NHBC Standards 2021 8
NHBC Standards 2021 8
CHAPTER 8.1
This chapter gives guidance on meeting the
Technical Requirements forinternal
services, including:
the supply of hot and cold water
plumbing
gas
electrical installations.
8.1.1 Compliance 01
8.1.2 Provision of information 01
8.1.3 Water services and supply 01
8.1.4 Cold water storage 03
8.1.5 Hot water service 04
8.1.6 Soil and waste systems 05
8.1.7 Electrical services and installations 06
8.1.8 Gas service installations 07
8.1.9 Meters 07
8.1.10 Space heating systems 08
8.1.11 Installation 08
8.1.12 Extract ducts 10
8.1.13 Testing and commissioning 11
2021
Internal services
1 1
CHAPTER 8.1
8.1.3 Water services and supply Also see: water regulations and guides, BS EN 806
Water services shall be based on the pressures and flow rates supplied from the incoming main.
Components shall be selected and installed to ensure satisfactory service for the life of the system,
with suitable precautions taken against corrosion and damage. Issues to be taken into account include:
a) suitability of materials and components c) durability
b) adequate supply d) protection from the cold.
Adequate supply
The design and installation of the water services supply should:
be in accordance with building regulations, statutory
ensure that stop valves within the curtilage and outside the
requirements and the recommendations of the water supplier home are protected by a shaft or box
ensure drinking water is provided at the kitchen sink direct
ensure service pipes are a minimum of 750mm below the
from the supply pipe or, where this is impracticable, from a ground surface – where this is not possible, adequate
storage cistern containing an adequate supply of precautions should be taken against frost and
drinking water mechanical damage
be based on a minimum 1.5 bar dynamic pressure at the
ensure that underground ducts are sealed at both ends to
stop valve inside the home prevent the entry of fluids, vermin and insects
ensure a minimum 20L/min flow rate is available at the stop
be of materials which are safe and minimise the risk
valve inside the home of corrosion
account for pressure and flow rate reductions (a wider
be in accordance with the recommendations of the water
supply pipe may be required inside the home) supplier, including compatibility of the supply with the
account for pressure fluctuations and surges, which may
materials and fittings.
occur within the system and potentially damage fittings
(surge arresters may be required)
The water system should be capable of being drained (hot and cold services separately).
Durability
The hot and cold water service should be installed using corrosion resistant pipes and fittings.
In areas where pitting corrosion of copper cylinders occurs, it may be necessary to fit aluminium protector rods. These should be
fitted during manufacture in accordance with the relevant British Standard. Sacrificial anodes should be installed where required
by the water supplier.
insulation
thickness
insulated
water pipes
cold air
Table 1: Minimum insulation thickness to delay freezing inside domestic premises for cold water systems
8.1
min.
750mm
any distance
Access should:
be provided to the main roof space and voids that contain
include a minimum 1m2 platform located for
cisterns and tanks, etc. (not required to roof spaces maintenance purposes
containing only water pipes) include securely fixed boarded walkways between the
be via an opening (access hatch) with a minimum width of
opening and the cistern or other permanent equipment
520mm in each direction (boarding should be securely fixed without compressing
not be located directly over stairs or in other
the insulation).
hazardous locations
(4)
0.20 (12)
(4)
0.30 (18)
0.20 (12)
Notes
1 Shower may be over the bath or in a separate enclosure within the bathroom.
2 Demand based on ‘Design’ flow rate of bath.
3 Demand based on minimum acceptable boiler output.
4 Demand based on use of the shower in preference to the bath.
5 The hot water system should supply at least the hot water demand stated and take account of distribution heat losses through the pipework. The suitability of
instantaneous systems (combination boilers) will be limited by their performance as quoted by the boiler manufacturer.
Hot water storage should comply with the minimum capacity in Table 5 (based on a draw-off temperature of 60°C), and where
appliances require greater volumes, the capacity should be increased accordingly.
2021
Internal services
55
CHAPTER 8.1
Where systems are heated by off-peak electricity, the storage capacity should be in accordance with the recommendations of the
electricity supplier.
