Masonry Works: CHB (Area Method) Ground Floor Interior

This document provides calculations for materials needed for masonry works, ceiling works, and roofing works on multiple floors of a building project. It calculates the quantities of cement, sand, concrete hollow blocks, rebar, tie wire, plywood, lumber, corrugated galvanized iron sheets, nails, and other materials needed. It also provides the total prices for each material.

Uploaded by

Asher Miley
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
61 views

Masonry Works: CHB (Area Method) Ground Floor Interior

This document provides calculations for materials needed for masonry works, ceiling works, and roofing works on multiple floors of a building project. It calculates the quantities of cement, sand, concrete hollow blocks, rebar, tie wire, plywood, lumber, corrugated galvanized iron sheets, nails, and other materials needed. It also provides the total prices for each material.

Uploaded by

Asher Miley
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 12

Masonry Works

CHB (Area Method)


GROUND FLOOR
Interior
Area=136.74 sq. m

MORTAR

4” CHB = Cement: (1.33 x A x 0.394)


Cement: (1.33 x 136.74 x 0.394) = 72 Bags

Sand: (1.00 x A x 0.044)


Sand: (1.00 x 136.74 x 0.044) = 6.01656 cu.m

6” CHB = Cement: (1.33 x A x 0.760)


Cement: (1.33 x 136.74 x 0.760) = 139 Bags

Sand: (1.00 x A x 0.089)


Sand: (1.00 x 136.74 x 0.089) = 12.16986 cu.m

PLASTERING

4” CHB = Cement: (0.192 x A x 2 faces)


Cement: (0.192 x 136.74 x 2 faces) = 53 Bags

Sand: (0.016 x A x 2 faces)


Sand: (0.016 x 136.74 x 2 faces) = 4.37568 cu.m

6” CHB = Cement: (0.192 x A x 2 faces)


Cement: (0.192 x 136.74 x 2 faces) = 53 Bags

Sand: (0.016 x A x 2 faces)

Sand: (0.016 x 136.74 x 2 faces) = 4.37568 cu.m

PCS of CHB (12.5 x A x 1.05)

(12.5 x 136.74 x 1.05) = 1795 pcs

1795 pcs * 10 = 1975 pcs

PCS of 6m RSB (600mm sp, 3 layers) [(A x 2.15) + (A x 2.13)] /6

[(136.74 x 2.15) + (136.74 x 2.13)] /6 = 98 pcs


Kls of Tiewire (0.0025 x # of CHB)

(0.0025 x 1975) = 4.94 kls

Exterior
Area=238.61 sq. m

MORTAR

4” CHB = Cement: (1.33 x A x 0.394)


Cement: (1.33 x 238.61 x 0.394) = 125 Bags

Sand: (1.00 x A x 0.044)


Sand: (1.00 x 238.61 x 0.044) = 10.49884cu.m

6” CHB = Cement: (1.33 x A x 0.760)


Cement: (1.33 x 238.61 x 0.760) = 241 Bags

Sand: (1.00 x A x 0.089)


Sand: (1.00 x 238.61 x 0.089) = 21.23629cu.m

PLASTERING

4” CHB = Cement: (0.192 x A x 2 faces)


Cement: (0.192 x 238.61 x 2 faces) = 92 Bags

Sand: (0.016 x A x 2 faces)


Sand: (0.016 x 238.61 x 2 faces) = 7.63552 cu.m

6” CHB = Cement: (0.192 x A x 2 faces)


Cement: (0.192 x 238.61 x 2 faces) = 92 Bags

Sand: (0.016 x A x 2 faces)


Sand: (0.016 x 238.61 x 2 faces) = 7.63552 cu.m

PCS of CHB (12.5 x A x 1.05)

(12.5 x 238.61 x 1.05) = 3132 pcs

3132 pcs * 10 = 3445 pcs

PCS of 6m RSB (600mm sp, 3 layers) [(A x 2.15) + (A x 2.13)] /6

[(238.61 x 2.15) + (238.61 x 2.13)] /6 = 170 pcs

Kls of Tiewire (0.0025 x # of CHB)


(0.0025 x 3445) = 8.62 kls

Masonry Works
CHB (Area Method)
SECOND FLOOR
Interior
Area=137.33 sq. m

MORTAR

4” CHB = Cement: (1.33 x A x 0.394)


Cement: (1.33 x 137.33x 0.394) = 72 Bags

Sand: (1.00 x A x 0.044)


