Case Study 2 SHARP PRINTING AG
Case Study 2 SHARP PRINTING AG
1.1.At this point what would you do if you were the project
manager?
Abstract
Discussion Question:
Question 1. At this point, what would you do if you were the
project manager?
To identify the project risks it is necessary to do deathly
analysis of entire
project. If I was in the project manager, firstly I will consider
firstly these three
factors 1. Project duration 2. Cost 3. Performance
After considering the basic factors I will arrange meeting
with the senior
management so it will be helpful to identify the other priorities
for project. And
also, with presence of senior management other constrain could
be discuss
effectively which are directly or indirectly relate to the project.
Moreover,
approval can be get directly from senior management. So, that
will be helpful to
take any big decision towards the project.
After discussing and getting approval with top management, I
will make new
project scope and project schedule based on research. So,
company can
complete the project efficiently on time.
Question 2. Was top management acting correctly in
developing an estimate?
As per my opinion, top-management was not current for
making a project
estimate due to following reasons
1. Before making the project estimate it is necessary to collect
and compare
the data with similar project or previous project but in this case,
they don’t
collect and compare.
2. They make the project estimation based on assumption rather
than using
standard method or formulated method
3. Project manager plays a vital role for making cost and time
estimation but
top management did not take advice from expert before making
estimation.