List of PPAP Documents: SR No. Document Title Documents Formats / Templates Remarks
List of PPAP Documents: SR No. Document Title Documents Formats / Templates Remarks
Customer Engineering Approval Customer Engineering Approval Format not provided - any
approved document
3 received from Gates is
acceptable
Design FMEA Design FMEA Format provided (same as
4 AIAG format)
Process Flow Diagram Process Flow Chart (for Processing & Format provided
5
Assembly)
Process FMEA Process FMEA Format provided (same as
6 AIAG format)
Initial Process Study Control Chart (for stability) with Pp & Format provided
9
Ppk Calculation Sheet
10 Measurement System Analysis Studies MSA for variable characteristics Format provided
MSA for attribute characteristics Format provided
Applicable Submitted /
Sr No. Document Title Remarks
Y/N Retained
1 List of documents submitted
2 Design Records
Bill Of Material
Drawing
Test Standards
3 Engineering Change Documents
4 Customer Engineering Approval
5 Design FMEA
6 Process Flow Diagram
Overall Process Flow (for Assembly)
Process Flow Chart (for Feeder shop & Assembly)
7 Process FMEA
8 Dimensional Results
9 Material Performance Test Results
10 Initial Process Study
Control Chart
Pp, Ppk Calculation Sheet
11 Measurement System Analysis Studies
MSA for variable characteristics
MSA for attribute characteristics
12 Qualified Laboratory Documentation
13 Control Plan
14 PSW
Weight Calculation Sheet
15 Appearance Approval Report
16 Bulk Material Requirements Checklist
17 Sample Product
18 Master Sample
19 Checking Aids
20 Records of Compliance With Customer-Specific
Requirements
List of approved TIER 2 suppliers
Process Qualification Records
Prepared by Date
Checked by Date
Approved by Date
Bill Of Material
Made In-house /
Sr No. Part Number Part Name Level Qty Name of TIER2 Remarks
Supplier
Prepared by Date
Checked by Date
Approved by Date
Potential failure mode and effects analysis (Design FMEA)
System: Design responsibility: FMEA Number:
Subsystem: Key date: Page:
Component: Model year(s) / Vehicle(s) : Prepared by:
Part no:
Core team: FMEA date (Orig) : (Rev)
Potential Current Current ACTION RESULTS
Potential Responsibility &
Potential failure cause(s) / design design
Item / Function effect(s) of Recommended actions target completion
Detect
Action
Occur
Class
mode mechanism(s) of controls controls
RPN
RPN
failures date
Occ
taken
Sev
Sev
Det
failure prevention detection
PROCESS FLOW DIAGRAM PAGE: OF
REV:-
MODEL :- PART NO:- PART NAME:- DATE:-
OPN. PROCESS
OPERATION MACHINE PROCESS CHARACTERISTICS PRODUCT CHARACTERISTICS
NO. FLOW
Core Team :-
C Action Results
O D
l Resp. &
Process Potential Potential S Potential Cause(s) / c e R.
a Current Process Current Process Recommended Target
Function / Failure Effect(s) of e Mechanism(s) of c t P. S O D R.
Controls Prevention Controls Detection Action(s) Completion
Requirements Mode Failure v Failure u e N. Action Taken e c e P.
s Date
r c v c t N.
