows for swing,
voltage regulated, and unregulated power sources with unlimited power grids and
generator connections. This load flow calculation software is capable of performing
analysis on both radial and loop systems. ETAP allows to select from several
different load flow calculation methods in order to achieve the most efficient and
accurate results.
10
The test results prove that the adaptive load flow method can improve the
convergence for distribution and transmission systems with significant series
capacitance effects (i.e. negative series reactance). It is also considered to possibly
improve convergence for systems with very small impedance values, but that is not
guaranteed.
One side effect of using this method is reduced calculation speed because of the
incremental steps in the solution
11
Network components Map
After running the simulation for the existing network using ETAP we can
realize the voltage drop at many points as follow:
- KAM S/S voltage drops due to very low voltage received from HAS S/S (33
KV Feeder).
12
- ALT S/S 33 KV Feeder from BAG S/S is overloaded and the losses are not
desirable.
13
The tables below show simulation results for current scenario
14
3.4 Proposed Scenario:
A proposed scenario has been summarized into the following steps:
- Installation of a new 33 KV Line as a second feeder for ALT S/S and also to
carry the loads from ALT-KAM 33 KV Line.
- Installation of 3 Mvar Capacitor at 11 KV side in ALT S/S.
- Installation of 1 Mvar – 33 KV Capacitor at BASH.
- Installation of 1 Mvar – 33 KV Capacitor at BUS 85.
- The maintenance and reoperation of KAM Substation capacitors – 2*4.5 Mvar
at 11 KV side.
15
16
17
After implementing the above mentioned (possible) solutions, new network
configuration was constructed and thus, simulated using ETAP software under
different working conditions, giving the following results:
Voltage Profile:
FARM 31 93.95
SHGAG 30.31 91.85
GAL 30.41 92.15
KAM-ALT LINE
MAK 30.31 91.84
18
Energy Savings:
ENERGY SAVING
DETAILS MW MILLION
SDG
CURRENT PROPOSED SAVING/HOUR SAVING/YEAR
SCENARIO SCENARIO
LOSSES LOSSES
VALUES 3.362 1.376 1.986 10.612
19
CHAPTER FOUR
4.1 Conclusion
After the completion of this project, an integrated idea about electrical losses in
energy, and reduction methods. In essence, the project objectives stated in project
i. The mainly causes of power losses in power system was well defined and
system.
iii. Real case simulated using ETAP to calculate technical losses. And the
v. The value of saved energy was obtained and the recovery period of the
20
4.2 recommendations
After implementation of above solutions and results obtained, we
distribution company:
i. Installing of new distribution line (33kv) from HAS S/S to KAM S/S
21
REFRENCES
[1]. Millard (South Africa) and Mike Emmerton (Hong Kong), “Non-Technical
Factor and Load Loss Factor Wagh institute”, Nashik India June 2012
November 2002.
engineering 1999
22