Final Paper Chapter 1 4 But Need To Edit
Final Paper Chapter 1 4 But Need To Edit
College of Engineering
Electrical Engineering Department
Designed by
DE CASTRO, GABRIEL I.
DEDICATORIA, MICHAEL ANGELO O.
DUMAGUIN, MIKE DEXTER H.
BSEE
Submitted to
September, 2021
POWER SYSTEM DESIGN
SURIGAO DEL NORTE
A
Design Project
Presented to
The Faculty of the Electrical Engineering Department
NATIONAL UNIVERSITY
In Partial Fulfillment
of the Requirement for the Degree of
Bachelor of Science in Electrical Engineering
By
DE CASTRO, GABRIEL I.
DEDICATORIA, MICHAEL ANGELO O.
DUMAGUIN, MIKE DEXTER H.
April 2021
ii
Preface
As part of BSEE program curriculum and in order to gain knowledge on designing a power system of a
city/town. The researchers conduct this research study to be able to practices the knowledge in mathematics, sciences
and engineering sciences. The main objective behind doing this design project is to be able to determine on how to
improve some of the power system here in Philippines specifically the Surigao Del Norte Electric Cooperative Power
System.
In addition, in this paper, the proponents included the new improved single line diagram of the SURENECO
Looc substation. The specification new improved system that has been installed and the analysis of system such as
system modeling, load flow analysis, and short circuit analysis.
iii
Acknowledgement
The proponent would like to express their sincere gratitude and appreciation to the following who helped
them to make this study possible:
First and foremost, to almighty God, for giving the strength, wisdom, courage, perseverance, and patience
which needed in performing this project.
To Engr. Christian Pao our professor, who instilled the knowledge of Power System Design. He taught us the
important factors that need to be consider on designing a power system.
To Engr. Dave Henson, our professor in Power System Analysis and Design Lecture, who taught us the
fundamentals of power system and short circuit computation.
To our Beloved De Castro, Dedicatoria, and Dumaguin Families for all the support that they gave to us.
Lastly, to all our classmates whom we asked whenever I'm in doubt of the design.
- The Researchers
Table of Contents
iv
Title Page………………………………………………………………………………………………………………...i
Proposal Page ………………...…………………………………………………………………………………………ii
Preface.....................................................................................................................................................................iii
Acknowledgement...................................................................................................................................................iv
Chapter 1..................................................................................................................................................................1
Introduction................................................................................................................................................................1
Chapter II..................................................................................................................................................................2
Targeted Area (Surigao Del Norte)..............................................................................................................................2
Specification of the Proposed System to be Installed.................................................................................................2
Existing single line diagram and the New Modified Single Line Diagram of the SURENECO.......................................3
The Reason Why the Proponents add a 11.22 MW Diesel Power Plant to SURENECO Power System.......................5
Power Interruption.................................................................................................................................................5
Inconvenience Loss Due to Power Outage..............................................................................................................5
New business registrations recorded......................................................................................................................6
Chapter III.................................................................................................................................................................7
Chapter IV.................................................................................................................................................................8
Appendices...............................................................................................................................................................9
RESEARCHERS’ PROFILE..........................................................................................................................................11
v
Chapter 1
This chapter presents the introduction of the study, the fundamentals of the power system, and the brief
description of the proposed project.
Introduction
Power system is a network which consists of three (3) parts - generation, transmission, and distribution.
Generation is the process of producing electricity from sources of primary energy such as coal, nuclear, biomass,
geothermal, solar, etc. Generator is the device that converts mechanical energy to electrical energy. Transmission is
the bulk movement of electrical energy from a generating site, such as power plant, to an electrical substation. It is
composed of interconnected lines which facilitates this movement. These interconnected lines are known as
transmission network. Distribution, which is the final stage in the delivery of electric power, is the delivery of
electricity to consumers. Power system consists of six main components - power plant, transformer, transmission line,
substations, distribution line, and distribution transformer. Power plant is the industrial facility where the electric
power is generated. This is where the generation of electricity takes place. Transformer is an electrical device which
steps down or up the voltage. Transmission line is a cable used for the transmission of electrical power. Substation is a
facility where voltage transformation takes place. It consists of high voltage electrical equipment such as
transformers, switch gear, and circuit breakers. Distribution line is a line or system for distributing power from a
transmission system to consumers. Finally, distribution transformer provides the final voltage transformation in the
electric power distribution system, stepping down the voltage used in the distribution lines to the level used by
consumers.
