Post-Tensioning Tendon Installation and Grouting Manual
Post-Tensioning Tendon Installation and Grouting Manual
Grouting Manual
Version 2.0
May 2013
FHWA-NHI-13-026
This Page Intentionally Left Blank.
Technical Report Documentation Page
1. Report No.
FHWA-NHI-13-026
5. Report Date
May 2013
7. Author(s)
John Corven, P.E. and Alan Moreton, P.E
16. Abstract:
This Manual includes state-of-the-art information relative to materials, post-tensioning systems,
construction practices and grouting of post-tensioning tendons for bridges. The Manual is
targeted at Federal, State and local transportation departments and private company personnel
that may be involved in the design, inspection, construction, or maintenance of bridges that
contain post-tensioning tendons. This Manual will serve as a reference and guide to designers,
inspectors and construction personnel for post-tensioning materials, installation and a grouting
of bridge tendons. The document is part of the Federal Highway Administration’s national
technology deployment program and may serve as a training manual.
21. No of Pages
184
22. Price
Table of Contents
Table of Figures
Figure 2.3 - Anchorage System for Flat Duct Tendon (Courtesy of DSI) .................................... 6
Figure 2.4 - Post-Tensioning Bar Anchorage System (Courtesy of DSI)..................................... 7
Figure 2.5 - Permanent Plastic Grout Caps (Courtesy of VSL) ................................................... 8
Figure 2.6 - Corrugated Metal Duct ...........................................................................................10
Figure 2.7 - Corrugated Plastic Duct .........................................................................................11
Figure 2.8 - Grout Vents at Center of a Precast Segmental Pier Segment ................................12
Figure 2.9 - Duct Coupler for Precast Segmental Internal Tendons...........................................13
Figure 2.10 - Duct Couplers in Precast Segmental Construction ...............................................13
Figure 2.11 - Pressure Distribution: Diabolos vs. Steel Pipe......................................................14
Figure 2.12 - Reusable Diabolo Inserts at Deviation Segment ..................................................15
Figure 2.13 - Standard and Modified ASTM C939 Flow Cone Testing ......................................19
Figure 2.14 - Wick-Induced Bleed Test .....................................................................................20
Figure 2.15 - Bleed Under Pressure Test (Gelman Filtration Funnel) ........................................21
Figure 3.1 - Typical Shop Drawing Approval Process for Post-Tensioning ................................. 4
Figure 3.2 - Frictional Losses Related to Friction and Wobble.................................................... 5
Figure 3.3 - Four-Span Girder .................................................................................................... 7
Figure 3.4 - Tendon Geometry ................................................................................................... 7
Figure 3.5 - Tendon force Diagram for Stressing at End A ......................................................... 9
Figure 3.6 - Tendon Force Diagram after Anchor Set at End A .................................................10
Figure 3.7 - Tendon Force Diagram after Stressing from End B ................................................11
Figure 3.8 - Tendon Force Diagram after Anchor Set at End B .................................................11
Figure 3.9 - External Deviated Tendon in End Span .................................................................12
Figure 3.10 - Example 2: External Tendon Force after Friction and Anchor Set ........................13
Figure 3.11 - On-Site Friction Test ............................................................................................16
Figure 3.12 – On-Site Bench Test for Modulus of Elasticity .......................................................17
Figure 3.13 - General and Local Anchor Zone in End of I-Girder ...............................................18
Figure 3.14 - Local Zone Reinforcing for Edge Anchor in Thin Slab ..........................................19
Figure 3.15 - Duct Spacing and Clearance in Post-Tensioned Precast Girders .........................20
Figure 3.16 - Check Longitudinal and Transverse Duct Alignments ..........................................21
Figure 3.17 - Anchor Recess and Checking of Duct Alignment .................................................22
Figure 3.18 - Unacceptable Duct Connections and Mistakes ....................................................23
Figure 3.19 - Duct Supports in Post-Tensioned Precast I-Girders .............................................24
Figure 3.20 - A Possible Result of Poorly Supported and Connected Ducts ..............................25
Figure 3.21 - Connections for Secondary, Vacuum Grouting Operations ..................................26
Figure 3.22 - Excess Wobble Due to Rebar and Duct Conflict ..................................................27
Figure 3.23 - Duct Size in Post-Tensioned I-Girders .................................................................27
Figure 3.24 - Placing Concrete in Box Segments ......................................................................28
Figure 3.25 - Use of Internal Vibrators for Consolidation of Concrete ........................................29
Figure 3.26 - Steel wire sock for installing multi-strand tendon ..................................................31
Figure 3.27 - Monostrand Jack ..................................................................................................33
Figure 3.28 - Typical Multi-Strand, Center Hole, Stressing Jack ................................................34
Figure 3.29 - Prestressing Bar Jack ..........................................................................................35
Figure 3.30 - Jack Calibration ...................................................................................................36
Figure 3.31 - Calibration Chart for Pressure Gauge and Jack Force .........................................37
Table of Tables
Chapter 1 - Introduction
1.1 Objective
One of the major advancements in bridge construction in the United States in the second half of
the twentieth century was the development and use of prestressed concrete. Prestressed
concrete bridges offer a broad range of engineering solutions and a variety of aesthetic
opportunities. The objective of this Manual is to provide guidance to individuals involved in the
design, installation, grouting and inspection of post-tensioning tendons for prestressed concrete
bridges.
Although cracks occur in reinforced concrete, the cracks are normally very small and well
distributed. Cracks in reinforced concrete can reduce long-term durability. Introducing a means
of precompressing the tensile zones of concrete members to offset anticipated tensile stresses,
reduces or eliminates cracking to produce more durable concrete bridges.
Figure 1.2(c) shows the two prestressed beams under the action of post-tensioning and applied
loads. The loads cause both the simple-span beam and cantilever beam to deflect down,
creating tensile stresses in the bottom of the simple-span beam and top of the cantilever beam.
The designer balances the effects of load and prestressing in such a way that tension from the
loading is compensated by compression induced by the prestressing. Tension is eliminated
under the combination of the two and tension cracks are prevented. As a result, durability is
increased and more efficient, cost effective construction is realized.
Tendons made up of strands are secured by steel wedges that grip each strand and seat firmly
in a wedge plate. The wedge plate itself carries all the strands and bears on a steel anchorage.
The anchorage may be a simple steel bearing plate or may be a special casting with two or
three concentric bearing surfaces that transfer the tendon force to the concrete. Bar tendons
are usually threaded and anchored by means of spherical nuts that bear against a square or
rectangular bearing plate cast into the concrete. For an explanation of post-tensioning
terminology and acronyms, see Appendix A.
The protruding “tails” of strands or bars of permanent tendons are cut off using an abrasive disc
saw or plasma cutting after stressing. Flame cutting should not be used as it negatively affects
the characteristics of the prestressing steel. Tendons are then grouted using a cementitious
based grout. This grout is pumped through a grout inlet into the duct by means of a grout pump.
Grouting is done carefully under controlled conditions using grout outlets to ensure that the duct
anchorage and grout caps are completely filled. After grouting, anchorages are protected by
multiple levels of protection appropriate to the environmental demand on the structure. See
Chapter 5 for details regarding corrosion protection of tendons.
