Culvert and Bridge Material.
Culvert and Bridge Material.
Lecture-01: Introduction
2
Course Outlines
Chapter One
1. INTRODUCTION
1.1. Why you study culvert and bridge hydraulics?
1.2. Hydraulic causes of culvert and bridge failure
1.3. Site selection and data required
Chapter Two
2. CULVERT HYDRAULICS
2.1. Introduction
2.2. Classification of flow types at culvert
2.3. Culvert flow controls (inlet and outlet control)
2.4. Principles and criteria of culvert design
2.5. Hydraulic design of culverts
Chapter Three
3. BRIDGE HYDRAULICS
3.1. Introduction
3.2. The effect of bridge on river flow
3.3. Hydraulic performance of bridge
3.4. Types of flow in bridge waterway
3.5. Hydraulic design of bridges
3
Chapter One: Introduction
Culverts and bridges are highway cross-drainage hydraulic
structures those accommodate the passage of:
– water, sediment and natural debri materials
– both the upstream and downstream movement of aquatic
organisms.
The purpose of both bridge and culvert is providing a
transportation route over obstructions ( such as river, lake
or even another roadway or railway)
According to P. Novak et al. (2007), culverts are submerged
structures buried under embankment usually shorter span (< 6
m), with the top not normally forming part of the road surface
like in a bridge structure.
4
Cont’d…
Culverts are enclosed conduits like:
– Complete pipe
– Elliptical
– Pipe arch
– Box
According to ERA (2011), culverts constructed at a water
course (Stream Culverts) or low points of road where there is no
define stream but cross drainage is required for the flow which
cannot be accommodated by side drains (Relief Culverts).
5
Cont’d…
6
Cont’d…
7
Cont’d…
8
Cont’d…
Bridges are highly costing structures that support a
roadway over the water body by means of a span.
Bridges does not have a constructed structural invert
(bottom) and does not fully enclose the channel.
Bridges consist of a deck supported on abutments or piers,
open‐bottom box or half‐pipe, or other structural arch.
Bridge construction was adopted in Ethiopia since 19th
century, in 1884 bridge erected over Temchi River (a
tributary of Blue Nile River) and 1886 over Awash River.
9
Cont’d…
10
Cont’d…
11
Cont’d…
Comparisons to Culverts and Bridges
Designer must determine:
• Which type of structure is best for a particular location
• Which one is chosen hydraulically, aesthetically and
economically
• How should the structure be analyzed (as a bridge with
free surface flow using GVF concepts or as a culvert with
head water based)
12
Cont’d…
In most of the sites, either a bridge or culvert will fulfill the
structural and hydraulic requirements.
– Traffic safety
– Environmental considerations
– Risk of failure
13
Cont’d…
Culverts are used where:
– bridges are not hydraulically required
– debris and ice potential are tolerable
– more economical than bridge
Bridges are used where:
– culverts are impractical
– more economical than a culvert
– to satisfy land-use and access requirements
– mitigate environmental concerns
– accommodate ice and large debris of heavy sediment loads
or moving boulders…etc.
14
Cont’d…
There are differences in the hydraulic assumptions and
analyses used for culverts and bridges.
Culvert hydraulic analysis assumes
– No velocity approaching the culvert or
– In the channel immediately downstream of the culvert,
which overestimates entrance and exit energy losses and
– Tail water condition in the channel downstream of a culvert
is typically based on normal depth analysis.
Bridge hydraulic analysis is typically based on GVF
calculations providing a more accurate water surface profile
throughout the crossing.
15
1.1. Why study bridge and culvert hydraulics
Studying the bridge & culvert hydraulics is important because of
nobody can be allowed to build a new bridge/culvert in a river
cross section without first being able to prove by:
17
1.2. Hydraulic causes of bridge and culvert failure
According to Smith (1976, 1977), 143 bridge failures occurred
throughout the world between 1847 and 1975. Almost half of the
failures were due to floods.
18
Cont’d…
Scour include side erosion of the river banks in the vicinity of a
bridge.
20
1.3. Site selection and Data Required
21
Site Selection
Culvert and bridge site selection is important in terms of:
– Cost of construction
– Maintenance
– Service life
The characteristics of an ideal site for a culvert and bridge
across a river are:
– straight reach of the river
– Steady river flow without cross tides
– A narrow channel with stable rock banks
– Suitable high banks above high flood level on each side
– Absence of sharp curves in the approaches
– Absence of expensive river training works
– Avoidance of excessive underwater construction
22
Cont’d…
Side drains will be released by cross structure after a maximum
length of 200m to:
23
Cont’d…
Adjustment of the road alignment is often justified to minimize
the cost of structures and risk of damage or erosion.
Careful site selection is essential to ensure ease of construction
and to minimize the whole life cost of the structure.
Poor site selection can result in a longer, wider or higher structure
than is actually necessary and can also lead to excessively high
maintenance costs.
#Q 3. Explain why the crossing structure should be located away from horizontal
24
Cont’d…
According to ERA (2011), the following criteria should ideally be
met when determining a site for water crossing:
26
Cont’d…
27
Cont’d…
#Q 4. List data required to design culvert and bridge
28
Cont’d…
Data Required
Topographic maps:- to identify channel width, possible
crossing sites, to obtain the channel gradient and to indicate
floodplain.
Geological maps, Soil maps and Geological records:- provide
some details about the local geology.
Hydrological data:-such as gauging station records, stage-
discharge relationship and flow-duration curve.
Meteorological data:- rainfall depths and intensities,
temperature range and wind speed. These data may help in
assessing the possibility of flash flood and ice loading on the
super structure.
29
Cont’d…
River channel data:- Roughness of the channel and floodplains.