Power system design encompasses different aspects of power system such as safety, reliability, simplicity,
maintenance, flexibility, costs, voltages, protection, fault calculations, grounding, power factor control and effects,
switching and voltage transformation, instruments and meters, cable constructions and turnkey installation.
This project is a design of power system of Surigao Del Norte Electric Cooperative where a 11.22 MW power
plant is installed. It discusses the important factors that must be considered in power plant installation. In addition, it
specifies the different electrical devices to be used such as generator and its exciter, current transformers, potential
transformers, among others. Finally, it shows the calculation of short circuit when a three-phase fault occurs.
1
Chapter II
This Chapter presents the technical specifications of the project, the targeted area, and the specification of the
systems existing and to be installed.
Technical Specifications
In this section it discussed the Technical Specification of the proposed power plant project that will be
connected to SURNECO Looc substation to be expected arise in Pan-Philippine Highway, Barangay Quezon in
Surigao Del Norte. The following technical specification parameters of the proposed project can be found below. It
also discussed the reason why it needs to install a 11.22 MW Diesel Power Plant on the target area.
On September 9, 1980, SURNECO's first energization ceremony was organized and conducted at the Imelda
Village/ Kaskag Terminal in Surigao City and on period covering from December 1980 to December 1981, the eleven
(11) municipalities are electrified by SURNECO. In year 2006, a total of 203 barangays with a percentage rate of
100% are also successfully energized.
There are roughly 57,728 household or 99% of the total potential residential connections of 58,543 with a
total registered membership of 57,629 or 99% of potential members of 58,163 and billed consumers of 55,280, this
data above-mentioned is as of December 31, 2010.
2
Figure 2. Location of Proposed Project Diesel Power Plant
The proposed project involves a 7.313-kilometer 69 kV line. The said line will start from the Power Plant site
in Barangay Quezon, Surigao City, Surigao del Norte, which will connect to SURNECO’s distribution system through
SURNECO’S Looc Substation, which will serve as the connection point.
The line uses a MCM ACSR conductors on 75-foot height steel poles, with the conductors arranged in a
vertical configuration. Furthermore, the gantry structure at the connection point, is an eight-legged I-beam steel
structure with two-levels of I-beam cross members. The said structure is where the disconnect switches, potential
transformers, current transformers, surge arresters, insulators, revenue metering, and other electrical components for
the line protection are installed.
Existing single line diagram and the New Modified Single Line Diagram of the SURENECO
The diagram displays the asset boundary between the TRANSCO/NGCP and SURNECO. As shown in figure
3, the 69 kV Bus of the Looc Substation, where the Power Plant is connected, is a distribution asset owned by
3
SURNECO. The asset boundary of SURNECO and TRANSCO/NGCP is between the said 69 kV Bus and the
Pacemco-Surigao 69 kV line of TRANSCO. Furthermore, the revenue meter of NGCP is at the asset boundary which
is beyond the 69 kV Bus the distribution assts of SURNECO. For this reason, it is sure that the subject facility of
proposed project is linked to the distribution network of SURNECO.
Figure 4. Propose Connection of a 11.22 MW Diesel Power Plant to the SURENECO Looc Substation.
However, Figure 4 shows the connection of the propose 11.22 MW Diesel Power Plant to the SURENECO.