Materials other than cementitious grout, such as wax, have been used to fill ducts after the
installation and stressing of tendons. These materials are not commonly used in the United
States and are not addressed in this Manual. Post-tensioning and grouting operations require
certain levels of experience and certification, as outlined in Appendix B.
Longitudinal post-tensioning typically comprises multi-strand tendons draped along the length of
the girder to a designed profile. In continuous spans, the tendon profile lies in the bottom of the
girder in the mid-span region and rises to the top of the section over interior supports. In simple
spans and at the expansion ends of continuous spans, post-tensioning anchors are arranged
vertically so that the resultant of the tendon anchor force passes close to the centroid of the
section. A draped profile of this type provides the most effective distribution of internal prestress
for this type of construction.
Post-tensioning ducts that are cast into the webs are spliced at the cast-in-place joints. The
ducts follow a smoothly curved, draped profile along each girder line, rising to the top of the
girders over the interior piers and draping to the bottom flange in mid-span regions. Before the
deck slab is cast, some or all of the tendons running the full length of the multi-span unit are
installed and stressed, making each simple span I-girder into a series of continuous spans.
When the deck slab has been cast and cured, additional tendons may be installed and stressed
on the fully composite section. Tendons may be anchored in a variety of configurations at the
ends of each continuous unit.
Longer spans can be built using similar techniques. A variable depth girder section
cantilevering over a pier can be spliced to a typical precast girder in the main and side-spans.
An example is shown in Figure 1.7.
Temporary supports are needed at the splice location in the side spans. The ends of girders
have protruding mild reinforcing to help secure the girder to the closure concrete and ducts that
splice with those of other girder segments to accommodate tendons over the full length of the
main unit. The variable depth girder sections are placed over the piers, aligned with the girders
of the side spans, and closures cast. Usually, temporary strong-back beams support the drop-in
girder of the main span while closures are cast.
The sequence for erecting and temporarily supporting this type of I-girder construction is
illustrated in Figure 1.8. After all closures have been cast and have attained the necessary
strength, longitudinal post-tensioning tendons are installed and stressed. To maximize the
efficiency of the post-tensioning, phased stressing is necessary. Some of the longitudinal
tendons are stressed on the I-girder section alone (i.e. while it is non-composite). The
remaining tendons are stressed after the deck slab has been cast and act upon the full
composite section.
Figure 1.8 - Erection Sequence and Temporary Supports for Spliced I-Girder
Figure 1.9 shows two typical methods of placing precast segments in balanced cantilever; using
cranes with stability towers at each pier and using an overhead launching gantry. When all
segments of a new cantilever have been erected and tendons stressed, a closure joint is made
at mid-span. Continuity post-tensioning tendons are installed and stressed through the closure
to make the cantilevers into continuous spans. Other methods of erecting the precast segments
are available, including deck mounted beam and winch systems and tire mounted segment
lifters.
Cantilever tendons in the top slab of a box section counteract the bending effect from the self-
weight of the cantilever during construction. This bending induces a longitudinal tension stress
in the top, reaching a maximum over the pier. The top cantilever post-tensioning counters these
effects by inducing a compression stress of equal or greater magnitude at each cross section
along the cantilever.
Figure 1.11 shows a typical layout for cantilever tendons that anchor on the end face of a
precast or cast-in-place segment. This feature requires special details to facilitate inspection of
the anchor head after tendon grouting and after additional segments have been erected on the
cantilever. (A possible detail for a face anchor to facilitate this inspection is shown in Chapter 5,
Figure 5.11).
An alternate approach is to anchor cantilever tendons in blisters (anchor blocks) cast into the
segments at the intersection of the top slab and web as shown in Figure 1.12. Anchorages of
these tendons can be inspected at any time during and after construction.
When a closure is several feet long and weighs more than one half as much as a typical
segment, it may be necessary to place the closure concrete in a very specific sequence in order
to prevent the closure opening or cracking as the cantilevers deflect. It may also be necessary
to apply a small amount of post-tensioning (10% to 20% of two continuity tendons) as soon as
the bottom slab concrete has taken an initial set (i.e., within about 2 to 4 hours of casting) to
keep the closure tight, even as more concrete is added. These are project specific
considerations.
Top continuity post-tensioning tendons are also typically required in balanced cantilever bridges.
A bridge built in balanced cantilever has little, if any, self-weight stress at the location of the
closure joint in the center of the span. Midspan bottom continuity tendons, along with live loads
in adjacent spans, produce tensile stresses in the top slab that need to be counteracted with top
continuity tendons. Subsequent application of the barrier railing and possible wearing surface
should produce top compression at this location, minimizing the need for the top continuity
tendons. In time, internal redistribution of forces and moments due to the creep of the concrete
will induce compression in the top at midspan, further reducing the need for top continuity
tendons. Figure 1.14 shows details of typical top continuity tendons.
Subsequent improvements in long-term creep prediction models for concrete have reduced
uncertainties in deflection calculations. Midspan hinges have again been used satisfactorily.
Deflection may be controlled by using steel beams on sliding bearings placed inside a box
girder, between cantilever tips, to allow for expansion and contraction, but restrain rotation.
Care should be exercised in the design and detailing of any type of in-span hinge because local
details may be subject to complex force and stress distribution.
Figure 1.17 shows the cast-in-place balanced cantilever construction of the Acosta Bridge in
Jacksonville, Florida. Figure 1.18 shows typical construction phasing for a three span bridge
built by the cast-in-place balanced cantilever method using form travelers.
Figure 1.18 - Typical Construction Stages for Cast-In-Place Balanced Cantilever Construction
The erection schematic shown in Figure 1.19 shows temporary erection trusses used to support
the precast segments during construction. Overhead erection gantries are also commonly used
to support the segments during erection.
For span-by-span construction, the use of external tendons provides for greater efficiency in the
cross section of the box for both longitudinal and transverse efficiency, by facilitating a web
thicker at the top than bottom. This raises the centroid of the whole cross section, and
maximizes the eccentricity and efficiency of the post-tensioning in the mid-span region needed
for the dominant effect of longitudinal flexure of this method. Figure 1.20 shows a typical layout
of span-by-span tendons for an interior span where all tendons deviate at a common deviation
saddle.
The tendons from one span overlap with the tendons of the next in the top of the pier segment
to achieve continuity between the spans. At the very ends of each continuous unit, the ends of
the tendons anchor in the diaphragm of the expansion joint segment with anchors dispersed
vertically and approximately parallel to the web of the box.
Figure 1.21 shows a similar layout for a typical expansion joint span. Current designs may
require an additional (straight) tendon per web to control the effects of thermal gradient and/or
provide added redundancy.
With this type of external-internal tendon, Service Limit State conditions are usually readily
satisfied. However, at the Strength Limit State, it is necessary to take into account the fact that
portions of such tendons are both external (i.e. unbonded) and internal (bonded or partially
bonded). An appropriate, non-linear, strain compatibility approach is usually necessary.
progressively to the advancing end. When the cantilever reaches midspan, a temporary support
is introduced. More segments are added in cantilever over the temporary support until the
advancing end reaches the next permanent pier. This process repeats until the superstructure
is completed all the way to the last abutment.