It may be difficult to determine the width and depth of the river
channel from maps. This requires evaluation of the following:-
– Design flood, base flood, overtopping flood, backwater and
tail water.
– Design flood is defined as the flood associated with the
probability of exceedance (frequency) selected for the design
of a highway breach.
30
Cont’d…
– Once the design frequency is determined, a discharge for the
selected frequency can be determined which is also known as
the “design discharge”.
– The base flood is the flood having a 1-percent chance of
being exceeded in any given year.
– The overtopping flood is described by the probability of
exceedance and water surface elevation at which flow begins
over the culvert/bridge.
– Backwater is the increase of water surface elevation induced
upstream from a bridge, culvert, dam …etc.
– Tail water for sizing of cross drains and the determination of
headwater and backwater elevations.
31
Cont’d…
In addition to the data requirements explained above, the site and
detailed investigation criteria should emphasize on the:
– Road Alignment:- cross the watercourse at 90 degrees as this
minimizes the span length of the bridge or pipe and to avoid
additional scouring.
– Location:- A site with a natural narrow channel width, at a
straight stretch of watercourse, approach roads should
preferably be straight on each side to ensure sufficient sight
distances and prevent traffic hazards.
– The location also should be away from waterfalls and
confluence zones.
32
Cont’d…
Existing Structure Assessment:- Where existing roads are being
improved, existing drainage sites should already have been
provided with an appropriate structure.
Site Investigation:- Is to provide a clear picture of the ground
conditions, to enable a suitable design to be carried out.
The level of site investigation clearly depends on the type and
complexity of the proposed structure.
A site investigation will involve taking samples of the ground
material to determine its bearing capacity.
33
Cont’d…
These samples can either be obtained through digging trial pits or
by using a hand auger.
34
Chapter Two: Culvert hydraulics
2.1. Introduction
Culvert designed hydraulically to increase hydraulic capacity and
used to convey surface runoff through embankments.
Common culvert diameters are 600mm and 900mm.
Cross culverts smaller than 600mm in diameter should not be
installed as they are very difficult to clean or maintenance (ERA,
2011).
During a storm event a culvert may operate under inlet control,
outlet control or both.
36
Cont’d…
Numerous cross-sectional shapes are available and the most
commonly used shapes like circular, box (rectangular),
elliptical, pipe-arch and arch.
37
Cont’d…
38
Cont’d…
Based on construction materials used culverts can be concrete
(reinforced and non-reinforced), steel (smooth and corrugated),
corrugated aluminum, vitrified clay, plastic, cast iron, wood and
stainless steel.
39
Cont’d…
Basic concepts that are important in culvert design include:
42
Cont’d…
Steep slope:- steep water surface slope occurs where the
flow).
1.2D. 43
Cont’d…
Freeboard is a safety margin over design water level before
overflow occurs.
44
2.2. Classification of flow types at culvert
A culvert barrel may flow full or partly full over all of its
length.
The hydraulic condition in a culvert flowing full is called
pressure flow
– One condition which can create pressure flow in a culvert is
the back pressure caused by a high downstream water
surface elevation.
Partly full (free surface) flow or open channel flow may be
categorized as subcritical, critical, or supercritical.
A determination of the appropriate flow regime is accomplished
by evaluating the dimensionless number called the Froude
number.
45
Cont’d…
When Fr > 1.0, the flow is supercritical and is
characterized as rapid
When Fr < 1.0, the flow is subcritical and is characterized
as tranquil (gradual)
If Fr = 1.0, the flow is defined as critical
V
Fr =
gy
46
Cont’d…
47
Cont’d…
48
2.3. Culvert flow controls (inlet and outlet control)
Types of flow control
49
Cont’d…
Inlet control
Critical depth occurs at or near this location, and the flow regime
immediately downstream is supercritical.
The upstream water surface elevation and the inlet geometry are
the major flow controls.
50
Cont’d…
.
51
Cont’d…
Outlet control
52
Cont’d…
53
Factors influencing culvert performance
– Inlet control.
𝑌1 𝑌4
< 1.2 𝑎𝑛𝑑 <1
𝐷 𝑌𝑐
55
Cont’d…
Flow type II: characteristics of the flow type-II are:
– Un-submerged inlet with low tail water
– Critical depth at outlet
– Partially full flow
– Mild slope
– Subcritical flow
at barrel
– Outlet control
𝑌1 𝑌4
< 1.2 𝑎𝑛𝑑 <1
𝐷 𝑌𝑐
56
Cont’d…
Flow type III: characteristics of the flow type-III are:
– Un-submerged inlet with tail water backing up in to outlet
– Partially full flow
– Mild slope
– Subcritical flow at barrel
– Outlet control
𝑌1 𝑌4
< 1.2 𝑎𝑛𝑑 >1
𝐷 𝑌𝑐
– Existence of GVF profile is the controlling factor, critical
depth cannot occur, and the upstream water surface elevation
is the function of the tail water elevation.
57
Cont’d…
Flow type IV: characteristics of the flow type-IV are:
– Any slope
– Outlet control
𝑌1 𝑌4
> 1 𝑎𝑛𝑑 >1
𝐷 𝐷
– The flow rate can be estimated directly from the energy
equation. The tail water depth is assumed to be critical depth
near the culvert outlet or in the downstream channel.
58
Cont’d…
Flow type V: characteristics of the flow type-V are:
– Submerged inlet with low tail water
– Partially full flow
– Any slope
– Short length of culvert
– Orifice flow control at inlet.
𝑌1 𝑌4
> 1.2 𝑎𝑛𝑑 ≤1
𝐷 𝑌𝑐
– An orifice is an opening, submerged on the upstream side and
flowing freely on the downstream side.