As shown above the connection point of the proposed power supply system will be tap at the 20MVA SURENECO
Looc Substation. The system has a 7.31km and a 69kV transmission system and an 15MVA substation. In addition,
the proponents add an 10MVA additional load to the feeder of the Looc substation. While on the NGCP side since the
existing SLD does not have a rating the researchers decided to assume a 25MVA transformer connect by a 50MVA
generator and a 10MVA load. The purpose of the 10MVA load at the NGCP placer side is to serve as a backup load.
So that when the Looc substation fail the generated power by the proposed powerplant will still have supply load
which is the 10MVA load at the NGCP side.
4
The Reason Why the Proponents add a 11.22 MW Diesel Power Plant to SURENECO Power System
The reasons why it needs to add a 11.22 MW diesel power plant because of the following basis: Power
Interruption, Inconvenience Loss Due to Power Outage, and New Business Registration Recorded.
Power Interruption
For so many years, residents have been experiencing long power outages almost every month due to
maintenance work. Example for this is, “Residents in Surigao del Norte and parts of Surigao del Sur are
bracing for a 12-hour power outage Sunday (January 28,) due to maintenance work”. This has been a monthly
predicament for power consumers in the area (Catato R, 2018). Said the outage will affect their entire
franchise area covering Surigao City and 11 towns of Surigao del Norte.
Also, until now there is a several media reports and NGCP post on Facebook advisory that it will have
rotational power on Surigao Del North. Still the purpose is maintenance activities at NGCP Placer Substation
and replacement of transmission line hardware and accessories
5
Figure 5. New Business Registrations, Caraga Region
Chapter
III
Design Analysis
This chapter
System Modelling
6
Figure ??. Single-line Diagram of the Proposed System with its Corresponding Values
230 kV 2
Zactual = = 126.96 Ω
37.5 MVA
Zactual = 105.8∠cos-1(0.8) = (101.568 + j76.176) Ω
101.568+ j 76.176
Zpu = 69 kV 2 = (0.96 + j 0.72) pu
( 45 MVA )
37.5∠cos−1 (0.8) MVA
Spu = = (0.666 + j0.5) pu
45 MVA
Transformer 1:
69 kV
Vbase = 13.8kV ( 13.8 kV )
= 69kV
20 MVA
Spu = = 0.444 pu
45 MVA
2
( j 0.10 ) 69 kV
( ) = j0.18 pu
25 MVA
Zpu =
69 kV 2
( 45 MVA )
Transmission Line 1:
Vbase = 69kV
Zactual = (0.3970 + j 0.4923) x 1.83km = (0.72651+ j0.9009) Ω
0.7265+ j 0.9009
Zpu = 69 kV 2 = (0.0068 + j0.0085) pu
( 45 MVA )
Transformer 2:
20 MVA
Spu = = 0.444 pu
45 MVA
2
( j 0.05 ) 13.8 kV
( ) = j0.1125 pu
20 MVA
