SNOC CM MOP 3G NodeB Rehoming Via TransferSiteTool ZTE v1.0
SNOC CM MOP 3G NodeB Rehoming Via TransferSiteTool ZTE v1.0
0 C2 VIL INTERNAL P a g e | 0
Document Details:
Domain
Document No. Document Title Author
Owner
Reviewers:
Reviewed
Name Version Approved Position
Date
Approvers:
Name Version Approved Position Approval Date
Distribution List:
Name/Position / Available at Published Date
Next Review*:
Next Review Date Domain Owner
Sumit Nangia
*Document should be reviewed once every quarter or whenever there is a major change, whichever is earlier. For
Feedback/Suggestions please drop a mail to: [email protected]
Contents
1. Purpose of Document.....................................................................................................................4
2. Objective.........................................................................................................................................4
3. Scope...............................................................................................................................................4
4. Resources........................................................................................................................................4
5. 2G BTS Rehoming.........................................................................................................................4
5.1 Pre-requisites..................................................................................................................................4
5.9 Performance
Monitoring………………………………………………………………………………..............................
..............12
1. Purpose of Document
This technical document covers the activity of 3G BTS rehoming Via TransferSite Tool in the BSC’s for
Circles. The purpose of this document is to describe the actions needed for 3G BTS rehoming Via TransferSite
Tool of 3G sites in ZTE BSC’s.
2. Objective
The objective of this MOP is to provide the user as to how to perform 3G BTS rehoming Via TransferSite Tool
in BSCs.
3. Scope
The scope of this process document is to present the process 3G BTS rehoming Via TransferSite Tool
in BSCs, which is to be observed by SNOC, for ZTE based circles and Corporate Team.
This process is for VIL Managed Circles Only.
4. Resources
5.1 Pre-requisites
NodeB Rehoming
Template.xlsx
If any critical/major alarms reported, shall be escalated to INM/Circle team immediately for
rectification before activity.
Coordinate with all involved team (NSS Core, CEN Transmission, BSS, and RF) for their readiness.
Take Backup
Export RNC Radio and Ground Data form Live Data Area
Select Source and Destination RNC
And Export all Radio & Unioffice Raw Data from Source & Destination RNC
Similarly as you have Done In BSC.
After checking status check current alarm of planned sites in respective RNC. if sites is found down
exclude from the plan or either try validation after site restoration. Also take pre alarm of OMMB before
validation plan
Right Click on Data Area and select Create Plan Area Fill User label and select Source and Destination BSC/RNC
and Select Ok.
Note: Below Snapshot Showing BSC Similarly You Can Do with RNC so Don’t Get Confused.
Template is attached
It this template You Have to Give Source & Destination Cell ID & NodeB name.
Kindly Refer Attached Sheet While Preparing Script.
UMTS_SiteTransferT
emplate_Plan_en_620to621.xlsx
Unioffice Template will be same as you Export from RNC. But you have to prepare Unioffice Template for
Destination RNC.
MEID_TX_621_UNI_
OFFICE.xlsx
After Clicking to TransferSite Option popup Window Will Appear Like Below
And Unioffice Template in Dest office Plane Data and Then Click on Execute
Similarly Then Click on Validity Check & click Start then Submit Task for Plane Activation process
NOTE: Always Activate Destination RNC Script First because if you activate Source RNC Script First then it
will delete Cell from Source RNC then you Can’t Transfer cell from Source to Destination RNC.
After Activation Destination Script First it will Transfer Cell from Source RNC to Destination RNC
Then Activate Source Script to Delete Cells in Source RNC because it Show two Similar Cells in Network.
Note :It will also transfer Neighbors between Source & Destination RNC but it will not transfer Neighbor of
Other RNC.
After activation and site creation via ICM we need to change site end Abis IP (If ABIS IP plan change) and
SCTP IP as well via OMMB in maintenance window.
Then further import the same as planning import tab and share directory location for result as well.
NOTE: kindly select UMTS for 3G migration so don’t get confused its same process as 2G migration
While synchronizing multiple sites via ommb kindly click on check parameter before sync as shown in snap.
After successful rehoming put the sites in testing mode in source BSC and delete the database after DT
confirmation from circle end.
For testing mode go through maintain status query and setting as in snap
Sr
Execution Outage Time Duartion for Activity in
No Activity Process
Time Inv mins
.
Checking CR if all required data
1 Day No 30
provided
2 Validation of plan in day time Day No 50
S.
Points need to be checked Status Remarks
No.
1 Verification of all parameters with RF planning sheet
2 Cross check all cell services and ensure no alarm in network
3 Ensure Voice & Data call testing done by BSS/RF engineer
Rate