Sand: (1.00 x 137.33x 0.044) = 6.04252 cu.m

6” CHB = Cement: (1.33 x A x 0.760)


Cement: (1.33 x 137.33 x 0.760) = 139 Bags

Sand: (1.00 x A x 0.089)


Sand: (1.00 x 137.33 x 0.089) = 12.22237 cu.m

PLASTERING

4” CHB = Cement: (0.192 x A x 2 faces)


Cement: (0.192 x 137.33 x 2 faces) = 53 Bags

Sand: (0.016 x A x 2 faces)


Sand: (0.016 x 137.33 x 2 faces) = 4.39456 cu.m

6” CHB = Cement: (0.192 x A x 2 faces)


Cement: (0.192 x 137.33 x 2 faces) = 53 Bags

Sand: (0.016 x A x 2 faces)

Sand: (0.016 x 137.33 x 2 faces) = 4.39456 cu.m

PCS of CHB (12.5 x A x 1.05)

(12.5 x 137.33 x 1.05) = 1803


1803 pcs * 10 = 1983 pcs

PCS of 6m RSB (600mm sp, 3 layers) [(A x 2.15) + (A x 2.13)] /6

[(137.33 x 2.15) + (137.33 x 2.13)] /6 = 99 pcs

Kls of Tiewire (0.0025 x # of CHB)

(0.0025 x 1983) = 4.96 kls

Exterior
Area=154.56 sq. m

MORTAR

4” CHB = Cement: (1.33 x A x 0.394)


Cement: (1.33 x 154.56 x 0.394) = 81 Bags

Sand: (1.00 x A x 0.044)


Sand: (1.00 x 154.56 x 0.044) = 6.80064 cu. m

6” CHB = Cement: (1.33 x A x 0.760)


Cement: (1.33 x 154.56 x 0.760) = 157 Bags

Sand: (1.00 x A x 0.089)


Sand: (1.00 x 154.56 x 0.089) = 13.75584.m

PLASTERING

4” CHB = Cement: (0.192 x A x 2 faces)


Cement: (0.192 x 154.56 x 2 faces) = 60 Bags

Sand: (0.016 x A x 2 faces)


Sand: (0.016 x 154.56 x 2 faces) = 4.94592 cu.m

6” CHB = Cement: (0.192 x A x 2 faces)


Cement: (0.192 x 154.56 x 2 faces) = 60 Bags

Sand: (0.016 x A x 2 faces)


Sand: (0.016 x 154.56 x 2 faces) = 4.94592 cu.m

PCS of CHB (12.5 x A x 1.05)

(12.5 x 154.56 x 1.05) = 2028 pcs

2028 pcs * 10 = 2,231 pcs

PCS of 6m RSB (600mm sp, 3 layers) [(A x 2.15) + (A x 2.13)] /6

[(154.56 x 2.15) + (154.56 x 2.13)] /6 = 111pcs


Kls of Tiewire (0.0025 x # of CHB)

(0.0025 x 2028) = 5.07 kls

Prices
Cement =1325x235

=Php 311,375.00

Sand =126.80121x500

=Php 63,400.605

4”THK CHB =3958x10

=Php 39,580.00

6”THK CHB =5676x14

=Php 79,464.00

Tie wire =23.55x70

=Php 1,648.50

Total consumption for masonry works =Php 495,467.605

Ceiling Works
A. Plywood on Good Lumber
Area=235.11
Plywood (pcs) = A / 2.88
= 235.11/ 2.88
= 82 pcs
2 x 3 GL (0.6 m x 0.6 m sp.) (bd. ft.) =Ax7
= 235.11x 7
= 1646 pcs
(0.4 m x 0.60 m sp.) (bd. ft.) = A x 8.312
= 235.11x 8.312
= 19543 pcs
2 x 2 GL (0.6 m x 0.6 m sp.) (bd. ft.) = A x 4.667
= 235.11x 4.667
= 1098 pcs
(0.4 m x 0.6 m sp.) (bd .ft.) = A x 5.445
= 235.11x 5.445
= 1281 pcs
CWN (kls) = (A x 0.05) + (# of plywood x 0.055)
= (235.11x 0.05) + ( 82 pcs. x 0.055)
= 17 pcs

Roofing Works
Area=326.44 sq. m

Long Span Roofing (ln-m) = A/0.8955

= 326.44/0.8955

= 216.48 ln-m

Tekscrew (pcs) =(A/3.29) x (22 or 26)

