CIDB Standard Form of Contract
CIDB Standard Form of Contract
BETWEEN………… ………………………………………………………………………………………..
[Name of Employer]
of ……………………………………………………………………………….………………………….
[Address of Employer]
……………………………………………………………………………………………………….
AND…………………………………………………………………………………………………
[Name of Contractor]
of ……………………………………………………………………………………………………
[Address of Contractor]
……………………………………………………………………………………………………….
WHEREAS:
(1) The Employer is desirous that certain Works should be designed (to the extent required
by the Contract), executed and completed by the Contractor, namely,
……………………………………………………………………………………………...
[Brief description of the Works]
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
applies) showing and describing the Works to be executed, to be prepared by or under the
(2) The Employer has accepted a Tender by the Contractor for the design (to the extent
provided for by the Contract Documents), execution and completion of the Works and the
remedy of Defects.
Article 1
mentioned the Contractor will upon and subject to the Contract Documents carry out the design
(to the extent required by the Contract), execute and complete the Works shown upon and
described by or referred to in the Contract Documents and remedy the Defects in accordance with
Article 2
The Employer will pay to the Contractor for the design (to the extent required by the Contract)
execution and completion of the Works and the remedy of Defects the sum of Malaysian Ringgit:
………………………………………………………………………………………………………
……………………………………………………………………… (RM………………………………….)
Only or such sum as may become payable under the provisions of the Contract (hereinafter called
the “Contract Sum”) at the times and in the manner prescribed by the Contract.
The following Contact Documents (in order of priority) shall be deemed to form and be read and
(7) The Schedule of Works or Bills of Quantities (if Option Module A applies); and
(a) ……………………………………………………….
(b) ……………………………………………………….
(c) ……………………………………………………….
(d) ……………………………………………………….
CIDB Standard Form of Contract for Building Works 2000 Edition III
- Articles of Agreement
Article 4
of ……………………………………………………………………………………………………
[Address of Superintending Officer]
……………………………………………………………………………………………………….
or in the event of his death or ceasing to be the Superintending Officer for the purpose of the
Contract, such other person as the Employer shall nominate and appoint within 30 days a
succeeding Superintending Officer for that purpose. Provided that during the continuance of the
Contract the person succeeding as the Superintending Officer shall not disregard or overrule any
decision, approval or instruction given to the Contractor in writing by his predecessor unless he is
satisfied that such action will not cause any pecuniary loss to the Contractor or unless such action
Article 5
or in the event of his death or ceasing to be the Architect for the purpose of the Contract, such
other person as the Employer shall nominate and appoint within 30 days a succeeding Architect
The term “Civil and Structural Engineer” in the Contract shall mean ……………………….……
……………………………………………………………………………………………………….
[Name of person]
of ……………………………………………………………………………………………………
[Address of Civil and Structural Engineer]
………………………………………………………………………………………………………
or in the event of his death or ceasing to be the Civil and Structural Engineer for the purpose of
the Contract, such other person as the Employer shall nominate and appoint within 30 days a
Article 7
The term “Mechanical and Electrical Engineer” in the Contract shall mean …………………….
……………………………………………………………………………………………………….
[Name of person]
of ……………………………………………………………………………………………………
[Address of Mechanical and Electrical Engineer]
………………………………………………………………………………………………………
or in the event of his death or ceasing to be the Mechanical and Electrical Engineer for the
purpose of the Contract, such other person as the Employer shall nominate and appoint within 30
Article 8
……………………………………………………………………………………………………….
[Name of person]
of ……………………………………………………………………………………………………
[Address of Quantity Surveyor]
………………………………………………………………………………………………………
Contract, such other person as the Employer shall nominate and appoint within 30 days a
Article 9
(1) ……………………………………………………………………………………………..
[Name of person]
in the capacity of …………………………………………………………………………...
[State the nature of specialist consultancy]
of …………………………………………………………………………………………...
[Address of the Specialist Consultant]
………………………………………………………………………………………………
(2) ……………………………………………………………………………………………..
[Name of person]
in the capacity of …………………………………………………………………………...
[State the nature of specialist consultancy]
of …………………………………………………………………………………………...
[Address of the Specialist Consultant]
………………………………………………………………………………………………
(3) ……………………………………………………………………………………………..
[Name of person]
in the capacity of …………………………………………………………………………...
[State the nature of specialist consultancy]
of …………………………………………………………………………………………...
[Address of the Specialist Consultant]
………………………………………………………………………………………………
or in the event of his death or ceasing to be the Specialist Consultant for the purpose of the
Contract, such other person as the Employer shall nominate and appoint within 30 days a
If any dispute or difference shall arise in connection with or out of the Contract or the execution
of the Works, such dispute or difference shall be resolved in accordance with the provisions of
Article 11
In these Articles of Agreement words and expressions shall have the same meanings as are
CIDB Standard Form of Contract for Building Works 2000 Edition VII
- Articles of Agreement
IN WITNESS WHEREOF
*The hand of the EMPLOYER has been hereunto set the day and year } Signature ……………….……………………….…...
}
first above written in the presence of:
}
} Name ……………………….……………..……..…..
}
}
Signature of Witness ………..……………………………………….… } Designation ………………………………………...
Name ……………………………………………….…………………...
IN WITNESS WHEREOF
*The hand of the CONTRACTOR has been hereunto set the day and } Signature ……………………….………….………...
}
year first above written in the presence of:
}
} Name ………………………………….……………..
}
Signature of Witness ….………………………………………….…… }
} Designation ………………………………………...
Name ……………………………………………………….…………...
* Delete as appropriate
The affixing of the Common Seal to be witnessed in accordance with the Articles of Association of the Company.
CIDB Standard Form of Contract for Building Works 2000 Edition VIII
- Articles of Agreement
TABLE OF CONTENTS
Page No.
