Dca20072 Practical - Levelling
Dca20072 Practical - Levelling
Instrument
Data Adjustment
(Include Sketches &Plotting)
Timeliness
Conclusion
Total CA Marks
(100%)
2. Display the ability to perform field work by using level, theodolite and electronic total station for
survey computation with appropriate procedures and measurements.
Teaching BLOOM’S
No. Lab.Title PLO CLO
Method TAXO.
2.3 Display the concept of
contouring
Levelling is involved with the use of a (usually) optical level to determine elevations. We do
this by starting from a point of known elevation (a benchmark), and proceeding to calculate
differences in elevation, until we get to another point of known elevation (often the original
benchmark). We can then calculate whether any errors (miss closure) exists in our measurements. If
the miss closure is small, we can distribute the error over all our measurements.
INSTRUMENTS
1. LEVEL
3. STAFF LEVEL AND STAFF
BUBBLE 3. MEASUREMENT TAPE
6. ARROW SURVEY
******REMINDER :
DAMAGE AND LOSS OF THE EQUIPMENT IS STUDENT RESPONSIBILITY.
1. Never place the instrument in its case when wet.
2. Check the accuracy each time before using the instrument, as we cannot assume any
responsibility for ANY errors and DAMAGED.
3. Follow the instructions for handling the batteries.
4. Treat the instrument with care.
Field Work : Contour using grid method
OBJECTIVE :
20m
5m
5m
5m
1. Perform the site survey to determine area work and observation data. Then plan the position
point (Refer Figure 7)
a3 b3 c3 d3 e3
b2 c2 d2 e2
a2
a1 b1 c1 d1 e1
BS
BM/TBM
STATION 1 STATION 2
2. Set-up a level at point of station 1 and perform temporary adjustment .(Refer Figure 8)
3. Set-up staff on BM/TBM as back sight (BS) and at point a1 until point c2 as intermediate sight
(IS). c3 as a Fore sight (FS). Take and record the reading.
4. After that, move a level to station 2 and set-up it. Make sure the staff is still at point c3 as a back
sight (BS) and the other staff move to point d1 until point e3 as a intermediate sight (IS). Take and
record the reading.
6. During the process, make sure the bubble of staff and a level always centre.
RESULT:
(Booking and adjustment using following table)
Adjustment
Reduce
BS IS FS Rise (+) Fall (-) Adjustment Reduce Remarks
Level
Level
1. Introduction - 5%
2. Objective - 5%
3. Instrument - 5%
4. Procedure - 20%
5. Required Data & Observation - 20%
6. Data Adjustment (include sketches &Plotting - 20%
7. Conclusion - 20%
8. Timeliness - 5%
Total - 100%