= (326.44/3.29) x (22 or 26)

= 99.22 x 22

=2183 pcs

G.I Sheet (pcs) = length / 0.6 or 0.7

= 55.7 / 0.7

=80 pcs

Umbrella Nail or Rivet (pcs) = (# of GI sheet x 26 for 12’ sheet)

= (262 x 26)

= 6812 pcs

For Ridge Roll (pcs) = L / 2.2

= 55.7 / 2.2

= 26 pcs

For Valley Roll (pcs) = L / 2.3

= 5.5 / 2.3

= 3 pcs

Prices
Long Span Roofing (ln-m) =216.48 x980

=Php 212,464.00

Tekscrew =2183x2

=Php 4,366.00

Ridge roll =26x495

=Php 12,870.00

Total consumption for masonry works =Php 229,700

Painting Works
Interior Wall
Area=274.07
Concrete
Concrete neutralizer (gals) = A / (25 x 2.5)

= 274.07/ (25 x 2.5)


= 5 gals

Flat latex paint (gals) = A / 25

= 274.07/ 25
= 11 gals

Semi-gloss (gals) = A x 2 / 25

= 274.07x 2 / 25
= 22 gals

Masonry putty (gals) = A / (25 x 2.5)

= 274.07/ (25 x 2.5)


= 5 gals

Tinting color (cans) = # of gals of semi-gloss

= 22 gals

Exterior Wall
Area=393.17
Concrete
Concrete neutralizer (gals) = A / (25 x 2.5)

= 393.17/ (25 x 2.5)


= 7 gals

Flat latex paint (gals) = A / 25

= 393.17/ 25
= 16 gals

Semi-gloss (gals) = A x 2 / 25

= 393.17x 2 / 25
= 32 gals

Masonry putty (gals) = A / (25 x 2.5)

= 393.17/ (25 x 2.5)


= 7 gals

Roofing
Area=326.44 sq. m

Red oxide primer (gals) = A / 25

= 326.44 / 25

= 14 gals

Roof master (gals) = A x 2 / 25

= 326.44 x 2 / 25

= 27 gals

Paint thinner (litters) = total gals of roof master

= 27 gals

Steel Casement
Area=11.25
Red oxide primer (gals) = A / 25

= 11.25/ 25
= 1 gal

Quick Dry Enamel (gals) = A x 2 / 25

= 11.25 x 2 / 25

= 1 gal

Paint thinner (litters) = total gals of quick dry enamel

= 1 gal
Prices
Concrete neutralizer =12 x20

=Php 240.00

Flat latex paint =27x550

=Php 14,850.00

Semi-gloss =54x580

=Php 31,320.00

Masonry putty =12x280

=Php 3,360.00

Tinting colors =105x22

=Php 2,310.00

Red oxide primer =14x375

=Php 5,250.00

Roof master =27x960

=Php 25,920.00

Paint thinner =28x260

=Php 7,280.00

Quick dry enamel =1x260

=Php 260.00

Total consumption for masonry works =Php 90,790.00

Tile Works
Toilet and Bath
Area= 24.66 sq. m
Tile grout (pack) = A/7
=24.66 /7
=4 packs
Adhesive (bags)=A/5
=24.66 /5
=5 bags
Tiles (pcs) =A/(.30x.60)
=24.66 /.18
=137 pcs
Granolithic tiles
White cement =Ax0.172
=24.66 x0.172
=5 bags
Cement =Ax0.225
=24.66x0.225
=6 bags
Sand =Ax0.018
=24.66 x0.018
=0.44388 cu. m
Terrace and Porch
Area= 33.47 sq. m
Tile grout (pack) = A/7
=33.47 /7
=5 packs
Adhesive (bags)=A/5
=33.47 /5
=7 bags
Tiles (pcs) =A/(.60x.60)
=33.47 /.36
=93 pcs
Cement tiles
Cement =Ax0.225
=33.47x0.225
=8 bags
Sand =Ax0.018
=33.47 x0.018
=0.60246 cu. m
Prices
Cement =14x235

=Php 3,290.00

Sand =1.04634x500

=Php 523.17

Grout =9x70

=Php 630.00

Adhesive =12x320

=Php 3,840.00

Tiles (.60x.60) =93x180

=Php 16,740.00

Tiles (.30x.60) =137x75

=Php 10,275.00

Total consumption for masonry works =Php 35,298.17