59
Cont’d…
Flow type VI: characteristics of the flow type-VI are:
– Any slope
– Outlet control
𝑌1 𝑌4
> 1.2 𝑎𝑛𝑑 ≤1
𝐷 𝐷
60
Cont’d…
Flow type VII: characteristics of the flow type-VII are
– Steep slope
– Outlet control
𝑌1 𝑌4
> 1.2 𝑎𝑛𝑑 ≤1
𝐷 𝐷
61
2.4. Principles and criteria of culvert design
– Channel characteristics
– Existing structures
62
Cont’d…
Culvert location in both plan and profile shall be:
63
Design criteria of culvert
Site Criteria
– The culvert invert aligned with the channel bottom and the
skew angle of the stream
64
Cont’d…
Debris Control shall be needed for culverts:
– Located in mountainous or steep regions
– Those are under high fills
– Where clean out access is difficult
Design Limitations for allowable headwater:
– Will not damage up stream property
– Not higher than 300 mm below the edge of the shoulder
– Equal to HW/D not greater than 1.5 (2 for D < 1m)
– No higher than the low point in the road grade
– Equal to the elevation where flow can be diverted around
the culvert.
65
Cont’d…
Tail water Relationship
Use the critical depth and equivalent hydraulic grade line if the
culvert outlet is operating with a free outfall
68
Cont’d…
End Treatment (Inlet or Outlet):-the culvert inlet or outlet type shall
be selected from standard details
Projected inlets or outlets are box or pipe culvert extensions
beyond the embankment of the roadway
69
Cont’d…
Improved Inlets may be considered for culverts that will operate
in inlet control to increase the hydraulic performance.
70
Cont’d…
Outlet Protection (energy dissipaters): efficient energy
dissipaters provided at culvert outlet to protect scour.
– The scour hole will damage the culvert outlet and the
expected scour hole may cause costly property damage.
71
Cont’d…
A simple energy dissipater at a culvert outlet. (If Fr > 3, design a stilling basin)
74
2.5. Hydraulic design of culverts
Important formula
75
Cont’d…
76
Cont’d…
77
Cont’d…
78
Cont’d…
79
Cont’d…
80
Cont’d…
81
Design using nomographs
Using nomographs provides a convenient and organized procedure for
designing culvert. Its disadvantage is that it needs trial and error.
Inlet control during un-submerged inlet (the entrance operates as a
weir).
𝐻𝑊𝑖 𝐻𝑐 𝐾𝑢 𝑄 𝑀 2
𝐹𝑜𝑟𝑚 1 = +𝐾 − 0.5 ∗ 𝑆
𝐷 𝐷 𝐴𝐷 0.5
𝐻𝑊𝑖 𝐾𝑢 𝑄 𝑀
𝐹𝑜𝑟𝑚 2 =𝐾
𝐷 𝐴𝐷0.5
Inlet control during submerged inlet (the entrance operates as an
orifice).
𝐻𝑊𝑖 𝐾𝑢 𝑄 2 2
=𝐶 + 𝑌 − 0.5 ∗ 𝑆
𝐷 𝐴𝐷0.5
Where, HWi = Head water depth above inlet control section invert, m
D = Interior height of culvert barrel, m
Hc= Specific head at critical depth (dc + Vc2/2g), m
Q = Discharge, m3/s, A = Full cross-sectional area of culvert barrel, m2
S = Culvert barrel slope, m/m, K, M, c, Y = Constants from Table 2.1
Ku = 1.811 82
Cont’d…
83
Cont’d…
In the inlet control design nomographs, HW is measured to the
total upstream energy grade line including the approach velocity
head.
Inlet control nomographs are shown below as Charts 2-1, 2-2 and
2-3, for concrete pipe culverts, corrugated metal culverts, and
box culverts respectively.
84
Cont’d…
85
Cont’d…
(1) Headwall
(2) Mitered to conform
to slope
(3) Projecting
86
Cont’d…
87
Cont’d…
Example # 2.2
The inlet of a 1.4m diameter reinforced concrete pipe (RCP) is
submerged by a flow of 5m3/s. The inlet has a Groove end
treatment with headwall. The slope of the culvert is 0.015 m/m.
(a) What is the inlet control headwater depth above the inlet invert
(flow line)? (b) Compute by using nomograph.
Example # 2.3
Compute the inlet control headwater depth and elevation using
the nomographs. The headwater needs to be determined for a
discharge of 2.88m3/s through a 1.2 m by 1.2m concrete box
culvert. The culvert has an entrance with wing wall 45o. The
barrel has an upstream invert elevation of 30m at the inlet.
88
Cont’d…
Q = 5m3/s
D = 1.4m
HW/D = 1.35
HW = 1.89m
89
Cont’d…
Q = 2.88m3/s
B = 1.2m
Q/B = 2.4m2/s
HW/D = 1.2
HW = 1.44m
90
Cont’d…
• Outlet Control Nomographs (full flow): the nomographs were
developed assuming that the culvert barrel is flowing full and:
– TW > D, Flow Type IV
– dc > D, Flow Type VI
• Vu is small and its velocity head can be considered as a part of the
available headwater (HW) used to convey the flow through the
culvert.
• Vd is small and its velocity head can be neglected.
Energy Equation becomes:
HW = TW + H – SoL
– HW = depth from the inlet invert to the energy grade line, m
– H = is the value read from the nomographs, m
– SoL = drop from inlet to outlet invert, m
91
Cont’d…
• Outlet Control Nomographs (Partly full flow):- for flow type 2 &
3, approximate method. The following equation should be used:-
HW = ho+ H – SoL
– ho = the larger of TW or (dc+ D)/2, m
– HW = depth from the inlet invert to the energy grade line, m
– H = is the value read from the nomographs, m
– SoL = drop from inlet to outlet invert, m
• If the headwater depth falls below 0.75D, the approximate
method shall not be used.