s
Dimensional Results
Stage of the Trials (Proto / Before Mass Production / Mass Production / Others - Pl specify):
Observation Result
Sl No Dimension / Specification Class Instrument USL LSL Remarks
1 2 3 4 5 OK / NOK
Prepared by Date
Checked by Date
Approved by Date
Material Test Results
Stage of the Trials (Proto / Before MP / Mass Production / Others - Pl specify): Name of Laboratory:
Checked by Date
Approved by Date
Performance Test Results
Stage of the Trials (Proto / Before MP / Mass Production / Others - Pl specify): Name of Laboratory:
Prepared by Date
Checked by Date
Approved by Date
GAGE REPEATABILITY AND REPRODUCIBILITY GAGE REPEATABILITY AND REPRODUCIBILITY
DATA COLLECTION SHEET REPORT
Part Number Gage Name Appraiser A Part Number Gage Name Appraiser A
MSA 3rd edition example XXXX A MSA 3rd edition example XXXX A
Part Name Gage Number Appraiser B Part Name Gage Number Appraiser B
XXXX XXXX B XXXX XXXX B
Characteristic/Specification Gage Type Appraiser C Characteristic/Specification Gage Type Appraiser C
XXXX XXXX C XXXX XXXX C
Total Tolerance Trials Parts Appraisers Date Performed Total Tolerance Trials Parts Appraisers Date Performed
0 3 10 3 12/3/2008 0 3 10 3 12/3/2008
A :- 2
B :- 2
C :- 2
NOTE:
(ENTER THE DATA ONLY IN YELLOW CELLS) DATE: 05.12.2008
PART NAME :- XXXX GAUGE NAME: XXX
Total Count 0 40 40
Ref
Total
0 1
A 0 Count 0 0 0
Expected Count 0.000 0.0 0.0
1 Count 0 40 40
Expected Count 0.00 40.000 40.0
Total Count 0 40 40
Expected Count 0.0 40.0 40.0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
1 - GOOD + Perfect agreement for all appraisers wrt Reference value (For GOOD)
0- NOT GOOD - Perfect agreement for all appraisers wrt Reference value (For NOT GOOD)
X Poor agreement between appraisers wrt Reference value
Before measurement ensure the following condition :
Sub-group 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
X1 14.000 14.070 14.020 13.870 14.000 13.890 14.000 14.140 13.990 13.990 14.020 14.130 14.010 14.120 14.140 13.870 14.150 13.940 13.850 14.130 14.070 13.890 13.990 14.120 13.940
X2 14.120 14.010 14.010 14.070 13.980 14.120 13.880 14.080 14.010 14.010 13.980 14.060 13.970 14.080 13.930 13.950 14.110 13.900 14.030 14.120 14.010 14.120 14.010 14.080 13.900
X3 14.090 13.900 13.990 14.090 14.030 14.140 14.130 14.050 14.130 14.020 13.980 14.090 14.130 13.960 14.130 14.010 13.990 14.010 14.080 14.080 13.900 14.140 14.020 13.960 14.010
X4 14.110 14.090 14.010 13.990 14.120 13.940 13.950 14.020 14.020 13.960 14.010 13.890 13.990 14.010 14.060 14.080 13.920 14.130 14.090 14.120 14.090 13.940 13.960 14.010 14.130
X-Bar 14.080 14.018 14.008 14.005 14.033 14.023 13.990 14.073 14.038 13.995 13.998 14.043 14.025 14.043 14.065 13.978 14.043 13.995 14.013 14.113 14.018 14.023 13.995 14.043 13.995
Range 0.120 0.190 0.030 0.220 0.140 0.250 0.250 0.120 0.140 0.060 0.040 0.240 0.160 0.160 0.210 0.210 0.230 0.230 0.240 0.050 0.190 0.250 0.060 0.160 0.230
Date 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
Time 8.45 9.00 9.15 9.30 9.45 10.00 10.15 10.30 10.45 11.00 11.15 11.30 11.45 12.00 12.15 12.30 12.45 13.00 13.15 13.30 13.45 14.00 14.15 14.30 14.45
X-bar X=
UCLX= LCLX= X-bar Chart
14.2000
14.1500
Values
14.1000
14.0500
14.0000
13.9500
13.9000
13.8500
13.8000
13.7500
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Sub-group No.
0.4500
0.4000
0.3500
0.3000
0.2500
0.2000
0.1500
0.1000
0.0500
0.0000
Subgroup No.
Week:
X-bar / R chart - Process Performance study Month: Dec.
Year: 2007
Part / Dimension details Enter Data / Values in green colour boxes only. Other cells are protected.