This technique was used to construct the Linn Cove Viaduct carrying the Blue Ridge Parkway
around Grandfather Mountain in North Carolina (Figure 1.23). Environmental restrictions
permitted the use of only walkways and light equipment on the terrain beneath the viaduct.
Consequently, equipment and materials for the installation of drilled micro-shaft piles and
foundation construction was lowered into each pier location from the advancing end of the
cantilever. After completing a footing, precast concrete pier shaft segments were transported
along the completed portion of the bridge and lowered into position, building the pier to receive
and support the next cantilever.
The progressive cantilever erection method with changing support conditions requires a
complex post-tensioning layout that includes internal cantilever and continuity tendons with
draped tendons in the webs. Most tendons were permanent, but a few were temporary and
were released as necessary for the changing support conditions.
Transverse post-tensioning has many uses in concrete bridge construction. Some examples
are offered in the following.
Wide bridges are often made of twin parallel boxes joined by a longitudinal cast-in-place
concrete strip. This closure strip may be conventionally reinforced or transversely post-
tensioned. When connected by transverse post-tensioning, only about half of the transverse
tendons within a segment are stressed for shipping and erection. The remainder are placed
through ducts in adjacent segments and the closure strip and stressed across the full width of
the bridge. The latter requires that tolerance be built into the details to accommodate mismatch
of the transverse (plan view) alignment due to casting, construction tolerances, differences in
elastic shortening, creep and shrinkage between one box and the other. Mismatch of vertical
alignment may also occur for similar reasons.
Suitable allowance should be made for mismatch of tendon alignments due to casting and
erection construction tolerances, elastic shortening, creep shrinkage and vertical deflection, in
the details for transverse tendons.
Proper attention should be given to the details in order to ensure that the tendons are effective
at the critical locations. For example, in Figure 1.25, the anchors are recessed into the web
face and the tendons do not contribute to the resistance of the interface-shear between the web
and diaphragm. They contribute only to the transverse tensile force capacity needed across
that portion of the diaphragm mostly inboard of the bearings.
depth. The tendons are internal to the concrete and are stressed and grouted after the pier
concrete has reached sufficient strength.
In a typical straddle bent, tendons drape to a prescribed profile that may be similar to the drape
in a beam on simple supports, or it may rise over the columns where a monolithic connection is
made to transfer moments into the columns and provide frame action. The columns may be
reinforced or post-tensioned, depending upon the magnitude of the forces and moments
induced in the frame.
Tendons in straddle bents are internal and grouted during construction. However, it is possible
to apply external tendons of a similar type to repair, or rehabilitate a damaged structure.
Detailing of cantilever piers should provide for proper development of prestressing forces in the
cantilever, column and footing. Anchors at corners must cross in an effective manner to oppose
tension and develop pre-compression all around the exterior of the pier. An alternative would
be to use a continuous tendon rather than two separate tendons.
Tendons are internal, stressed and grouted during construction. Similar external tendons may
be used for repair or rehabilitation. Special attention would be needed, however, to anchor
them and develop forces around the top corner and into the footing.
Precast segmental piers with an I-section were used for the Mid-Bay Bridge in Florida. The
taller piers were post-tensioned with strand tendons, looping through the foundations, (Figure
1.33).
Depending on the size of the segment, there may be three to eight temporary bars distributed
around the cross section. In most precast cantilever bridges, there is at least one temporary PT
bar in a duct in the concrete wing of the segment. In some bridges, temporary external PT bars
anchor in blocks on the underside of the top slab and on the top of the bottom slab.
Alternatively, bars may be installed in ducts within the top and bottom slabs and anchored in
blockouts at the segment joints. Figure 1.35 shows the application of epoxy on the Foothills
Bridge No. 2. Figure 1.36 shows the stressing of temporary post-tensioning bars for the same
project.
2.1.1.1 Strands
Strand for post-tensioning is made of high tensile strength steel wire. A strand is comprised of 7
individual wires, with six wires helically wound to a long pitch around a center “king” wire. All
strand should be Grade 1860 MPa (270 ksi) low relaxation, seven-wire strand conforming to the
requirements of ASTM A416 “Standard Specification for Steel Strand, Uncoated Seven Wire
Strand for Prestressed Concrete.” ASTM A416 provides minimum requirements for mechanical
properties (yield, breaking strength, elongation) and maximum allowable dimensional
tolerances. Strand from different sources may meet ASTM A416 but not necessarily be
identical in all respects.
Strand is most commonly available in two nominal sizes, 12.7mm (0.5in) and 15.2mm (0.6in)
diameter, with nominal cross sectional areas of 99mm 2 and 140mm 2 (0.153 and 0.217 square
inches), respectively. Though the majority of post-tensioning hardware and stressing equipment
is based on these sizes, the use of 15.7mm (0.62in) diameter strand has been increasing.
Strand size tolerances may result in strands being manufactured consistently smaller than, or
larger than nominal values. Recognizing this, “Acceptance Standards for Post-Tensioning
Systems” (Post-Tensioning Institute, 1998) refers to the “Minimum Ultimate Tensile Strength”
(MUTS), which is the minimum specified breaking force for a strand. Strand size tolerance may
also affect strand-wedge action leading to possible wedge slip if the wedges and strands are at
opposite ends of the size tolerance range.
Strand conforming to ASTM A416 is relatively resistant to stress corrosion and hydrogen
embrittlement due to the cold drawing process. However, since susceptibility to corrosion
increases with increasing tensile strength, caution is necessary if strand is exposed to corrosive
conditions such as marine environments and solutions containing chloride or sulfate, phosphate,
nitrate ions or similar. Consequently, ASTM A416 requires proper protection of strand
throughout manufacture, shipping and handling. Protection during the project, before and after
installation, should be specified in project drawings and specifications.
Various methods have been developed to provide improved corrosion protection to individual
prestressing strands. Some of these methods include:
• Greased and plastic sheathed mono-strand for unbonded tendons has been widely used
in buildings, but not generally in bridges in the United States. Plastic sheathed mono-
strands are, however, available for cable-stays or external tendon applications for new
structures and the repair of old ones.
• Epoxy coated strand meeting the same requirements as ASTM A416 is available and
should also conform to ASTM A882 “Standard Specification for Epoxy-Coated Seven
Wire Strand.” Epoxy coated strand is available as an outer coating only, or as a coating
that also fully fills the interstices between wires. The latter is preferred for post-
tensioning or cable stay applications. Special wedges are required that bite through the
thickness of the coating and engage the strand; power seating of the wedges is usually
required.
• Strand made from fiber material (such as carbon or aramid fibers) has limited application
as post-tensioning to date. These composite materials offer advantages for enhanced
corrosion resistance, but lack the benefit of a high modulus of elasticity that is routinely
provided by steel and which is crucial to good load-deflection behavior of a prestressed
structure without excessive cracking under service loads.
• Few U.S. manufacturers supply galvanized strand. The galvanizing process leads to
some reduction in tensile strength of prestressing steel. This reduction is typically
compensated by starting the wire drawing process with rod of higher strength (or utilizing
larger rod for drawing) so that at conclusion of the process dimensions and minimum
strength specified for equivalent non-galvanized prestressing wire is achieved. This
strand is not typically used in U.S. bridges.
