SPECIFICATIONS Final
SPECIFICATIONS Final
24. Overhead water tank stand upto 4‘ht will be provided if required.
25. First floor hall pop & ground floor hall pop flower & cornice will be done
PAYMENT TERMS:
1. Advance before starting of work---------------15%
2. Plinth level completion---------------------------15%
3. Ground floor slab----------------------------------10%
4. First floor slab---------------------------------------10%
5. Tower floor slab------------------------------------5%
6. Plastering--------------------------------------------10%
7. Flooring work completion-----------------------10%
8. Putty Work Finishing------------------------------10%
9. Doors fitting completion-------------------------10%
10. At Possession---------------------------------------05%
MODE OF MEASUREMENT:
1. All R.C.C roof slabs should be measured outer to outer after finishing of plaster
work.
2. Stair case towers should be measured.
3. Sloping roof should be measured along the length of slope.
4. All hangings should be measured in the same rate.
5. Any enclosed duct in roof slab of either size or any shape should not be deducted
from the measurement on each floor level height.
6. Service tax will be levied as per norms.
COST OF CONSTRUCTION:
As per the above clauses the final cost of construction comes out to be Rs.1275/sqft which
is strictly adhering to the terms above.