Fundamental Manual First Revision
Fundamental Manual First Revision
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-14514 0
INDEX
1. INTRODUCTION ................................................................................................................. 4
1. INTRODUCTION
The 2004 revision N° 1 of the Company Fundamentals Manuals is based on the feed-
back received from the Eni’s affiliate companies and Eni head-quarter Drilling &
Production Optimization Services Units technicians.
The revision N° 1 started in June 2003, ended in July 2004 and has been carried out with
the supervision performed by head quarter well operations standards department.
The purpose of the revision N° 1 was:
• eliminate the errors present in the first release
• update the Fundamentals Manuals on the bases of the new state of art of the
well operations
• reorganise the structure of the manuals in way to facilitate the research of that
topics which require particular attention to improve performance and
efficiency in terms of safety, quality and costs.
In the following sections, for each manual are listed the main topics reviewed, update or
added.
Following this guide the technicians can easily recognise the changes brought to the
manuals in this way they can align they self to the new Company’s statements.
SPEO IDENTIFICATION CODE PAG 5 OF 34
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-14514 0
have been eliminated and treated in the STAP-P-1-M-6140 “Drilling Procedures Manual”.
Paragraph 2.5 “Dog leg Potential (DLP) and Dog leg Severity (DLS)”
In this paragraph the specific definition of Dog leg Potential (DLP) and Dog leg Severity
(DLS) have been given.
Paragraph 4.2.5
Contractor Drilling Operations Coordinator (CDOC)
Paragraph 4.2.9
Contractor Surveying Representative “ Rig-Site” (CSR)
Paragraph 7.9 “The Definitive: Wellhead Coordinates, Well Survey and Bottom Hole
Coordinates Data Acquisition”
This is a new paragraph where the Definitive Wellhead Coordinates, Well Survey And
Bottom Hole Coordinates Data Acquisition process is defined replacing the Eni document
1.4.2.25 rev. 00 issued in April 01 1996.
SPEO IDENTIFICATION CODE PAG 13 OF 34
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-14514 0
Paragraph 6.1.4 “BOP, Wellhead and X-Mas Tree Pressure rating selection
The pressure rating that has to be selected is:
• For wellhead and X-Mas Tree that stated in ISO 10423 (Api 6A) just superior
at the working pressure calculated/estimated.
• For BOP that stated in ISO 13533 (Api 16A) just superior at the working
pressure calculated/estimated. Exception is made for Bag Preventer; in fact,
this type of preventer is normally indicated and used for the initial well closure.
Immediately after, the pipe rams preventer is requested to activation following
the proper drill pipe space out. For this reason, the bag preventer pressure
rating can be just lower than pipe rams preventer.
Paragraph 6.2.1 BOP Stack System (Land Rigs, Jack-Ups And Fixed Platform)
• In 10000 and 15000 psi stack, a set of pipe rams must be always installed
below the hang-off pipe rams.
• For HT-HP operation, it is recommended to use a BOP stack equipped with
an injection line to pump methanol or glycol, in order to reduce the probability
of hydrates forming during well control operations. It is also recommended to
install temperature gauges in the BOP stack.
• Spare parts for BOP and valves must be available on rig site.
Paragraph 4.7.1
This paragraph has been renamed as “Brines Transportation and Handling” and its
section “Brine handling precautions” has been inserted.
• Orientate and lower the Tubing Head Adapter / Xmas Tree into position using
bolts or alignment bars in position to provide guidance. Tighten the bolts in
the specified sequence ensuring that correct torque is applied, and the seals
energised. The use of a “hydraulic stud tensioning system” is recommended
to reduce flange make-up time.
• All pressure testing of energised seals should be carried out according to the
procedures stipulated in the manufacturer’s manual or well programme
procedures. When testing is complete, bleed off pressure from the test port,
remove test apparatus and replace the check valves and plugs.
• Pressure test the tubing hanger seals by pressuring through the Xmas tree
bore. The test port or valves in the flange must be open during this test to
monitor for leaks.
• Pressure test the tubing hanger seals and ring joint from the test port of the
flange, ensuring the casing side outlet valves are open during this test.
• If X-mas Tree valves are of the quality level “PSL 3G” or “PSL 4”, seals
among tubing hanger, tubing head adapter and tubing spool must be tested
with gas at the X-mas Tree WP.
In Paragraph 8.1
The Bottom Hole Data Acquisition Equipment has been introduced.
From MOR-REX-BASE FLUID (KLM) the concept” Do not add alkaline agent to starch
simultaneously as it may cause an increase of viscosity. Pre-solubilised lignite may be
convienvent” has been eliminated.
Has been eliminated the Description of the System of the Agip Code:
• PO-IE