92
Cont’d…
H = 0.29m
93
Cont’d…
94
Cont’d…
L = 93m
A = 0.36m2
Ke = 0.5
H = 2.2m
Q = 1.1m3/s
95
Cont’d…
Example #2.4
96
Cont’d…
Given
Q = 7m3/s
L = 60m H = 1.15m
Ke = 0.2
D = 1400 * 1400
97
Design procedure
98
Cont’d…
• Step 2:-Determine Hydrology, Minimum data required:- drainage
area maps and discharge frequency plots.
– Q100 if Qd ≤ Q100
104
Cont’d…
• Step 15:- Related Designs
• Consider the following options (design features and related
design):
– Tapered inlets if culvert is in inlet control and has limited
available headwater.
– Flow routing if a large upstream headwater pool exits.
– Energy dissipaters if Vo is larger than the normal V in the
downstream channel.
– Sediment control storage for sites with sediment concerns
such as alluvial fans.
• Step 16:- Documentation
• Prepare report and file with background information
105
Cont’d…
Example (follow the Design Procedure Steps)
• Step 1: Assemble site data and project file
Site survey project file contains:
Figure Cross-Section
– Roadway profile and
– Embankment cross-section
• Design criteria
– 50-year frequency for design and
– 100-year frequency for check
106
Cont’d…
• Step 2: Determine Hydrology
– Q50 = 11.33 m3/s
– Q100 = 14.16m3/s
• Step 3: Design Downstream Channel
So = 0.025
n = 0.06
Side slope 1H: 1V
– b. If HWr ≤ 0, Qr = 0
112
Cont’d…
– barrel has (4m – 2.1m) = 1.9m of cover
– L = 90m
Use Q100 for the upper limit, Steps 6 through 12 should be repeated
for each discharge used to plot the performance curve
113
Cont’d…
114
Cont’d…
• Step 15: Related Designs
Consider the following options (Design Features, and Related
Designs)
a) Consider tapered inlets, culvert is in inlet control and has
limited available headwater
– No flow routing, a small upstream headwater pool exists
– Consider energy dissipaters since Vo = 6.2m/s > 2.24 m/s in
the downstream channel
– No sediment problem
• Step 16: Documentation
Report prepared and background filed
115
Chapter Three: Bridge Hydraulics
3.1. Introduction
Studying the bridge hydraulics is important to:
– Check the effect of constructing the bridge on the upstream
reach
– Hydraulically inefficient bridge could cause flooding
upstream and extremely damaging a large number of
properties.
– A properly designed bridge is one that balances the cost of
the bridge with concerns of safety, impacts to the
environment and regulatory requirements.
– Proper hydraulic analysis and design of bridges is as vital
as structural design.
117
Cont’d…
Hydraulic analysis of bridge involves the following:
Determining the backwater surface profile
Determining the effects on flow distribution and velocities
Estimating scour potential
The deliverables of the hydraulic analysis of bridge involves the
following:
Location and orientation of the bridge
Bridge span and piers spacing if any
Type/shape of piers and abutment
Bridge profile and lower chord invert level
Recommended foundation levels (scour calculations)
Protection extent (upstream and downstream).
118
Cont’d…
Hydraulic design flow chart
119
Cont’d…
Design flow calculations
– Determine the design return period
– Pick out the design flow corresponding to the obtained design
return period
120
Cont’d…
Determination of return period based on risk analysis
Risk:- is simply defined as the probability of failure
• Within n years we have two events only: occurrence of
failure or no failure
• Probability of failure + Probability of no failure at all = 1
i.e Probability of failure in n years = 1 – probability of no
failure at all.
• Probability of no failure at all in n years = (1 – 1/R.P.)n
Risk ~ 1 – (1 – 1/R.P.)n
Pick out the design flow corresponding to the obtained design
return period
Example:- Estimate the risk related to adopting a design return
period of 50 years during the first 30 year period.
Risk ~ 1 – (1 – 1/R.P.)n
~ 1 – (1 – 0.02)30
~ 0.455 or 46% 121
Cont’d…
If this is too large risk, then increase design level to the 100
year where p = 0.01
Risk ~ 1 – (0.99)30
~ 0.26 or 26%
122
Bridge location
Generally, the stream crossing location is primary selected during
the planning phase of a highway project.
But the final location should not be confirmed unless you obtain
the detailed survey information and after completing the
preliminary hydraulic studies.
The crossing should: minimize skew, be located at the narrowest
portion of the flood plain, be located on a stable reach of stream,
minimize impacts of meander migration. and have appropriately
located auxiliary/relief openings (if needed).
Locate and center the bridge on the main channel portion of the
entire floodplain.
123
Cont’d…
124
Cont’d…
The need for auxiliary waterway openings, or relief openings,
arises on streams with wide floodplains.
125
3.2. The effect of bridge on a river flow
When a bridge is placed in a river it forms a narrowing of
the natural channel and an obstacle to the flow.
This results in a loss of energy as the flow contracts,
passes through the bridge and then re-expands back to the
full channel width.
Additional head is necessary to overcome the energy loss,
the upstream water level increases above that level.
This additional head is called the afflux, and its variation
with distance upstream is called the backwater profile.
If the narrowing is very severe, the flow is usually
subcritical with GVF upstream and downstream of the
structure and RVF at the bridge.
126
Cont’d…
127
Cont’d…
When investigating, the hydraulic capacity of the main
river channel without the bridge (QR) should be
compared with the capacity of the bridge waterway
(QWB) and the design flood (QDF).
