Unit 2

The document describes four projects with activities and precedence relationships to construct network diagrams for: 1) An assembly project with 8 activities including turning, polishing, and assembling parts X and Y. 2) A project with 10 activities labeled A-J with various precedence relationships. 3) A project with 5 activities labeled A-E where some must be completed before others can start. 4) A maintenance job with 9 activities for cleaning and repairing heat exchangers, such as dismantling connections and cleaning/replacing parts.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views2 pages

Unit 2

The document describes four projects with activities and precedence relationships to construct network diagrams for: 1) An assembly project with 8 activities including turning, polishing, and assembling parts X and Y. 2) A project with 10 activities labeled A-J with various precedence relationships. 3) A project with 5 activities labeled A-E where some must be completed before others can start. 4) A maintenance job with 9 activities for cleaning and repairing heat exchangers, such as dismantling connections and cleaning/replacing parts.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

1. An assembly is to be made from two parts X and Y.

Both parts must be turned on a lathe


Y must be polished where as X need not be polished. The sequence of acitivities, together
with their predecessors, is given below

Activit
Description Predecessor Activity
y

A Open work order -

B Get material for X A

C Get material for Y A

D Turn X on lathe B

E Turn Y on lathe B,C

F Polish Y E

G Assemble X and Y D,F

H Pack G
Draw a network diagram of activities for the project.

2. Construct a Network diagram for each of the projects whose activities and their
precedence relationships are given below:

Activity A B C D E F G H I J K
Precedenc - - - A B B C D E H,I F,G
e

3) Construct a Network diagram for each of the projects whose activities and their
precedence relationships are given below:

A< C,D,I; B<G,F; D<G,F; F<H,K; G,H<J; I,J,K<E

(Note: A<C means that ‘C’ cannot be started until ‘A’ is completed)

4. Listed in the table are the activities and sequencing necessary for a maintenance job on
heat exchangers in a refinery
Activit
Description Predecessor Activity
y
A Dismantle pipe connections -
B Dismantle heater, closure and floating front -
C Remove tube bundle A,B
D Clean bolts B
E Clean heater and floating head front B
F Clean tube bundle A,B
G Clean shell F,D
H Replace tube bundle F,D
I Prepare tube pressure test and reassemble C,G
Draw a network diagram of activities for the project.