Zpu =
13.8 kV 2
( 45 MVA )
8
Load 2:
Vbase = 13.8kV
20 MW
Sactual = = 25MVA
0.8
13.8 kV 2
Zactual = = 7.6176 Ω
25 MVA
Zactual = 12.696∠cos-1(0.8) = (6.094+ j4.570) Ω
6.094+ j 4.570
Zpu = 13.8 kV 2 = (2.4 + j 1.8) pu
( 45 MVA )
25∠ cos−1 (0.8) MVA
Spu = = (0.444 + j0.333) pu
45 MVA
Transmission Line 2:
Vbase = 69kV
Zactual = (0.3970 + j 0.4923) x 7.313km = (2.903261+ j3.600) Ω
2.903+ j 3.6
Zpu = 69 kV 2
( 45 MVA ) = (0.027 + j0.034) pu
Transformer 3:
69 kV
Vbase = 13.8kV ( 13.8 kV )
= 69kV
15 MVA
Spu = = 0.333 pu
45 MVA
2
( j 0.10 ) 13.8 kV
( ) = j0.3 pu
15 MVA
Zpu =
13.8 kV 2
( 45 MVA )
Generator 2:
Vbase = 13.8kV
13.8 kV
Vpu = = 1.0 pu
13.8 kV
11.2MVA
Spu = = 0.2488 pu
45 MVA
9
2
( j 0.128 ) 13.8 kV
( ) = j0.514 pu
11.2 MVA
Zpu =
13.8 kV 2
( 45 MVA )
10
Figure ?? . Impedance Circuit of the Proposed Power System
11
Bus 2, 3, 5– PQ Bus
Y 11 Y 12 Y 13 Y 14 Y 15 Y 16
[ ]
Y 21 Y 22 Y 23 Y 24 Y 25 Y 26
Y 31 Y 32 Y 33 Y 34 Y 35 Y 36
Y 41 Y 42 Y 43 Y 44 Y 45 Y 46
Y 51 Y 52 Y 53 Y 54 Y 55 Y 56
Y 61 Y 62 Y 63 Y 64 Y 65 Y 66
For Bus 1:
1
Y11 = = - j5.555 pu
j 0.18
−1
Y12 = = j5.55 pu
j 0.18
Y13 ~ Y16 = 0
For Bus 2:
−1
Y21 = = j5.555 pu
j 0.18
1 1
Y22 = + = (57.38 – j77.29) pu
0.0068+ j 0.0085 j0.18
−1
Y23 = = (-57.38 + j71.73) pu
0.0068+ j 0.0085
Y24 ~ Y25 ~Y26 = 0
For Bus 3:
Y31 = Y36 = 0
12
−1
Y32 = = (-57.38 + j71.73) pu
0.0068+ j 0.0085
1 1 1
Y33 = + + = (71.71 – j98.66) pu
0.0068+ j 0.0085 j 0.1125 0.027+ j 0.034
−1
Y34 = = (j8.88) pu
j 0.1125
−1
Y35 = = (-14.32 + j18.03) pu
0.027+ j0.034
For Bus 4:
Y41 = Y42 = Y45 = Y46 = 0
−1
Y43 = = j8.88 pu
j 0.1125
1
Y44 = = -j8.888pu
j 0.1125
For Bus 5:
Y51 = Y52 = Y54 = 0
−1
Y53 = = (-14.32 + j18.03) pu
0.027+ j0.034
1 1
Y55 = + = (14.32 – j21.37) pu
0.027+ j0.034 j 0.3
−1
Y56 = = j3.333 pu
j 0.3
For Bus 6:
Y61 = Y62 = Y63 = Y64 = 0
−1
Y65 = = j3.33 pu
j 0.3
1
Y66 = = –j3.333 pu
j 0.3
13
Admittance Matrix
[ 11 2
− j5.555
3 4 5 6
j5.555 0 0 ¿
0 ¿ 2 ¿ j5.555 ¿ 57.38 – j77.29 ¿−57.38+ j71.73 ¿ 0 ¿ 0 ¿ 0 ¿ 3 ¿ 0 ¿−57.38+ j71.73 ¿ 71.7
1
V 3( 1 ) = ¿
Y 33
1 0
V 3( 1 ) =
71.71−98.66 j 1 [ ]
− (−57.38+71.73 j )( 1 ) −(−8.888 j ) ( 1 )−(−14.21+18.03 j ) (1 ) =1.002230−0.001722 j
1
V 5( 1 ) = ¿
Y 55
1 0
V 5( 1 ) =
14.21−21.37 j 1 [ ]
−(−14.32+18.03 j ) ( 1.003568−0.0027551 j ) −(−3.333 j )( 1 ) =1.003156−0.002049 j
1
V 6( 1 ) = ¿
Y 66
1 0.2488
V 6( 1 ) =
−3.333 j 1 [ ]
−( 3.333 j ) ( 1.005050−0.003278 j ) =1.005050+0.071369 j
15
Iteration 2:
Qg1(2) = -Im[(V1(1)*)(Y11V1(1) + Y12V2(1))]
Qg1(2) = -Im[ ( 1.09000+0.07992 j ) [(− j5.555)(1.09000+0.07992 j)+( j5.555)(1.00349+0.005391 j)] ]
Qg1(2) = -.00179
1