CONDITIONS OF CONTRACT
4 CONTRACT DOCUMENTS 12
4.1 Contract Documents to be Mutually Explanatory 12
4.2 Custody of Contract Documents 12
4.3 Supply of Drawings by Superintending Officer 12
4.4 Supply of Drawings by the Contractor 13
4.5 Drawings to be Kept on Site 13
4.6 Need for Further Drawings 13
4.7 Supplementary Drawings and Instructions 14
4.8 Consequences of Delay in Supplying Further Drawings 14
4.9 Confidentiality and Limitation of Use of Documents 14
4.10 As-Built Drawings 15
CIDB Standard Form of Contract for Building Works 2000 Edition (i)
.- Contents for Conditions of Contract
Page No.
8 NOTICES 18
8.1 Serving of Notices 18
11 ENVIRONMENTAL MATTERS 21
11.1 Compliance with Environmental Quality Act 1974 21
12 SETTING OUT 21
12.1 Accurate Setting Out 21
12.2 Errors in Setting Out 21
13 SITE ADMINISTRATION 22
13.1 Days and Hours of Working 22
13.2 Contractor’s Representative 22
13.3 Removal of Workmen and Other Personnel 23
13.4 Access for Superintending Officer 23
15 QUALITY IN CONSTRUCTION 25
15.1 Equipment, Materials, Goods and Workmanship 25
15.2 Quality Assurance and Quality Control 25
15.3 Supply of Samples 25
15.4 Cost of Test 25
15.5 Examination and Measurement of Works before Covering Up 26
15.6 Uncovering and Making Openings 27
15.7 Defects during the Progress of the Works 27
16 LABOUR 28
16.1 Engagement of Workmen and Labour 28
16.2 Returns of Labour 28
CIDB Standard Form of Contract for Building Works 2000 Edition (ii)
.- Contents for Conditions of Contract
Page No.
18 OTHER CONTRACTORS 30
18.1 Employer’s Right to Employ Other Contractors 30
18.2 Inspection of Work Done by Other Contractors 30
19 SUSPENSION 31
19.1 Suspension of Work 31
19.2 Prolonged Suspension 31
19.3 Effects of Prolonged Suspension 32
21 TEST ON COMPLETION 34
21.1 Notice of Tests and Test Reports 34
21.2 Failure to Appoint Time for Test 34
21.3 Facilities for Test on Completion 34
21.4 Repeat Tests 34
22 SECTIONAL COMPLETION 35
22.1 Completion in Sections 35
CIDB Standard Form of Contract for Building Works 2000 Edition (iii)
.- Contents for Conditions of Contract
Page No.
28 VARIATIONS 45
28.1 Power to Order Variations 45
29 VALUATION OF VARIATIONS 46
29.1 Valuation Method 46
29.2 Agreement on Valuation 47
29.3 Inclusion of Variations in Interim Certificates 48
30 MEASUREMENT 48
30.1 Contractor to Attend Measurement 48
30.2 Contractor to Provide Assistance 48
30.3 Record of Measurements 49
30.4 Failure to Agree Measurements 49
CIDB Standard Form of Contract for Building Works 2000 Edition (iv)
.- Contents for Conditions of Contract
Page No.
34 GENERAL RESPONSIBILITIES 54
34.1 Care of the Works 54
34.2 Responsibility to Rectify Damage, Loss or Injury 55
35 INDEMNITY PROVISIONS 55
35.1 Injury to Persons 55
35.2 Damage to Property 55
35.3 Contribution 56
35.4 Contractor to Rectify Damage 56
35.5 Damage to Property of Employer or Relevant Authority 56
CIDB Standard Form of Contract for Building Works 2000 Edition (v)
.- Contents for Conditions of Contract
Page No.
42 PAYMENT 70
42.1 Statement of Work Done 70
42.2 Valuation and Interim Certificates 70
42.3 Retention Monies 71
42.4 Correction of Certificates 73
42.5 Statement at Completion 73
42.6 Penultimate Certificate 74
42.7 Final Claim Statement 74
42.8 Final Account and Final Certificate 75
42.9 Period of Honouring Certificate 76
42.10 Suspension for Non Payment 77
42.11 Deemed Payment 78
42.12 Delay in Certification 78
42.13 Effect of Payments other than Payment of Final Certificate 78
44 DETERMINATION BY EMPLOYER 80
44.1 Determination Due to Default By Contractor 80
44.2 Determination Due to Bankruptcy or Insolvency 81
44.3 Effects of Determination of Contractor’s Employment 82
44.4 Certificate of Termination Costs 84
44.5 Notices under Clause 44 85
47 SETTLEMENT OF DISPUTES 89
47.1 Reference to the Superintending Office 89
47.2 Reference to Mediation 89
47.3 Reference to Arbitration 90
47.4 Settlement of Dispute in the Event of Determination 92
49 GOVERNING LAW 92
49.1 Law 92
CIDB Standard Form of Contract for Building Works 2000 Edition (vi)
.- Contents for Conditions of Contract
Page No.
51 MISCELLANEOUS PROVISIONS 93
51.1 Business Ethics 93
51.2 Declaration Against Waiver 93
51.3 Notice of Garnishment 93
51.4 Stamp Duties 93
APPENDIX 94
CIDB Standard Form of Contract for Building Works 2000 Edition (vii)
.- Contents for Conditions of Contract
CONDITIONS OF CONTRACT
1 DEFINITIONS AND INTERPRETATION
1.1 Definitions Definitions
All Risks Insurance the insurance which provides cover against any
physical damage, loss or injury to work
executed and Equipment, materials or goods
and against the reasonable cost of the removal
and disposal of debris and of any shoring and
propping of the Works which results from such
physical damage, loss or injury but excluding
the cost necessary to repair, replace or rectify:
Contract Sum the sum set out in the Letter of Award and
Article 2 of the Articles of Agreement, and
shall be fixed subject only to adjustments
expressly provided for in the Conditions.
