SNOC - CM - MOP - GUFTL Removing Insufficient Space On CC Board - ZTE - V1.0
SNOC - CM - MOP - GUFTL Removing Insufficient Space On CC Board - ZTE - V1.0
Document Details :
Domain
Document No. Document Title Author
Owner
Reviewers:
Reviewed
Name Version Approved Position
Date
Approvers:
Name Version Approved Position Approval Date
Distribution List:
Name/Position / Available at Published Date
SNOC, Circle BSS team, Corporate team
Next Review*:
Next Review Date Domain Owner
Sumit Nangia
*Document should be reviewed once every quarter or whenever there is a major change, whichever is
earlier. For Feedback/Suggestions please drop a mail to: [email protected]
Contents
1. Purpose of Document.....................................................................................................................3
2. Objective.........................................................................................................................................3
3. Scope...............................................................................................................................................3
4. Resources........................................................................................................................................4
5. Impact on Service...........................................................................................................................4
1. Purpose of Document
This technical document covers the activity of Removing Insufficient Space on CC Board in the
OMMB for Circles. The purpose of this document is to Create Space in CC Board to perform
following Activity like Version Upgrade, New Software Addition, New Patch Activation, New
technology Addition on site etc.
2. Objective
The objective of this MOP is to provide the user as to how to perform Removing Insufficient
Space on CC Board in OMMB.
3. Scope
The scope of this process document is to present the process Removing Insufficient Space on CC
Board in OMMB, which is to be observed by SNOC, for ZTE based circles and Corporate Team.
This process is for Vodafone Managed Circles Only.
4. Resources
5. Impact on Service
Outage Involved: YES
Outage Severity: Major
Outage Severity in case of fallback: Total
Outage Time & Duration: 20 mins
1. Symptom
The problem of insufficient flash space on the CC board of a base station often occurs in network
maintenance or base station upgrade. Consequently, data may not be writeable or new version files
may not be storable on the CC board. To solve this problem, flash space on the CC board should
be freed-up effectively.
2. Probable cause
This problem is caused because the space usage on the CC board reaches the configured threshold
or because there is not enough free space on the CC board to store new version files.
3 .Action
Figure 4 shows the directory of the version files and its space usage information.
Run the following commands to enter the directory and delete the version files in this directory:
#cd /mnt/flash/PRODUCT/UMTS/SW1
# rm file name
Keep deleting the files until there is enough flash space, which is calculated automatically.
After the backup version files are deleted, the alarm for insufficient flash space is cleared, but the alarm
for abnormal backup version files is raised. You can clear the alarm by deleting the backup version
files on the OMCB.
If the problem cannot be solved using all the above methods, the CC board is faulty, and should be
replaced or reconfigured.
Open two cmd windows. Enter "telnet 192.254.1.16" in one window, and do not press the Enter button.
Run the "ping 192.254.1.16 –t" command in the other window, and check the status of the ping packet,
as shown in Figure 5. 192.254.1.16 is the default IP address of the CC board.
If the CC board can be pinged, press Enter in the first cmd window, and telnet to the CC board with the
username and password "zte" and "zte" respectively.
If the telnet UI shown in Figure 7 is displayed after a successful login, run the following commands:
# cd /GSM/SW1/data/temp/
# rm -rf *
The CC board automatically restarts. After that, repeat step a.
Sr
Execution Outage Time Duration for Activity in
No Activity Process
Time Inv mins
.
Checking CR if all required data
1 Day No 20
provided
2 Validate the plan Day No 10
Removing Insufficient Space on CC
3 Night yes 10 per site
Board
5 Post check Night Yes 10
S. Statu Remark
Points need to be checked
No. s s
1 Check Flash Space on CC Board
2 Cross check all cell services
3 Ensure after activity no alarm in network