Tendons in prestressed concrete structures do not experience stress cycling significant enough
to induce fatigue problems. Fatigue is a concern only in certain applications such as cable-
stays in cable-stayed bridges where traffic loads significantly affect stress variations.
2.1.1.2 Bars
Bars should be Grade 1035 MPa (150 ksi), high strength, thread bar meeting the requirements
of ASTM A722, “Standard Specification for Uncoated High-Strength Steel Bar for Prestressing
Concrete,” Type II bar. Bars are available in both a coarse and fine thread depending on the
manufacturer. Each may have advantages in different situations. It is good practice to limit the
stress level and number of re-uses for temporary applications, according to recommendations of
the Manufacturer. In the absence of such information, it is suggested that for new bars, the
stress should not exceed 50% fpu and the number of re-uses be conservatively selected based
on the critical nature of usage. Re-use of bars should only be after inspection for damage from
previous uses.
Post-tensioning bars are available in various sizes from 16mm (5/8in) to over 50mm (2in)
diameter. However, for convenience in handling, installation, and removal and re-use in normal
applications for post-tensioned bridges, 32mm (1-1/4in) or 35mm (1-3/8in) diameter bars are
typically used.
Bars are not as easily damaged by corrosion as strands because of their lower strength, large
diameter and smaller ratio of exposed surface to cross section area. Hot rolled bars also
acquire a natural surface oxidation from the rolling process that enhances their protection.
Nevertheless, bars need to be protected during extended periods of exposure especially in
aggressive environments.
All bars of each size from each mill heat of steel and all strand from each manufactured reel to
be shipped to the site should be assigned an individual LOT number and be tagged in a manner
that each such LOT can be accurately identified at the site. All unidentified prestressing steel
(strand or bar) or loss of positive proof of identification is sufficient reason for rejection.
Shipping containers should be clearly marked with a statement that it contains high-strength
prestressing steel, the type of care needed for handling, the type and amount of corrosion
inhibitor used and the date it was placed, and any other safety precautions and instructions.
Strand should be clearly identified that it is low-relaxation (stabilized) strand per the
requirements of ASTM A416 and the corresponding LOT number for which quality control test
samples have been taken. Strands not so designated should be rejected.
Reels of strand should be examined by the Contractor and inspected by the Construction
Inspector when first received on site and periodically while in storage. During use, any reel that
is found to contain broken wires or corrosion should be carefully examined. Lengths of strand
containing broken wires or corrosion should be removed and discarded. Prestressing steel
should also be protected during installation in the structure.
Post-tensioning bars for both temporary and permanent applications should be identified in a
similar manner and inspected for damage or excessive corrosion. At any time during
construction, the Construction Inspector should have the authority to reject any prestressing
steel that has sustained physical or corrosion damage.
2.1.3 Acceptance
To ensure that correct materials are supplied and used, specific quality control procedures for
material acceptance should be in place. Procedures may differ from State to State or from
Owner to Owner. An Owner may require that post-tensioning systems be pre-qualified prior to
use in construction by the Owner’s pre-qualification program. Pre-qualification in this manner
involves prior submission and approval of test reports and certifications.
Samples for testing should be furnished at the job site for each manufacturer of prestressing
steel and bar. Each sample furnished for testing should be accompanied by certification
showing:
• For strand: three randomly selected samples, 1.5m (5ft) long, per manufacturer, per size
of strand, per shipment, with a minimum of one sample per ten delivered reels and
minimum of one per LOT/HEAT.
• For bar: three randomly selected samples, 1.5m (5ft) long, per size of bar, per heat of
steel with a minimum of one sample per shipment.
One of each of the samples furnished to represent a LOT should be tested in accordance with
appropriate ASTM standard. The remaining samples should be properly identified, tagged, and
stored. In the event of a loss or failure, the stored samples should be used for evaluation. For
acceptance of the LOT represented, test results must demonstrate 100% of fpu.
Following initial acceptance, the Contractor should maintain good control over the storage,
identification, and record keeping regarding the prestressing steel. The Contractor should
supply copies of certifications and test results to the Construction Inspector. The latter should
regularly and periodically check stored components, records and results.
Prior to use, strand should be inspected with respect to corrosion. Refer to Section 11.5 of
“Guide Specification for Grouted Post-Tensioning” (PTI/ASBI M50.3-12) for strand
condition/acceptance with regard to corrosion.
Approval of any prestressing materials by the Construction Inspector should not preclude
subsequent rejection if material is damaged in transit or later found to be defective for any
reason. Costs of acceptance and quality control tests are typically included in the project bid
items for post-tensioning work and no separate payment is made. Testing should conform to
the applicable ASTM Specifications. The location where the post-tensioning is to be installed is
considered the “site” and may be the project site or a casting yard.
Basic bearing plate anchorages should comply with the requirements of Section 10.3.2 of the
AASHTO LRFD Bridge Construction Specifications.
Figure 2.3 - Anchorage System for Flat Duct Tendon (Courtesy of DSI)
Use of a special bearing plate or anchorage device is acceptable if it complies with the testing
requirements of Section 10.3.2.3 of the AASHTO LRFD Bridge Construction Specifications.
Wedges should comply with PTI’s “Guide Specifications for Grouted Post-Tensioning,” Section
4.3.2.
Permanent grout caps should be made of a non-corrosive material such as fiber reinforced
plastic, stainless steel, or galvanized ferrous metal with a minimum thickness of zinc of 120 μm.
To ensure an enduring, maintenance-free, life of 75 years fiber reinforced plastic caps should
contain an anti-oxidant additive with an environmental stress cracking endurance of 192 hours
per ASTM D1693; stainless steel caps should meet the requirements of ASTM A240 Type 316.
Grout caps shall meet the requirements of PTI/ASBI M50.3-12 Section 4.3.3.
2.3 Ducts
Ducts are used to form a continuous void through the concrete for later placement of the post-
tensioning tendon steel. Originally, little attention was paid to the possible role of the duct as a
barrier to corrosive agents. Today, strong emphasis is placed on the quality, integrity and
continuity of the duct as a corrosion barrier in itself. This has resulted in a move toward the use
of plastic ducts in some states. Nevertheless, previous duct materials are still available and
their use continues in other regions. Consequently, the following recommendations should be
adapted as appropriate to meet local needs and conditions in accordance with Protection Levels
specified in Section 3.0 of “Guide Specification for Grouted Post-Tensioning PTI/ASBI,” M50.3-
12.
Oval “flat” ducts are commonly used for transverse tendons in deck slabs of concrete box
girders. These transverse tendons have typically been made of up to 4 strands of 0.6in
diameter, though there are systems that will accept up to 5 strands. The internal clear
dimensions of oval duct should be a minimum of 25mm (1 in) vertically and 75mm (3 in)
horizontally.
The wear resistance of the tight-radius corrugated plastic duct should be confirmed for the
minimum bend radius as a function of tendon size (number of strands). For further information,
refer to “Improved Performance Using Corrugated Plastic Duct in Tight-Radius Post-Tensioning
Applications” (Krauser).