Then as a rough guide:
• If QR < QWB the bridge is relatively blameless
• If QR < QDF flooding of the floodplains would occur without
the bridge
• If QWB < QR the bridge forms is under an obstacle to flow and
may cause flooding
• If QWB < QDF the waterway is under designed
• If QWB > QDF the waterway is over designed or has a margin of
safety
128
Cont’d…
129
Cont’d…
Fig.(a) longitudinal section of uniform flow at normal depth
(YN) in a river channel with (superimposed) the surface profile
arising due to provision of a bridge,
Fig.(b) Plan view showing how the flow separates and forms a
vena contracta of width Ccb.
Zone of drawdown approximates a semicircle of radius “b”
radiating from the Centre line of the opening at the upstream
face.
The maximum afflux is generally assumed to occur on the
center line of the channel at one opening width (span) of the
upstream face of the constriction. (And at this point lets say
section-1).
130
Cont’d…
With wide flooded valleys (of water surface width B) section-1
may be better located around 0.5 (B – b) upstream of the
constriction.
After passing through section-1 the water surface is drawn down
and passing through normal depth at section-2 at (or near) the
upstream face of the bridge.
Section-3 (at minimum width and depth) may be located either
in the opening or some distance downstream of it.
Section-4 is far enough downstream for normal depth conditions
to have been re-established and for the flow to be unaffected by
the bridge. 131
Cont’d…
132
Cont’d…
Maximum afflux (H1* = Y1 – YN) or H1* = H1 – (H4 + SoL1-4).
Piezometer head loss is the difference in the elevation of the water
surface between two points.
• For example between sections 1 & 3:
(∆h = H1* + SoL1-3 + H3*).
• head loss across the constriction is measured between section 1
and 4, i.e.
• Head loss1-4 = H1 – H4 = H1* + SoL1-4
Energy loss or total head loss, is the difference in the elevation of
the energy line between two points,
Energy loss1-4 = (H1 + α1V12/2g) – (H4 + α4V42/2g)
Where α is the dimensionless velocity head coefficient (kinetic
energy correction factor) to allow for the non-uniform velocity.
133
Cont’d…
Slope variation of the energy line near a bridge & the definition of the
energy loss for uniform flow at normal depth. 134
Cont’d…
The increased depth upstream of the bridge results in lower
velocities and shallower energy or friction gradient (SF) than
downstream, where the reverse happens.
The energy loss caused by a bridge can be assumed to rise from
three main things:
– Contraction of the flow caused by the abutments, noses of the
piers and when the opening is submerged the soffit or deck of
the bridge (15%);
– Friction between the water and the surface of the piers,
abutments and when the opening is submerged, the soffit of
the bridge (20%);
– Expansion of the live stream downstream of the bridge (65%)
135
Definition of terms
Normal crossings: is one with alignment at approximately 90o to the
general direction of flow during high water level.
Eccentric crossings: is one where the main channel and the bridge are not
in the middle of the flood plain.
Skewed crossings: is one that is other than 90o to the general direction of
flow during flood stage
Conveyance (K): is a measure of the ability of a channel to transport
flow. Conveyance can be expressed either in terms of flow factors or
geometric factors.
In bridge waterway computations, conveyance is used as a means of
approximating the distribution of flow in the natural river channel
upstream from a bridge.
136
Cont’d…
Width of Constriction, b: b is simply the horizontal distance
between abutment faces.
In the more usual case involving spill-through abutments, where
the cross-section of the constriction is irregular, it is suggested
that the irregular cross-section be converted to a regular trapezoid
of equivalent area.
138
Cont’d…
A weighted average value of the kinetic energy is obtained
by multiplying the average velocity head by a kinetic
energy coefficient, α1, defined as:
Where,
– Vi = Average velocity in a subsection (Qi/A)
A second coefficient, α2, is required to correct the velocity head for non-
uniform velocity distribution under the bridge.
139
Cont’d…
140
3.3. Hydraulic performance of a bridge
Factors that affect the hydraulic performance of a bridge
Bridge opening ratio (M): expressed as the ratio of the flow which
can pass unobstructed through the bridge constriction to the total
flow of the river.
Since conveyance is proportional to discharge, assuming all
subsections to have the same slope, M can be expressed also as:
Cont’d…
If at section-1, it is assumed that both the normal depth (YN) and the
associated mean velocity (VN) are constant across the full width of the
channel,
– Qb = Flow in portion of channel within projected length of bridge opening at
section-1
– Qa, Qc = Flow over that portion of the natural flood plain obstructed by the
roadway embankments
– Q = Qa + Qb + Qc = Total discharge
– Kb = Conveyance of portion of channel within projected length of bridge at
section-1
– Ka, Kc = Conveyance of that portion of the natural flood plain obstructed by
the roadway embankments.
– K1 = Total conveyance at section-1
143
Cont’d…
Eccentricity, (e)
If a bridge openings is eccentricity located in the river channel, as shown in
figure below this can affect the flow through the constriction.
144
Cont’d…
145
Cont’d…
There are two possible types of skew in addition to a normal
crossing
• Normal crossing:- embankments perpendicular to the flow,
waterway parallel to the flow
• Skew-1:- embankments skewed to the flow, water parallel to the
flow
• Skew-2:- embankments skewed to the flow, waterway skewed to
the flow
146
Cont’d…
Depth of flow, Y:- For a given discharge, flow can occur over a wide
range of depths depending upon the slope and geometry of the channel
and the flow is uniform or non-uniform.
The values of many variables, such as the Froude number (Fr),
conveyance (K) and opening ratio (M) are functions of the depth.