Where homes have one bathroom or shower room, the system should be able to provide adequate hot water:
immediately after the bath has been filled, for tasks such
for a second bath after 20 minutes.
as washing
Where homes have two or more bathrooms, the system should be able to provide adequate hot water immediately after each of
the baths have been filled, for tasks such as washing.
Where a shower is installed, adequate provision should be made to ensure that the outlet temperature of the water is not
significantly affected by the use of other hot or cold outlets in the home. This may be achieved by the provision of a thermostatic
shower mixing valve, the appropriate design of pipe sizes or dedicated supplies.
Instantaneous systems (using combination boilers) produce hot water on demand (generally at lower flow rates than
storage systems), and should only be used where:
simultaneous demand for hot water is limited. Where there
storage combination boilers have the capacity as required
are three or more outlets, the design for simultaneous in Table 5. Where boilers can control and prioritise hot water
discharge can omit the outlet at the kitchen sink outputs the storage capacities can be less than the figures
in Table 5 subject to manufacturer’s recommendations on
meeting the demand.
Storage systems provide higher flow rates than instantaneous systems, and:
require a suitable space for the siting of the storage vessel
where vented, should be provided with an expansion pipe.
Unvented hot water storage systems should be:
assessed in accordance with Technical Requirement R3, or
installed by competent installers.
meet the requirements of BS EN 12897 and be the subject
of third-party certification, e.g. Kitemarking (applies to both
the assembled system and components)
Hot water cylinders should be:
supported in accordance with accessible for maintenance
manufacturer’s recommendations insulated as specified in the design.
installed vertically, unless designed otherwise
Where an immersion heater is fitted, it should be:
appropriate for the type of water supplied to the home
located to facilitate replacement
controlled by a thermostat
fitted with an on/off switch.
8.1.6 Soil and waste systems Also see: BS EN 752 and BS EN 12056
8.1
Soil and waste systems shall be in accordance with relevant building regulations and installed to ensure
that effluent is removed without affecting health or creating unnecessary noise and smell.
Soil and waste systems should be:
in accordance with the requirements of the water supplier
900mm
min.
adequately ventilated at the head of underground drains
(this may be by a soil pipe or separate ventilation pipe)
openings soil pipe or
adequately ventilated at each branch
ventilation
pipe
arranged to ensure foul air from the drainage system cannot
less than 3m
enter homes (e.g. ventilated to 900mm above openings when
within 3m)
fixed neatly and securely to provide the correct falls
fitted to prevent the entry of vermin.
2021
Internal services
66
CHAPTER 8.1
The junctions of wall tiling with baths and showers should be made watertight using a flexible sealant to accommodate
movement. The manufacturer’s instructions should be followed.
8.1.7 Electrical services and installations Also see: BRE report ‘Thermal insulation: avoiding risks’
Electrical installations shall be provided in accordance with relevant regulations, codes and standards.
The installation shall ensure safe and satisfactory operation and be protected from chemical attack.
Electrical services and installations should:
comply with BS 7671 ‘Requirements for
be installed in accordance with the
electrical installations’ manufacturer’s recommendations
comply with BS 6004 ‘Electric cables. PVC insulated and
ensure cables are not placed under, against or within
PVC sheathed cables for voltages up to and including thermal insulation, unless they have been appropriately
300/500 V, for electric power and lighting’. sized and derated
have fittings and components located in accordance with
ensure PVC covered cables are not in contact with
relevant building regulations polystyrene insulation.
Rooms should be provided with the minimum number of 13A outlets listed in Table 6 (dual outlets count as two).
Table 6: Minimum number of outlets
8.1
Cables without special protection, such as an earthed vertically or horizontally in shaded zone
to switch or outlet 150mm wide
metal conduit, should be positioned:
vertically or horizontally from the outlet or switch being served
within the shaded zone in the diagram, or
a minimum of 50mm from the surface of a wall, or a minimum
of 50mm from the top or bottom of a timber joist, or batten in
a floor or ceiling.
Where the position of switches or sockets can be determined
from the reverse side of the wall or partition, the zone on one
side of the wall or partition applies to the reverse side.