2.3.2.5 Smooth, High Density Polyethylene Pipe (HDPE) for External Tendons
HDPE smooth pipe is available in different diameters, wall thickness, physical and chemical
properties. Though there can be some variability in commonly available materials, all HDPE for
ducts should conform to Section 4.3.5.3 of “Guide Specification for Grouted Post-Tensioning”
(PTI/ASBI M50.3-12). In addition, it is very important that the duct has satisfactory properties
for handling, storage, installation and durability for the application.
The color of HDPE smooth pipe for duct is normally black from a small amount of carbon in the
material, to protect against degradation from ultraviolet light. The wall thickness, diameter and
physical strength (Hydrostatic Design Basis) should be sufficient to initially withstand grouting
pressures, and in the long term, not deteriorate or split. Wall thickness requirements are
specified in Section 10.8.3 of the AASHTO LRFD Bridge Construction Specifications.
Tubes for inlets and outlets for strand tendons should have a minimum inside diameter of 20mm
(3/4 in). For bar tendons and for tendons comprising up to 4 strands, tubes should be at least
10mm (3/8 in) internal diameter. Inlets and outlets should be closeable with suitable valves or
plugs. For grouting of long vertical tendons, dual mechanical shut-off valves are usually
necessary to facilitate intermediate stages of grouting and venting.
Inlets and outlets should be arranged and attached to ducts, anchorages and grout caps in a
manner that allows all air and water to escape in order to ensure that the system is completely
filled with grout. (See Chapter 4 for examples of locations of inlets and outlets).
2.3.2.11 Diabolos
Diabolos are curved pathways cast into precast segmental deviators and/or pier segment
diaphragms that allow external tendons to pass through without the need for connecting to an
embedded rigid steel duct. The curved pathways flare at each end to accept a range of angle
changes in tendon geometry. Diabolos are created either by casting a permanently embedded
diabolo pipe into the segment, or through the use of reusable diabolo form inserts.
Where diabolos offer an alternative solution to calculating and detailing individual tendon pipe
bends, they are structurally different from individual pre-bent pipes that bear evenly over a
uniform radius. The actual contact length in diabolos varies, and may be quite short, depending
upon the minimum radius of the deviator flare.
Figure 2.11 illustrates the difference in bearing and contact between pre-bent pipes and diabolo
deviators. Figure 2.12 shows reusable diabolo form inserts used for the Phase 1 Dulles
Corridor Metrorail Project in Tysons Corner, VA.
For acceptance and approval of a post-tensioning system, all components’ tests and results of
post-tensioning system approval tests should be carried out by an independent approved body
or testing laboratory. This testing should be completed prior to submission of Shop Drawings
and other related documents to the Engineer for approval.
• Technical documents and drawings of general assembly of the system and details of
components.
• Instructions and method statements for installation, stressing and grouting.
• A quality assurance plan covering production, shipping, handling, storage and
installation of the system.
• Instructions for surveillance and maintenance of the system in service.
On site, the Contractor should maintain a complete record of all documentation, test reports,
shipping dockets and approvals. Copies should be provided to the Inspector (CEI) to ensure
compliance.
2.4 Grout
2.4.1 Purpose
Cement grout is chemically basic and provides a passive environment around the post-
tensioning bars or strands. The grout also serves to bond internal tendons to the structure.
Appropriate protection of post-tensioning tendons begins with complete filling of the ducts with
high quality grout.
Refer to Section 3.3 of “Specification for Grouting of Post-Tensioned Structures,” PTI M55.1-12,
for further information concerning grout classifications.
• Slag Cement - Conforming to ASTM C989/C989M. Only Grade 120 slag shall be
specified for use in post-tensioning grouts.
• Silica Fume - Conforming to ASTM C1240. Densified silica fume shall not be used.
2.4.3 Admixtures
Grouts made of only cement and water often exhibit segregation and voids due to excessive
bleed water. Like concrete, admixtures may be used to improve workability and reduce the
water required, reduce bleed, improve pumping properties or entrain air. Care must be
exercised to use the correct quantities in the proper way according to the manufacturer’s
instructions and to remain within the mix properties established by qualifying laboratory tests.
Calcium nitrite may help improve corrosion resistance in some situations by bonding to the steel
to form a passive layer and prevent attack by chloride ions. The use of calcium nitrite may
influence other properties such as setting time and strength.
High range water reducer (HRWR) improves short term fluidity. However, a grout with HRWR
may lose fluidity later when being injected through hoses and ducts. Unlike a concrete mix, it is
not possible to re-dose a grout especially when it is in the pump, hoses and ducts. Also, HRWR
tends to cause bleed in grouts. On-site grout mixing with HRWR is not recommended.
Other admixtures include: Set Controlling, Air Entraining, Anti-Bleed, Expansion Creating, and
Corrosion Inhibiting.
A manufacturer of a pre-bagged grout may already have had the material pre-qualified by a
State DOT or other agency. In this case, it is appropriate to accept it on the basis of a written
certification; providing that the manufacturer has on-going quality control tests that can be
confirmed by submitting test reports to the Engineer. The certification should show the mixed
grout will meet the pre-qualified standard. On site, daily grout production must be monitored by
various field tests in order to maintain quality control and performance.
A critical feature of a grout is that it should remain pump-able for the anticipated time to fully
inject the tendon. This may be significant for long tendons or where a group of several tendons
is to be injected in one continuous operation. Some thixotropic grouts can have very low
viscosity after agitation, becoming easy to pump.
Laboratory tests typically performed on grouts are presented in the following sections. Refer to
the “Specification for Grouting of Post-Tensioned Structures,” PTI M55.1-12 for additional
information. Testing of grouts previously prequalified through testing may be waived by the
Design Engineer. Testing of prepackaged grouts shall be performed at the minimum and
maximum water/bagged material ratios.
2.4.6.3 Permeability
Grout permeability should be tested in accordance with ASTM C1202 “Test Method for
Electrical Indication of Concrete’s Ability to Resist Chloride Ion Penetration.” A value less than
2500 Coulombs after 6 hours is generally acceptable when subjected to a potential of 30 volts.
Figure 2.13 - Standard and Modified ASTM C939 Flow Cone Testing
(a) Perform the test in a temperature conditioned laboratory. Condition the room, grout,
water, duct, pump, mixer and all other equipment to be used to a temperature of 32.5°C
(90°F) for a minimum of 12 hours prior to the test.
(b) Use 122m (400 ft, ± 3m (10 ft)) of duct (tube) for the test. Use a duct with an inside
diameter of 25mm (1 inch).
(c) Mix the grout to the specified water content. Pump the grout through the duct until
the grout discharges from the outlet end of the duct and is returned to the pump.
(d) Start the one hour test period after the duct is completely filled with grout. Record the
time to circulate the grout through the duct. Constantly pump and re-circulate the grout
into the commercial grout mixer storage tank.
(e) Pump and re-circulate the grout for a minimum of one hour.
(f) Record at 15 minute intervals throughout the test period, the pumping pressure at the
inlet, grout temperature, and fluidity at the discharge outlet.
The result is satisfactory if the flow-cone efflux time (standard or modified ASTM C 939) after
one hour of recirculation is not greater than 30 seconds.
