Schedule of Rates Amravati-Nagpur Region YEAR 2018-2019: Material
Schedule of Rates Amravati-Nagpur Region YEAR 2018-2019: Material
AMRAVATI-NAGPUR REGION
YEAR 2018-2019
MATERIAL
REINFORCEMENT
AREA: 10
NO. OF LABOUR: 4 KARIGAR + 3 HELPER + 1 FOREMAN
RATE OF LABOUR: KARIGAR- ₹ 800
HELPER - ₹ 362
FOREMAN- ₹ 1000
AMOUNT PAID: 4*800+3*362+1*1000= ₹ 5286
AREA: 10 sq. m.
APPROXIMATE RATE: ₹ 280/sq. m.
AMOUNT TO BE PAID: ₹ 2800
SHUTTERING
AREA: 10 sq.m.
NO. OF LABOUR: 7 KARIGAR + 3 HELPER + 1 FOREMAN
RATE OF LABOUR : KARIGAR- ₹800
HELPER - ₹362
FOREMAN - ₹1000
AMOUNT PAID: 7*800+3*362+1*1000= ₹7686
AREA: 10 sq. m.
APPROXIMATE RATE: ₹ 200 sq.m.
AMOUNT PAID: ₹ 2000
CASTING
AREA: 10
NO. OF LABOUR: 3 LABOUR
RATE OF LABOUR: ₹ 362
AMOUNT PAID: 3*362= ₹ 1086
AREA: 10 sq.m.
APPROXIMATE RATE: ₹100 sq.m. (JUST LABOUR)
AMOUNT PAID: ₹1000
AREA: 10 sq.m.
APPROXIMATE RATE: ₹150 sq.m. (INCL. LABOUR, RAIL, MIXER MACHINE)
AMOUNT PAID: ₹1500
MASONRY
AREA: 10
NO. OF LABOUR: 2 MASONS + 3 HELPER
RATE OF LABOUR: MASON-₹312
HELPER-₹312
AMOUNT PAID: 2*312+3*312=₹1560
AREA: 10 sq.m.
APPROXIMATE RATE: ₹150 sq.m. (INCL. LABOUR, RAIL, MIXER MACHINE)
AMOUNT PAID: ₹1500
PLASTER
AREA: 10
NO. OF LABOUR: 2 MASONS + 3 HELPER
RATE OF LABOUR: MASON-₹312
HELPER-₹312
AMOUNT PAID: 2*312+3*312=₹1560
AREA: 10 sq.m.
APPROXIMATE RATE: ₹150 sq.m. (INCL. LABOUR, RAIL, MIXER MACHINE)
AMOUNT PAID: ₹1500
FLOORING
AREA: 10
NO. OF LABOUR: 2 MASONS + 2 HELPER
RATE OF LABOUR: MASON-₹312
HELPER-₹312
AMOUNT PAID: 2*312+2*312=₹1560
AREA: 10 sq.m.
PAINT
AREA: 10
NO. OF LABOUR: 1 MASONS + 1 HELPER
RATE OF LABOUR: MASON-₹312
HELPER-₹312
AMOUNT PAID: 1*312+1*312=₹1560
AREA: 10 sq.m.
APPROXIMATE RATE: ₹150 sq.m. (INCL. LABOUR, RAIL, MIXER MACHINE)
AMOUNT PAID: ₹1500
APPROXIMATE RATE: ₹150 sq.m. (INCL. LABOUR, RAIL, MIXER MACHINE)
AMOUNT PAID: ₹1500
CARPENTARY
AREA: 10
NO. OF LABOUR: 1 MASONS + 1 HELPER
RATE OF LABOUR: MASON-₹312
HELPER-₹312
AMOUNT PAID: 1*312+1*312=₹1560
AREA: 10 sq.m.
APPROXIMATE RATE: ₹150 sq.m. (INCL. LABOUR, RAIL, MIXER MACHINE)
AMOUNT PAID: ₹1500
CONSTRUCTION COST
BILL OF QUANTITY
ITEM QUANTITY UNIT RATE TOTAL AMT.
