WMS - (Pre-Action Sprinkler System Procedure)
WMS - (Pre-Action Sprinkler System Procedure)
No:
PROJECT
Date: 05 Nov 2021 Revision: 00
Approval
PT PT. D
DAFTAR ISI
1. PURPOSE ........................................................................................................................................ 3
5. SCHEDULE ...................................................................................................................................... 4
7. REFERENCE .................................................................................................................................... 4
1. PURPOSE 1. TUJUAN
PT. ……………. JKT Date: Nov 05 2021
I……………..CENTER Page 2 of 9
Internal Ref. No. Rev. No. 00
Doc. No:
PROJECT
Date: 05 Nov 2021 Revision: 00
This pre-action sprinkler system pressure Pernyataan metode uji tekanan sistem
test method statement is prepared to pre-action sprinkler ini disiapkan untuk
describe the activity and is used for menguraikan kegiatan dan digunakan
pipeline pressure testing whether or not untuk uji tekanan pipa apakah terdapat
there is a leak in the pipeline of pre-action. kebocoran atau tidak pada pipa pre-action.
7. REFERENCE 7. REFERENSI
This document refers to the following Dokumen ini mengacu pada standar dan
standards and references: referensi sebagai berikut:
6.1. Approved shop drawing. 6.1. Shop drawing yang telah disetujui.
6.2. Approved tools. 6.2. Peralatan yang telah di setujui.
6.3. NFPA-13, Standard for the installation 6.3. NFPA-13, Standar untuk
of sprinkler system. pemasangan system sprinkler.
6.4. NFPA-14, Standard for the installation 6.4. NFPA-14, Standar untuk
of standpipe & hose system. pemasangan sistem standpipe &
hose.
leakage test at 40 Psi (2.8 bar) udara pada 40 Psi (2,8 bar) harus
shall be conducted for 24 hours. dilakukan selama 24 jam. Setiap
Any leakage that results in a loss kebocoran yang mengakibatkan
1
of pressure in excess of 1 /2 Psi hilangnya tekanan lebih dari 11/2
(0.1 bar) for the 24 hours shall be Psi (0,1 bar) selama 24 jam harus
corrected. diperbaiki. Pipa atau tabung yang
Pipe or tube specifically diperiksa secara khusus untuk
investigated for suitability in dry kesesuaian dalam pipa kering dan
pipe and double interlock pre- sistem double interlock pre-action
action system and listed for this dan terdaftar untuk layanan ini,
service, shall be permitted to be harus diizinkan untuk diuji sesuai
tested in accordance with their dengan batasan daftarnya.
listing limitations.
Methode: Metode:
A. check with the construction A. Pemeriksaan bersama dengan
management that the pre- manajemen konstruksi bahwa
action system pipes are instalasi pipa pre-action
correct. system tersebut sudah benar.
B. Prepare location to be tested. B. Siapkan lokasi yang akan di
C. Prepare all testing equipment. lakukan pengetesan.
D. Then drop all the dropper pipes C. Siapkan semua peralatan
with a plug that has been pengetesan.
wrapped with seal tape. D. Lalu dop semua pipa droper
E. Making a bypass pipe dengan plug yang sudah dililit
connection: Connecting the seal tape.
supply and return pipes into a E. Membuat sambungan pipa
single unit so that air is bypass : Menyambungkan
channeled to the two pipes. antara pipa supply dan return
F. Set all valves to close. menjadi kesatuan agar angin
G. Open valve at fitting introduce tersalurkan kepada kedua pipa
air merged and enter to all pipe tersebut.
pre-action; valve bypass must F. Atur semua valve di tutup.
PT. ……………. JKT Date: Nov 05 2021
I……………..CENTER Page 6 of 9
Internal Ref. No. Rev. No. 00
Doc. No:
PROJECT
Date: 05 Nov 2021 Revision: 00
12. ATTACHED