Additionally, the depth of flow relative to the height of bridge
opening can influence both the type of flow that occurs at a bridge
site and the hydraulic performance of the structure.
147
Cont’d…
Shape of the waterway opening:- may affect the hydraulic
performance of a bridge.
For instance, a rectangular opening with a width twice its height (b
= 2Z) has a 27% larger cross-sectional area than the equivalent
semicircular arch.
This means that at any given stage a rectangular opening will
probably have a larger discharge and a smaller afflux than an arch
of the same span.
148
Cont’d…
Froude number (Fr), subcritical and supercritical flow:
In open channel flow Fr also affects the discharge through the
bridge opening.
Flow at the critical depth (Fr = 1.0) can be used to optimize the
performance of a waterway, so a knowledge of the critical
contraction that will cause this condition is important.
A waterway narrower than the critical contraction may result in an
unexpectedly large afflux due to the phenomenon known as
choking.
Yarnell (1934) and Chow (1981) (F3=1.0)
149
Cont’d…
Where,
150
Cont’d…
The Froude number is important to indicate where a backwater
analysis should begin.
If (gY)1/2 > V (subcritical flow through a bridge) the upstream
reach is in hydraulic communication with the downstream reach
and the control is downstream of the constriction and this would
be the starting point for a backwater analysis.
If V > (gY)1/2 (supercritical flow through a bridge) the upstream
reach is not in hydraulic communication with the downstream
reach and the control is upstream so the calculations for the
backwater analysis proceed in a downstream direction.
Entrance Rounding: entrance rounding reduces the contraction of
the live stream and increases the width of the vena-contracta and
hence increases the coefficient of discharge, such as Cd. 151
Cont’d…
Example 3.1 (L Hamill on page111): Abridge has a single rectangular
opening 10m wide, which is the same width as the main river channel
at low stages (Fig. below). However during flood the bridge obstructs
the flow over the floodplains. The dimensions and Manning
roughness coefficients are shown in the diagram. Assuming uniform
flow, that the longitudinal slope of the channel and floodplains is 1 in
1000, and a depth of 4m in the main channel, estimate the following:
(a) the conveyance of the upstream cross-section, K; (b) the velocity
distribution coefficient, α; (c) the bridge opening ratio, M.
152
3.4.Types of flow under bridge waterway
A. Low flow case (waterway opening is not submerged) (Type I, II
or III)
153
Cont’d…
154
Types of flow in bridge waterway in low flow case
There are three types of flow in bridge waterway at flow low case.
Type I Flow (sub-critical flow)
• Normal water surface is everywhere above critical depth
• Actual water surface is everywhere above critical depth
• This type usually encountered in practice
Backwater expression for type-I flow is obtained by applying the
conservation of energy principle between sections-1 and 4.
155
Cont’d…
157
Cont’d…
Energy loss caused by constriction (hb) also can be expressed as
the product of a loss coefficient, K*, and a velocity head.
Where,
• h1* = H1* = total backwater (m)
• K* = total backwater head loss coefficient
• α1= velocity head correction coefficient at sections-1 and 4
• α2= velocity head correction coefficient at constriction
• An2 = gross water area in constriction measured below normal
stage (m2)
• Vn2 = average velocity in constriction for flow at normal stage
or Q/An2 (m/s)
• A4 = water area at section-4
• A1 = total water area at section 1, including backwater (m2)
If piers are present in the constriction, these are ignored in the
determination of An2. (including the area occupied by any piers). 159
Cont’d…
The expression represents the difference in kinetic energy
between sections-4 and 1.
160
Cont’d…
Type-IIA Flow:
163
Cont’d…
• Type-IIB flow is similar except the water surface not only dips
below Y2c but also Y4c downstream from the constriction.
• Both types of flow are subject to the same analysis since the
criterion here is that the flow passes through critical depth.
164
Cont’d…
165
Cont’d…
Solving for backwater:
Where,
– h1*= total bridge backwater (m)
– Yn = normal flow depth (m) (model)
– Y = normal flow depth or [An2/b] (m) (prototype)
– Y2c = critical depth in constriction or [(Q2/(b2g))1/3] (m)
– V2c = critical velocity in constriction or [Q/(Y2c*b)] (m/s)
– V1 = velocity at section 1 or [Q/A1] (m/s)
– α1, α2 = velocity head correction coefficients at section-1
and in the constriction respectively
– Cb = backwater coefficient for type-II flow (constriction
loss only) should the backwater coefficient be desired
166
Cont’d…
167
Cont’d…
Type-III Flow
169
Cont’d…
172
Cont’d…
Effect of Piers (Normal Crossings), ∆Kp
Backwater caused by introduction of piers in a bridge constriction
has been treated as an incremental backwater coefficient (∆Kp),
which is added to the base curve coefficient Kb when piers are
present in the waterway.
∆Kp is depends on:
• The ratio that the area of the piers bears to the gross area of the
bridge opening (J = Ap/An2)
• The type of piers
• The value of the bridge opening ratio (M)
• The angularity of the piers with the direction of flood flow. 173
Cont’d…
• Ap, An2 both based on the normal water surface.
174
Cont’d…
178
Effect of eccentricity (∆Ke)
179
Effects of skew (∆Ks)
The opening width is projected upstream on section-1, which is
perpendicular to the general direction of flow.
Note that the incremental backwater coefficient, ∆Ks, can be
negative or positive.
The negative values result from the method of computation and do
not necessarily indicate that the backwater will be reduced
(increasing hydraulic efficiency) by employing a skewed crossing.
These incremental values are to be added to Kb.