V 1( 2 ) = ¿
Y 11
1 0.4444+ j .00179
V 1( 2 ) = [
− j5.555 0.993809+0.111094 j
−( j5.555)(1.005588+0.0086261 j) =1.085840+ 0.098023 j ]
V 1 acc (2)=V (1) ( 2) ( 1)
1corr + α ( V 1 −V 1 corr ) =1.144014+0.127884 j+1.6 ( 1.085840+0.098023 j−1.144014+ 0.127884 j ) =1
= 1.005936+0.001147j
1.006144-0.003340j
1
V 3( 2 ) = ¿
Y 33
1 0
V 3( 2 ) = [
71.71−98.66 j 1.003568−0.002755 j
−(−57.38+71.73 j ) ( 1.003568−0.002755 j ) −( 8.888 j )( 1.04 )−(−
1
V 5( 2 ) = ¿
Y 55
16
1 0
V 5( 2 ) = [
14.32−21/37 j 1.005050−0.003278 j
−(−14.32+ 18.03 j )( 1.007441−0.005144 j )−(−3.333 j )( 0.9936
1
V 6( 2 ) = ¿
Y 66
1 0.2488+0.0056 J
V 6( 1 ) = [
−3.333 j 0.993645+0.112555 j ]
− ( 3.333 j )( 1.019720+0.015843 j ) =1.009623+0.089824 j
17
Figure ??. Bus Voltages Converges at Iteration 9
1
Power Flow Analysiss
2nd Iteration
1
Short Circuit Analysis
2
Chapter IV
3
Appendices
4
List of References
Catoto, R. (2018, January 27). Surigao Norte residents brace for 12-HOUR power OUTAGE Sunday.
MindaNews. Retrieved September 14, 2021, from https://www.mindanews.com/top-
stories/2018/01/surigao-norte-residents-brace-for-12-hour-power-outage-sunday/.
Coorporation, C. (2017, February). Study on Wind Power Energy Generation Project in Caraga Region of
the island of Mindanao, Republic of the Philippines. Meti.go.jp. Retrieved September 24, 2021, from
https://www.meti.go.jp/meti_lib/report/H28FY/000014.pdf.
Garciano, L. E. (2021). Assessing vulnerabilities and costs of power outages to extreme floods in Surigao
City, Philippines. International Journal of GEOMATE, 20(82). https://doi.org/10.21660/2021.82.6308
Marcos, D. D. (2018, December). Hikdop Island In Surigao Gets 24-Hour Electricity. National Power
Corporation. Retrieved September 24, 2021, from
https://www.napocor.gov.ph/index.php/news/archived-news/503-hikdop-island-in-surigao-gets-24-
hour-electricity.
San Miguel Avenue, Pasig City , & Devanadera, A., ERC Case No. 2017-00513–16 (2019). Pasig City,
Philippines; ERC.
User, S. (2016). Brief history of Surneco. SURNECO, INC. Retrieved September 24, 2021, from
http://www.surneco.com.ph/index.php/pages/brief-history.
5
RESEARCHERS’ PROFILE
PERSONAL DATA:
EDUCATIONAL BACKGROUND:
ORGANIZATION:
6
DE CASTRO GABRIEL I.
Address: 188 A. Palon Street Barangay 75, Caloocan City
Contact #: 09153138498
Email Address: [email protected]
PERSONAL DATA:
EDUCATIONAL BACKGROUND:
ORGANIZATION:
7
DUMAGUIN, MIKE DEXTER G.
Address: B3 L2 Sarao Compound. Santos
Drive Zapote, Las Pinas City
Contact #: 09357653164
Email Address: [email protected]
PERSONAL DATA:
EDUCATIONAL BACKGROUND:
ORGANIZATION: