Gantt Chart

This Gantt chart outlines the tasks, owners, timelines, and progress for a project over 12 weeks. It is divided into 4 phases: project initiation, planning, conception and initiation, and performance/monitoring. The chart allows you to see task dependencies and view project details like owners, start/end dates, and percentage completed over time for each task.

Uploaded by

sham sham
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views

Gantt Chart

This Gantt chart outlines the tasks, owners, timelines, and progress for a project over 12 weeks. It is divided into 4 phases: project initiation, planning, conception and initiation, and performance/monitoring. The chart allows you to see task dependencies and view project details like owners, start/end dates, and percentage completed over time for each task.

Uploaded by

sham sham
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

A Gantt chart's visual timeline allows you to see details

Not you Smartsheet Tip ➜


about each task as well as project dependencies.

PROJECT TITLE [Project's title] COMPANY NAME [Company's name]

PROJECT MANAGER [Project Manager's name] DATE 12/03/18

PHASE ONE PHASE TWO PHASE THREE PHASE FOUR


PCT OF TASK
WBS NUMBER TASK TITLE TASK OWNER START DATE DUE DATE DURATION WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12
COMPLETE
M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F

1 Project Conception and Initiation


1.1 Project Charter Leon W 12/03/18 15/03/18 3 100%
1.1.1 Project Charter Revisions Kylie R 15/03/18 16/03/18 1 100%
1.2 Research Pete S 15/03/18 21/03/18 6 90%
1.3 Projections Steve L 16/03/18 22/03/18 6 40%
1.4 Stakeholders Allen W 18/03/18 22/03/18 4 70%
1.5 Guidelines Malik M 19/03/18 22/03/18 3 60%
1.6 Project Initiation Malik M 23/03/18 23/03/18 0 50%

2 Project Definition and Planning


2.1 Scope and Goal Setting Steve L 24/03/18 28/03/18 4 22%
2.2 Budget Allen W 29/03/18 02/04/18 3 16%
2.3 Communication Plan Malik M 0 0%
2.4 Risk Management Malik M 0 0%

3 Project Conception and Initiation


3.1 Status and Tracking Pete S 0 0%
3.2 KPIs Leon W 0 0%
3.2.1 Monitoring Kylie R 0 0%
3.2.2 Forecasts Kylie R 0 0%
3.3 Project Updates Pete S 0 0%
3.3.1 Chart Updates Malik M 0 0%

4 Project Performance / Monitoring


4.1 Project Objectives Steve L 0 0%
4.2 Quality Deliverables Allen W 0 0%
4.3 Effort and Cost Tracking Malik M 0 0%
4.4 Project Performance Malik M 0 0%