WMS - (Pre-Action Sprinkler System Procedure)

This document provides a pressure test procedure for a pre-action sprinkler system. It outlines the purpose, scope of work, project details, roles and responsibilities, schedule, preparation activities, references, tools, safety equipment, and risk analysis. The procedure involves checking the work area, using approved shop drawings and tools, requesting a work permit, and pressure testing the pre-action sprinkler pipes to check for leaks according to NFPA standards. Safety precautions are specified to prevent falls, electric shocks, and other potential risks during the testing.

Uploaded by

Untung utami
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
174 views

WMS - (Pre-Action Sprinkler System Procedure)

This document provides a pressure test procedure for a pre-action sprinkler system. It outlines the purpose, scope of work, project details, roles and responsibilities, schedule, preparation activities, references, tools, safety equipment, and risk analysis. The procedure involves checking the work area, using approved shop drawings and tools, requesting a work permit, and pressure testing the pre-action sprinkler pipes to check for leaks according to NFPA standards. Safety precautions are specified to prevent falls, electric shocks, and other potential risks during the testing.

Uploaded by

Untung utami
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

Doc.

No:
PROJECT
Date: 05 Nov 2021 Revision: 00

WORK METHODE STATEMENT


PRE-ACTION SPRINKLER SYSTEM
PRESSURE TEST PROCEDURE

Approval

Prepared by: Knowleadge by: Approved by:

PT PT. D

PT. ……………. JKT Date: Nov 05 2021


I……………..CENTER Page 1 of 9
Internal Ref. No. Rev. No. 00
Doc. No:
PROJECT
Date: 05 Nov 2021 Revision: 00

DAFTAR ISI

1. PURPOSE ........................................................................................................................................ 3

2. SCOPE OF WORK ........................................................................................................................... 3

3. PROJECT DEFINISION ....................................................................................................................3

4. PERSON IN CHARGE ...................................................................................................................... 3

5. SCHEDULE ...................................................................................................................................... 4

6. PREPARATION WORKS .................................................................................................................4

7. REFERENCE .................................................................................................................................... 4

8. TOOLS & ACCESSORIS ..................................................................................................................5

9. SAFETY TOOLS ............................................................................................................................... 5

10. RISK ANALYSIS .............................................................................................................................. 5

11. PROCEDURE OF WORKS ............................................................................................................... 6

12. ATTACHED ...................................................................................................................................... 9

1. PURPOSE 1. TUJUAN
PT. ……………. JKT Date: Nov 05 2021
I……………..CENTER Page 2 of 9
Internal Ref. No. Rev. No. 00
Doc. No:
PROJECT
Date: 05 Nov 2021 Revision: 00

This pre-action sprinkler system pressure Pernyataan metode uji tekanan sistem
test method statement is prepared to pre-action sprinkler ini disiapkan untuk
describe the activity and is used for menguraikan kegiatan dan digunakan
pipeline pressure testing whether or not untuk uji tekanan pipa apakah terdapat
there is a leak in the pipeline of pre-action. kebocoran atau tidak pada pipa pre-action.

2. SCOPE OF WORK 2. RUANG LINGKUP PEKERJAAN


The scope of work is as described Ruang lingkup pekerjaan dijelaskan
bellowing. bahwa ini:
2.1. Pressure test. (pre-action system 2.1. Tes tekanan. (pipa sistem pre-action)
pipe).

3. PROJECT DEFINISION 3. DEFINISI PROYEK


3.1. Assignor : IKDC. 3.1. Pemberi tuggas : IKDC
3.2. Supervising consultant : PT. JKI. 3.2. Konsultan pengawas : PT. JKI.
3.3. Management construction : PT. JRP. 3.3. Managemen konstruksi : PT. JRP.
3.4. Architectural planning consultant. 3.4. Konsultan perencana Konstruksi.
3.5. MEP planning consultant : DSCO. 3.5. Konsultan perencana MEP : DSCO.
3.6. Main contractor MEP : PT. BINKEI. 3.6. Kontraktor utama MEP : PT. BINKEI.
3.7. Project name : IKDC DATA CENTER. 3.7. Nama proyek : IKDC DATA CENTER
3.8. Location : Citeureup, Bogor. 3.8. Lokasi : Citeureup, Bogor.

4. PERSON IN CHARGE 4. PENANGGUNG JAWAB


3.1. Project manager. 3.1. Manager proyek.
3.2. Site manager. 3.2. Manager lapangan.
3.3. Quality control. 3.3. Quality control.
3.4. Safety supervisor. 3.4. Supervisor keselamatan kerja (K3).

5. SCHEDULE 5. JADWAL PELAKSANAAN


The implementation schedule will be Jadwal pelaksanaan akan disesuaikan
adjusted to the schedule that has been dengan jadwal pelaksanaan yang sudah
determined by the civil contractor, and the ditetapkan bersama dengan kontraktor
PT. ……………. JKT Date: Nov 05 2021
I……………..CENTER Page 3 of 9
Internal Ref. No. Rev. No. 00
Doc. No:
PROJECT
Date: 05 Nov 2021 Revision: 00

related parties. sipil dan pihak terkait lainnya.

