SOW - General - Formwork
SOW - General - Formwork
Suspended Formwork
Project Name:
Client: LAHC
Version: 0
Table of Contents
1. Scope of Works .......................................................................................................................................... 2
1.1 Scope ................................................................................................................................................. 2
2. General Inclusions ..................................................................................................................................... 5
3. Site extents ................................................................................................................................................ 5
4. Connection to existing works and services ............................................................................................... 5
5. Avoidance of interference with others...................................................................................................... 6
6. Storage and laydown ................................................................................................................................. 6
7. Protection of existing services ................................................................................................................... 6
7.1 Existing services indicated on drawings ............................................................................................ 6
7.2 Notification of Authorities ................................................................................................................. 6
7.3 Charges and co-operation ................................................................................................................. 6
7.4 Payment for relocations .................................................................................................................... 7
7.5 Avoidance of damage ........................................................................................................................ 7
8. Damage to existing infrastructure ............................................................................................................. 7
9. Traffic management .................................................................................................................................. 7
9.1 Site Office .......................................................................................................................................... 7
10. Signage................................................................................................................................................... 8
11. Work on Site by others .......................................................................................................................... 8
12. Materials and work................................................................................................................................ 8
12.1 General .............................................................................................................................................. 8
12.2 Editions of Standards ......................................................................................................................... 8
13. Notice for examination of works ........................................................................................................... 9
14. PC supplied material .............................................................................................................................. 9
15. Specifications ......................................................................................................................................... 9
16. Practical Completion and Quality Assurance Documentation Handover ........................................... 10
16.1 Practical Completion ....................................................................................................................... 10
16.2 Handover manuals........................................................................................................................... 10
16.3 As-constructed drawings ................................................................................................................. 10
16.4 Post Practical Completion requirements ......................................................................................... 10
17. Progress Claims.................................................................................................................................... 10
18. Project safety and meeting requirements ........................................................................................... 11
19. Safety, Environment and Quality......................................................................................................... 11
20. Drawings & Documentation Register .................................................................................................. 11
Principal: LAHC
Scope of works Site: 31-37 Carr Street Towradgi
Job no: 1617_1710
ABN: 19 128 617 774, Lic No 232745c REV: 0 Page: Page 2 of 55
1. Scope of Works
1.1 Scope
This scope of works is for the formwork and concreting works at 31-37 Carr Street Towradgi.
Formwork Design
The formwork designer must be competent in formwork design including documenting temporary
work platforms and special equipment needed for safe formwork construction on-site
Formwork design to be issued to Van Mal Group prior to any works starting onsite
Rigid
Watertight
Braced and tied together to maintain position and shape during construction and able to be
removed easily and safely without damaging the formed concrete, or have components that
remain as part of the finished structure so the rest can be removed without damaging the
structure.
Sealing procedures
Ties
The formwork designer should determine the vertical pour rates for walls, columns and other
vertical concrete elements before completing the formwork design.
Formwork design to be issued to Van Mal Group prior to any works starting onsite
Principal: LAHC
Scope of works Site: 31-37 Carr Street Towradgi
Job no: 1617_1710
ABN: 19 128 617 774, Lic No 232745c REV: 0 Page: Page 3 of 55
Suspended Formwork
Supply and installation of all materials and equipment required for all suspended formwork works including
the following:
o Suspended slabs
o Balcony parapets
o Staircases
Contractor is to give VMG 48 hours notice prior to inspection and check hold points by client
Inspection and checks will be done prior to any concrete pours onsite for the following:
o Completed formwork
o Reinforcement fixed in place. For reinforcement inspection all embedded items, cores etc.
o Placing of concrete
o Stripping of formwork
Exclusions:
The Sub-contractor is responsible for the performance of the Works which includes the Works Under Contract (WUC)
and shall ensure that:
a) (WUC) complies with all the requirements of the Contract (including the drawings, scope of works and specifications set
out in the appendices) and all applicable legislative requirements
b) all goods, materials and workmanship incorporated into, and forming part of WUC will satisfy the specified
requirements in the Contract, will be free from all defects and comply with all relevant warranties expressly or impliedly
available at law;
c) unless otherwise specified in the Contract, all plant, equipment and materials incorporated in the WUC shall be new;
d) as between the Sub-contractor and the Principal, upon practical completion, WUC shall be free of all liens, charges and
other encumbrances;
e) any drawing, specification, other documents, plant, equipment, materials and methods of working used by the Sub-
contractor (not specified by the Principal) in connection with performance of the obligations under the Contract shall
not infringe any intellectual property right; and
f) at all times it shall be suitably qualified and experienced, and shall exercise due skill, care and diligence in the execution
and performance of the Contract.