Rates for the Works those rates in the Schedule of Rates or the rates
and prices contained in the Bills of Quantities,
whichever is applicable, including any
modifications or additions to the same agreed
in writing by the Superintending Officer and
the Contractor.
(a) an individual, or
(b) the principal of a sole proprietorship, or
(c) a partner of a partnership, or
(d) a director of a corporation;
Time for Completion time for the completion of the Works or any
section of the Works set out in the Letter of
Award and/or Appendix subject to such
extension or extensions of time (if any) as the
Contractor may be entitled under the Contract.
(b) The Superintending Officer shall forthwith comply with any such
request, and if the Contractor shall thereafter comply with the
said instruction (neither party before such compliance having
given to the other a notice of his intention to refer the matter to
mediation under Clause 47.2 in order that it may decide whether
or not the provision specified by the Superintending Officer
empowers the issue of the said instruction), then the issue of the
same shall be deemed for all the purposes of the Contract to have
been empowered by the provisions of the Contract specified by
the Superintending Officer in answer to the Contractor’s request.
4 CONTRACT DOCUMENTS
4.1 Contract Documents to be Mutually Explanatory Contract
Documents to be
The several documents forming the Contract are to be taken as mutually Mutually
explanatory of one another but in the event of any conflict or Explanatory
inconsistency between the documents forming the Contract, the priority
shall be as follows:
(b) The Contractor may obtain from the Superintending Officer at his
own cost any further copies of the said documents required by
him.
(b) The Contractor shall supply at the Employer's cost any further
copies of such drawings, specifications and other documents as
the Superintending Officer may request in writing.
and if the progress or completion of the Works or any part of the Works
has been materially affected by such failure on the part of the
Superintending Officer then the Superintending Officer shall, subject to
Clauses 32 and 42, certify any Loss and Expense which the Contractor
has incurred and, subject to Clause 24, grant the Contractor an extension
of time.
(a) such drawings describing the Works or any section of the Works
as-built not later than 3 months from the Date of Practical
Completion of the Works (or the Date of Practical Completion in
respect of the relevant section of the Works, in the case of
completion in sections); and
5.2 Works Programme and Method Statement not Part of Contract Works
Document Programme and
Method Statement
(a) The works programme and method statement shall not constitute not Part of
Contract
part of the Contract Documents.
Document
(b) The submission to and approval by the Superintending Office of
such works programme and method statement shall not relieve
the Contractor of his obligations under the Contract
(c) The Employer shall pay the Contractor in accordance with Clause
42.
(d) The Employer shall not obstruct or interfere with the performance
of the Contract by the Contractor, except where expressly
provided in the Contract.
(e) The Employer shall not interfere with or influence or obstruct the
issue of any certificate by the Superintending Officer under the
Contract.
(b) Where the Contract expressly provides for part of the Works to be
designed by the Contractor (in which case Option Module D
applies), he shall be fully responsible for the design of that part of
the Works, notwithstanding any approval by the Superintending
Officer.
(b) The Superintending Officer shall then explain and adjust the
Discrepancy and issue to the Contractor an instruction so as to
resolve the Discrepancy.
8 NOTICES
8.1 Serving of Notices Serving of Notices
(b) Either party may change the address set out in the Articles of
Agreement by giving 14-Day notice to the other party and the
Superintending Officer and in the case of the Superintending
Officer by giving 14-Day notice to both parties.
(a) The Contractor shall defend and indemnify the Employer from
and against all claims, costs, damages, charges and proceedings
whatsoever for or on account of infringement of any patent rights,
design trademarks or name or other protected rights in respect of
any Construction Plant, Equipment, materials, goods or design
(submitted by the Contractor pursuant to his obligations under the
Contract) used for or in connection with or for incorporation in
the Works, except where such infringement results from
compliance with an instruction, the design or Specifications
provided by the Superintending Officer.
(c) The Employer shall be liable for any default or delay by any
public authority or public service company in the enforcement or
implementation of the Statutory Requirements provided always
that the Contractor shall have fulfilled his contractual obligations
and taken all actions for compliance with the Statutory
Requirements.
12 SETTING OUT
12.1 Accurate Setting Out Accurate Setting
Out
(a) The Superintending Officer shall be responsible to provide the
original reference points, lines and levels necessary for the
Contractor to set out the Works at ground level.
13 SITE ADMINISTRATION
13.1 Days and Hours of Working Days and Hours
of Working
(a) Unless otherwise stated elsewhere in the Contract, no work shall
be carried out during the night or on Public Holidays without the
written permission of the Superintending Officer except when
such work is rendered unavoidable or necessary for the saving of
life or property or for the safety of the Works, in which case the
Contractor shall inform the Superintending Officer at the earliest
possible opportunity of the same.
(c) For the purpose of this Clause 13.1, the term “night” shall mean
the period from 7.00 p.m. to 7.00 a.m.
(b) Where any such Equipment, materials, goods or work are being
manufactured, fabricated, assembled, prepared or stored in the
factories, workshops or other places of a sub-contractor or
supplier, the Contractor shall by a term in the sub-contract secure
a similar right of access to those factories, workshops or other
places for the Superintending Officer and any person authorised
by the Superintending Officer, and shall take reasonable steps
required of him by the Superintending Officer to enforce or assist
in enforcing such right.
(a) The Contractor shall ensure that the Construction Plant together
with all other tools and equipment, Temporary Works and other
items used in the execution of the Works are in a safe, sound and
good condition and capable of performing the functions for which
they are intended.
