PROJECT PROPOSAL Vermicomposting

This proposal requests funding to construct a vertical vermicompost housing structure with a vermicompost tea catcher. The structure will allow the farm to increase monthly vermicompost production from 2 to 6 tons. This will generate more income to support the family and employ local youth. The housing will cost 42,680 pesos to build and is expected to operate for 10-15 years, increasing farm income by at least 50% annually through vermicompost and vermicompost tea sales.

Uploaded by

Fe Pilosopo
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (5 votes)
2K views

PROJECT PROPOSAL Vermicomposting

This proposal requests funding to construct a vertical vermicompost housing structure with a vermicompost tea catcher. The structure will allow the farm to increase monthly vermicompost production from 2 to 6 tons. This will generate more income to support the family and employ local youth. The housing will cost 42,680 pesos to build and is expected to operate for 10-15 years, increasing farm income by at least 50% annually through vermicompost and vermicompost tea sales.

Uploaded by

Fe Pilosopo
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Project Title : Construction of VERTICAL VERMI-CULTURE HOUSING with VCT CATCHER

Proponent. : Joseph Marchan Mille R. Tangeres

Designation. : Farm Manager/Owner

Institution. : 4J’s INTEGRATED FARM

Address: Purok Kamagong, Lower Jugno, Amlan, Negros Oriental

Contact no. : 09999152126 smart; 09531672482 TM

Email: [email protected]
Implementing Agency: ATI RTC 7
PAO, Neg. OR.
LGU, Amlan

PROJECT PROPOSAL

I. Project Title: Construction of VERTICAL VERMI-CULTURE HOUSING with VCT CATCHER

II. Introduction/Rationale

Vermicast production is one of the viable sources of organic fertilizers as promoted by the
Organic Agriculture Program implemented by the Department of Agriculture supported by the Philippine
Organic Agriculture Act of 2010 or RA 10068. Essentially, the program aims to promote, propagate,
further develop and implement the practice of Organic Agriculture in the Philippines towards a
competitive and sustainable OA industry to contribute to better farm incomes and sustainable
livelihood; Improved health; Environmental protection; Disaster risk reduction and resilience to Climate
Change. Hence, the availability of vermicasts in Negros Oriental is very limited.

During the height of the pandemic last year (2020), our father whom the head of our family who
was the breadwinner, worked with the Foundation University Farm as Crop Maintenance/Driver,
discharged from work permanently because the institution seriously affected and could not sustained
retain their employees anymore. In order to get through with the crisis due to pandemic, we used what
we learned in the previous work of my father in the farm which is organic farming specifically
Vermicomposting. Using the ample space available in our backyard and available farm waste materials
(animal manure, rice straws, mudpress, slurry) from the nearby farms with the help of our siblings, we
were able to produce vermicasts around two (2) tons per month or equivalent of 40bags (50kg/bag).
Through the help of online selling facilitated by the farmers cooperative in Amlan, we were able to sell
at P300.00 per bag as retail price, bulk buyers can avail a discount up to 20%. We generated around
9,000 to 12,000 monthly gross incomes out from vermicast and other vegetable products. We were
able to support the family’s daily needs.
Today, as we continue to maintain the quality and increase the volume of production to cater
the needs of the market which is eventually developed, we need to do expansion of the vermi-culture
housing. To maximize the limited space in our backyard, we will be using the VERTICAL COMPOSTING
SYSTEM. However, the cost of the construction of the structure would be much higher, however it is
more feasible and sustainable. It will increase the production from 2 tons to 6 tons per month (300%)
with an estimated lifespan of 10 to 15 years.

Vermicompost teas (VCT) are documented to increase plant growth and yield and reduce plant
fungal and bacterial diseases and nematode infestation in the soil (Selvaraj, Abira, 2011). According to
the author from University of California Riverside conducting a thesis in titled “Effect of Vermicompost
Tea on the Growth and Yield of Tomato Plants and Suppression of Root Knot Nematode in the Soil” in
completion of the course Master of Science in Plant Biology. In view, we decided to incorporate the
vermi-tea (VCT) catcher in the VERTICAL VERMI-CULTURE PRODUCTION HOUSING as additional benefit
with the design.

We are glad to avail the financial assistance from the ATI RTC 7 to the 4-H Club AFY to help in
the construction of the proposed expansion of vermi-culture housing to realize our specific objectives as
follows:

1. Increase the vermicast production from 2 tons to 4 tons monthly.

2. Encourage the The Dreamers 4-H Club members in Jugno, Amlan to engage in agriculture production
and activities.

3. Increased the family net income to at least 50%.

General Objectives

Help produce available supply of quality vermicasts/vermicompost to the vegetable/organic


farmers and Organic Agriculture Program project implementations and interventions. Help promote
farmers to produce organically grown vegetable products for food safety.