6. PREPARATION WORKS 6. PERSIAPAN PEKERJAAN


The purpose and objectives of preparing Maksud dan tujuan dari persiapan
The pre-action sprinkler system on work to pekerjaan tes tekan pre-action sprinkler
pressure test achieve these and objectives system agar sesuai dengan target maka
are carried out: dilakukan:
5.1. Check actual condition area. 5.1. Memeriksa kondisi aktual di
5.2. Prepared approved shop drawing. lapangan.
5.3. Prepared operational working tool. 5.2. Menyiapkan shop drawing yang telah
5.4. Requested issue work permit to main disetujui.
contractor. 5.3. Menyiapkan peralatan kerja.
5.4. Mengajukan izin kerja kepada
kontraktor utama.

7. REFERENCE 7. REFERENSI
This document refers to the following Dokumen ini mengacu pada standar dan
standards and references: referensi sebagai berikut:
6.1. Approved shop drawing. 6.1. Shop drawing yang telah disetujui.
6.2. Approved tools. 6.2. Peralatan yang telah di setujui.
6.3. NFPA-13, Standard for the installation 6.3. NFPA-13, Standar untuk
of sprinkler system. pemasangan system sprinkler.
6.4. NFPA-14, Standard for the installation 6.4. NFPA-14, Standar untuk
of standpipe & hose system. pemasangan sistem standpipe &
hose.

8. TOOLS & ACCESSORIS 8. PERALATAN & AKSESORIS


8.1. Air Compressor. 8.1. Air Compressor.
8.2. Plug. 8.2. Plug.
8.3. Valve. 8.3. Valve
8.4. Seal tape. 8.4. Seal tape.
PT. ……………. JKT Date: Nov 05 2021
I……………..CENTER Page 4 of 9
Internal Ref. No. Rev. No. 00
Doc. No:
PROJECT
Date: 05 Nov 2021 Revision: 00

8.5. Pressure gauge. 8.5. Pressure gauge.


8.6. Air hose 8.6. Selang angin.
8.7. Combination wrench. 8.7. Kunci pas kombinasi.
8.8. Adjustable wrench. 8.8. Kunci inggris.
8.9. Pliers. 8.9. Tang.

9. SAFETY TOOLS 9. PERALATAN KESELAMATAN


9.1. Scaffolding according to safety 9.1. Scaffolding yang sesuai standar
standard keselamatan.
9.2. Ladder according to safety 9.2. Tangga yang sesuai standar
standard. keselamatan.
9.3. Safety glass / googles. 9.3. Kacamata
9.4. Safety glove. 9.4. Sarung tangan.
9.5. Safety helmet. 9.5. Alat pelindung kepala.
9.6. Body Harness. 9.6. Body harness.

10. RISK ANALYSIS 10. ANALISIS RESIKO


10.1. Fall. 10.1. Terjatuh.
10.2. Electric shock. 10.2. Tersengat aliran listrik.
10.3. Falling the object. 10.3. Tertimpa material.
10.4. Pinched. 10.4. Terjepit.

11. PROCEDURE OF WORKS 12. PROSEDUR KERJA


11.1. Test Pressure (Pipe Pre-action 12.1. Tes Tekanan (Pipa Sistem Pre-
System). action).
The pressure test procedure is Prosedur uji tekanan dilakukan
carried out to determine leaks at untuk mengetahui kebocoran pada
the piping system connections. sambungan sistem pemipaan.
Note: In addition to the standard Catatan: Selain uji standar
hydrostatic test, an air pressure hidrostatik , uji kebocoran tekanan
PT. ……………. JKT Date: Nov 05 2021
I……………..CENTER Page 5 of 9
Internal Ref. No. Rev. No. 00
Doc. No:
PROJECT
Date: 05 Nov 2021 Revision: 00