(b) Without limiting his liability under the Contract, the Contractor
shall provide at his own expense all workmen on Site with the
necessary safety equipment including but not limited to safety
boots, safety helmets and protective clothing.
(a) The cost of carrying out any test shall be borne by the Contractor
if such test is:
(b) The cost of carrying out any test shall be borne by the Employer
if such test is:
(b) If any such part of the Works has been covered up or put out of
view after compliance with the requirements of sub-clauses
15.5(a) and 15.5(b) and is found to be executed in accordance
with the Contract then, such work carried out by the Contractor
shall be deemed a Variation.
15.7 Defects during the Progress of the Works Defects during the
Progress of the
(a) If the Superintending Officer finds Defects during the progress of Works
the Works, notwithstanding any previous test or interim payment
for the Works or part of the Works, he may instruct the
Contractor to do any or all of the following:
(b) Where there is delay in the giving of possession of the Site or any
part of the Site as provided in Clause 17.2 then, the
Superintending Officer shall, subject to Clauses 32 and 42, certify
any Loss and Expense which the Contractor had incurred by
reason of such delay and, subject to Clause 24, grant the
Contractor an extension of time.
(c) The Contractor shall also provide at his own cost and expense any
additional accommodation, land or facilities outside the Site
required by him for the purpose of the Works.
18 OTHER CONTRACTORS
18.1 Employer’s Right to Employ Other Contractors Employer’s Right
to Employ Other
(a) The Employer reserves the right to employ any person or Contractors
contractor to carry out on the Site work which does not form part
of the Contract, whether or not information in respect of such
work is provided in the Contract. Every person or contractor so
employed shall be deemed to be a person or contractor for whom
the Employer is responsible for and not to be a sub-contractor.
(b) The Contractor shall permit the execution of any work by such
person or contractor employed by the Employer.
(iii) necessary for the proper execution of the Works or for the
safety of the Works or any part of the Works.
(f) failure of the Employer to give possession of the Site or any part
of the Site to the Contractor as required by Clause 17.2; or
(i) damage, loss or injury to the Works or part of the Works caused
by any one or more of the risks covered by the insurance policies
referred to in Clause 38A, 38B or 38C, whichever is applicable;
or
(b) in the case where such suspension affects only a part of the
Works, elect to treat such suspended part as an omission under
Clause 28.
(c) The Contractor shall provide to the Superintending Officer all test
reports required by the Contract.
(b) Provided that where the permanent connection for any of the
utilities to the Works are completed by the relevant authority or
public utility company, the Employer shall, on a written request
of the Contractor, make available such utilities to the Contractor
for the purpose of Test on Completion.
(c) The cost of using any such utilities which is provided by the
Employer for the use of the Contractor for the purpose of Test on
Completion shall be reimbursed by the Contractor to the
Employer or may be deducted by the Employer from any
payment due or to become due to the Contractor.
Any part of the Works which fails to pass the Test on Completion and
any replacement item required under sub-clause 15.7(a) shall upon the
instruction of the Superintending Officer be tested again at the
Contractor's expense within a reasonable time after the instruction until
the successful completion of the Test on Completion.
(i) Failure of the Employer to give possession of the Site or any part
of the Site to the Contractor as required by Clause 17.2;
(l) A Variation;
(m) Damage, loss or injury to the Works or part of the Works caused
by any one or more of the risks covered by the insurance policies
referred to in Clause 38A, 38B or 38C, whichever is applicable;
(b) If the Superintending Officer is of the opinion that the notice and
particulars provided by the Contractor under sub-clause 24.2(a)
are insufficient to enable him to decide on the Contractor’s
application, the Superintending Officer may require the
Contractor to provide within 14 Days or such other period as may
be specified by the Superintending Officer such further
information which the Superintending Officer may reasonably
require including particulars concerning any event and the
circumstances of the delay and the measures planned and/or taken
to avoid or reduce delay.
(c) Where the Superintending Officer considers that he does not have
sufficient information to enable him to decide on the Contractor’s
application in accordance with sub-clause 24.3(b), the
Superintending Officer may nevertheless grant such extension of
time as may in his opinion appear to be fair, reasonable and
necessary on the information available, taking into account all the
matters set out in sub-clause 24.3(d) below.
(a) fix a Time for Completion later than that previously granted if in
his opinion the granting of such longer Time for Completion is
fair and reasonable; or
(b) Such extension of time shall be added to the Time for Completion
for the Works or any section of the Works.
(c) The Employer shall then pay or repay the Contractor any amounts
of Liquidated Damages recovered, allowed or paid under Clause
26.2 for the said extension of time.
(c) If the Contractor is not liable for such Defects under the Contract
then such work of searching and remedy carried out by the
Contractor shall be deemed a Variation.
The provisions of Clauses 27.1 to 27.6 shall not derogate in any way
whatsoever from the Contractor’s liability under the Contract or
otherwise for defective work at law.
28 VARIATIONS
28.1 Power to Order Variations Power to Order
Variations
(a) The Superintending Officer may at any time issue an instruction
in writing requiring a Variation. Provided that (where Option
Module A is applicable) no instruction shall be required for
increase or decrease in the quantity of any work where such
increase or decrease is not the result of an instruction given under
this Clause 28.1, but is the result of the remeasurement of
provisional quantities stated in the Bills of Quantities.
(d) The Contractor shall carry out with due diligence and expedition
all Variations pending the valuation of the Variation by the
Superintending Officer pursuant to Clause 29.
29 VALUATION OF VARIATIONS
29.1 Valuation Method Valuation
Method
All Variations shall be valued in accordance with the following
valuation methods:
(c) Where paragraphs (a) and (b) above do not apply, then by
valuation at fair market rates and prices; or
(e) The Rates for the Works as set out in the Contract shall be used
for the valuation of work omitted; provided that if the omission
varies the conditions under which any remaining work are carried
out, the values for such remaining work shall be determined in
accordance with sub-clauses 29.1(b) or (c) or (d) as the case may
be. For the avoidance of doubt, the Contractor shall not be
entitled to Loss and Expense for omission of work unless such
work is carried out by the Employer or by another contractor.