Lighting outlets
Lighting outlets should be provided:
in each room, hall, landing and staircases
in the common areas of homes and controlled by either
with two-way switching at each floor level in a staircase
manual switching or automatic light-sensitive controls.
Cooking spaces
Cooking spaces should:
have a minimum 30A supply which is suitably switched
where provided, have cooker panels located to the side of
and terminated the cooker space.
have a 13A socket outlet where there is a gas supply
Electrical supply to gas appliances
Where a gas appliance requires an electrical supply, a suitable fixed spur or socket outlet should be provided.
TV
Aerials are not required; however, one of the following should be provided:
a concealed, coaxial cable from the roof void to a terminal
a conduit and draw wire or suitable alternative.
outlet in the main living room
8.1.8 Gas service installations Also see: Chapters 6.2, 6.8, BS 6400 and BS 6891
Gas service installations shall be adequate and comply with the gas safety regulations, and be in
accordance with relevant standards and codes to ensure safe and satisfactory operation.
Gas service installations should ensure:
service pipework up to and including the emergency control where there is a gas supply to the home, a gas point at
valve and meter is in accordance with the requirements of the cooker space should be provided. This is not required
the gas transporter, gas supplier and primary meter owner where an electric hob is provided
installation of pipework and appliances complies with where gas pipework is to be installed in timber frame,
relevant standards and codes including those published by allowance is made for differential movement.
the Institution of Gas Engineers and Managers (IGEM) or
Gas Safe Register (GSR)
Openings in walls for meter cabinets shall be structurally adequate and prevent dampness entering the home.
Openings set into external walls should be provided with: cavity tray
Space heating appliances, including all components and controls, should be of a type approved by the relevant authority,
including:
Solid fuel – Solid Fuel Association, Heating Equipment
Electricity – British Electrotechnical Approvals Board
Testing & Approval Scheme Oil – OFTEC.
The provision of whole home or central heating is discretionary. Where provided, it should be designed in accordance with
Table 7, recognised standards, and:
the number of air changes per hour from kitchens and
design temperatures should be verified by calculations and
bathrooms should account for any mechanical ventilation not by performance tests
where rooms contain open flued appliances, the rate of
the main living room should have a heating appliance or a
air change used for the design should be increased in heat output as part of a whole home heating system
accordance with BS EN 12828 temperature calculations should be based on
a -3°C external temperature.
Table 7: Room temperatures and ventilation rates
Room Room temperature °C Ventilation rate (air changes per hour)
Living room 21 1.5
Dining room 21 1.5
Bedroom 18 1
Hall and landing 18 1.5
Kitchen 18 2
Bathroom 22 2
Toilet 18 2
8.1.11 Installation
Internal services shall not adversely affect the stability of the home and be installed to ensure
satisfactory operation. Issues to be taken into account include:
a) fitting of pipes and cables c) concealed services.
b) notching and drilling of joists
8.1
Metallic tape should be placed behind plastic pipework, where it is concealed behind wall surfaces, and would otherwise not be
located by a metal detector or similar equipment.
Joints in pipes should be made:
strictly in accordance with the manufacturer’s instructions
using lead-free flux recommended by the pipe manufacturer,
with traces removed immediately after jointing.
Fire stopping should be provided around any services which penetrate fire-resisting floors, walls or partitions. Where a proprietary
system, such as an intumescent seal is used, it should be installed in accordance with the manufacturer’s instructions.
holes separated
by a min. 3 x
hole diameter
Where the structural strength is impaired by notching or drilling, the element should be replaced or correctly repaired.
Holes should be spaced at a minimum of three times the hole diameter.
Notches and holes in the same joist should be separated by a minimum horizontal distance of 100mm.
Instructions should be obtained from the designer when notching and drilling, where:
the joist is deeper than 250mm, or
it is close to heavy loads, such as those from partitions,
the dimensions are not in accordance with Table 8, or
cisterns, cylinders and stair trimming.
I-joists
Preformed holes are provided, and additional holes and notches should not be cut without the approval of the manufacturer.