2.4.6.7 Bleed
The “Wick Induced Bleed Test” involves immersing a 1000 mm (40 in) length of conditioned,
clean, seven wire strand (either 0.5” or 0.6” in diameter) in a cylinder with a height of 1000 mm
(40 in) and diameter of 80 mm (3 mm), filled with 900 mm (35 in) of carefully prepared grout and
following a modified version of ASTM C940 to record the bleed water above the grout as
detailed in the Section 4.4.1 of “Specification for Grouting of Post-Tensioned Structures,” PTI
M55.1-12. A bleed of 0.0% after 3 hours at normal ambient room temperature of approximately
20ºC (68ºF) is acceptable (Figure 2.14).
The “Schupack Pressure Bleed Test” uses a Gelman Filter to retain grout particles and records
the bleed water expelled under air pressure applied up to 0.34MPa (50 psi) (Figure 2.15). The
test should be performed per ASTM C1741. Refer to Section 4.4.6.2 of “Specification for
Grouting of Post-Tensioned Structures,” PTI M55.1-12 for additional test information and test
limits.
2.4.6.8 Corrosion
An Accelerated Corrosion Test (ACT) may be used to quantify the expected level of corrosion
for a specific grout. The test is based on research made under FHWA-RD-91-092 which
indicates that a mean time to corrosion of 1,000 hours when tested at 0.2V is suitable. This test
is not yet standardized. However, it is particularly useful in determining combinations of
admixtures that may adversely affect the corrosion protection performance of a grout. The
maximum chloride content for grout is 0.08%.
Once this range has been established, wet density can be monitored in the field to ensure that
grout water content is appropriate, using an American Petroleum Institute Mud Balance (API
Recommended Practice 13B-1: “Standard Procedures for Field Testing Water-Based Drilling
Fluids”).
It is essential that the Contractor maintain a record of all delivered materials. A copy of the
manufacturer’s quality control data sheet should accompany each LOT of grout components
shipped to the site. A LOT is that parcel of material from the same production run shipped to
the site. Each shipment should be clearly identified with the corresponding LOT number so that
it can be tracked to the manufacturer’s quality control records. Copies of shipment records and
quality control test reports should be maintained by the Contractor and copies provided to the
Construction Inspector.
Prior to use, all materials in storage should be checked to make sure they have not exceeded
the manufacturer’s shelf life or have not absorbed moisture and begun to clump or hydrate. It is
recommended that cementitious materials and pre-bagged grouts not be stored on site for more
than one month before they are used.
Dry silica fume is available in bags. Special care is essential when mixing dry silica fume with
cement and additives in order to produce a job-site grout mix, as it can lead to clumping and a
poor result. Pre-bagged grouts containing silica fume have been dry blended and do not exhibit
this problem.
Any material with a total time from manufacture to use in excess of six months should be
retested, or recertified by the supplier before use or else be rejected and replaced. Approval of
any grout or grout materials by the Construction Inspector should not preclude subsequent
rejection if material is damaged in transit or later found to be defective for any reason.
2.4.8 Acceptance
A proposed grout is normally accepted on the basis of the laboratory tests listed in Section 2.4.6
performed before construction, or on the basis of certification from the manufacturer that the
(pre-bagged) grout materials meet the pre-qualification requirements of the Owner or project
specifications. The manufacturer should have a continuing quality control program to ensure
that production continues to meet the specified requirements. Copies of certificates should be
checked and a record kept by the Contractor and the Construction Inspector. Use of a
particular grout on site may continue providing that certification and documentation is kept up to
date, that materials in storage remain usable and that daily grout mix production tests meet
specified limits. Approval to use a grout should be withdrawn if these quality control standards
are not maintained.
Mock-up Tests should be in accordance with Section 4.7.2 of “Specification for Grouting of Post-
Tensioned Structures,” PTI M55.1-12. As far as possible, a mock-up should simulate the type
and size of tendon, duct, anchorages and proposed attachments and be arranged to a similar,
representative, geometric duct profile. The following field mock-up tests are suggested for
guidance:
(A) For continuously draped tendons in spliced girders or cast-in-place construction: one
tendon mock-up of the longest tendon from anchor to anchor, including all proposed
intermediate duct couplings and grout inlets and vents. The profile should simulate the tendon
with the maximum accumulated curvature from anchor to anchor.
(B) For cantilever or continuity internal and external tendons in precast or cast-in-place
segmental construction: one tendon mock-up of the longest tendon from anchor to anchor,
including all proposed intermediate duct couplings and grout inlets and vents. The profile
should simulate the tendon with the maximum accumulated curvature from anchor to anchor.
(C) For vertical tendons: one tendon mock-up of the longest tendon from anchor to anchor,
including all proposed intermediate duct couplings and grout inlets and vents. The profile
should simulate the tendon with the maximum accumulated curvature from anchor to anchor.
The following tests should be conducted and satisfied during the field mock-up trials:
3.1.1.1 Purpose
To permit competition and to encourage further development in the field of post-tensioned
bridge construction, in general, normal contract plans and specifications do not specify a
particular manufacturer’s post-tensioning system. The Engineer of Record usually selects the
type, size, location and number of tendons, but the Contractor selects the anchorage system.
All post-tensioning systems should have prior approval before being used.
All systems now in general use have been developed by independent companies and represent
different methods by which the prestressing force is applied. Each offers certain advantages as
compared to the others, but each will, when properly installed and stressed, accomplish the
intended result.
Shop drawings are normally reviewed by the Bridge Designer or Construction Inspector (CEI).
The Designer normally checks them for completeness, contract compliance, clearances or
interference of ducts and reinforcing steel. Despite the approval process, the Contractor
remains responsible for the correctness of the shop drawings and ensuing construction.
Shop drawings are needed for integration of approved post-tensioning systems (i.e. post-
tensioning supplier’s information and details), reinforcement, post-tensioning, and other
embedded items (including those for the Contractor’s chosen “means and methods” of
construction) for precast and cast-in-place components. Shop drawings should also include
corrosion protection details and designate the level of protection achieved, as defined in “Guide
Specification for Grouted Post-Tensioning,” PTI/ASBI M50.3-12.
Often, much of the above information is available from a catalogue data, particularly for
anchors, couplers, wedges, nuts, bars, ducts, jacks and equipment. Other information shown
on additional shop drawings prepared by a Contractor or his (Specialty) Engineer or in a post-
tensioning or construction manual for a specific project usually includes procedures, such as:
• Contractor: Arrange for the preparation of the necessary shop drawings and other
relevant information required by the Contract. Receive and review shop drawings from
Suppliers, Manufacturers, and the Contractor’s Engineer. Submit shop drawings to the
Owner in accordance with the project plans and specifications. Coordinate distribution
of approved shop drawings or return shop drawings for changes and resubmittal.
• Engineer (Designer): Receives post-tensioning calculations and shop drawings from the
Owner (often the Contractor makes simultaneous submissions to the Owner and
Engineer in order to expedite approvals.) Reviews submittals for compliance with the
information shown on the plans. Approves (completely or “as noted”) or rejects the
submittal and returns the submittal to the Owner. Forwards a copy of the information
transmitted to the Owner to the Construction Inspector (CEI).