Principal: LAHC
Scope of works Site: 31-37 Carr Street Towradgi
Job no: 1617_1710
ABN: 19 128 617 774, Lic No 232745c REV: 0 Page: Page 5 of 55
Exclusions
2. General Inclusions
General
Allow for all supervision, labour, materials, plant, equipment, freight, fees, licences, consultants and bonds to fully
complete works
Make necessary allowances for site conditions, access arrangements, identification of services, staging of works, co-
ordination with other trades, client and building users / occupants.
Attendance at meetings and participate in investigations if required
Testing and commissioning certificates, compliance certificates, as built drawings, operation and maintenance
manuals, warranties and guarantees are to be submitted at the completion of works or two weeks before practical
completion.
Set out of works is the responsibility of the subcontractor
Allowance for design if required to complete works
All product or materials must be as stated on the drawings or specifications. Any alternative product or material must
be approved by VMG management
Subcontractors are responsible for the handling of their materials.
The subcontractor is to allow for all investigations, site inspections, travel and accommodation
The subcontractor to accept a defect period of 52 weeks from project completion. All defects must be completed
within 4 working days unless separately agreed. The subcontract must bear any cost associated with rectifying your
defects and other peripheral works required
3. Site extents
The site extents are all limited to 31-37 Carr Street Towradgi property. Access and egress will be subject to council
requirements and the individual Site Traffic Management Plans must be adhered to. Site access will be limited to
areas relevant to the sub-contractors and the sub-contractor is to ensure all staff are informed of site extents.
If the Sub-contractor discovers any discrepancy between the locations, lines, levels, dimensions and materials actually
existing and the corresponding indications on the drawings the Sub-contractor shall notify the VMG of the discrepancy
and shall not proceed with work affected by the discrepancy until VMG has directed the action, if any, that is to be
taken.
Principal: LAHC
Scope of works Site: 31-37 Carr Street Towradgi
Job no: 1617_1710
ABN: 19 128 617 774, Lic No 232745c REV: 0 Page: Page 6 of 55
The Sub-contractor shall minimise interference with Principal or its direct or indirect contractors and their sub-
contractors operations at the site during the execution of the work under the Contract.
Storage and laydown areas will be provided for each site. Deliveries and laydown requirements must be agreed to by
the site supervisor and SWC prior to the delivery to ensure safe and timely co-ordination of traffic management.
Such indications are not guaranteed to be accurate or complete and shall not relieve the Sub-contractor of any
responsibility under the contract.
In the event of damage by the Sub-contractor, actions to repair the damage shall be proposed by PC or the Principal
and actioned by the Sub-contractor as directed by the Contractors Authorised Person.
The damaged infrastructure shall be repaired to the same standard prior to the damage occurring.
The cost of all work required in rectifying or repairing any damage to the infrastructure shall be borne by the Sub-
contractor.
Where work is to be done adjacent to or connecting to any existing service the Sub-contractor shall notify the relevant
authority or owner in writing and shall obtain that authorities or owners written approval to carry out the work, giving
any period of notice stipulated by the authority and before commencing work.
The Sub-contractor shall be held solely responsible for any damage to existing services and in the event of damage
shall immediately advise the relevant authority or owner and shall co-operate with the authority or owner in making
safe and/or restoring the service and shall bear any costs so incurred.
Where the Sub-contractor’s activities result in the damage of the existing infrastructure, the Sub-contractor shall
immediately notify both the Contractors Authorised Person and the Principal.
Actions to repair the damage shall be proposed by the Contractors Authorised Person and actioned by the Sub-
contractor as directed by the Contractors Authorised Person .
The damaged infrastructure shall be repaired to the same standard prior to the damage occurring.
The cost of all work required in rectifying or repairing any damage to the existing SWC infrastructure shall be borne by
the Sub-contractor.
9. Traffic management
Prior to commencing work on Site, the Sub-contractor shall submit a TMP that complies with the requirements of the
Contractors TMP.
All large vehicles or high risk movements shall use a spotter to ensure safe travel through site. Working plant such as
excavators, backhoes etc shall be signed, fenced and/or delineated to prevent other sub-contractors or Principals
operational staff from entering high risk areas. Excavated areas will be fenced off to prevent access.
The Lunchroom will be available to the Sub-contractor and its Sub-contractors. The sub-contractor will ensure all of
its employees are using the provided facilities in a reasonable manner. And will be responsible for the day to day
cleaning from the impact of its employees. Any damage or cleanliness issues arising from misuse will be at the sub-
contractors expense.
Principal: LAHC
Scope of works Site: 31-37 Carr Street Towradgi
Job no: 1617_1710
ABN: 19 128 617 774, Lic No 232745c REV: 0 Page: Page 8 of 55
10. Signage
The Sub-contractor may erect such signs as it requires to direct traffic to and through the Site and to indicate the
locations of the various parts of the Works.
