Course in Measurements QS
Course in Measurements QS
OF
BUILDINGS
AND
BY QS A. NDIBALEMA
1
COURSE OUTLINE
Measuring the quantities of building works and the use of SMM (BW)
Measurement of Building services and the use of SMM (BW)
Measurement of Civil Works the use of CESMM
Preparation of bills of quantities
Importance, requirements, definition and pricing preliminaries
1. Two Assignments
2. Two Tests
3. End Semester Examination
References
2
INTRODUCTION
3
CIVIL ENGINEERING WORKS AND BUILDING WORKS
There are two separate and distinct practice of measurement operating for civil
engineering works and building works such as:-
(i) Building works are generally measured in accordance with Standard Method
of Measurement (SMM) FOR East Africa
(ii) Civil Engineering works are generally measured in accordance with Civil
Engineering Standard Method of Measurement (CESMM)
The comparisons between the two types of works that necessitate different method of
measurement are as follows:-
4
(ii) Small rates
Some rates in building works are very small as a result of small items
measured separately.
(iv) Variations
In building works, no much variations since almost all the items can be
measured with certainty. In the absence of variations in design most
building works with the exception of sub-structure, drainage and external
works will not be subject to re-measurements and the contractor will be
paid for the quantities incorporated in the Bills of Quantities.
(vii) Administration.
The structure of the team concerned with the construction of a civil
engineering project is similar to that for building works. In Civil engineering
works, the head of construction team is an engineer assisted by Resident
engineer while for buildings is an Architect assisted by the clerks of works.
6
MEASUREMENT OF BUILDING WORKS
HISTORICAL BACKGROUND
The architect was responsible for the creation of buildings as well as their design, and
he/she employed a number of master craftsmen who performed the work in each trade.
On completion each master craftsmen submitted an account for the materials used and
labor employed on the work.
The need of quantity surveyors became obvious for the following reasons:-
Due to the above reasons, general contractors became established during the period of
the industrial revolution and they submitted inclusive estimates covering the work of all
trade. Furthermore, they engaged surveyors to prepare bills of quantities on which their
estimates were based.
7
As competitive tendering became more common the general contractors began to
combine to appoint a single surveyor to prepare a bill of quantities, which all the
contractors priced.
In addition, the architect on behalf of the building owner usually appointed a second
surveyor, who collaborated with the surveyor for the contractors in preparing the bill of
quantities, which was used for tendering purposes.
In later years, it became the practice to employ one surveyor only who prepared an
accurate bill of quantities and measured any variation that arose during the progress of
the job. This was the origin of the independent and unbiased quantity surveyor as he
operates today.
COMMON TERMS:-
2. Taking off – measuring of quantities in which the dimensions are scaled or read
from drawings and entered in a recognized form or specially ruled paper, called
“dimension paper”.
4. Contractor – Is a person or corporate body whose bid to carry out the works
has been accepted by the employer and eventually engaged to undertake the
works.
5. Employer - Is the party who employs the contractor to carry out the works.
8
6. Provisional Sums – works which cannot be measure accurately during taking
off. It is a sum provided for work or for costs which cannot be entirely foreseen,,
defined or detailed at the time of tendering documents are issued. Examples are
such as testing of materials, progress photographs and contingencies. The sum
is to be used under instruction.
7. Prime Cost Sum (P.C) – Cost for works provided by nominated sub contractors
for example, electrical installations, telephone installation, lifts installation etc.
Since this is a specialist work carried out by persons other than the general
contractors provision is to be made for profit to the general contractor and for
attendance.
8. Preliminaries - items in the bill of quantities entered for the purpose of setting
out all general liabilities and obligations of the contractor. These are items
required to be executed pre-commencement of the actual required work, during
the work and after the work completion.
10. Preambles – able clauses inserted at the head of each work section bill
covering matters relating to the specific work section that should be brought to
the attention of the estimator as they will affect the rates that he inserts against
billed items of measured work.
9
MEASUREMENT PROCEDURES
In any measurement there are a number of essential factors that should always be
considered and applied to follow good established practice as follow:-
1. Examine the drawing carefully to become familiar with the work and to identify
any parts where information is lacking.
2. Interpret carefully and apply in a sound and logical way of provisions in Standard
Method of Measurement of building works. (SMM).