Friction losses along the length of the tendon, between anchorages, are attributed to two
sources. The first of these frictional losses is the result of the expected friction between tendon
and duct as the profile of the tendon changes. These losses are related to angular changes in
the tendon profile. The top sketch in Figure 3.2 shows the trajectory of a tendon within a
desired duct profile. The friction coefficient (µ) is defined to predict losses of this type. The
value of the friction coefficient is a function of the duct material.
Predicting frictional losses along the length of a tendon using the friction coefficient alone does
not typically correlate well with field results. Another coefficient of frictional loss, wobble (k), is
used to account for additional friction between strand and duct as a result of unintended duct
misalignments. The concept of duct wobble is shown in the bottom sketch of Figure 3.2.
The equation relating tendon force at a point along the length of a tendon, as a function of
friction and wobble determined from the formula:
− + kx
P( x) = Pjack ⋅ e
Equation (3.1)
Where: x = distance along length of tendon where tendon force is being evaluated
P(x) = Force in tendon at a distance x along tendon length
Pjack = Stressing force at anchorage
µ = friction coefficient
K = wobble coefficient
θ = total angular change from stressing end to point x
Anchor set should be taken into account for both the stressing end and dead end of a tendon.
For long tendons, often the elongation may be greater than the travel on the jack. It is then
necessary to take more than one pull of the jack. Each time the jack is released, the anchor set
occurs again at the jacking end. Since the load is picked up again upon re-gripping, the anchor
set of individual pulls is not cumulative. Only the final anchor set affects the loss of tendon
force. However, keeping account of cumulative elongations and anchor set during repeated
pulls by a jack is always helpful for resolving unforeseen problems.
Stressing of a tendon may be performed from one or both ends. Stressing from both ends may
be sequential, first from one end then the other, or simultaneous using two jacks. In some types
of construction, it may only be necessary to stress from one end; for example, where tendons
are relatively short, say up to about 50m (150 feet) and have relatively small friction loss.
However, for long tendons, especially those within internal ducts set to a curved profile that
passes continuously through three or four spans, friction loss may be so significant that it is
essential to stress the tendon from both ends to ensure adequate force throughout.
Stressing calculations are illustrated with two examples: first for a long tendon draped to a
profile through four continuous spans and stressed sequentially from both ends; second for a
deviated external tendon in an end span stressed from the expansion joint.
Various parameters for calculation of tendon forces and elongations are defined as follows:
Typical values for friction and wobble coefficients are provided in Table 5.1 of “Guide
Specification for Grouted Post-Tensioning”, PTI/ASBI M50.3-12. Section 5.4 of the same guide
specification provides typical values for the modulus of elasticity of the post-tensioning steel.
The total elongation is obtained by summing the increments of elongation for each portion of the
tendon, based on the average of the force at the beginning and end of that portion:
Pave ⋅ xij
∆L = ∑
As ⋅ Es
Equation (3.2)
Where: Pave = average force over xij
Stressing calculation information should be forwarded to the site engineer or inspector. This
information should include:
• Tendon identification
• Assumed area of strands (A)
• Assumed modulus of elasticity (E)
• Required jacking force, P jack
• Anchor set (W) assumed for each end of each tendon
• Calculated elongation at each end, before release of the jack and anchor set for each
end of the tendon, depending upon the ends to be jacked first and second
• The anticipated total elongation, ∆L, before anchor set
Calculations of tendon force and elongation are made using assumed values for the tendon
area (A) and modulus of elasticity (E). If elongations measured during stressing operations are
outside of tolerances, actual values of A and E for the particular reel of strand should be used to
resolve discrepancies.
elongations accounting for friction, wobble, and anchor set. The tendon is made of 12-0.5”
diameter strands, giving it a cross sectional area of 6.24 in2. The tendon is stressed from both
ends, first at End A and then End B. The stressing force is 1264 kips (75% fpu). The modulus of
elasticity of the tendon is 28,000 ksi. The friction coefficient is 0.25 and the wobble coefficient is
0.0002ft/ft.
The calculation is made by considering each arc of the profile in turn and applying Equation 3.1
to determine the force at the beginning and end of each segment of tendon length. The
calculation begins at the stressing end and continues across the length of the tendon. Table 3.1
shows a table of the results of these calculations. The total elongation is found by summing the
last column of the table in Table 3.1. For this example, the total elongation is calculated to be
41.62 inches.
Loss Segment
Loss Force
Section x h Segment Elongation
(%) (kips)
(%) (inches)
Table 3.1 shows a graph of the tendon force along the length of the tendon when the tendon
has been stressed to the full jacking force. Note that the area below the tendon force curve is
equal to the work to elongate the tendon. Dividing this area by the tendon area and modulus of
elasticity produces the elongation of the tendon when stressing at End A.
When the jacking force is reached at End A, the wedges are made snug and the tendon force
released. The tendon draws the wedges, or seats them, into the wedge plate. Values of wedge
can vary with post-tensioning system, but a typical value is 3/8 inch. As the wedge seating is
being seated the tendon is shortening, reducing the tendon force at the wedges. Only a portion
of the length of the tendon may, however, be affected by the anchor set. This is because the
work to seat the wedges is typically much less than the work done to elongate the tendon.
Figure 3.6 shows the effect of an anchor set of 0.375 inches on the forces along the length of
the tendon after stressing at End A. The shaded area in Figure 3.6 represents the work
performed during the anchor seating. This area is determined by finding a point along the
length of the tendon to a location where the anchor set does not impact the tendon stressing
force (point of zero movement). Working back from the tendon force at that point to the
anchorage, the loss in tendon force is related to the geometry of the tendon, friction and wobble,
just as when originally stressed. A typical simplification for this calculation is to mirror image the
force loss diagram about a horizontal line passing through the point of zero movement.
For this example, the point of zero movement was determined by trial and error to be 75.2’ from
the stressing end. The force at the point of zero movement is 1187.5 kips, and the force at the
anchorage with anchor set loss is 1111 kips. The convergence on these values was found by
equating the shaded area in Figure 3.6, divided by the tendon cross sectional area and modulus
of elasticity, to the anchor set of 3/8”:
Equation (3.3)
((94.0 k ⋅ 54 ') + (17.5k ⋅ 21.2 '))12
Set = = 0.374" ≈ 0.375"
6.24in 2 28, 000ksi
The second stage of stressing is now performed from End B. After stressing from End A, the
force in the tendon at End B is calculated to be 712 kips. When jacking at End B, the jack will
not begin to move until the load exceeds this amount. The jack at End B will pick up load at 712
kips and continue to the final jacking force of 1264 kips, effecting the force in the tendon until it
reaches a point where the force is equal to that from jacking at End A. In this case, because the
bridge is symmetrical, this occurs at the middle of the tendon, over the middle pier.
The shaded area shown in Figure 3.7 between the two tendon force diagrams, divided by the
tendon area and modulus of elasticity is equal to the elongation due to stressing the tendon at
End B. For this example the tendon elongation due to second stage stressing is 5.93 inches.
It should be noted that in this example, no account has been taken for the elastic shortening of
the structure under the axial compression force of the tendon. If this stressing is performed only
on the girder before any deck slab has been cast and if the above tendon is the first of several,
then the elastic shortening is estimated approximately as follows:
Consider an average force in the tendon of 960 kips while stressing from End A. Also consider
a girder cross sectional area of 80 ft2, a bridge length of 630 feet, and a modulus of elasticity of
concrete of 650,000 ksf. The elastic shortening of the bridge during the stressing of the tendon
from End A would be 0.14 inches.