Metal web joists
Services should run in the gaps between the metal webs. Conduits may need to be inserted before the joists are fixed in position.
8.1
Lightweight steel
Light weight steel should be used in accordance with Chapter 6.10 ‘Light steel framed walls and floors’.
Concealed services
Services concealed in walls or floors should be located so that significant cracking of the surface does not occur. Where chases
in walls are necessary, their depth should not exceed:
1/6 thickness of the single leaf for horizontal chases
1/3 thickness for vertical chases.
Hollow blocks should not be chased unless specifically permitted by the manufacturer.
2021
Internal services
10
10
CHAPTER 8.1
Building integration
The route of ductwork should take account of other building elements. Ductwork passing through structural elements should not
adversely affect the structural or fire performance of the building. Where alterations to structural elements, such as I-joists,
are required, this should only be carried out in accordance with the manufacturer’s recommendations, or be designed by an
engineer in accordance with Technical Requirement R5.
The fire requirements of the building should be in accordance with relevant building regulations and standards. Issues that
should be taken into account include:
suitable detailing of components passing through other the integrity of protected stairs and halls
elements of the building the integrity of walls and floors.
the location and type of dampers and firestops to be used
Resistance to airflow
Ductwork systems should be designed to minimise the resistance to airflow, and be formed from compatible components.
Rigid duct is preferable to flexible, but where flexible duct is used, it should be restricted in length to ensure that the airflow
resistance does not prevent the designed ventilation rate from being achieved. Flexible duct should be installed:
straight
in accordance with the manufacturer’s recommendations.
Bends should generally be formed with proprietary rigid components. Where flexible duct is used to form bends on an
intermittent extract system, they should be restricted to a maximum of:
two for systems up to 30 L/s one for extract rates higher than 30 L/s.
Control of condensation
Where extract ductwork passes through unheated spaces, it should be continuously insulated to achieve a thermal resistance
equivalent to a minimum of 25mm of insulating material with a thermal conductivity of 0.04W/(mK). This can be achieved by
using:
suitable pre-insulated ductwork, or
a proprietary insulation system.
8.1
Alternatively, the ductwork can be fitted with a condensate trap that discharges to the outside or installing the duct to slope to
the outside.
unheated
unheated space
space
condensate trap
2021
Internal services
11 11
CHAPTER 8.1
Installation
Ductwork should be installed in a neat and workmanlike manner, be securely fixed, and have:
adequate support throughout its length
sealed mechanically fixed joints and connections.
Where ductwork passes through an external wall, it should be positioned to slope slightly outwards to prevent water entering
the building. Clips and supports for ductwork should be spaced at equal distances and in accordance with the ductwork
manufacturer’s recommendations. For rigid ductwork, they should not generally be more than 750mm apart.
Ductwork should not be in direct contact with other surfaces, such as plasterboard ceilings, that may transfer noise to the home.
Terminals
Ventilation systems should terminate freely to open air.
The air flow resistance of terminals should not adversely affect the performance of the ventilation system. Airflow resistance of
terminals can be obtained through testing in accordance with BS EN 13141-2.
terminal extracting
to open air
insulation removed
for clarity
8.2.1 Compliance 02
8.2.2 Provision of information 03
8.2.3 Clean Air Act 03
8.2.4 System design 03
8.2.5 Access 04
8.2.6 Handling, storage and protection 04
8.2.7 Sequence of work 04
8.2.8 Location 04
8.2.9 Building integration 04
8.2.10 Fixing 05
8.2.11 Electrical installation requirements 06
8.2.12 Pipes, insulation and protection
from cold 06
8.2.13 Ground collectors 06
8.2.14 Fuel storage 07
8.2.15 Safe discharge 07
8.2.16 Testing and commissioning 07
8.2.17 Handover requirements 07
8.2.18 Further information 07
2021
Low or zero carbon technologies
1 1
CHAPTER 8.2
Introduction
This chapter provides guidance on low or zero carbon (LZC) technologies acceptable to NHBC. Other systems that
follow the general principles of this chapter may also be acceptable, subject to specific agreement with NHBC.
