This weekly progress report summarizes work done on the Gabon Road Project from May 30th to June 5th, 2021. Survey work was completed from PK50 to PK75. Geotechnical investigation was 100% completed for PK50 to PK75. Mobilization was 40% complete. Main carriageway activity started from PK50 to 62. Hot mix and crusher plants were being erected. Training was conducted for school children and safety meetings were ongoing. Looking ahead, more manpower and equipment will be mobilized over the next 4 weeks to continue earthworks, paving and construction. Support is requested regarding permissions, payments, visas and land acquisition to help maximize efficiency of operations.

Uploaded by

Adrian Frantescu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
54 views9 pages

Weekly Progress Report No 19 Revised

This weekly progress report summarizes work done on the Gabon Road Project from May 30th to June 5th, 2021. Survey work was completed from PK50 to PK75. Geotechnical investigation was 100% completed for PK50 to PK75. Mobilization was 40% complete. Main carriageway activity started from PK50 to 62. Hot mix and crusher plants were being erected. Training was conducted for school children and safety meetings were ongoing. Looking ahead, more manpower and equipment will be mobilized over the next 4 weeks to continue earthworks, paving and construction. Support is requested regarding permissions, payments, visas and land acquisition to help maximize efficiency of operations.

Uploaded by

Adrian Frantescu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

GABON ROAD PROJECT SATURDAY

JUNE 2021
TOTAL SAFE MANHOURS WEATHER STASTICS
128 OF
547 ACHIEVED ON PROJECT
05
DAYS DURATION
245,190 NO RAINF ALL IN THIS WEEK

REHABILITATION & UPGRADATION OF 2 LANE NATIONAL ROAD RN1 FROM PK24+000 TO


PK 105+000 ON EPC BASIS IN GABON
WEEKLY PROGRESS REPORT 19 (30th May 2021 to 05th June 2021)

 NAVIGATOR
WEEKLY UPDATE PROJECT STATUS 
START
Monday SURVEY WORKS GEO TECHNICAL MOBILISATION FINISH
Monday

COMPLETED FOR PK50- INVESTIGATION FOR


JAN 2021 PK75. PK50-PK75. JUL 2022

22 100 % 100 % 40 % 22

COMPLETION FOR
NTP FOR SEGMENT 4
PROJECT NTP FOR NTP FOR
CONSTRUCTION 22 FEB 2022
COMMENCEMENT CONSTRUCTION CONSTRUCTION
FOR SEGMENT 4 FOR SEGMENT 5 &6 FOR SEGMENT 1 &3
DATE- 22 JAN OVERALL PROJECT
22 MAR 2021 22 JUN 2021 22 SEP 2021
2021 COMPLETION DATE-
22 JUL 2022
NTP FOR
NTP FOR
DETAILED
DETAILED
DESIGN FOR
DESIGN FOR
SEGMENT 4,5 & 6
SEGMENT 1, 2 & 3
- 22 JAN 2021
22 APR 2021

2021 2022
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18

 NAVIGATOR
WEEKLY UPDATE KEY HIGHLIGHTS OF THIS WEEK 
KEY HIGHLIGHTS :

 Employer’s Office & Accommodation is in Progress


 Main Carriageway Activity started from PK 50 to 62
 Hot Mix Plant Erection work is in Progress
 TBM inspection with Client and Road Ministry team
 Plate Load Test conducted on Trial section of GNT2, 0/31.5 MM at base camp PK50
 Crusher Plant in foundation work is in Progress in Makora Area
 Conducted a training program for the school children's at PK.50+800 as per social
management plan
 Regular Tool Box Talks, Safety Meeting ongoing at site
 Embankment formation is in Progress at PK 56 LHS Side

 NAVIGATOR
MATERIAL, MACHINERY, MANPOWER MOBILISATION
WEEKLY UPDATE
STATUS AND SCHEDULE 
Total (Upto Previous
To Be mobilised
Sl. No. Manpower Week)
for 2 Weeks
Expats + National
1 Environment Engineer 2
2 Health & Safety Engineer 5
3 Male Nurse 1
4 Doctor 2
5 QA/QC Engineer 4
6 Survey 4
7 Execution Team 31 20
8 Skilled/Unskilled Workforce 258 150
Total 311 170

 NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN- 4 WEEKS 
LOOK AHEAD PLAN

 NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN- 4 WEEKS 
LOOK AHEAD PLAN

 NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN- 4 WEEKS 
LOOK AHEAD PLAN

 NAVIGATOR
WEEKLY UPDATE SUPPORT REQUIRED 
SUPPORT REQUIRED:

 Permission from administration for operation in curfew hours/other received through


Laissez passer. However, these passes couldn’t be used as vehicles and drivers still
pending as we are able to operate at 50% efficiency.
 Expediting of Euro payments against 2nd and 3rd Payment Milestone.
 Intervention in expediting VISA process for expats.
 Facilitation for royalty exemption for the earth, laterite and sand being project of national
importance as per taxation rules of Gabon and precedence of earlier projects executed
in Gabon.
 Expediting land handing over for construction operation at site.
 Requesting for partial drawing clearance for starting physical works at site.
 Variation instruction regarding Ministry approved drawings awaited. KEY HIGHLIGHTS

 NAVIGATOR
WEEKLY UPDATE SITE PHOTOS 

Field Density Checking Plantation on Environment Day HMP Main Structure RCC

Crusher Foundation

Training Programme for Children Embankment Preparation Plate Load Test on GNT Trial

TBM Inspection with Client Bitumen Tanker Erection HMP Foundation concreting