64360-K60 - B600 Cover, L Under Side - Done
64360-K60 - B600 Cover, L Under Side - Done
Model: K2VJ
Part No.: 64360-K60 -B600
Part Name: COVER, L UNDER SIDE
DWG PART Material Process Investment Total Cost Total Cost
NO. SUPPLIER Volume Amort. Cost Admin cost Profit Cost CKD COST Variance Variance (%) JUDGEMENT / RECOMMENDATION
WEIGHT w/o Amort. w/ Amort.
Type Input wt. Cost/kg Expense Process MC Tons Rate/sec CT Expense Tool (Mold Cavity / Rack Qty.) Cost
MATERIAL
0.177 PP-IMP-21 0.18399 80.00 14.72 Injection 650 TONS 0.495 27.5 13.61 500,000 MOLD 2 CAVITY 4,500,000.00 9.00 >99% - PP, 1% - COLORANT
PROCESS
M/B (TIC- >DATA FROM K81 , ATLANTIC PROCESS COST. FOR 650T: M/C COST -
UVMB)
0.00186 460.00 0.85 Inspection 1.00 500,000 RACKS 2,000,000.00 4.00 0.495. ATLANTIC COST FOR 2 CAVITY IS 55. FOR 1 CAVITY, 55/2 = 27.5
INVESTMENT
10 Wheeler >Check MP model for K81 Cover Under Side for process verification
0 SELF ESTIMATE Delivery Truck 5,000.00 600.00 8.33 3.85 1.93 44.30 57.30 42.12 15.17 36% >Mold: Compare the K81 investment for K81 Cover L,Under Side
>Racks: 500,000/2/12/4/6 = 868.05555≈869 pcs/day.
>If with allowance, 1000/day(Required Delivery). 1000 delivery a day,
they can finish the delivery in 500 working days = 19.32 months
TOTAL MATERIAL COST: 15.57 TOTAL PROCESS COST: 22.95 TOTAL INVESTMENT COST: 6,500,000.00 13.00
MATERIAL
INABATA 0.1803 82.36 14.41 Injection 1000 TONS 0.790 55.00 21.73 500,000 MOLD 2 CAVITY 3,200,000.00 6.40 >Change the material allocation, 99% - PP & 1% - Colorant
PROCESS
M/B (TIC- 50PCS X 84 >Data from K81, Atlantic MC cost for 1000T is 0.9.
UVMB) 0.00560 462.71 2.58 Inspection 1.50 500,000 RACKS RACKS 2,100,000.00 4.20 >Check if Atlantic can use 650T for 1 Cavity. Data from K81, Atlantic
MC Cost for 650T is 0.495.
PACKAGING 10 Wheeler >Inspection must add in Admin Cost
2.50 Delivery 1,000.00 4,500.00 4.50 INVESTMENT
PLASTIC Truck
1 ATLANTIC 4.92 2.46 56.60 67.20 42.12 25.07 60% >Check how much mold if 1 Cavity
>Racks: 869/50 = 17.38≈18 racks. 18 racks x 3 = 54 Racks only. (84
BOX 2.00 Racks = 2,1000,000. Therefore, 54/84 = 0.6429 x 2,100,000.00 =
1,350,000.00)
>If 1000/day: 1000/50 = 20 Racks. 20 x 3 = 60 Racks Only.
TOTAL MATERIAL COST: 21.49 TOTAL PROCESS COST: 27.73 TOTAL INVESTMENT COST: 5,300,000.00 10.60
2 MOLDS MATERIAL
PP-IMP-21 180.27500 80.00 14.42 Injection 1200 TONS 0.72 40.00 28.80 500,000 MOLD 9,240,000.00 18.48 >Change the material allocation, 99% - PP & 1% - Colorant
(1+1 CAVITY)
PROCESS
M/B (TIC- 50PCS X 72 >Check if Paintplas can use 1000T for 2 Cavity
5.57600 460.00 2.56 Inspection 0.06 40.00 2.40 500,000 RACKS 4,593,600.00 9.19 >Check if Paintplas can use 650T for 1 Cavity. From K81, 650T MC cost
UVMB) RACKS
is 0.44
10 WHEELER >Inspection must add in Admin Cost
Delivery 7,000.00 500.00 14.00 INVESTMENT
2 PAINTPLAS TRUCK 6.22 3.11 71.52 99.18 42.12 57.06 135%
>Check how much mold if 1 Cavity
>Racks: 869/50 = 17.38≈18 racks. 18 racks x 3 = 54 Racks only. (72
Racks = 4,593,600. Therefore, 54/72 = 0.75 x 4,593,600 = 3,445,200.00)
>If 1000/day: 1000/50 = 20 Racks. 20 x 3 = 60 Racks Only.