This amount of elastic shortening is small. However, in the field, it would have the effect of
increasing the measured elongations; approximately in proportion to the calculated elongation at
each end. It follows that stressing of a subsequent tendon of the same profile would result in
the same elongations for that tendon. However, it also follows that elastic shortening caused by
stressing of a second tendon reduces the effective force in the first tendon. Such reduction also
occurs for the effect of all subsequent tendons stressed after earlier ones. The effect of such
staged post-tensioning is normally taken into account by the Designer during design of the
bridge. The Designer should consider the effects of elastic shortening in the design of post-
tensioning forces.
Friction between the tendon and duct can only occur at deviators and in those portions of duct in
the diaphragms of pier or expansion joint segments where the tendon path curves to an anchor.
In this example, there is a curve at the dead end only and none at the stressing end. Curvature
friction, μ, applies at the deviators and the dead end diaphragm, but there is no loss due to
wobble in external tendons, so k = 0.0.
As with Example 1, the calculation for tendon force and elongation is made by considering each
angular change in turn and applying Equation 3.1 to determine the force at the beginning and
end of each segment of tendon length. The calculation begins at the stressing end and
continues across the length of the tendon. Table 3.2 shows a table of the results of these
calculations. The total elongation is found by summing the last column of the table in Table 3.2.
For this example, the total elongation is calculated to be 11.87 inches.
Loss Segment
Loss Force
Section x h Segment Elongation
(%) (kips)
(%) (inches)
The final force diagram after friction and anchor set loss for Example 2 is shown in Figure 3.10.
Note the horizontal force lines between deviation points. The lack of change in force in these
regions is a result of there being no wobble for external tendons.
Figure 3.10 - Example 2: External Tendon Force after Friction and Anchor Set
3.2.1 Friction
The purpose of a friction test is to verify the assumptions for the coefficients of friction and
wobble. This test would be appropriate for all but small scale applications where it would suffice
to adopt friction and wobble values from other, previous, experience.
A friction test is normally performed on a typical tendon representative of the type or group of
tendons being installed – for example, on one tendon in one girder of several in the span or on
perhaps two similar cantilever tendons in the top of precast or cast-in-place segments.
For any tendon, there are two unknowns, the coefficients of friction (μ) and wobble (k).
However, for any given test set up where the force is measured at each end of the tendon, there
can only be one equation and result based upon the standard force loss equation.
Consequently, two unknowns (μ and k) have to be derived from one equation. This is not
possible unless one of the unknowns is already known.
For an external tendon in, say a span-by-span bridge, the points of curvature are relatively
discrete and the angles consumed are known. In the straight portions there is no wobble. So in
such a case, providing that the pre-curved steel pipe ducts in the pier diaphragms and deviator
saddles have been correctly installed, then it may be assumed that k = 0. Thus a test on this
type of tendon should provide a reasonable result for the effective coefficient of friction, μ,
between the tendon and the steel pipes.
For a tendon in the top of a segmental precast or cast-in-place cantilever, usually the alignment
is relatively, but not completely, straight between two curves at each end anchor. If the duct for
this type of tendon has been carefully and well installed so that there is no wobble, then it may
be assumed that k = 0 and a test should provide a reasonable result for μ.
On the other hand, if there is uncertainty as to how well a duct has been installed or if it is
known to have significant unintentional wobble, it is necessary to make a judgment as to a
suitable proportion of loss due to friction and loss due to wobble. It is suggested that the wobble
coefficient be taken as the assumed value for “k” – and use the test result to give “μ”.
An alternative approach to determine both coefficients μ and k would be to perform the friction
test on two similar, say cantilever tendons – a short one and a long one. Assuming the tendons
are installed with the same materials and standard of care, this would provide two independent
results (i.e. two equations) which could be solved simultaneously for μ and k.
In any event, it is recommended that each friction test be performed on at least two, very similar
or identical, tendons – of the same length and curvature layout - for example, in a segmental
cantilever, one tendon over the left web and its counterpart over the right web. The average of
the pair represents one result (i.e. one equation). In an I-girder with a continuously draped
tendon profile, the two tests could be performed on two very similar tendons in the same girder
or the same profile of tendon in two parallel girders – where again, the average of the two
represents one result (equation).
In general, friction testing is likely to give reasonable results only on relatively long tendons
(over about 30m (100 ft)) since it is necessary to measure both forces and elongations under
incremental loading to a sufficient level of accuracy. For this reason, an in-place friction test is
not appropriate for some applications such as, straight longitudinal or transverse tendons in
“flat-oval” ducts or similar in voided precast slabs or transverse deck slab tendons in precast or
cast-in-place segments.
It is usual to test a minimum of one tendon in a group of tendons performing the same function –
e.g. one tendon in each web of a two-web box. Tendon function may be generally described as:
Selected tendons should represent the general size (that is number of strands) and length. It is
recommended that friction test groups be identified on shop drawings for approval.
The test procedure is to tension the tendon at one anchor assembly and measure the force at
the dead end using a load cell or calibrated jack. The tendon should be tensioned to 80% of
ultimate in increments of not less than 20%. For each increment, the gauge pressure at the
jacking end, the load cell (or jack) force at the dead end and the elongation at the jacking end
should be recorded. Also, note the anchor set at both ends. Take into account the loss of force
due to friction in the anchorages and wedge plates as the strands deviate slightly through them
and any friction in the jack. The manufacturer of the post-tensioning system should be able to
provide percentage estimates for these losses. For very long tendons that require multiple jack
pulls, it is essential to keep an accurate account of elongation at the jacking end and each
corresponding intermediate anchor set (wedge pull-in).
If wedges are not installed, and if the available jacking equipment can facilitate it, forces and
elongations measured while gradually releasing the jacking load should reveal a lag or
hysteresis resulting from the reverse effect of friction (Fig. 3.11). The force and elongation may
not immediately return to zero due to residual friction effects.
When performing friction tests, it is recommended that forces and elongations be reconciled
within a tolerance of 5% for all tendons. The 5% to 7% tolerance in AASHTO LRFD
Construction Specifications is for production tendon elongations – no guidance is given for
friction tests.
If the total measured elongation is different to the anticipated (calculated) elongation by more
than 5% then the reasons for it should be investigated. It may be necessary to make more
detailed calculations or to run a similar test on another tendon. It is suggested that assumed
values for friction (μ) and wobble (k) not be varied by more than 10% when attempting to
reconcile measured and anticipated results.
The strands must be removed after completion of the friction test in order to remove the load
cell, and the strands cannot be reused due to wedge “bite marks” on the strands.
The modulus of elasticity for an individual strand is generally about 193 to 200GPa (28,000 to
29,000 ksi.) There is a school of thought that the effective modulus of elasticity of a bundle of
strands made up into a multi-strand tendon may be slightly less than that of an individual strand
because of the bundle effect or the “un-wrapping”, if any, as strands are stressed. This is not
necessarily so. In some bench-tests performed on an approximate gauge length of 9m (30 feet)
with no contact between tendon and duct, the modulus of the group of strands proved to be the