Takt Time: Takt Time Calculation Production Time Available Required Units of Production (Customer Requirement)
Takt Time: Takt Time Calculation Production Time Available Required Units of Production (Customer Requirement)
TAKT TIME-
▪ Total Scheduled Run Time = 3 Shifts x 420 min = 1260 min =
75,600 sec
EXAMPLE
Weekly Customer Requirements-
▪ 6750 parts per week
▪ How many shifts per week do you operate?
▪ 5 days schedule = 1,350 parts per day 6750 /5 = 1,350
▪ 6 days schedule = 1,125 parts per day 6750 /6 = 1,125
▪ Scheduled Run Time = 75,600 sec.
▪ Weekly Customer Requirement = 6,750 parts
TAKT TIME-
6 days schedule = 1,125 parts/day
▪ Takt Time
Takt instills routine functions on the production line, enabling operators to work
faster and produce more output
Limitations of Takt Time