Part: Cover Clutch Sub-group details n --> 2 3 4 5 Values obtained Process Capability/Performance
Drawing No. N xxxxxxx Rev. b Sub-groupNo.of sub D4 3.27 2.57 2.28 2.11 X= 14.0298 Standard Deviation:
Parameter: Dome Centre Height size groups D3 0.00 0.00 0.00 0.00 R- 0.1750 s 0.0752 s 0.0789
Dimension: 14.00 +/- 0.40 n N A2 1.88 1.02 0.73 0.58 UCLX= 14.1308 Process Capability/Performance:
USL 14.400 d2 1.13 1.69 2.06 2.33 LCLX= 13.9288 Cp 1.77 Pp 1.69 PROCESS
5 20 CAPABLE
LSL 13.600 E2 2.66 1.77 1.46 1.29 UCLR- 0.3700 Cpk 1.64 Ppk 1.56
Sub-group 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20
X1 14.000 14.070 14.020 13.870 14.000 13.890 14.000 14.140 13.990 13.990 14.020 14.130 14.010 14.120 14.140 13.870 14.150 13.940 13.850 14.130
X2 14.120 14.010 14.010 14.070 13.980 14.120 13.880 14.080 14.010 14.010 13.980 14.060 13.970 14.080 13.930 13.950 14.110 13.900 14.030 14.120
X3 14.090 13.900 13.990 14.090 14.030 14.140 14.130 14.050 14.130 14.020 13.980 14.090 14.130 13.960 14.130 14.010 13.990 14.010 14.080 14.080
X4 14.120 13.950 14.020 13.920 14.080 14.110 14.150 14.070 14.080 13.980 13.950 13.950 14.110 14.170 14.120 13.900 14.040 14.050 13.950 13.970
X5 14.110 14.090 14.010 13.990 14.120 13.940 13.950 14.020 14.020 13.960 14.010 13.890 13.990 14.010 14.060 14.080 13.920 14.130 14.090 14.120
X-Bar 14.088 14.004 14.010 13.988 14.042 14.040 14.022 14.072 14.046 13.992 13.988 14.024 14.042 14.068 14.076 13.962 14.042 14.006 14.000 14.084
Range 0.120 0.190 0.030 0.220 0.140 0.250 0.270 0.120 0.140 0.060 0.070 0.240 0.160 0.210 0.210 0.210 0.230 0.230 0.240 0.160
Date 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
Time 10.00 10.15 10.30 10.45 11.00 11.15 11.30 11.45 12.00 12.15 12.30 12.45 13.15 13.15 13.30 13.45 14.00 14.15 14.30 14.35
X-bar X=
UCLX= LCLX= X-bar Chart
14.1500
14.1000
Values
14.0500
14.0000
13.9500
13.9000
13.8500
13.8000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Sub-group No.
0.4000
0.3500
0.3000
0.2500
0.2000
0.1500
0.1000
0.0500
0.0000
Quality Laboratory Documentation
Prepared by Date
Checked by Date
Approved by Date
PART SUBMISSION WARRANT
Checking Aid No. __________________________ Engineering Change Level _________________________ Dated ______________
______________________________________________
Supplier Name & Supplier code Dimensional Materials/Functional Appearance
Address:
______________________________________________ Customer Name/Division _______________________________________
Note: Does this part contain any restricted or reportable substances Yes No
Are plastic parts identified with appropriate ISO marking code Yes No
Level 2-Warrant with product samples and limited supporting data submitted to customer.
Level 3-Warrant with product samples and complete supporting data submitted to customer.
Level 5-Warrant with product samples and complete supporting data reviewed at supplier's manufacturing location.
Submission Results
The results for dimensional measurements material and functional tests appearance criteria statistical process package
These results meet all drawing and specification requirements : Yes No (if "No" Explanation Required)
Declaration
I here by affirm that the samples represented by this warrant are representative of our parts, have been made to the applicable Production Part Approval
Process Manual 3rd edition requirements .I further warrant these samples were produced at the production rate of ______ /8 hours.I have noted any deviations
from this declaration below.
Explanation/Comments:__________________________________________________________________________________________
Other Waived
Customer Name ____________________________________ Customer Signature _______________________ Date ______________
Appearance Approval Report
Part Name - Supplier Name
Finished part number
Rev no and date - Supplier Code
Approval Signatures
Supplier representative
GUIC Quality
Product Weight Details
10
Average
Prepared by Date
Checked by Date
Approved by Date
Master Sample Identification Card
Part Name
Part Number
Rev No. & Date
Date of PSW Approval
Printing Identification Details
Sample Identification Details
Project Reference
Storage Location
Validity date
Approved by
Date Date
List of Checking Aid
Prepared by Date
Checked by Date
Approved by Date
List of TIER 2 Suppliers
Prepared by Date
Checked by Date
Approved by Date
Special Process Qualification Record (Sheet 1)
Names of the Special Processes involved (Eg. Welding, Soldering, Brazing, Painting, Plating, Heat treatment, Crimping, etc.)
Prepared by Date
Checked by Date
Approved by Date
Special Process Qualification Record (Sheet 2)
Section 3 : Experiment Details
Result
Name of the Name of the Result (OK /
Sr No. Process Parameters Set Value Product Parameters Record Remarks
Special Process Experiment NOK)
Reference
1 SP1 LSL experiment Process Parameter 1 SV 1 Parameter Specs Actuals
Process Parameter 2 SV 2 Product Parameter 1 Lsl - Usl A1 OK Annex 1
Process Parameter 3 SV 3 Product Parameter 2 Lsl - Usl A2 OK Annex 2
Process Parameter 4 SV 4 Product Parameter 3 Lsl - Usl A3 OK Annex 3
Process Parameter 5 SV 5 Product Parameter 4 Lsl - Usl A4 OK Annex 4
Prepared by Date
Checked by Date
Approved by Date