Additional requirements for solid fuel and oil fired boilers are given in Chapter 6.8 ‘Fireplaces, chimneys and flues’.
Guidance on other internal services is given in Chapter 8.1 ‘Internal services’.
This chapter provides guidance on the following technologies:
expansion pump
vessel
feed
feed
output
(demand)
generation export pump
inverter meter meter
output output
solar
(export) thermal
consumer import
unit meter
PV array expansion
vessel +
relief valve discharge
storage
feed vessel
AC mains supply
Wind turbine
Systems which convert wind energy into electricity.
8.2
output
(demand)
generation export
inverter meter meter
output
(export)
consumer import
unit meter
AC mains supply
The illustrations provided within the introduction are generic and do not indicate the only possible systems acceptable to NHBC.
2021
Low or zero carbon technologies
22
CHAPTER 8.2
LZC technologies that comply with the guidance in this chapter will generally be acceptable.
Relevant standards
LZC should comply with relevant standards including where applicable:
Product certification
LZC technologies should have current certification confirming satisfactory assessment by an appropriate independent authority
acceptable to NHBC.
Systems, products and installations that are assessed through the Microgeneration Certification Scheme (MCS) will generally be
acceptable to NHBC. Certification and test documentation should be made available to NHBC upon request.
Other certification bodies or test documentation may be acceptable where they are considered by NHBC to be a suitable
alternative.
Operative competency
LZC systems should be installed by operatives:
competent and familiar with the system being installed, and
certified to a standard acceptable to NHBC.
Installers who have been trained in accordance with the MCS installer standards will generally be acceptable to NHBC.
Biomass boilers to be installed within a smoke controlled area should comply with the Clean Air Act 1993 or
Clean Air (Northern Ireland) Order 1981.
LZC technologies should be designed in accordance with the manufacturer’s recommendations, certification scheme requirements
and appropriate standards.
8.2
Location
The design and location of LZC technologies should take account of factors such as orientation, roof pitch and shading.
For stand-alone wind turbine systems, suitable exclusion zones should be provided in accordance with the manufacturer’s
recommendations and geographical location.
Acoustics
Design and location should take account of:
internal and external noise
the effect on neighbouring properties, particularly the
vibration
positioning of the LZC technology in relation to openings.
2021
Low or zero carbon technologies
44
CHAPTER 8.2
Systems
Each system should generally be supplied from one manufacturer as a package and not as individual components or materials.
However, where components from more than one manufacturer are used, they should be compatible to ensure
satisfactory performance.
Compatibility
LZC technologies should be installed so as not to adversely affect the performance of the building to which they are fixed, and in
accordance with the manufacturer’s recommendations.
Multiple systems should be compatible with each other.
Performance
LZC technologies designed to contribute towards space and water heating should be designed in accordance with the
performance requirements in Chapter 8.1 ‘Internal services’.
8.2.5 Access
Appropriate arrangements shall be provided for the purposes of cleaning, inspection, maintenance and
repair of LZC technologies.
Safe access should be provided to the LZC technologies, including switchgear, inverters, meters and controls. This is to
enable the cleaning, inspection, maintenance and repair of systems. Access should be provided in accordance with the
manufacturer’s recommendations.
To ensure performance, certain LZC systems and ancillary components should be installed in a logical and timely sequence in
accordance with the manufacturer’s recommendations.
8.2.8 Location
LZC technologies shall be correctly located.
LZC technologies, including ancillary components should be located and identified in accordance with the
manufacturer’s recommendations.
LZC technologies shall be securely fixed and not adversely affect the weather resistance of the building.
Foundations and anchor points for stand-alone LZC technologies should be designed by an engineer in accordance with Technical
Requirement R5 to withstand the structural forces acting upon them.
The structure to which the LZC technology is attached should be assessed according to its ability to accept the loadings and
prevent detrimental effects arising from movement or vibration. The design of the structure should take account of:
the self-weight of the LZC components
snow loads
imposed loads
dynamic loading (where relevant).
wind loads
2021
Low or zero carbon technologies
55
CHAPTER 8.2
All interfaces between the LZC technology and the building should ensure adequate weather resistance, sealed to limit air leakage
and prevent moisture from reaching the interior or any part of the structure that could be adversely affected by its presence. The
envelope should be weatherproofed using appropriate flashings and fixings. Weatherproofing details that rely solely on sealant are
not acceptable. Flashings should be formed from the materials listed in Table 1.