BAZRI 46.53 Cu.m. 1400
BINDING WIRE 42.3 Kg 70
BITUMEN 71.91
BRICK BLAST 19.035
BRICK TILES 8460
BRICKS 41031
CEMENT 797.355
CEMENT FOR BASE COARSE 35.955
CEMENT GREY 48.645
CI PIPE 31.725
COARSE SAND 25.38
EARTH 19.035
EMULSION PAINT WITH LABOUR 888.3
EXTERIOR FINISHING WITH LABOUR 317.25
FINE SAND 29.3879
GLAZE TILES 105.75
IRON GRILLS 528.75
LABOUR FOR BRICK SUPER STRUCTURE
LABOUR FOR BRICK WORK FOUNDATION
LABOUR FOR CEILING PLASTER
LABOUR FOR CEMENT CONCRETE
LABOUR FOR DPC
LABOUR FOR EARTH EXCAVATION & EARTH FILLING
LABOUR FOR PIPE INCLUDING COST OF JOINTS
LABOUR FOR POINTING
LABOUR FOR RCC
LABOUR FOR STEEL RCC
LABOUR FOR WALL PLASTER
LABOUR FOR WHITE MARBLE FLOOR
MARBLE 226.305
MS STEEL 4230
SAND 65.565
SHUTTERING 3172.5
SPECIAL PAINT WITH LABOUR 423
STONE BLAST 40.185
TEAK WOD SHUTTER 31.725
TEAK WOOD 951.75
TEAKWOOD AND DECORATIVE 8.46
PLYWOOD
TEAKWOOD WINDOW SHUTTER 63.45
WHITE CEMENT 4.23
SUB TOTAL
FOUNDATION
ITEM QUANTITY UNIT RATE TOTAL AMT.
CEMENT CONCRETE 1:4:8
CEMENT 143.82
STONE BLAST 40.185
SAND 21.15
LABOUR FOR CEMENT CONRETE
TOTAL FOR CEMENT CONCRETE 1:4:8
BRICK WORK IN FOUNDATION WITH CEMENT MORTAR 1:4
LABOUR FOR BRICK WORK
FOUNDATION
SAND
CEMENT
BRICKS
TOTAL FOR BRICK WORK IN FOUNDATION WITH CEMENT
MORTAR 1:4
HORIZONTAL DPC WITH CEMENT CONCRETE 1:2:4( 40MM)
LABOUR FOR DPC
BITUMEN
CEMENT
COARSE SAND
BAZRI
TOTAL FOR HORIZONTAL DPC WITH CEMENT CONCRETE 1:2:4
( 40MM)
EARTH WORK IN EXCAVATION IN FOUNDATION AND FILLING UNDER FLOORS
LABOUR FOR EARTH EXCAVATION & EARTH FILLING
TOTAL FOR EARTH WORK IN EXCAVATION IN FOUNDATION AND
FILLING UNDER FLOORS
SUPER STRUCTURE
ITEM QUANTITY UNIT RATE TOTAL AMT.
RCC without Steel Cement Concrete 1:1.5:3
LABOUR FOR RCC
SHUTTERING
BAZRI
COARSE SAND
CEMENT
TOTAL FOR RCC WITHOUT STEEL CEMENT CONCRETE 1:1.5:3
MS Steel For RCC
MS STEEL
BINDING WIRE
LABOUR FOR STEEL RCC
TOTAL FOR MS STEEL FOR RCC
BRICK WORK IN SUPER STRUCTURE CEMENT MORTAR 1:4
LABOUR FOR BRICK SUP. STR
CEMENT
SAND
BRICKS
TOTAL FOR BRICK WORK IN SUPER STRUCTURE
CEMENT MORTAR 1:4
BRICK TILE TRACING ON ROOF
EARTH
SAND
CEMENT
LABOUR FOR BRICK TILES
BRICK TILES
BITUMEN
TOTAL FOR BRICK TILE TRACING ON ROOF
RAIN WATER PIPE
CI PIPE
LABOUR FOR PIPE INCLUDING COST
OF JOINTS
TOTAL FOR RAIN WATER PIPE
FLOORING
ITEM QUANTITY UNIT RATE TOTAL AMT.
White Marble Flooring
Marble
Cement Grey
White Cement
Cement for Base Coarse
Fine Sand
Brick Blast
Coarse Sand
Labour for White Marble Floor
Total for White Marble Flooring
PLASTERING/WALL TILES
ITEM QUANTITY UNIT RATE TOTAL AMT.
PLASTER ON CEILING (ROOF) CEMENT MORTAR 1:4
SAND
CEMENT
LABOUR FOR CEILING PLASTER
TOTAL FOR PLASTER ON CEILING (ROOF) CEMENT MORTAR 1:4
PLASTER ON WALLS CEMENT MORTAR 1:4
LABOUR FOR WALL PLASTER
CEMENT
SAND
TOTAL FOR PLASTER ON WALLS CEMENT MORTAR 1:4
CEMENT POINTING CEMENT MORTAR 1:2
Sand
Labour for Pointing
Cement
Total for Cement Pointing Cement Mortar 1:2
GLAZED TILES IN DADO OR SKIRTING IN BATHROOM SND KITCHEN WALLS
GLAZE TILE