180
Cont’d…
Figure: skewed span (bs) required to give the same backwater as an opening of
width b perpendicular to the direction of the approaching flow. 182
Cont’d…
Bridge backwater computation procedure
The following steps are used to determine the backwater produced by a
bridge constriction:
1. Determine the magnitude and frequency of the discharge for which the
bridge is to be designed.
2. Determine the stage of the stream at the bridge site for the design
discharge.
3. Plot a representative cross section of stream for design discharge at
section-1.
4. Subdivide the cross section plotted in step-3 according to marked
changes in depth of flow and changes in roughness. Assign values of
Manning roughness coefficient, n, to each sub-section (Table).
5. Compute conveyance and then discharge in each subsection
6. Using cumulative conveyance and discharge at section-1, compute
slope of stream, So.
7. Determine value of kinetic energy coefficient, α1
8. Plot natural cross section under proposed bridge based on normal
water surface for design discharge and compute gross water area
(including area occupied by piers).
183
Cont’d…
9. Compute bridge opening ratio, M
10. Obtain value of Kb* from base curve for symmetrical normal crossings.
11. If piers are involved, compute value of J and obtain incremental
coefficient, ∆Kp, from curve.
12. If eccentricity is severe, compute value of e and obtain incremental
coefficient, ∆Ke, from curve.
13. If a skewed crossing is involved, observe proper procedure in previous
steps, then obtain incremental coefficient, ∆Ks, from curve.
14. Determine total backwater coefficient, K*, by adding incremental
coefficients to base curve coefficient, Kb.
15. Estimate α2 from curve, then make allowable for any unusual
topographic, vegetative or approach condition which may lead to further
asymmetrical velocity distribution in the bridge constriction.
16. Compute backwater h*
17. Convert backwater to water surface elevation at section-1 if
computations are based on normal stage at bridge.
184
Cont’d…
Example 3.2
A bridge is being designed to cross the channel described in example
3.1. The crossing will have a skew (ø) of 30o with vertical wing wall
abutments parallel to the flow, as shown in figure below. As in the
previous example, assume that the design flood is 98.030m3/s, YN =
4m and the height of the opening is 5m above bed level. Two
alternate designs are being considered:
• (a) a single span with a skewed width of 11.547m, which leaves
the main channel free of obstruction, and
• (b) a two -span structure with a skewed width of 11.547m between
the abutments including a round-nosed pier with a skewed width
of 1.000m in the Centre of the main channel. Calculate the afflux
h1*.
• ***(b)***individual assignment-II
185
Cont’d…
186
Cont’d…
Group assignment-(III)
The channel crossing shown in figure below is with the following
information: Cross section of river at bridge site showing areas,
wetted perimeters and values of Manning n; normal water surface
for design = Elv. 9m at bridge; average slope of river in vicinity of
bridge So =0.0005 m/m; cross section under bridge showing area
below normal water surface and width of roadway = 12m. The
stream is essentially straight, the cross section is relatively constant
in the vicinity of the bridge and the crossing is normal to the general
direction of flow.
187
Cont’d…
Find:
a) Conveyance at upstream cross section (K)
b) Discharge of stream at Elv. 9m
c) Velocity head correction coefficient, α1
d) Bridge opening ratio, M
e) Backwater produced by the bridge
188
B) High flow case (waterway opening is submerged)
Orifice flow (sluice gate pressure flow)
189
Cont’d…
Where,
• Cd-orifice = is the coefficient of discharge, it ranges from
0.35 – 0.5
• Ao = is the net area of the bridge opening, Ao = Z*bnet
• Z = is the bridge low chord height
• bnet = clear span width of bridge opening.
190
Cont’d…
Pressurized Flow
191
Cont’d…
Weir flow
192
Bridge scour
Scour is the removal of material from the bed and banks of streams
as a result of the erosive power of flowing water.
The most common cause of bridge failures is from floods eroding
bed material around bridge foundations.
Such failure is primarily due to:
– Inadequate knowledge about scour phenomenon when the
bridge was constructed
– Inadequate data and knowledge about design flood
Scour rate depends mainly on:
– Flow power, material resistance, sediment in/out balance
(equilibrium scour).
193
Cont’d…
(a) Pier piles and pile cap exposed (b) Pier and abutment riprap moved d/s
(c) D/s scour hole and bank erosion (d) D/s scour hole arising from submergence
(pressure flow) 194
Cont’d…
e. Slumped material at the toe arising from failure of the riprap or bank.
f. Erosion and failure of the highway embankment with flow on both sides
of the abutment.
195
Cont’d…
196
Types of Scour
Based on bridge crossings scour as clear water scour and live bed
scour.
If mean velocity (V) of the flow at upstream is less than the scour
critical velocity (Vs) then the bed material upstream of the bridge is
at rest:
– this is referred to as the clear water condition because the
approach flow is clear and does not contain sediment.
In this case any bed material that is removed from a local scour
hole is not replaced by sediment being transported by the approach
flow.
Live-bed scour occurs where V > Vs and the bed material upstream
of the crossing is moving.
This means that the approach flow continuously transports
sediment into a local scour hole.
197
Cont’d…
The equilibrium scour depth is achieved when material is
transported into the scour hole & at the same rate at which it is
transported out.
To determine whether the flow condition is clear-water or live-bed,
Neill (1968) equation given below, applied to the unobstructed
flow. If the average velocity (V = Q/A m/s) in the scour will be live
bed.
Figure above shows the variation of local scour depth (dSL) with approach velocity
The main components of scour include:- long term or natural scour (degradation
or aggradations), contraction scour (bridge opening) and local scour (piers and
abutments)
Degradation or Aggradations:- can only occur with a live bed (V > Vs), and it is
not the result of bridge or embankment construction.