30 MEASUREMENT
30.1 Contractor to Attend Measurement Contractor to
Attend
The Superintending Officer shall give reasonable notice to the Measurement
Contractor when he requires any part of the Works to be measured. The
Contractor shall then:
(e) Failure of the Employer to give possession of the Site or any part
of the Site to the Contractor as required by Clause 17.2;
(h) A Variation;
(j) Any other ground for Loss and Expense expressly mentioned in
the Contract but not mentioned in this Clause 31.1;
Provided always that the Contractor shall not be entitled to any such
Loss and Expense where the event arises from or is necessitated by or is
intended to cure any default or breach of contract by the Contractor.
(b) Where the events giving rise to the claim has a continuing effect,
such account shall be considered to be an interim account and the
Contractor shall, at such intervals as the Superintending Officer
may require, send such further interim accounts giving the
accumulated amount of the claims and any further grounds upon
which they are based. Within 30 Days of the end of the effects
resulting from the event, the Contractor shall submit to the
Superintending Officer a final account of the claim supported
with detailed particulars.
(b) The Contractor shall use his best endeavours to ensure that all
books, documents, papers or records in the possession custody or
control of a sub-contractor or supplier that are material to the
claim are similarly made available.
(b) The Contractor shall not without the written consent of the
Superintending Officer remove such Construction Plant,
Temporary Works, Equipment, materials or goods or any part of
the same except for the purpose of moving it within the Site.
Provided that the consent of the Superintending Officer shall not
be required for vehicles engaged in transporting any staff, labour,
Construction Plant, Equipment, materials or goods to and from
the Site.
(c) Upon the completion of the Works and the making good
of all Defects, the property in the remainder of such
Construction Plant, Temporary Works, Equipment,
materials or goods shall, subject to Clause 44
(Determination by Employer), re-vest in the Contractor.
34 GENERAL RESPONSIBILITIES
34.1 Care of the Works Care of the
Works
(a) From the Date of Commencement of the Works until the Date of
Practical Completion (or the latest Date of Practical Completion
if more than one) certified by the Superintending Officer pursuant
to Clause 20.2, the Contractor shall take full responsibility for the
care of the whole or any section of the Works as well as
Equipment, materials or goods intended for or connected with the
Works and all Construction Plant, Temporary Works and any
other things of whatsoever nature required by the Contractor for
the purposes of the Contract.
(b) In the event of any damage, loss or injury to the Works arising
from any of the Excepted Risks, the Contractor shall, if and to the
extent required by any instruction of the Superintending Officer,
rectify and make good the same.
(c) In the event of any damage, loss or injury to the Works arising
from an Excepted Risk and also from a risk for which the
Contractor is responsible under Clause 34.1, the Superintending
Officer shall, when certifying the amount of Loss and Expense
under Clause 32, make a fair apportionment of the costs so that
the Employer shall not be obliged to pay costs for which the
Contractor is otherwise responsible under the Contract.
35 INDEMNITY PROVISIONS
35.1 Injury to Persons Injury to
Persons
The Contractor shall be liable for and shall indemnify the Employer
against any loss, expense, costs, damages, liability or claim whatsoever
whether arising at law or by statute in respect of personal injury to or
death of any person whomsoever arising out of or in the course of or by
reason of the execution of the Works, subject always to Clause 35.3.
(b) The indemnities given by the Contractor under Clauses 35.1 and
35.2 shall not be defeated or reduced by reason of any negligence
or omission of the Employer or the Superintending Officer or any
person for whom they are responsible in failing to supervise or
control the Contractor’s site operations or methods of working or
Temporary Works, or to detect or prevent or remedy defective
work, or to ensure proper performance of any other obligations of
the Contractor under the Contract.
(b) For the purpose of Clause 37, the term “local workmen” shall
include workmen who are Malaysian citizens and those who have
permanent resident status.
(c) The Contractor shall submit the Code Number and Social
Security Numbers of all the workmen registered under the said
Scheme to the Superintending Officer for verification and make
payment of all necessary contributions from the Date for
Commencement until the Date of Practical Completion of the
Works. It shall be the duty of the Contractor to produce to the
Superintending Officer contribution statement or payment
vouchers as evidence of payment of such contributions, whether
demanded or not.
37.3 Insurance for Local Workmen not Subject to SOCSO Insurance for
Local Workmen
(a) Without prejudice to his liability to indemnify the Employer not Subject to
under Clause 35.1, the Contractor shall take out and maintain an SOCSO
insurance policy for local workmen who are not subject to
registration under SOCSO in accordance with the Employee’s
Social Security Act, 1969 or any subsequent modification or re-
enactment of the said Act.
(d) The Contractor shall deposit with the Superintending Officer the
original of each of the relevant policy or policies of insurance and
the receipts in respect of premiums paid under such policy or
policies.
(b) Each policy taken out pursuant to Clause 38A shall provide
expressly for the payment, in the first place, to the Employer of
any insurance money due under the policy.
(c) The Contractor shall deposit with the Superintending Officer the
original of each of the relevant policy or policies of insurance and
the receipts in respect of premiums paid under such policy or
policies.
(c) The Employer shall maintain of the said insurance and produce a
copy of such insurance policy and receipt for the premium paid to
the Contractor.
(d) Prior to the date of Tender the Employer shall make known to the
Contractor the terms of the said policy or policies including any
limitations or exclusions of liabilities or insurance excess and the
Contractor shall be deemed to have noted the same without
affecting the Contractor’s liability pursuant to Clause 34.
