SNOC CM MOP 3G NodeB Rehoming Via TransferSiteTool ZTE v1.0

This document provides a method of procedure for 3G BTS rehoming using the TransferSite tool in ZTE BSCs. It outlines the pre-requisites, pre-execution checks, detailed job description, impact on service, and step-by-step procedures for rehoming 3G BTS sites between BSCs. The process involves exporting radio and ground data from the source and destination BSCs, importing site migration files, configuring neighboring cells and targets, and activating the plan in a scheduled outage window while monitoring for errors or issues. The rehoming impacts service with a major outage of approximately 60 minutes duration.

Uploaded by

Mohammad Aslam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views

SNOC CM MOP 3G NodeB Rehoming Via TransferSiteTool ZTE v1.0

This document provides a method of procedure for 3G BTS rehoming using the TransferSite tool in ZTE BSCs. It outlines the pre-requisites, pre-execution checks, detailed job description, impact on service, and step-by-step procedures for rehoming 3G BTS sites between BSCs. The process involves exporting radio and ground data from the source and destination BSCs, importing site migration files, configuring neighboring cells and targets, and activating the plan in a scheduled outage window while monitoring for errors or issues. The rehoming impacts service with a major outage of approximately 60 minutes duration.

Uploaded by

Mohammad Aslam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 25

VIL/SNOC/MOP/2019/3G BTS_Rehoming_ZTE_v1.

0 C2 VIL INTERNAL P a g e | 0

VODAFONE IDEA LIMITED

3G BTS rehoming Via TransferSite Tool

Method of Procedure (Mop) v1.0

Document Details:
Domain
Document No. Document Title Author
Owner

VIL/SNOC/MOP/2019/ 3G BTS SNOC CHM ZTE BSS- 3G BTS


Prakhar Sharma Sumit Nangia
rehoming Via TransferSite Tool rehoming Via TransferSite Tool

Reviewers:
Reviewed
Name Version Approved Position
Date

Nilesh Amte, Suraj Sinha 1.0 SNOC-Change Management Head

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 0


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 1

Sumit Nangia Lead - Mobility

Abhijit Ray RAN Lead

Approvers:
Name Version Approved Position Approval Date

Vinay Tyagi 1.0 SNOC Head

Distribution List:
Name/Position / Available at Published Date

SNOC, Circle BSS team , Corporate team

Next Review*:
Next Review Date Domain Owner

Sumit Nangia
*Document should be reviewed once every quarter or whenever there is a major change, whichever is earlier. For
Feedback/Suggestions please drop a mail to: [email protected]

Contents

1. Purpose of Document.....................................................................................................................4

2. Objective.........................................................................................................................................4

3. Scope...............................................................................................................................................4

4. Resources........................................................................................................................................4

5. 2G BTS Rehoming.........................................................................................................................4

5.1 Pre-requisites..................................................................................................................................4

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 1


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 2

5.2 Pre execution checks......................................................................................................................5

5.3 Detailed Job Description...............................................................................................................5

5.4 Impact on Service...........................................................................................................................5

5.5 Detailed Step by Step Procedures.................................................................................................5

5.6 Roll Back Plan..............................................................................................................................11

5.7 Activity Process and Time Line..................................................................................................11

5.8 Post Execution Checks.................................................................................................................12

5.9 Performance
Monitoring………………………………………………………………………………..............................
..............12

1. Purpose of Document

This technical document covers the activity of 3G BTS rehoming Via TransferSite Tool in the BSC’s for
Circles. The purpose of this document is to describe the actions needed for 3G BTS rehoming Via TransferSite
Tool of 3G sites in ZTE BSC’s.

2. Objective
The objective of this MOP is to provide the user as to how to perform 3G BTS rehoming Via TransferSite Tool
in BSCs.

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 2


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 3

3. Scope
 The scope of this process document is to present the process 3G BTS rehoming Via TransferSite Tool
in BSCs, which is to be observed by SNOC, for ZTE based circles and Corporate Team.
 This process is for VIL Managed Circles Only.