Table 1: Materials for flashings
Flashing material Guidance
Rolled lead sheet Minimum code 4. BS EN 12588.
Aluminium and aluminium alloys BS EN 485 and BS EN 573, 0.6-0.9mm thick and protected from contact with mortar by
a coating of bituminous paint.
Zinc alloys BS EN 988 and 0.6mm thick.
Copper BS EN 1172 0.55mm thick and fully annealed. Where two metals are to be joined,
they should be compatible and not cause bimetallic corrosion in that environment
Alternatively, they should be isolated from each other.
Proprietary flashing, Assessed in accordance with Technical Requirement R3.
including plastic and composite.
To avoid potential surface or interstitial condensation, the design should take account of thermal bridging, particularly where any
part of the system, including fixings, penetrates the thermal envelope.
Materials that comply with recognised standards, which provide equal or better performance to those above, are also acceptable.
The type, size, number, position and fitting tolerance of fixings should be in accordance with the manufacturer’s recommendations.
Issues that should be taken into account include:
the provision of suitable locking nuts and washers
the isolation of aluminium from cementitious material.
the isolation of dissimilar metals
Electrical installations should comply with BS 7671 ‘Requirements for Electrical Installations’.
Where parallel electrical generation occurs, inverters should have a current Engineering Recommendation G83/2 type test
certificate and comply with all other parts of ER G83/2 for standard installations. Larger installations should comply with
ER G59/3-2.
The electrical installation should be capable of being isolated from all other electrical sources when required, for maintenance
or testing.
LZC technologies which generate electricity and are connected to the mains should automatically disconnect when there is a
mains power failure. This is to prevent them from feeding the network or local distribution system during a planned or unscheduled
loss of mains supply. This is known as ‘islanding’.
The depth and layout of ground collectors should be specified to avoid freezing of adjacent ground. Where open loop systems are
proposed, consultation with the appropriate environment agency should be made and may require one or more of the following:
A licence to investigate groundwater.
A discharge consent.
An abstraction licence.
Excavations for the installation of ground collectors should not adversely affect aquifers, foundations, drainage, water supply pipes
and other services. Design should take account of local planning authority guidance, including excavations that are close to trees
and hedgerows.
Ground collectors should be protected and tested prior to backfilling.
2021
Low or zero carbon technologies
77
CHAPTER 8.2
8.2.14 Fuel storage Also see: The HVCA Guide to Good Practice Installation of Biofuel Heating (TR/38)
Fuel storage for biomass boilers shall be suitable for the installation.
Solar thermal water heating systems should discharge into a storage vessel. The discharge pipework and vessel should be
suitable to withstand high temperatures.
The installer should check that the system is in accordance with the certification requirements, the manufacturer’s
recommendations and the design. Issues to be taken into account include:
the safety of the system
the correct operation of the system.
the correct installation of the system
Upon completion, the installer should provide a certificate to confirm that the LZC technology has been installed, tested and
commissioned in accordance with the above.
ER G59/3-4 Recommendations for the Connection of recommendations for the protection against corrosion of iron
Generating Plant to the Distribution Systems of Licensed and steel in structures. Sherardizing
Distribution Network Operators’
BRE Digest DIG 489 Wind loads on roof-mounted
ER G83/2-1 Recommendations for the Connection of Type photovoltaic and solar thermal systems’.
Tested Small-scale Embedded Generators (Up to 16A per
Phase) in Parallel with Low-Voltage Distribution Systems
BS EN ISO 14713-1:2017. Zinc coatings. Guidelines and
recommendations for the protection against corrosion of
iron and steel in structures. General principles of design and
corrosion resistance
Mechanical ventilation
with heat recovery
CHAPTER 8.3
This chapter provides guidance on
mechanical ventilation with heat recovery
(MVHR) systems acceptable to NHBC.