(f) Each policy taken out pursuant to Clause 38B shall provide
expressly for the payment in the first place to the Employer of
any insurance money due under the policy
(a) The Employer shall insure against all damage, loss or injury from
whatever cause arising in respect of the existing building or
structure within which the Works are to be executed together with
the contents in the existing building or structure owned by him or
for which he is responsible, for the full cost of reinstatement,
repair or replacement of such damage, loss or injury to such
existing building or structures.
(b) The Employer shall take out and maintain an All Risks Insurance
policy in respect of the whole of the Works as well as Equipment,
materials or goods intended for or connected with the Works and
Temporary Works (but excluding tools and Construction Plant
owned or hired by the Contractor or any sub-contractors) to the
value of not less than the Contract Sum plus the percentage for
professional fees and the amount for removal of debris (if any) as
stated in the Appendix.
(d) Prior to the date of Tender the Employer shall make known to the
Contractor the terms of the said policy or policies including any
limitations or exclusions of liabilities or insurance excess and the
Contractor shall be deemed to have noted the same without
affecting the Contractor’s liability pursuant to Clause 34.
(f) The Employer shall maintain the said insurance and produce a
copy of such insurance policy or policies and receipts for the
premium paid to the Contractor.
(g) Each policy taken out pursuant to Clause 38C shall provide
expressly for the payment, in the first place, to the Employer of
any insurance money due under the policy.
(d) All monies from such insurance in respect of the damage, loss or
injury referred to in sub-clause 38C.4(a) paid to the Employer
shall be released to the Contractor (less only the said percentage
for professional fees, if any) by instalments on the Interim
Certificates issued by the Superintending Officer.
(b) The Contractor shall take all reasonable precautions to prevent his
workmen or any other persons from removing or damaging any
such article or thing and shall, immediately upon discovery and
before removal of such article or thing, inform the Superintending
Officer of such discovery and carry out the Superintending
Officer’s instructions for dealing with the same.
(c) Any work carried out by the Contractor in accordance with such
instructions shall be deemed a Variation.
(a) The Contractor shall not sub-contract the whole of the Works.
Except where otherwise provided in the Contract, the Contractor
shall not sub-contract any part of the Works without the prior
consent of the Superintending Officer. Any such consent shall
not relieve the Contractor from any liability or obligation under
the Contract and he shall be responsible for the acts, defaults and
neglects of any sub-contractor, his agents, servants or workmen
as fully as if they were the acts, defaults or neglects of the
Contractor, his agents, servants or workmen.
(a) In respect of any and every Prime Cost or P.C. Sum provided in
the Contract, the amount due to the Contractor shall be
determined by deducting the said Prime Cost or P.C. Sum and
the relevant profit and/or attendance charges from the Contract
Sum and substituting for the same with the actual amount due to
the relevant Nominated Sub-Contractor or Nominated Supplier
as valued in accordance with the relevant sub-contract and the
sums due to the Contractor by way of profit and/or attendance
charges at the rates or prices stipulated in the Contract
Documents (if any).
(b) any other items shown and separately priced in the Contract
including those for Construction Plant, Temporary Works and
the like;
(c) the percentage (as stated in the Appendix) in respect of the value
of any Equipment, materials or goods delivered by the
Contractor on the Site for incorporation in the Works;
(d) any other sums to which the Contractor may consider himself to
be entitled under the Contract with itemisation of such sums
with reference to relevant provisions of the Contract; and
(d) Except for the Penultimate Certificate under Clause 42.6 or the
Final Certificate under Clause 42.8, the Superintending Officer
is not obliged to but may at his discretion issue any Interim
Certificate under sub-clause 42.2(a) if either:
(b) When the sum of the amounts so certified for retention equals or
exceeds the amount stated in the Appendix as Limit of Retention
Monies or that amount is reduced pursuant to Clause 22 or 23
(as the case may be) then no further amounts shall be certified
for retention by virtue of this Clause 42.3.
(b) The Statement at Completion shall set out in detail the final
amounts to which the Contractor considers himself to be entitled
in respect of all matters set out in Clause 42.1 showing all
adjustments made to the Contract Sum together with a complete
set of documents in support of such entitlement.
(b) The Final Claim Statement shall set out in detail the final
amounts to which the Contractor considers himself to be entitled
in respect of all matters set out in Clause 42.1
(d) If the Contractor does not submit the Final Claim Statement
within the 30 Day period referred to in sub-clause 42.7(a) the
Employer may on the expiry of the said 30 Days give notice in
writing to the Contractor that if the Final Claim Statement is not
submitted by the Contractor within a further 30 Days from the
date of the written notice the Superintending Officer may
proceed to prepare the Final Account (as defined in Clause 42.8)
based on the information available to him in accordance with
Clause 42.8.
(ii) after the expiry of the 30 Day period following the receipt
by the Contractor of the Final Account during which no
notification of disagreement has been received from the
Contractor; or
(i) the Contract Sum as set out in the Final Account; and
(g) For the avoidance of doubt, the Superintending Officer shall not
be obliged to issue the Final Certificate before the Certificate of
Making Good Defects referred to in Clause 27.6 (or the
Certificate of Making Good Defects in respect of the last section
of the Works, in the case of completion in sections) is issued,
and the issue of the Final Account before the issue of the said
Certificate of Making Good Defects shall not relieve the
Contractor from his obligations and liabilities arising during the
Defects Liability Period.
(b) In the event that the Employer fails to make the whole or any
part of the payment due to the Contractor within the Period of
Honouring Certificate, the Employer shall pay to the Contractor
in addition to the amount certified, simple interest at the rate
stated in the Appendix in respect of any sum unpaid from the
date by which the same should have been paid until the payment
of such sum.