4. Resources

 NetNumens & ICM Applications via SRAS.


 BSS Engineer should be technically equipped for BSC activity.
 SPOC’s details ( Circle & SNOC)

5. 3G BTS Sites Rehoming

5.1 Pre-requisites

 Pre Validation of Plan in day time. (SNOC Responsibility).


 BSC should be in healthy condition. If any critical/major alarms reported same shall be escalated to
INM/Circle team immediately for rectification
 CR needs to be approved from all concern before 17::00 hrs.
 Activity Owners should be technically equipped to perform the activity.
 All changes should be done through SRAS.
 CR data should be as per attached format.( Get rehoming plan xml one day advance from RF team )

NodeB Rehoming
Template.xlsx

5.2 Pre execution checks.


 Take a Pre check in day time.

 If any critical/major alarms reported, shall be escalated to INM/Circle team immediately for
rectification before activity.
 Coordinate with all involved team (NSS Core, CEN Transmission, BSS, and RF) for their readiness.
 Take Backup

Export RNC Radio and Ground Data form Live Data Area
Select Source and Destination RNC
And Export all Radio & Unioffice Raw Data from Source & Destination RNC
Similarly as you have Done In BSC.

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 3


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 4

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 4


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 5

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 5


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 6

Export UMTS data as well as pre dump and for execution.

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 6


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 7

Checking pre-status of sites via status management.

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 7


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 8

After checking status check current alarm of planned sites in respective RNC. if sites is found down
exclude from the plan or either try validation after site restoration. Also take pre alarm of OMMB before
validation plan

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 8


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 9

5.3 Detailed Job Description


 3G sites rehoming is the process of doing migration of site connectivity from one RNC to another
RNC .
 The 3G sites rehoming plan is done with the help of tools like ICM via Netnemus and activating the
plan.
 The process is done by loading the data in background in the RNC and activating in the outage
Windows.
 Post Migration SON end configuration file need to be update.

5.4 Impact on Service


 Outage Involved: Yes
 Outage Severity: Major
 Outage Severity in case of fallback: Total
 Outage Time & Duration: 60 mins

5.5 Detailed step-by-step procedures

Site Transfer Using ICM-Table of Contents

 Create Plan Area


 Export RNC Radio and Ground Data form Live Data Area
 Site Migration Sheet
 Export Uni Office Plan
 Import Uni Office Plan
 Import the files generated in Step
 Source _ Neighboring Cell
 Dest _ Cell
 Dest _ Target
 Deletion Script for Source BSC
 ICM Check, Conflict, Validity and Activation procedure

Create Plan Area

Right Click on Data Area and select Create Plan Area Fill User label and select Source and Destination BSC/RNC
and Select Ok.
Note: Below Snapshot Showing BSC Similarly You Can Do with RNC so Don’t Get Confused.

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 9


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 10

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 10


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 11

Site Migration Sheet


It Include 2 Sheets
1) RNC Radio Sheet
2) UniOffice(Transmission) Sheet.

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 11


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 12

1) RNC Radio Sheet will be like

Template is attached
It this template You Have to Give Source & Destination Cell ID & NodeB name.
Kindly Refer Attached Sheet While Preparing Script.

UMTS_SiteTransferT
emplate_Plan_en_620to621.xlsx

5.3 Detailed step-by-step procedures


2) UniOffice(Transmission) Sheet .

Unioffice Template will be same as you Export from RNC. But you have to prepare Unioffice Template for
Destination RNC.

Reference Unioffice Template Attached Hare.

Kindly Refer Attached Sheet While preparing Destination Unioffice Script.

