10) If V is the velocity of jet and u is the velocity of vanes, efficiency is maximum when
𝑣
a) u = V b) u = 1.5 V c) u = d) none of the above
2
__________________________________________________________________________________________________
11) the width of the bucket in a pelton wheel is generally ___________ times the diameter of the jet
a) two b) three c) four d) five
__________________________________________________________________________________________________
12) A kalpan turbine is an ________ flow reaction turbine
a) tangential b) axial c) inward d) outward
__________________________________________________________________________________________________
13) In case of diffuser type centrifugal pumps, the vanes mounted on diffuser ring provided ____ passage of fluid
a) gradually decreasing b) uniform c) gradually increasing d) both (a) and (b)
__________________________________________________________________________________________________
14) Practical limiting head against which a single impeller may be used is about
a) 8 m b) 18 m c) 28 m d) 38 m
__________________________________________________________________________________________________
15) It is better to limit number of multistage pumps to _______ to reduced mechanical construction difficulties
a) 3 b) 5 c) 7 d) 10
__________________________________________________________________________________________________
16) Net positive suction is given by
𝑃𝑠 𝑃𝑣 𝑉2𝑠 𝑃𝑠 𝑃𝑣 𝑉2𝑠 𝑃𝑠 𝑃𝑣 𝑉2𝑠 𝑃𝑠 𝑃𝑣 𝑉2𝑠
a) 𝛾
+ 𝛾
+ 2𝑔 b) 𝛾
- 𝛾
+ 2𝑔 c) 𝛾
+ 𝛾
- 2𝑔 d) 𝛾
- 𝛾
- 2𝑔
𝑃𝑠 𝑃𝑣 𝑉𝑠2
where 𝛾
= absolute pressure head at inlet 𝛾
= vapour pressure head of liquid 2𝑔
= velocity head in the suction pipe.
__________________________________________________________________________________________________
17) For well maintained reciprocal pumps, slip is of the order
a) 2 % b) 5 % c) 10 % d) 15 %
__________________________________________________________________________________________________
18) Hydraulic press is a device used to
a) Lift small quantity of water to greater height b) lift larger loads by applying smaller force
c) increase the pressure of a liquid d) all of the above
__________________________________________________________________________________________________
19) Which one of the following is the wrong statement about sprinkler system of irrigation?
advantages of sprinkler irrigation are:
a) there is no seepage loss b) land leveling is not required
c) it leaches down salt and prevents waterlogging. d) it is ideally suited for paddy field
__________________________________________________________________________________________________
20) among the following, which crop has the highest value to delta?
a) wheat b) vegetables c) rice d) cotton
__________________________________________________________________________________________________
21) In a channel bed made of fine sand, when the velocity is gradually increased the sequence of bed formation is:
a) flat surface – dunes – saw tooth ripples – antidunes
b) saw tooth ripples – dunes – flat surface – antidunes
c) flat surface – dunes – antidunes – saw tooth ripples
d) saw tooth ripples – flat surface – antidunes – dunes
__________________________________________________________________________________________________
22) According to Lacey
a) Natural silt transporting channels have a tendency to assume a semi-elliptic
b) finer the silt, channel closely approximates a semi-circle
c) silt is kept in suspension due to the force of vertical eddies
d) all of these
2
Maharashtra Academy for Civil Engineers, Dhule 8459467941
3
Maharashtra Academy for Civil Engineers, Dhule 8459467941
33) The value of angle of wall friction for concrete retaining walls is generally taken as
2 1 1
a) ∅ b) 3 ∅ c) 2 ∅ d) 3 ∅
__________________________________________________________________________________________________
34) The elastic settlement may be found by the formula
1−𝜇 1+𝜇 1−𝜇2 1+𝜇2
a) Se = qn B 𝐸𝑠
b) Se = qn B 𝐸𝑠
c) Se = qn B 𝐸𝑠
d) Se = qn B 𝐸𝑠
__________________________________________________________________________________________________
35) In plate load test preloading recommended by IS code is
a) 70 gm/cm2 b) 100 gm/cm2 c) 120 gm/cm2 d) 125 gm/cm2
__________________________________________________________________________________________________
36) During electrical stabilization of soil
a) soil particles get flocculated to form large particles b) friction between particles increase
c) fine grained soil is drained d) all the above
__________________________________________________________________________________________________
37) Ringelmann’s scale is used to
a) measure CO b) measure SO2
c) grade density of smoke d) grade automobile exhaust gas
__________________________________________________________________________________________________
38) What will be the resultant decibel level when two sources make noise of equal decibels?
a) Decibel level will the same b) Decibel level will increase by 3 decibels
c) Decibel level will decrease by 3 decibels d) Decibel level will be equal to the sum of decibels of 2 sources
__________________________________________________________________________________________________
39) Dioxin is released during which one of the following processes?
a) composting b) incineration c) compost plants d) Bio-fertilization
__________________________________________________________________________________________________
40) Suitable method for forecasting population of a large city, which has reached its saturation population is
a) arithmetic increase method b) geometric increase method
c) incremental increase method d) graphical method
__________________________________________________________________________________________________
41) Maximum daily consumption of water varies ___________ percentage of annual average daily rate of demand.
a) 125 b) 140 c) 160 d) 180
__________________________________________________________________________________________________
42) An egg-shaped section of sewer
a) is more stable than circular section b) provides self-cleansing velocity at low discharge
c) is economical compared to circular sections d) is easy to construct
__________________________________________________________________________________________________
43) List – I List - II
Name of formula formula for estimating water demand for fire
A. Kuching’s formula 1. Q = 4637 √𝑝 (1 − 0.01√𝑝)
B. Buston’s formula 2. Q = 1136 (p/5 + 10)
C. freeman’s formula 3. Q = 3182 √𝑝
D. National board of fire underwriter’s formula 4. Q = 5663 √𝑝
Where Q is quantity in liters/minute
P is population in thousands
codes: A B C D
a) 4 3 1 2
b) 4 2 3 1
c) 3 4 1 2
d) 3 4 2 1
4
Maharashtra Academy for Civil Engineers, Dhule 8459467941
5
Maharashtra Academy for Civil Engineers, Dhule 8459467941
6
Maharashtra Academy for Civil Engineers, Dhule 8459467941
Codes: A B C D
a) 3 1 2 4
b) 4 2 1 3
c) 3 2 1 4
d) 4 1 2 3
__________________________________________________________________________________________________
68) The following items related to hydrologic requirements in hydropower system. match List I with list II
List-I List-II
A. stream flow in order of magnitude is plotted as 1. Mass-curve
ordinate and percent of time as abscissa
B. cumulative value of stream flow is plotted 2. Flow duration curve
against time for whole period of record
C. plot of available power against percent of time 3. hydrograph
D. plot of flow in a stream against time at specific interval 4. power duration curve
Codes: A B C D
a) 2 3 4 1
b) 4 1 2 3
c) 2 1 4 3
d) 4 3 2 1
__________________________________________________________________________________________________
69) Calibration of a current meter for use, in channel flow measurement is done is a
a) wind tunnel b) water tunnel c) towing tank d) flume
__________________________________________________________________________________________________
70) Consider the following statements:
1. Time area histogram method aims at developing an IUH
2. Isochrone is a line joining equal rainfall on a map
3. Linear reservoir is a reservoir having straight boundaries
4. Linear channel is a fictitious channel in which an inflow hydrograph passes through with only translation and
no attenuation.
which of these statements are correct
a) 1, 2, and 3 b) 1 and 4 c) 2, 3 and 4 d) 1, 2, 3 and 4
__________________________________________________________________________________________________
7
Maharashtra Academy for Civil Engineers, Dhule 8459467941
71) Match List-I (floods) with List-II (parameters) and select the correct answer using the codes given below the lists:
List-I List-II
A. standard project flood (SPF) 1. Includes catastrophic floods
B. Maximum probable flood (MPF) 2. Includes floods of severe conditions
C. Design flood 3. Peak flow obtained from observed data
D. maximum flood 4. Flood of desired recurrence interval
Codes: A B C D
a) 2 1 4 3
b) 1 2 3 4
c) 2 1 3 4
d) 1 2 4 3
__________________________________________________________________________________________________
72) Match List-I with List-II and select the correct answer using the codes given below the lists:
List-I List-II
A. specific yield 1. volume of water retained per unit volume of aquifer
B. specific capacity 2. volume of water drained by gravity per unit drained volume of aquifer
C. specific retention 3. difference of porosity & specific storage
D. specific storage 4. well yield per unit draw-down
5. volume of water released from unit volume of aquifer for unit decline in
piezometric head
Codes: A B C D
a) 2 4 1 5
b) 4 2 3 5
c) 2 5 1 4
d) 4 2 3 1
__________________________________________________________________________________________________
73) Which one of the following flood routing methods involves the concepts of wedge and prism storages?
a) coefficient method b) Muskingum method
c) Pul’s method d) Lag method
__________________________________________________________________________________________________
74) segmental roof section is best suitable for _____
a) subways b) navigation tunnels c) Rock tunneling d) all of these
__________________________________________________________________________________________________
75) ‘Primer’ is _________
a) type of paint used in tunneling b) small quantity of explosive
c) a small cut at the centre of tunnel cross section d) type of drill bit
__________________________________________________________________________________________________
76) size of liner plates is usually _______
a) 200 mm × 300 mm b) 300 mm × 400 mm c) 400 mm × 900 mm d) 500 mm × 950 mm
__________________________________________________________________________________________________
77) Every tunnel has ____
a) invert b) portal c) lining d) only (a) and (b)
__________________________________________________________________________________________________
78) ‘Shove of shield’ means __________
a) to change direction of shield b) forward movement of shield
c) Backward movement of shield d) removal of muck from shield
__________________________________________________________________________________________________
79) permanent ventilation of tunnel is essential for tunnel lengths greater than ______
a) 200 m b) 300 m c) 750 m d) 1200 m
8
Maharashtra Academy for Civil Engineers, Dhule 8459467941
82) Full face method of tunneling is usefull for tunnels having diameter upto,
a) 3 m b) 6 m c) 10 m d) 12 m
__________________________________________________________________________________________________
83) Generally a culvert has a span less than________
a) 4m b) 1 m c) 6 m d) 10 m
__________________________________________________________________________________________________
84) If afflux is more, scour depth
a) will be less b) will be more c) will have no effect on it d) none of these
__________________________________________________________________________________________________
85) The free board for a high level bridge should not be less than ____
a) 60 cm b) 90 cm c) 120 cm d) 30 cm
__________________________________________________________________________________________________
86) IRC recommendations for minimum width of foot path on bridge is
a) 1.0 m b) 1.5 m c) 2.0 m d) 2.5 m
__________________________________________________________________________________________________
87) IRC standard loading for bridge designs are
a) class A, Class B, class AB and class 70-R b) class A, Class B, class AB and class 90-R
c) class A, Class B, class BB and class 70-R d) class A, Class B, class AA and class 70-R
__________________________________________________________________________________________________
88) The bridge having its floor supported at the top of structure is known as ---
a) semi through bridge b) deck bridge c) through bridge d) submersible bridge
__________________________________________________________________________________________________
89) abutment piers are provided in multiple span
a) arch bridges b) submersible bridges c) temporary bridges d) suspension bridges
__________________________________________________________________________________________________
90) The center to center distance between any two adjacent support of a bridge is called
a) span b) economic span c) clear span d) none of the above
__________________________________________________________________________________________________
91) for preparing the site plan for a bridge the scale generally adopted is
a) 1 in 1000 b) 1 in 100 c) 1 in 10000 d) 1 in 5000
__________________________________________________________________________________________________
92) C.B.R.I. stands for
a) Central bureau of building Institute b) central building research India
c) Central building research institute d) central bureau & research of India
__________________________________________________________________________________________________
93) Appropriate cost of all electrical works is ________ % of estimate cost of building.
a) 9 % b) 12 % c) 3 % d) 5 %
__________________________________________________________________________________________________
94) Aggregate, ballast, grit, sand, etc are measured in ______
a) m3 b) tonn c) mm d) cm2
__________________________________________________________________________________________________
95) Limits of measurement shall be in accordance with ________
a) SP : 27 1984 b) SP : 26 c) SP 46 : 2003 d) SP 20 : 1997