(iii) all and only such extension of time (if any) as are due
under Clause 24 have been given; and
(ii) the Employer does not give the further notice referred to
in sub-clause 44.1(b),
(a) The Employer shall be entitled to repossess the Site and the
Contractor shall immediately cease all operations on the Works,
remove his personnel and workmen from and yield up
possession of the Site leaving any Construction Plant,
Temporary Works, temporary buildings, structures, tools, goods
and all unfixed Equipment, materials or goods left on the Site,
except only such as he may at any time be specifically instructed
by the Superintending Officer to remove from the Site.
(c) The Employer may carry out and complete the Works himself or
through the employment of other contractors and he or they may
use any of the Construction Plant, Temporary Works, temporary
buildings, structures, tools, goods and any unfixed Equipment,
materials or goods left on the Site –
(f) No sum shall be certified as due to the Contractor nor shall the
Employer be liable to pay to the Contractor any sum, whether or
not certified by the Superintending Officer (including damages
and amounts for which the Employer was liable at the date of
determination) in respect of the Contract until the expiry of the
Defects Liability Period of the whole of the Works and
thereafter until the Superintending Officer has issued the
Certificate of Termination Costs in accordance with Clause 44.4.
(i) the amount which would have been payable under the
Contract on completion in accordance with the Contract,
allowing for any Variations or other matters which
would have resulted in the adjustment of the original
Contract Sum; and
(i) he does not pay to the Contractor the amount due on any
certificate within the Period of Honouring Certificate
stated in the Appendix (unless and to the extent that
under the terms of the Contract the said Interim
Certificate has been modified or corrected by a later
Interim Certificate or the Employer may be expressly
empowered either not to pay, or to make deductions
from, the sum shown as due in the Interim Certificate);
or
(b) If:
(c) If:
(iii) the Contractor does not give the further notice referred
to in sub-clause 45.1(b),
(a) The Contractor shall with all reasonable dispatch remove from
the Site all his Construction Plant, Temporary Works, temporary
buildings, tools, equipment, materials or goods and shall give
facilities for his sub-contractors to do the same (subject always
to sub-clause 45.3(b)(iv)) and indemnify the Employer in respect
of injury, death or damage caused by such removal to the extent
of his liability under Clause 35.
(ii) The total value of work begun and executed but partially
completed at the date of determination, the value being
ascertained in accordance with Clause 29 as if such
work were a Variation required by the Superintending
Officer under Clause 28 but after taking account of any
amounts referred to in sub-clauses 45.3(b)(iii) to (vi);
(b) No later than the expiry of 30 Days after the date upon which the
Superintending Officer has received such reference, the
Superintending Officer shall give his decision in writing to the
Employer and to the Contractor which shall be final and binding
on the parties to the Contract unless, as hereinafter provided,
either party requires that the decision should be referred to
mediation under Clause 47.2
(e) Upon every or any such reference the costs incidental to the
arbitration and award shall be the discretion of the arbitrator who
may determine the amount of costs, or direct the amount to be
taxed as between solicitor and client or as between party and
party, and shall direct by whom and to whom and in what
manner the same shall be borne and paid.
(f) The award of the arbitrator shall be final and binding on the
parties.
49 GOVERNING LAW
49.1 Law Law
The law governing the Contract shall be the law of Malaysia, and the
parties hereby submit to the jurisdiction of the Malaysian Courts for the
purpose of any action or proceedings arising out of the Contract.
51 MISCELLANEOUS PROVISIONS
51.1 Business Ethics Business Ethics
The Contractor, his servants or agents and his sub-contractors are not
expected or authorised to take any action on behalf of the Employer
which violate applicable laws. All financial statements, reports, billings
and other documents rendered shall properly reflect the facts about all
activities and transactions handled for the account of the Employer.
The proper Stamp Duty, if any, on the Contract shall be borne by the
Employer.
CLAUSE
……………………………………… …………………………………..
……………………………………… …………………………………..
……………………………………… …………………………………..
……………………………………… …………………………………..
……………………………………… …………………………………..
……………………………………… …………………………………..
……………………………………… …………………………………..
……………………………………… …………………………………..
……………………………………… …………………………………..
AMOUNT TO BE ADDED TO
CONTRACT SUM AS INSURED
AMOUNT: 38A.1 or
38B.1or 38C.1
Percentage in respect of Professional …………………………………..
Fees
Stage: Percentage:
………………………………………… ……………………………………
………………………………………… ……………………………………
………………………………………… ……………………
………………………………………… ……………………………………
………………………………………… ……………………………………
………………………………………… ……………………
……………………………………… …………………………………..
……………………………………… …………………………………..
……………………………………… …………………………………..
……………………………………… …………………………………..
……………………………………… …………………………………..
……………………………………… …………………………………..
Retention Percentage
(10% if none stated) …………………………………..
PAYMENT BOND E1
(if Option Module E is applicable) …………………………………..
(5% of Contract Sum, if none stated)
AMOUNT OF PERFORMANCE
SECURITY DEPOSIT F1 …………………………………..
(if Option Module F is applicable)
(5% of Contract Sum, if none stated)
(i) The Employer shall not at any time be liable for damage, loss or
injury to any of the said Equipment, materials or goods except
and to the extent that the same is due to Excepted Risks or any
act or neglect of the Employer or of any person for whom the
Employer is responsible; and
(c) All Prime Cost or P.C. Sum items designated in the Contract shall
be reserved for execution or supply by a person to be nominated
in such ways on such terms and for such amount as may be
instructed by the Superintending Officer in accordance with the
provisions of this Option Module C. The Contractor shall not
without the instruction of the Superintending Officer order
execution of any work or supply of any Equipment, materials or
goods under such Prime Cost or P.C. Sum items or Provisional
Sum.