TOTAL MATERIAL COST: 16.99 TOTAL PROCESS COST: 45.20 TOTAL INVESTMENT COST: 13,833,600.00 27.67
MATERIAL
PP-IMP-21 0.17170 82.00 14.08 Injection 1000 TONS 0.62 45.00 27.90 500,000 MOLD 1 CAVITY 3,000,000.00 6.00 >Change the material allocation, 99% - PP & 1% - Colorant
PROCESS
M/B (TIC- 50 PCS X 40 >Check if Triton can use 650T for 1 Cavity. If can use 800T, From K81,
0.00560 462.71 2.59 Inspection 2.00 500,000 RACKS 2,000,000.00 4.00 Triton MC cost for 800T is 0.5
UVMB) RACKS
>Inspection must add in Admin Cost
10 WHEELER INVESTMENT
3 TRITON PLASTIC 2.00 Delivery TRUCK 5,000.00 600.00 8.33 5.69 2.85 65.44 75.44 42.12 33.32 79% >Check the mold cost since competitor is 3.2M = 2 Cavity
>Check how much if 2 Cavity
>Racks: 869/50 = 17.38≈18 racks. 18 racks x 3 = 54 Racks only. Check
with Triton if 40 racks are possible to accommodate required delivery
target a day.
TOTAL MATERIAL COST: 18.67 TOTAL PROCESS COST: 38.23 TOTAL INVESTMENT COST: 5,000,000.00 10.00
■ COST EVALUATION SUMMARY □ MATERIAL COST CALCULATION LOGIC □ PROCESS COST CALCULATION LOCIC
Base Model BEFORE AFTER BEFORE AFTER BEFORE AFTER SELF RESIN MATERIAL GRADE: PP-IMP-21 Injection Tonnage Formula:
CONTROL
ITEMS (KPGM) - ATLANTIC HEARING HEARING HEARING HEARING HEARING HEARING ASSESTMENT MASTER BATCH: TOKYO INK (TIC-UVMB)
COVER L SIDE (ATLANTIC) (ATLANTIC) (PAINTPLAS) (PAINTPLAS) (TRITON) (TRITON) (TARGET) Area (Drawing:cm2)* Injection Pressure by Material
AMORT 0 9.98 10.60 28.15 27.67 10.18 10.00 13.00 Material Drawing Weight
PROFIT 5.46 2.19 2.46 4.42 3.11 3.29 2.85 1.93 0.177 Length Width Thickness Area
(PP) Injection Pressure: 0.35
ADMIN 5.46 4.65 4.92 8.84 6.22 6.58 5.69 3.85
PROCESS 32.45 23.23 27.73 72.50 45.20 47.18 38.23 22.95 Material Calculation Formula: d b e Injection Tonnage:
MATERIAL 38.95 20.59 21.49 15.93 16.99 18.57 18.67 15.57 Resin Material Input Weight = Material Drawing Weight (97%)* 1.05
82.32 60.64 67.20 129.85 99.18 85.79
0
75.44 57.30 Master Batch Input Weight = Material Drawing Weight (3%) * 1.05 Legend:
NOTE: NO AMORT INDICATED IN QUOTATION
Transfer Mold 129.85 Resin Material Input Weight
0.1803
TOTAL MATERIAL COST: 17.36 TOTAL PROCESS COST: 18.83 TOTAL INVESTMENT COST: 4,500,000.00 9.00
■ COST EVALUATION SUMMARY □ MATERIAL COST CALCULATION LOGIC □ PROCESS COST CALCULATION LOCIC
Base Model BEFORE AFTER BEFORE AFTER BEFORE AFTER SELF RESIN MATERIAL GRADE: PP-IMP-21 Injection Tonnage Formula:
CONTROL (KPGM) - ATLANTIC HEARING HEARING HEARING HEARING HEARING HEARING ASSESTMENT
ITEMS MASTER BATCH: TOKYO INK (TIC-UVMB)
COVER L SIDE (ATLANTIC) (ATLANTIC) (PAINTPLAS) (PAINTPLAS) (TRITON) (TRITON) (TARGET) Area (Drawing:cm2)* Injection Pressure by Material
AMORT 0 9.98 9.40 28.15 16.90 10.18 9.00 13.00 Material Drawing Weight
PROFIT 5.46 2.19 1.63 4.42 1.69 3.29 1.81 1.95 0.177 Length Width Thickness Area
