Energy Regulatory Commission: of Distribution Utilities
Energy Regulatory Commission: of Distribution Utilities
ARTICLE I
GENERAL PROVISIONS
ARTICLE II
“Heat Rate Caps” shall refer to the heat rate caps approved by the
ERC.
2
“NGCP” shall refer to the corporation awarded the concession to
operate the transmission facilities of the National Transmission
Corporation pursuant to Republic Act No. 9136 and Republic Act No.
9511
“NGCP”
ARTICLE III
1. The DU/NGCP sources the shortage from its various IPP's with
existing/ERC-approved contracts, as applicable.
2. If alternative source is not enough to cover the shortage, the
DU/NGCP shall activate its Interruptible Load Program through
the following procedure:
a) Match the expected time of the shortage with the time the
Interruptible LoadParticipating Customers prefer to be de-
loaded.
b) Sort the load of the PCcustomer at the time of expected
shortage based on customerits load profile. PCsCustomers
with larger loads are prioritized to be requested to de-load.
c) Check that PCcustomers have been de-loaded for less than
agreed number of hours in the current month.
d) Call the PCcustomer and request to de-load.
e) If the PCcustomer cannot de-load, customers the next in the
list are called to be requested to de-load.
3. If Interruptible Load is not sufficient to cover the shortage then
the Manual Load Dropping (MLD) is activatedaffected.
Where:
ARTICLE V
ARTICLE VI
8
or NGCP under the Open Access Transmission Service (OATS)
Rules..
ARTICLE VII
REPORTORIAL REQUIREMENT
ARTICLE VIII
9
FINAL PROVISIONS
Section 5. Effectivity. These Rules shall take effect fifteen (15) days
following its publication in a newspaper of general circulation.
ZENAIDA G. CRUZ-DUCUT
Chairperson
10
fpss/ajmo/fgb/FSCJ
11