CIDB Standard Form of Contract for Building Works 2000 Edition 100
- Conditions of Contract
C2. Nomination Nomination
CIDB Standard Form of Contract for Building Works 2000 Edition 101
- Conditions of Contract
(3) that payment due to the Nominated Sub-
Contractor or Nominated Supplier less any
deductions in accordance with the sub-contract
shall be made by the Contractor within 7 Days
after the Period of Honouring Certificate or after
the Contractor has received payment, whichever
is the earlier, under any Interim Certificate issued
by the Superintending Officer pursuant to Clause
42 which includes the value of any such sub-
contract works or supply of any Equipment,
materials or goods;
CIDB Standard Form of Contract for Building Works 2000 Edition 102
- Conditions of Contract
(ii) the Superintending Officer and the Contractor have
agreed on the list of selected sub-contractors or suppliers
prior to invitation to tender for the execution of the work
or supply of any Equipment, materials or goods, the
subject of Prime Cost or P. C Sums or Provisional Sums
under the Contract;
CIDB Standard Form of Contract for Building Works 2000 Edition 103
- Conditions of Contract
(b) In addition to each of the certificates issued pursuant to Clause
42, the Superintending Officer shall certify separately the
amounts due to each of the Nominated Sub-Contractors or
Nominated Suppliers in respect of the work executed or the
Equipment, materials or goods delivered. Such separate
certificates shall be given to the Nominated Sub-Contractor or
Nominated Supplier by the Superintending Officer with a copy to
the Contractor.
(d) Before issuing each Interim Certificate under Clause 42.2 (except
the first Interim Certificate) and the Final Certificate under
Clause 42.8 , the Superintending Officer shall be entitled to
request from the Contractor reasonable proof that all amounts
included in previous Interim Certificates in respect of amounts
due to the Nominated Sub-Contractors or Nominated Suppliers
(less any amounts due from the Nominated Sub-Contractor or
Nominated Supplier to the Contractor) have been paid or
otherwise discharged by the Contractor pursuant to sub-clause
C3(c). In the event of default by the Contractor to provide such
reasonable proof, the Employer shall be entitled, but not obliged,
to pay direct to such Nominated Sub-Contractor or Nominated
Supplier the amounts due but which have not been paid by the
Contractor under the current or previous Interim Certificates
issued by the Superintending Officer under Clause 42.2. The
amounts so paid direct to the Nominated Sub-Contractors or
Nominated Suppliers by the Employer pursuant to this sub-clause
C3(d) shall be deducted from any payment due or which may
become due from the Employer to the Contractor.
CIDB Standard Form of Contract for Building Works 2000 Edition 104
- Conditions of Contract
(ii) sent through the Contractor to the Superintending Officer
all documents necessary for the final adjustment of the
sub-contract sum; and
(g) Neither the existence nor the exercise of powers pursuant to sub-
clauses C3 (d) and (e) nor anything else under this Clause C3
shall create a privity of contract between the Employer and the
Nominated Sub-Contractors or Nominated Suppliers or render the
Employer liable to any of them.
CIDB Standard Form of Contract for Building Works 2000 Edition 105
- Conditions of Contract
(b) The Contractor shall not
(b) The Contractor shall not determine or assign any sub-contract
with the Nominated Sub-Contractor or Nominated Supplier
without the prior written consent of the Employer.
CIDB Standard Form of Contract for Building Works 2000 Edition 106
- Conditions of Contract
OPTION MODULE D
WORKS DESIGNED BY THE CONTRACTOR
(b) Insofar as the Contractor is responsible for the design of any part
of the Works, he shall have in respect of Defects or insufficiency
in such design the like liability to the Employer, whether under
statue or otherwise, as would an architect, or as the case may be,
other appropriate professional designer holding himself out as
competent to take on work for such design who, acting
independently under a separate contract with the Employer, had
supplied such design for or in connection with works to be carried
out and completed by a contractor not being the supplier of the
design.
(c) Any references to the design which the Contractor has prepared
or shall prepare or issue for the works shall include a reference to
any design which the Contractor has caused or shall cause to be
prepared or issued by others.
(d) The Contractor shall obtain from all his professional consultants
direct warranties for the adequacy and suitability of the designs.
The direct warranties shall be given by the Contractor’s
professional consultants in favour of the Employer.
(ii) the Contractor shall proceed with the design to meet the
Employer’s Requirements.
CIDB Standard Form of Contract for Building Works 2000 Edition 107
- Conditions of Contract
Provided however the Contractor shall not proceed with the
execution of the same until he has submitted to the
Superintending Officer in accordance with Clause 4.4 such
Drawings, Specifications, manuals, calculations and other
information as shall be necessary to demonstrate the suitability,
adequacy, integrity, durability and practicality of such design to
meet the Employer’s Requirements (hereinafter collectively
called “the Design Documents”) and the Superintending Officer
has issued his acceptance in writing of such design.
CIDB Standard Form of Contract for Building Works 2000 Edition 108
- Conditions of Contract
(g) For the avoidance of doubt the Superintending Officer may
instruct Variations in respect of Works designed by the
Contractor to the same extent as for other works by way of
changes to the Employer’s Requirements in which case the
provisions of Clause 28 shall apply.
CIDB Standard Form of Contract for Building Works 2000 Edition 109
- Conditions of Contract
OPTION MODULE E
PAYMENT BOND
(c) Provided that the Employer shall not be obliged to extend the
validity of the Payment Bond if the delay is due any default or
breach of contract by the Contractor.
CIDB Standard Form of Contract for Building Works 2000 Edition 110
- Conditions of Contract
OPTION MODULE F
PERFORMANCE SECURITY DEPOSIT
CIDB Standard Form of Contract for Building Works 2000 Edition 111
- Conditions of Contract
(c) The notice of default shall state:
CIDB Standard Form of Contract for Building Works 2000 Edition 112
- Conditions of Contract