All signs erected by the Sub-contractor shall be subject to the approval of the Contractors Authorised Person, who
may direct the Sub-contractor to change the size, layout and location of any sign and to remove any sign.
All such signs shall be erected at the Sub-contractor's expense and no separate payment shall be made in respect of
them. Any ground penetrating signs or fence shall be installed with due regard for underground services.
The Sub-contractor shall permit any authority or owner of a service to have access to the Site and to execute work on
the site and shall co-operate with such authorities and shall co-ordinate his own work with that being carried out by
such authorities or owners. Notwithstanding that such authorities or owners may not have been engaged by the
Principal.
The Sub-contractor will work collaboratively with the Principal, the PC and PC’s other sub-contractors (if required)
during the WUC so as to ensure a smooth transition to the commencement of the next phase of works concerning the
Electrical and Controls. PC will confirm as soon as possible who the other proposed Sub-sub-contractors are and the
nature of the works to be undertaken by each of these Sub-sub-contractors.
12.1 General
All materials used and practices followed in the execution of the works, if not specified or described in the
specification or the drawings or the contract sum, shall comply with the relevant Australian Standards.
Where the edition of any Australian Standard or other standard referred to in the specification or relevant in
accordance with Clause 12.1 above is not stated in the specification, the edition current at the time of Contract award
shall apply.
Standard of Work
All works to be in full compliance with the following -
Current National Construction Code
Current Australian Standards
Principal: LAHC
Scope of works Site: 31-37 Carr Street Towradgi
Job no: 1617_1710
ABN: 19 128 617 774, Lic No 232745c REV: 0 Page: Page 9 of 55
Unless otherwise specified the Sub-contractor shall give VMG not less than one working days’ notice of its intention to
commence each of the following operations:
clearing
excavation of trenches
backfilling trenches
Erecting steelwork.
If the Sub-contractor does not give the notice specified by this Clause any work covered up or made inaccessible by
the work for which the notice was required shall be deemed to be work covered up or made inaccessible without a
required prior approval by the PC.
No PC supplied materials.
15. Specifications
The specifications applicable to this Scope of works are listed in this SOW, in the Contract Documents and any other
documents forming part of the Contract.
Any cross references to additional specifications listed within the specifications listed above shall also be applicable to
this SOW.
Principal: LAHC
Scope of works Site: 31-37 Carr Street Towradgi
Job no: 1617_1710
ABN: 19 128 617 774, Lic No 232745c REV: 0 Page: Page 10 of 55
The Sub-contractor shall provide drawings in hardcopy (two copies in A3 format), and as an editable electronic file,
inclusive of all survey data collected for the project. Submission of all “as constructed” drawings and survey data is a
pre-requisite to the issue of a certificate of Practical Completion.
Commercial Terms
th
Terms of Payment: Invoices are to be submitted on the 25 of each month, forecasted to the end of the month. Invoices will be
paid of the next month or the next working day after
Retention will be held at 10% of the progress claim until a maximum of 5% of the contract total is reached including variations.
Upon completion 2.5%, will be retained for the project defect liability period. During this period, the subcontractor will be required
to repair any defects at no extra charge to VMG or the principal
Defects Liability period: 52 weeks from project date of practical completion
The subcontractor indemnifies VMG against all claims, actions and loss or damage and all other liability arising out of any acts or
omissions of the Subcontractor
The subcontractor shall not sub-let or assign all or any part of the works without prior written consent of VMG. Any variation to the
Works (“the varied works”) shall be executed or omitted by the subcontractor only after written instructions from VMG. VMG is not
liable to the subcontractor for the cost of varied works unless VMG has given written instructions for the varied works together with
an agreed amount prior to the varied works being carried out.
Principal: LAHC
Scope of works Site: 31-37 Carr Street Towradgi
Job no: 1617_1710
ABN: 19 128 617 774, Lic No 232745c REV: 0 Page: Page 11 of 55
Payment statutory declaration forms to be signed and evidence of superannuation contribution and redundancy funds are required
prior to payments being made.
The subcontractor is to allow for all the necessary insurances
The subcontractor will adhere to the Principals and PC’s safety and reporting requirements. The PC’s requirements are
generally in accordance with the Principals requirements. The safety system will be a behavioural based safety system
that requires the sub-contractor to provide observations and inspections of the works and provide lead indicators for
the works and not just lag indicators.
Contract Documentation
Architectural Drawings Type Drawing no. Revision Date
Principal: LAHC
Scope of works Site: 31-37 Carr Street Towradgi
Job no: 1617_1710
ABN: 19 128 617 774, Lic No 232745c REV: 0 Page: Page 12 of 55
Specifications