(PP) Injection Pressure: 0.35
ADMIN 5.46 4.65 3.26 8.84 3.38 6.58 3.62 3.89
PROCESS 32.45 23.23 15.64 72.50 33.80 47.18 18.83 21.95 Material Calculation Formula: d b e Injection Tonnage:
MATERIAL 38.95 20.59 16.99 15.93 0.02 18.57 17.36 16.99 Resin Material Input Weight = Material Drawing Weight (97%)* 1.05
82.32 60.64 46.92 129.85 55.79 85.79 50.63 57.77 Master Batch Input Weight = Material Drawing Weight (3%) * 1.05 Legend:
0
NOTE: NO AMORT INDICATED IN QUOTATION
Resin Material Input Weight
Transfer Mold 129.85 0.1803
67.20
60.64
Machine Tonnage 1 Cavity
C
M/B (TIC- 0.00186 462.71 O
UVMB) S
T
PACKAGING :
PLASTIC T
O
BOX T
A
1 ATLANTIC L
M
A
T
E
R
I
A
L
C
PP-IMP-21 0.18399 80.00 O
S
T
:
M/B (TIC- 0.00186 460.00
UVMB) T
O
T
A
L
2 PAINTPLAS
M
A
T
E
R
I
A
L
C
O
■ COST EVALUATION SUMMARY S
T
:
CONTRO Base Model (KPGM) - BEFORE AFTER BEFORE
L ITEMS ATLANTIC COVER L HEARING HEARING HEARING
SIDE (ATLANTIC) (ATLANTIC) (PAINTPLAS)
Process
Volume
Expense Process MC Rate/se CT Expense
14.72 Injection 650Tons
TONS c 0.495 27.5 13.61 500,000
T
0.85 Inspection 1.00O 500,000
T
A
Delivery 10 Wheeler 5,000.00 600.00 8.33L
Truck
P
R
O
15.57 22.95C
E
S
S
14.41 Injection 650 TONS 0.495 45.00 11.14 500,000
C
O
2.58 Inspection S 500,000
T
Delivery 10 Wheeler 1,000.00 4,500.00 4.50:
Truck
T
O
T
A
L
P
R
O
16.99 15.64C
E
S
S
C
0.01 Injection 650 TONS 0.44 45.00 19.80O 500,000
S
T
:
0.00 Inspection 0.06 40.00 2.40 500,000
T
O
Delivery 10 WHEELER 7,000.00 500.00 14.00T
TRUCK
A
L
P
R
O
0.02 36.20C
E
S
S
C
15.09 Injection 800T 0.50 45.00 22.50O 500,000
S
T
0.86 Inspection 2.00: 500,000
P
R
O
17.95 32.83C
E
S
S
C
O
S
□ MATERIAL
T COST CALCULATION
:
TOTAL
INVES
TMEN 3,600,000.00 7.20
T
COST:
MOLD CAVITY 1,600,000.00 3.20
TOTAL
INVES
TMEN 2,082,142.86 4.16
T
COST:
TOTAL
INVES
TMEN 5,222,166.67 10.44
T
COST:
TOTAL
INVES
TMEN 4,500,000.00 9.00
T
COST:
51.50 47.62 3. 88
8%
MATERIAL
> Need to change percentage ration from 3% going to 1% for Maste
-Check if posible to eliminate plastic or box cost since other maker
have declaration like this.
PROCESS
>In 64450-KPGM-H000, 1360T was used with 1.16 mc cost and 27.5
Therefore, for K2VJ COVER R, UNDER SIDE, 1000T with 0.79 mc cost
must be lowered. (CT:45sec)
>Check if Atlantic can use 650T for 1 Cavity. Data from K81, Atlantic
Cost for 650T is 0.495.
>Inspection must be included on the CT injection process. it must b
41.69 47.62
(5.94) -12% deleted.
INVESTMENT
>Check how much mold if 1 Cavity
>RACKS: 1,350,000.00/84 = 16,071.4286 per Rack. Required Rack =
racks. Therefore, 16,071.4286 x 30 = 482,142.858
MATERIAL
> Need to change percentage ration from 3% going to 1% for Maste
PROCESS
>Check if Paintplas can use 1000T for 2 Cavity
>Check if Paintplas can use 650T for 1 Cavity. From K81 Cover Unde
MC cost is 0.44 and CT is 45 sec.
