Item Pengujian Commisioning Pltu Baruta 2X7 MW No System Test Item Comm. Status Remark

The document provides a list of 33 systems to be tested during the commissioning of the 2x7 MW Baruta power plant in South East Sulawesi, Indonesia. The systems include the fire fighting system, coal feeder, coal transfer, induced draft fan, emissions control, cooling systems, water treatment, generators, and protection systems. Tests will check equipment operation, loading, interlocks, safety functions, and performance according to specifications.

Uploaded by

bernard
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views

Item Pengujian Commisioning Pltu Baruta 2X7 MW No System Test Item Comm. Status Remark

The document provides a list of 33 systems to be tested during the commissioning of the 2x7 MW Baruta power plant in South East Sulawesi, Indonesia. The systems include the fire fighting system, coal feeder, coal transfer, induced draft fan, emissions control, cooling systems, water treatment, generators, and protection systems. Tests will check equipment operation, loading, interlocks, safety functions, and performance according to specifications.

Uploaded by

bernard
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

PREPARED FOR COMMISIONING

IPP PLTU 2 X 7 MW BARUTA, SANGIA WAMBULU, BUTON SELATAN


SULAWESI TENGGARA
ITEM PENGUJIAN COMMISIONING PLTU BARUTA 2x7 MW
Update : 28 April 2015
No System Test Item Comm. Status Remark
· Motor No Load Run
Main Pump
Jockey Pump
Diesel Pump
· Motor & PumpLoad Run
Main Pump
Jockey Pump
1 Fire Fighting System Diesel Pump
· Interlock & Sequence
· Hidrant Function
Coal Bunker
Coal Yard
· Spray Function
· Sensor & Alarm Function
· MCC
· Motor & gearbox load run
2 Boiler Slag Remove
· MCC
· Coal Feeder function
3 Coal Feeder
· Belt scale calibration
· Motor No Load Run
· Safety switch function
Sway switch
Pulled switch
· Motor & Conveyor Load Run
4 Coal Transfer · Interlock & Sequence
· Vibrating feeder function
· Belt weight calibration
· Conveyor capacity
· Coal Srapper function
· MCC
5 Coal bunker · Interlock level control
· Individual motor
·Motor No Load Run
·Motor & Fan Load Run
6 Induced Draft Fan
·Inverter Function
·Interlock & sequence
·MCC
· Individual motor
·Motor No Load Run
·Motor & Fan Load Run
7 Primary Draft Fan
·Inverter Function
·Interlock & sequence
·MCC
· Individual motor
·Motor No Load Run
·Motor & Fan Load Run
8 Secondary Draft Fan
·Inverter Function
·Interlock & sequence
·MCC
PREPARED FOR COMMISIONING
IPP PLTU 2 X 7 MW BARUTA, SANGIA WAMBULU, BUTON SELATAN
SULAWESI TENGGARA
· Individual motor
·Motor No Load Run
9 Recycle Air Fan ·Motor & Fan Load Run
·Inverter Function
·Interlock & sequence
·Rectifier transformer
Insulation resistance
10 ESP ·Repping & hammering function
·Efficiency
·Test equipment monitor & display
·Function test
11 Sootblower ·Valve function
·Interlock & sequence
12 Desuperheater system ·Operation
·Motor No Load Run
Air blower
·Motor & blower Load Run
13 Fly ash
Air blower
·Air compressor function
·Interlock & sequence
·Bottom ash & slag gate funtion
·Conveyor motor no load run
·Safety switch funtion
14 Bottom ash & slag Sway switch
Pulled switch
·Motor & Conveyor load run
·Interlock & sequence
·Motor & Pump/Fan Load Run
Circulating water pump 1
Circulating water pump 2
Primary pump 1
Primary pump 2
Cooling tower fan 1
15 Closed cooling
Cooling tower fan 2
·Interlock & sequence
·Cooling tower performance
water flow
water temperature (inlet/outlet)
· MCC
· Individual motor
·Motor No Load Run
·Motor & Fan Load Run
16 Sea Water Intake ·Sofsarter Function
·Valve function
·Interlock & sequence
· MV Panel
·Motor & Pump Load Run
AC pump
DC pump
· MCC
17 Turbine lube oil
·Interlock & sequence
·Oil cooler function/performance
Oil inlet/outlet temperature
17 Turbine lube oil

PREPARED FOR COMMISIONING


IPP PLTU 2 X 7 MW BARUTA, SANGIA WAMBULU, BUTON SELATAN
SULAWESI TENGGARA
Oil inlet/outlet pressure
PREPARED FOR COMMISIONING
IPP PLTU 2 X 7 MW BARUTA, SANGIA WAMBULU, BUTON SELATAN
SULAWESI TENGGARA
·Motor No Load Run
18 Turning gear
·Engage & disengage function
·Backwash function
19 Condenser ·Vacuum breaker valve function
· Function
·Motor & Pump Load Run
Condensate pump 1
20 Condensate Extraction Condensate pump 2
· Valve Function
· Change over
·Motor & Pump Load Run
Water jet pump 1
21 Water Jet Steam Ejector Water jet pump 2
· Valve Function
· Change over

22 Heater · Valve Operation (LP, daerator, HP, drain, extraction steam)

·Motor No Load Run


·Motor & Pump/fan Load Run
23 Water Treatment Plant ·Interlock & sequence
·Water Quality
·Capacity
·Interlock & sequence
24 Waste WaterTreatment Plant
·Operation test
25 Chemical dosing ·Operation test
25 Sampling rack ·Operation test
·Individual generator
- Generator
·Busbar generator
·Power cable
26 - PTSA ·Individual Current Transformer
·Individual VoltageTransformer
·Power cable
- NGR
·Individual VoltageTransformer
·Power cable
·Individual VoltageTransformer
27 Excitation
·Function test
·AVR
·Individual Test
28 DC Supply Power System
·Interlock
·Individual Test
29 UPS
·Interlock
·Individual Test
30 Emergency Genset
·Interlock
31 Synchron ·Individual
·Individual Test

32 Generator Protection System ·Function Protection all Generator Relay

·Stability Test
·Individual Test
·Function
33 MCC Panel
·Function ProtectionTest
·The breaker interlock
PREPARED FOR COMMISIONING
IPP PLTU 2 X 7 MW BARUTA, SANGIA WAMBULU, BUTON SELATAN
SULAWESI TENGGARA
·Boiler Management System
·Sequence Control System
34 Boiler Instrument Control System
·Sequence of Event Recorder
·Modulation Control System
·Turbine Supervisory Instrument
·Emergency Trip System
35 Turbine Instrument Control System ·Sequence Control System
·Sequence of Event Recorder
·Modulation Control System
·Function
36 Turbine Generator Interlock Turbine Trip
Generator Trip
37 Condeser Vacuum Up Test ·Function
38 Emergency Trip Turbine Test ·Emergency Trip Local, CCR
·Friction & rub check at low speed
39 Steam admission & first rolling turbine ·Critical Speed Measurement
·Coast down time check
·Throttle Stop Valve
40 Steam valve Tighness Test
·Turbine control Valve
41 Over Speed Test ·Over Speed Electrical, Mekanikal