Project Description:

Project location : Purok Kamagong, Lower Jugno, Amlan, Negros Oriental

Project Beneficiaries :

Direct – Joseph Marchand Mille R. Tangeres family

Indirect – Farmer/customers

- The Dreamers 4-H Club members to avail the labor employment in


collection of raw materials and participate in the production activities

Project Duration : 3 months

Mechanics of the Implementation/Intervention Design and Strategy:


Activities and Timeline

2021 2022 RESPONSIBLE


ACTIVITIES OCTOBER NOVEMBE DECEMBER JANUARY PERSON
R
1. Proposal Proponent
preparation/finalization/approval/Release ATI RTC 7 Staff
of funding
2. Procurement of needed materials Proponent
3. Construction of (1 UNIT 10ftx8ftx8ft) Proponent
VERTICAL VERMI-CULTURE HOUSING with 1 Carpenter
VCT catcher 1 Helper/Laborer
4. Start of production operation Proponent

Project Output

At the end of the project duration of three (3) months the finished construction of 1 unit 10ft x
8ft x 8ft VERTICAL VERMI-CULTURE with VCT CATCHER will be ready for production operation. After one
and a half month or 45days (production cycle) will produce approximately 120bags (50kgs) of
vermicasts/vermicompost.

Marketing Aspect:

Financial Aspect/Budgetary Requirement:

ITEM UNIT QTY UNIT COST AMOUNT PROPONENT’S PROJECT


COUNTERPART REQUESTED
Hollowblocks Pcs 500 12.00 6,000.00 6,000.00
Steel Bars (9mm) Length 7 120.00 840.00 840.00
Steel Bars (10mm) Length 28 150.00 4,200.00 4,200.00
Tie Wire #16 Kg 3 80.00 240.00 240.00
Cement Bags 28 217.50 6,090.00 6,090.00
Sand Cu.mete 6 800.00 4,800.00 4,800.00
r
Lumber:
2x2x14 pcs 6 115.00 690.00 690.00
2x3x10 pcs 9 120.00 1,080.00 1,080.00
GI Pipe #1.0 Length 3 1,450.00 4,350.00 4,350.00
PVC #1/2 Length 1 90.00 90.00 90.00
Corrogated GI Sheet Sheet 12 380.00 4,560.00 4,560.00
L=10ft
Umbrella nails Kg 1 100.00 100.00 100.00
Common nails:
#4 Kg 2 80.00 160.00 160.00
#3 Kg 3 80.00 240.00 240.00
Vulca seal (250ml) Can 1 240.00 240.00 240.00
Labor:
Carpenter MD 12 450.00 5,400.00 5,400.00
Helper/Laborer MD 12 300.00 3,600.00 3,600.00
TOTAL PROJECT 42,680.00 27,680.00 15,000.00
COST

Socio-Economic Impact of the Project:

Annual Projected Production and Income Statement

Production cycle: 45days or 8 cycles per year


Volume of Vermicast Production: 6 tons or 120bags per cycle
Vermicast Discounted price (20%): 240.00/bag
Gross income of vermicast per cycle: 28,800.00
VCT projected production per cycle: 20 liters
VCT Proposed Price: 200/liter
VCT projected gross income: 4,000.00
PARTICULARS PER CYCLE (45 DAYS) ANNUAL (8 CYCLES) REMARKS
Projected Sales:
VERMICAST 28,800.00 230,400.00
VCT 4,000.00 32,000.00
TOTAL PROJECTED SALES 32,800.00 262,400.00
Less Projected
Production Cost:
Mud Press 4,500.00 36,000.00 Hired labor
Rice Straws 1,000.00 8,000.00 Family labor
Animal Manure 1,600.00 12,800.00 Family/4-H
members
Saw Dust 1,000.00 8,000.00 Family labor
Sacks (120pcsx10.00) 1,200.00 9,600.00
Labor Maintenance 6,750.00 54,000.00 Family labor
Transportation Cost 2,400.00 19,200.00
(20.00/bag)
Housing dep. Cost. 533.50 4,268.00
(10YRS)
Bottles 120.00 960.00
Miscellaneous (load, 1,000.00 8,000.00
internet, water)
TOTAL PROJECTED 20,103.50 160,828.00
PRODUCTION COST
PROJECTED NET INCOME 12,696.50 101,572.00
ROI 63.15%
BREAK-EVEN PRICE PER 167.53
BAG

As to the economic impact of the project to the proponent’s family and The Dreamers 4-H Club
members, it initially shows that it will help increase their family income as well as to the club members
and encourage them to participate in the agricultural production or activities. Obtaining an income will
motivate them and eventually develop the passion in agriculture or even their parents and other family
members and neighbors.