8.3.1 Compliance 01
8.3.2 Provision of information 01
8.3.3 Building integration 01
8.3.4 Noise 02
8.3.5 Design considerations 02
8.3.6 Access and operation 04
8.3.7 Ductwork 04
8.3.8 Fixing and jointing of ductwork 04
8.3.9 Commissioning and balancing 05
8.3.10 Handover requirements 05
Also see: Chapter 2.1, Approved Document F, Domestic Ventilation Compliance Guide,
Section 3 of the Technical Handbooks, Domestic Ventilation Guide in Scotland and
8.3.1 Compliance Technical Booklets in Northern Ireland
MVHR design, materials and sitework shall comply with the Technical Requirements, and be installed by
competent operatives.
MVHR systems that comply with the guidance in this chapter and are in accordance with the relevant British Standards and
building regulations will generally be acceptable.
MVHR systems should be installed by operatives:
competent and familiar with the system being installed, and
trained in accordance with the BPEC installer scheme,
or other suitable scheme acceptable to NHBC.
a) weathertightness c) firestopping.
b) fixing of fan units
Weathertightness
Proprietary roof terminals should be used to ensure the weathertightness of the roof covering.
Firestopping
The MVHR system should not adversely affect the fire performance of the building. Issues to be taken into account include:
ensuring that the fire requirements of the building are in
location and type of firestops to be used
accordance with relevant building regulations integrity of protected stairs and halls
suitable detailing of components passing through other
integrity of walls and floors.
elements of the building
Proprietary fire components should be suitably tested, and specified to take account of the test conditions.
Relevant standards include:
BS 476 ‘Fire tests on building materials and structures.’
BS EN 1365-2 ‘Fire resistance tests for loadbearing elements. Floors and roofs.’
BS EN 1366-3 ‘Fire resistance tests for service installations. Penetration seals.’
8.3.4 Noise
MVHR systems shall be designed to minimise disturbance caused by noise.
MVHR fan units should be sized to run at their optimum speed and to provide suitable performance whilst taking the resulting
noise and vibration into account. Specifying MVHR fan units that can provide the required airflow rates when running at less than
full speed can reduce unnecessary noise.
Ductwork should be sized to allow air to pass freely without causing excessive noise disturbance. To reduce noise transfer
along ductwork, a short length of flexible duct can be installed adjacent to air valves and fan units. Other issues to be taken into
account include:
noise between habitable rooms
location of the MVHR fan unit
external noise
the type of mountings used to secure the MVHR fan unit.
Performance
The MVHR system should be designed to provide satisfactory performance and be installed according to the design and
manufacturer’s recommendations. Variations from the design should maintain the satisfactory performance of the system and be
approved by the designer.
Issues that should be taken into account include:
ventilation rates as set out in appropriate building
ensuring the even distribution of airflow, taking into account
regulations and standards airflow resistance, including from bends and fittings.
fan capacity, accounting for airflow resistance of
8.3
the system
Airflow resistance should be calculated using figures for air valves and terminals determined in accordance with BS EN 13141-2
and data supplied by the duct manufacturer. Ductwork should be as direct as possible to reduce the number of bends.
Allowance should be made for air transfer within the home. Where gaps between the underside of internal doors and the floor
finish are used for air transfer, the guidance in Chapter 9.1 ‘A consistent approach to finishes’ should be considered.
Systemised approach
The MVHR system should be designed as a complete package, taking into account the performance of all components
and materials, to ensure compatibility and the performance requirements of the system.
Particular consideration should be given where components from different manufacturers are specified on the same system.
2021
Mechanical ventilation with heat recovery
33
CHAPTER 8.3
To create cross-ventilation within a room and to ensure satisfactory operation, air valves on low velocity systems should be:
positioned on the opposite side of the room from internal positioned to account for the likely location of tall furniture
door openings and to avoid draughts over beds and seating areas
a minimum of 200mm from walls, where located on a ceiling lockable, where adjustable.
a maximum of 400mm from the ceiling, where located
on a wall
a minimum of 600mm (on plan) from hobs in kitchens
To prevent cross-contamination, intake terminals should generally be separated from exhaust terminals and other potential
sources of pollution by a minimum of 1m measured on plan. Increased separation distances may be required between the intake
and any:
soil and vent pipe terminal biomass or solid fuel chimney terminal.
boiler flue outlet
Control of condensation
Ductwork should be insulated to prevent condensation formation where:
it passes through spaces outside the insulated parts of carrying cold air through spaces that are within the insulated
the home, such as a roof void parts of the home.