leakage test at 40 Psi (2.8 bar) udara pada 40 Psi (2,8 bar) harus
shall be conducted for 24 hours. dilakukan selama 24 jam. Setiap
Any leakage that results in a loss kebocoran yang mengakibatkan
1
of pressure in excess of 1 /2 Psi hilangnya tekanan lebih dari 11/2
(0.1 bar) for the 24 hours shall be Psi (0,1 bar) selama 24 jam harus
corrected. diperbaiki. Pipa atau tabung yang
Pipe or tube specifically diperiksa secara khusus untuk
investigated for suitability in dry kesesuaian dalam pipa kering dan
pipe and double interlock pre- sistem double interlock pre-action
action system and listed for this dan terdaftar untuk layanan ini,
service, shall be permitted to be harus diizinkan untuk diuji sesuai
tested in accordance with their dengan batasan daftarnya.
listing limitations.
Methode: Metode:
A. check with the construction A. Pemeriksaan bersama dengan
management that the pre- manajemen konstruksi bahwa
action system pipes are instalasi pipa pre-action
correct. system tersebut sudah benar.
B. Prepare location to be tested. B. Siapkan lokasi yang akan di
C. Prepare all testing equipment. lakukan pengetesan.
D. Then drop all the dropper pipes C. Siapkan semua peralatan
with a plug that has been pengetesan.
wrapped with seal tape. D. Lalu dop semua pipa droper
E. Making a bypass pipe dengan plug yang sudah dililit
connection: Connecting the seal tape.
supply and return pipes into a E. Membuat sambungan pipa
single unit so that air is bypass : Menyambungkan
channeled to the two pipes. antara pipa supply dan return
F. Set all valves to close. menjadi kesatuan agar angin
G. Open valve at fitting introduce tersalurkan kepada kedua pipa
air merged and enter to all pipe tersebut.
pre-action; valve bypass must F. Atur semua valve di tutup.
PT. ……………. JKT Date: Nov 05 2021
I……………..CENTER Page 6 of 9
Internal Ref. No. Rev. No. 00
Doc. No:
PROJECT
Date: 05 Nov 2021 Revision: 00

open status. G. Buka valve pada saat


H. After all preparations are memasukkan angin yang
complete, then check and menyatu dan masuk ke semua
make sure that all pipe pipa preaction system, valve
installations pre-action system bypass status harus terbuka.
are ready for pressure test. H. Setelah semua persiapan
I. Fill air from outside to selesai, lalu cek dan pastikan
sectional, than to the newly bahwa semua instalasi pipa
installed pre-action system pre-action system sudah siap
pipe. untuk dilakukan tes tekan.
J. Before starting the pressure I. Isi angin dari luar ke sectional,
test test, the contractor is terus ke pipa preaction system
obliged to invite construction yang baru dan sudah selesai di
management representative. pasang.
K. After that, do a pressure test J. Sebelum memulai pengetesan
on the pre-action pipe tes tekan, kontraktor wajib
installation with pressure mengundang perwakilan
according to specifications, manajemen konstruksi.
namely 40 Psi (2.8 bar), for 1 x K. lakukan tes tekan pada
24 hours. instalasi pipa pre-action
L. Seal the gate valve and system dengan tekanan sesuai
pressure gauge, and install a dengan spesifikasi yaitu 40 Psi
hazard warning sign high (2.8 bar), selama 1 x 24 jam.
pressure in the pre-action L. Segel gate valve dan pressure
piping installation. gauge, dan pasang tanda
M. If within 1 x 24 hours the peringatan bahaya akan
pressure on the pressure tekanan tinggi pada instalasi
gauge drops / there is a pipa pemipaan pre-action
change, then immediately find system tersebut.
the point where the leak came M. Jika dalam 1 x 24 jam, tekanan
from, immediately make repairs pada pressure gauge turun /
and do a re-press test as ada perubahan, maka segera
PT. ……………. JKT Date: Nov 05 2021
I……………..CENTER Page 7 of 9
Internal Ref. No. Rev. No. 00
Doc. No:
PROJECT
Date: 05 Nov 2021 Revision: 00

before. cari dititik mana kebocoran


N. But if within 1 x 24 hours the tersebut berasal, segera
pressure on the pressure lakukan perbaikan dan lakukan
gauge does not go down / does tes tekan ulang seperti
not exist changes, then the sebelum nya.
pre-action piping installation is N. Tetapi jika dalam 1 x 24 jam,
declared Good and not leaking. tekanan pada pressure gauge
O. After everything is finished, tidak turun / tidak ada
immediately make a test report perubahan, maka instalasi pipa
signed by the sub-contractor, pemipaan pre-action system
contractor and sonstruction tersebut dinyatakan baik dan
management, stating that the tidak bocor.
chiller piping installation which O. Setelah semuanya selesai
has been under pressure test segera buat berita acara
is declared good or not leaking. pengetesan yang di tanda
tangani oleh Sub-kontraktor,
Kontraktor dan Manajemen
Konstruksi, yang menyatakan
bahwa instalasi pipa pemipaan
chiller yang sudah di test tekan
tersebut dinyatakan bocor atau
tidak bocor.

12. ATTACHED

PT. ……………. JKT Date: Nov 05 2021


I……………..CENTER Page 8 of 9
Internal Ref. No. Rev. No. 00
Doc. No:
PROJECT
Date: 05 Nov 2021 Revision: 00

Air Compressor Plug Valve Seal Tape

Pressure Gauge Air Hose Combination Wrench Adjustable Wrench Piller

13.1 Tools & Accessoris for Pressure Test.

PT. ……………. JKT Date: Nov 05 2021


I……………..CENTER Page 9 of 9
Internal Ref. No. Rev. No. 00