>Inspection must be included on the CT injection process. it must b
deleted.
INVESTMENT
MATERIAL
> Need to change percentage ration from 3% going to 1% for Maste
PROCESS
>Check if Paintplas can use 1000T for 2 Cavity
>Check if Paintplas can use 650T for 1 Cavity. From K81 Cover Unde
MC cost is 0.44 and CT is 45 sec.
>Inspection must be included on the CT injection process. it must b
deleted.
INVESTMENT
52.09 47.62 4. 47
MATERIAL
> Need to change percentage ration from 3% going to 1% for Maste
-Check if posible to eliminate plastic or box cost since other maker
have declaration like this.
PROCESS
>Check if Triton can use 650T for 1 Cavity. If can use 800T, From K8
MC cost for 800T is 0.5. In K81 Cover R, Body Side, CT is 30 sec for 8
Therefore, CT for Cover R, Under Side must be lower than 50sec.
>Inspection must be included on the CT injection process. it must b
deleted.
67.40 47.62
19.78 42% INVESTMENT
>Check how much if 2 Cavity
>Racks: 2,000,000.00/40 = 50,000.00 each rack. 50,000.00 * 30 = 1,
LCULATION LOCIC
(PP) Injection
Area Pressure:
Injection Tonnage:
0
Calculation Formula:
2c) :(e+2f)+(e+50) +100
JUDGEMENT / RECOMMENDATION
MATERIAL
>99% - PP, 1% - COLORANT PROCESS
>DATA FROM K81 , ATLANTIC PROCESS COST. FOR 650T: M/C COST -
0.495. ATLANTIC COST FOR 2 CAVITY IS 55. FOR 1 CAVITY, 55/2 = 27.5
INVESTMENT
>Check MP model for K81 Cover Under Side for process verification
>Mold: Compare the K81 investment for K81 Cover L,Under Side
>Racks: 500,000/2/12/4/6 = 868.05555≈869 pcs/day. REQUIRED DELIVERY:
1,000 pcs/day
MATERIAL
> Need to change percentage ration from 3% going to 1% for Masterbatch.
-Check if posible to eliminate plastic or box cost since other maker don’t
have declaration like this.
PROCESS
>In 64450-KPGM-H000, 1360T was used with 1.16 mc cost and 27.5 CT.
Therefore, for K2VJ COVER R, UNDER SIDE, 1000T with 0.79 mc cost, CT
must be lowered. (CT:45sec)
>Check if Atlantic can use 650T for 1 Cavity. Data from K81, Atlantic MC
Cost for 650T is 0.495.
>Inspection must be included on the CT injection process. it must be
deleted.
INVESTMENT
>Check how much mold if 1 Cavity
>RACKS: 1,350,000.00/84 = 16,071.4286 per Rack. Required Rack = 30
racks. Therefore, 16,071.4286 x 30 = 482,142.858
MATERIAL
> Need to change percentage ration from 3% going to 1% for Masterbatch.
PROCESS
>Check if Paintplas can use 1000T for 2 Cavity
>Check if Paintplas can use 650T for 1 Cavity. From K81 Cover Under, 650T
MC cost is 0.44 and CT is 45 sec.
>Inspection must be included on the CT injection process. it must be
deleted.
INVESTMENT
MATERIAL
> Need to change percentage ration from 3% going to 1% for Masterbatch.
PROCESS
>Check if Paintplas can use 1000T for 2 Cavity
>Check if Paintplas can use 650T for 1 Cavity. From K81 Cover Under, 650T
MC cost is 0.44 and CT is 45 sec.
>Inspection must be included on the CT injection process. it must be
deleted.
INVESTMENT
>Check how much mold if 1 Cavity
>Racks:1,445,200/72 = 20,0722.22 each rack. 20,0722.22 * 30 =
602,166.6667
MATERIAL
> Need to change percentage ration from 3% going to 1% for Masterbatch.
-Check if posible to eliminate plastic or box cost since other maker don’t
have declaration like this.
PROCESS
>Check if Triton can use 650T for 1 Cavity. If can use 800T, From K81, Triton
MC cost for 800T is 0.5. In K81 Cover R, Body Side, CT is 30 sec for 800T.
Therefore, CT for Cover R, Under Side must be lower than 50sec.
>Inspection must be included on the CT injection process. it must be
deleted.
INVESTMENT
>Check how much if 2 Cavity
>Racks: 2,000,000.00/40 = 50,000.00 each rack. 50,000.00 * 30 = 1,500,000
0.35
Injection Tonnage:
0