Degradation is the scouring of bed material due to increased stream sediment
transport capacity that results from an increase in the energy gradient or a
decrease in the sediment load.
Aggradation is the deposition of bed load due to a decrease in stream sediment
transport capacity that results from a reduction in the energy gradient or an
increase in the sediment load.
200
Cont’d…
Where, Q is the water discharge, So is the channel bed slope, Qs is the bed material
discharge, and D50 is the median grain size of the bed material.
201
Cont’d…
– The significance of degradation scour to bridge design is that
the engineer has to decide whether the existing channel
elevation is likely to be constant over the 100 year life of the
bridge or whether it will change.
– If change is probable then it must be allowed for when
designing the waterway and foundations.
Contraction Scour:- occurs over a whole cross section as a result of
the increased velocities arising from a narrowing of the channel by
a constriction.
202
Cont’d…
– The approach flow depth h1 and average approach flow velocity
V1 result in the sediment transport rate qs1.
– The total transport rate to the contraction is W1qs1, in which W1
is the width of the approach.
– If the water flow rate Q1 = W1q1 in the upstream channel is
equal to the flow rate at the contracted section then by
continuity:
203
Cont’d…
– The depth of scour ∆z that is due to the contraction is then,
∆z = h2 – h1. The contracted scour depth represents an average
the channel width, and symmetry is assumed in the calculation.
– Local scour (Piers, abutments):- arises from the increased
velocities and associated vortices as water accelerates around
the corners of abutments, piers and spur dykes.
– Local pier scour:- The velocity upstream of the pier accelerate
around the pier and flow is directed downward along the front
face of pier.
– A “horseshoe” vortex forms where the downward flow reaches
the bed and the size of the vortex increases as the scour hole
enlarges.
– Sediment deposition occurs in the wake area downstream of the
pier.
204
Cont’d…
Figure above shows the flow pattern and scour hole at a cylindrical
pier. The down flow, horseshoe vortex and wake vortex are the
principal cause of local bed erosion
206
Cont’d…
There are many factors that influence the magnitude of pier scour:
Hydraulic factors: (velocity (V), depth (y) and angle of attack (θ)
of the flow approaching the pier, the water’s density and viscosity,
Froude number)
Pier factors: (width, length, shape); Scour depth increases with
increasing pier width (bp).
Square shape piers increasing scour depths by 10 – 30% than round
nosed piers.
Sediment factors: (grain size distribution, size (D50), density,
cohesive properties).
Bed configuration: those with D < 0.7mm can have various bed
configurations: ripples, dunes, plane bed or antidunes…etc.
For both clear water and live bed conditions Richardson et al.
(1993) recommended the Colorado State University (CSU)
equation for the estimation of equilibrium pier scour depth (dspm)
207
Cont’d…
Where, Y2 is the flow depth (m) at the bridge section directly upstream
of the pier (m), K1P is an adjustment factor for pier nose shape
obtained from Table below for ø < 5o, K2P is an adjustment factor for
the angle of attack (ø > 5o) obtained from curve, K3P is an adjustment
factor for bed configuration obtained from Table, bp is the pier width
(m) V2 is the mean velocity of flow (m/s) at the bridge directly
upstream of the pier and F2 is the Froude number = V2/(gy2)1/2.
• Note that if ø > 5o the factor K2P dominates, so K1P can be taken as
1.0.
208
Cont’d…
209
Cont’d…
210
Cont’d…
211
Cont’d…
a) Approximate pier scour depth, dSP, for various pier shapes aligned to the
approach flow, where bp is the pier width perpendicular to the flow. If the
depth of flow exceeds 5bp then dSP should be increased by 50%.
b) If the approach flow is at an angle to the pier then multiply dSP from part
(a) by the factor shown in the table. After (Neill, 1973).
212
Cont’d…
For both clear water and live bed conditions Richardson et al. (1993)
recommended for the calculation of abutment scour depths, dSA.
215
Cont’d…
Where: YM1 is the mean depth of flow (m) on the upstream
floodplain, K1A is the coefficient for abutment shape from Table, K2A
= (ɸ/90)0.13 is the coefficient for the angle of the embankment
abutment relative to the approach flow, LA is the length (m) of the
embankment/abutment projected normal to the flow and FM1 is the
Froude number of the approach flow upstream of the abutment.
216
Cont’d…
Note that with respect to the angle of the approach flow, ɸ < 90o if
the embankment abutment points downstream and ɸ > 90o if the
embankment abutment points upstream.
217
Cont’d…
Total scour depth (ds)
Degradation, contraction and local scour are additive, but
only where the scour holes overlap.
For instance, contraction scour may have to be added to
pier or abutment scour to get the total scour depth.
However, pier scour and abutment scour would not be
added unless the two scour holes overlap.
218
Cont’d…
Example 3.3
Just upstream of a 0.9m wide round nosed pier the depth of flow
is 1.3m with a velocity of 1.6m/s. The pier is skewed to the
approach flow with ø = 15o. The length of the waterway in the
direction of flow (L) is 14.4m. Assume that the channel bed is
plane. Calculate the local pier scour depth.
Example 3.4
The longitudinal Centre line of an embankment leading to a
bridge abutment is skewed at an angle of 30o compared with a
perpendicular crossing. The length of the embankment/abutment
is 33m measured along the Centre line. The abutments are of the
vertical wall type. It is estimated that the mean depth on the
upstream floodplain is 1.2m with a mean velocity of 0.7m/s.
Calculate the maximum abutment scour depth.
219
References
1. L Hamill-Bridge hydraulics-E. & F.N. Spon.1999.
2. Larry W Mays Hydraulic design handbook.1999.
3. Hydraulic Structures, P. Novak. 2004.
220