MEID_TX_621_UNI_
OFFICE.xlsx

After Preparing Both Script Import Script in TransferSite Tool

Right click on Plane Area which you Prepared Above

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 12


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 13

After Clicking to TransferSite Option popup Window Will Appear Like Below

Select GU-OMMR Online Option then

Add your RNC Radio Sheet in Transfer Site Template

And Unioffice Template in Dest office Plane Data and Then Click on Execute

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 13


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 14

After 100% Completion then you have to Go for Check option

Then click on Conflict check & click on Start

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 14


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 15

Similarly Then Click on Validity Check & click Start then Submit Task for Plane Activation process

Automatic Plane Activation Window Will be open then

Then Compare then Download it After That Activate the Plane

NOTE: Always Activate Destination RNC Script First because if you activate Source RNC Script First then it
will delete Cell from Source RNC then you Can’t Transfer cell from Source to Destination RNC.

After Activation Destination Script First it will Transfer Cell from Source RNC to Destination RNC

Then Activate Source Script to Delete Cells in Source RNC because it Show two Similar Cells in Network.

Note :It will also transfer Neighbors between Source & Destination RNC but it will not transfer Neighbor of
Other RNC.

So Create or Modify Neighbor of Other RNC after Migration.

After activation and site creation via ICM we need to change site end Abis IP (If ABIS IP plan change) and
SCTP IP as well via OMMB in maintenance window.

First we will export public dump from respective OMMB

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 15


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 16

After exporting public dump we will modified SCTP IP in SCTP tab.

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 16


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 17

Then further import the same as planning import tab and share directory location for result as well.

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 17


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 18

NOTE: kindly select UMTS for 3G migration so don’t get confused its same process as 2G migration

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 18


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 19

While synchronizing multiple sites via ommb kindly click on check parameter before sync as shown in snap.

Only synchronize modified data not all data.

NOTE: SCTP IP need to modify in Maintenance window.

After OMMB sync process kindly check post services alarm

1. BSC ALARM STATUS


2. OMMB ALARM STATUS
3. BSC STATUS Management of BTS

After successful rehoming put the sites in testing mode in source BSC and delete the database after DT
confirmation from circle end.

For testing mode go through maintain status query and setting as in snap

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 19


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 20

Export current data status

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 20


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 21

After exporting put testing on planned sites as shown

Then import as well for same

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 21


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 22

Now all sites will be in testing mode.

During Maintenance window follow below steps:

 Put in Testing mode to NodeB in old RNC


 Run the Site end IP change plan (Check 3G SCTP status of migrated site)
 Activate the site in New RNC
 Check the cell STATUS at New RNC
 Run Neighbour plan which available in your Migration project
 Communicate to core Team regarding Lac changes
 Do the Drive Test for migrated site without fail
 After RF KPI verification, Run the Old site deletion plan

5.6 Roll Back Plan


 In case of Roll back the above plan is activated with changed parameter values( i.e.
change the values to previously present)
 Roll out should be completed before maintenance window i.e. 05:00
 Roll back plan should be decided/activated before 03:30 am.

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 22


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 23

5.7 Activity Process and Time Line

Sr
Execution Outage Time Duartion for Activity in
No Activity Process
Time Inv mins
.
Checking CR if all required data
1 Day No 30
provided
2 Validation of plan in day time Day No 50

3 Activating the plan Night Yes 40

5 Post check Night No 30


6 For Roll Back Night Yes 40

5.8 Post execution checks

SNOC 2G eGBTS Rehoming Post-checks

S.
Points need to be checked Status Remarks
No.
         
1 Verification of all parameters with RF planning sheet      
         
2 Cross check all cell services and ensure no alarm in network      
         
3 Ensure Voice & Data call testing done by BSS/RF engineer      
         

5.9 PERFORMANCE MONITORING


After Rehome the sites,, performance monitoring is carried out for 06:00 hrs and 07:00 hrs in comparison to the
previous day’s same period to check any abnormalities in KPI. KPIs monitored are:

SDCC EDGE DL TBF Handover_


TCH_D SD_Dro TCH_ Total_
H_Bloc Total_ Average Complet Success_
ROP_R p_SPT_ Blockin Traffi
king_R Payload Thruput ion Rate_Voice
ATE 1 g_Rate c
ate per RTSL Success >50Calls

VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 23


VIL/SNOC/MOP/2019/2G BTS_Rehoming_ZTE_v1.0 C2 VIL INTERNAL P a g e | 24