This can be achieved by using suitable pre-insulated ductwork, or a proprietary insulation system with a thermal resistance
equivalent to a minimum of 25mm of insulating material, with a thermal conductivity of 0.04W/Mk.
Ductwork insulation, including that used for proprietary duct insulation systems and pre-insulated ducts should be:
inert, durable and suitable for use with the ductwork system installed in a neat and workmanlike manner to ensure that
continuous and vapour resistant there are no gaps
not adversely affected by moisture vapour installed in accordance with the
manufacturer’s recommendations.
Where a vapour control layer is incorporated, the joints should be sealed using appropriate tapes or sealants as recommended
by the manufacturer.
Table 1: Ductwork insulation
Type of duct Ductwork continuously insulated
Ductwork located inside the insulated Ductwork located outside the insulated part of
part of the home the home
Intake Yes Yes
Exhaust Yes Yes
Service (supply and extract) No Yes(1)
Notes
8.3
1 Additional insulation should be provided to protect the system from the cold.
Any condensate that forms within the fan unit or ductwork should be able to drain to a suitable outfall. Fan units should be
located to enable connection of the condensate drain to the soil and waste system via a dry trap.
To prevent damage to the components and ensure satisfactory operation, MVHR systems should be fitted with automatic
frost protection.
2021
Mechanical ventilation with heat recovery
44
CHAPTER 8.3
Horizontal sections of service ductwork, outside the insulated pre-insulated to achieve a thermal
performance equivalent to at least 25mm
parts of the home, should be insulated to achieve a thermal of insulating material with a thermal
conductivity of 0.04W/Mk
resistance equivalent to at least 150mm of insulating material
with a thermal conductivity of 0.04W/Mk. This may be
achieved by installing the ductwork between the layers
of horizontal insulation.
Condensate drains located outside the insulated part of the
home should be insulated to prevent freezing.
loft insulation used to achieve a total thermal performance
equivalent to at least 150mm of insulating material with
a thermal conductivity of 0.04W/Mk
8.3.7 Ductwork
Ductwork design and the materials used should be suitable for the intended purpose and not adversely
affect the performance of the building.
Ductwork should:
provide satisfactory performance for the life of the system
be routed as directly as practicable
be of a rigid or semi-rigid material suitable for use in MVHR
systems
be fixed in accordance with the manufacturer’s
recommendations.
air valve
8.3
Bends, connections and junctions should be formed using proprietary components that are part of the ductwork system.
Flexible ducting should:
only be located adjacent to fan units or air valves not be used to form bends.
not be more than 300mm in length
Where ductwork routes require alterations to structural elements, these should be in accordance with the manufacturer’s
recommendations or in accordance with Technical Requirement R5.
Jointing
The method and materials used for jointing ductwork should be specified by the duct manufacturer, and be:
durable and airtight
sealed with purpose-designed connections in accordance
securely fixed
with the manufacturer’s recommendations.
Where tapes and sealants are used, they should be suitable for the intended purpose and be recommended by the
ductwork manufacturer. Issues to be taken into account in relation to the durability of the jointing method include:
thermal movement
temperature
moisture
compatibility with the duct material.
Tape should be installed in a neat and workmanlike manner, and surfaces should be dry and free from grease and dust
before applying. Excess sealant should not extrude to the inside of the duct.
Where the system cannot be balanced using the air valves and system controls, the complete system should be checked to
ensure that it complies with the design.
Any changes from the design should be referred back to the designer. Adjusting the fan speed above the designed output may
result in noise disturbance, and should be avoided.
A copy of the commissioning certificate should be made available to NHBC upon request.
8.3