5. All descriptions should be adequate, concise and written in a logical and easily
understood format following the sequence adopted in SMM.
6. Adopt a logical sequence of items so that each one following the preceding one
in a natural progression.
10
GENERAL PRINCIPLES OF TAKING – OFF
1. General rules:-
Bills of quantities shall fully describe and accurately represent the works
to be executed. The billed description is to be comprehensive and
sufficient to enable the estimator to fully understand what is required and
to give a realistic price. Those works whose extent cannot be
determined with reasonable degree of accuracy should be described as
“Provisional”.
Works are to be measured net as fixed in position each measurement are
to be taken to the nearest 10mm i.e > 5mm regarded as 10mm while <
5mm are disregarded.
Openings under the measured area shall be deducted.
2. Dimension paper:
Measured items, scaled or taken from drawings are entered on a special paper
known as ‘dimension paper’. This dimension sheet is split into two identically
ruled parts each consisting of four columns as follows:-
1 2 3 4 1 2 3 4
11
Key:
Column 1 – “Timesing column” Multiplying figures are entered when there
is more than one of the particular items being measured.
3/ 5.00
This means that the length of 5.00m of the same item appears three times in
the measured drawing
5.00
3/ 5.00 15.00
3.00
1.50
0.50
5.00
3/ 5.00 15.00 Hor. Dpc. 110mm wide
of single layer of
Hessian base bit. to
B.S. 743 Lapped
100mm at jts and
bedded in c.m (1:3)
Hor. Dpc……………….. are in “Description column”.
12
1. Entering of Dimensions:-
(b) Spacing of items - It is essential that ample space is left between all items
on the dimension sheets so that it is possible to enable any items which may
have been omitted when the dimensions were first taken off to be
subsequently inserted without cramping the dimension disproportionately.
10.00
0.69
0.23
(c) Waste - The right hand side of the description column is used for
preliminary calculations, built up lengths, explanation notes, location of
measured work etc. This should not be overlooked. All steps that have been
taken in arriving at dimensions, no matter how elementary or trivial they may
appear should be entered in the waste section.
(d) Timesing – If there were five such items, then this dimension would be
multiplied by five in the timesing column:-
5/ 10.00 Conc. Grade 20
0.69 in beds
0.23
7.94
13
(e) Grouping of Dimensions
(i) Where the same dimension applies to more than one item the best
procedure is to segregate each of the separate description by & sign and to
bracket the descriptions.
Site clearance by
removing up
bushes, shrubs
and the like
100.00 including grubbing
50.00 up their roots
&
Exc. O`site av.
150m deep to
remove all veg.
matter wheel 20m
then spread and
level.
(ii) Where more than one set of dimensions relate to the same
description, the dimensions should be suitably bracketed.
25.00 21.10
3.50 20.30
17.00 15.10
Exc o’site av.
3.50 230 mm bwk laid & 12.50
150mm db to
jtd in c.m (1.3) revome all
15.00 18.75
veg. matter
3.50 10.00
wheel 20m
then s &l
10.00
3.50
14
(f) Abbreviations
Abbreviations are used in the description space in order to save space and time.
There are standard and acceptable abbreviations used in measurement such as
follows:-
conc. - Concrete
a.b - as before
a.b.d - as before described
n.e - not exceeding
bldg - building
B.S - British Standard
Bwk - Blockwork
Ddt - Deduct
b&j - bed and joint
bott. - Bottom
(g) Deductions
When measuring areas of excavation, concrete oversite, blockwork etc the best
practice is to measure the full area in the first instance and, subsequently adjust
for any voids or openings. e.g Adjustment for blockwork are done when “taking
off the windows & door openings.
15
2. Measurement of Irregular figures
It is often necessary to measure the areas of triangles and circles, the
circumferences of circles and volumes of cylinders, etc., and the usual method
of entering the dimensions is illustrated in the following examples:
½/ 4.00
3.00 Area of triangle with a base of
4m and a height of 3m
(area=½base x height)
22 2.00
7 2.00 Area of circle with 2 m radius
(area = πr2)
Circumference of semi-circle
½ /2/ 22 2.00 with 2 m radius (circumference
7 of whole circle = 2πr)
3. Alterations to dimensions
16
23.50 Exc. fdn. tr. n.e. 1.50m
0.75 dp.comm.at stripd.level
0.80
&
|
8.20 Nil
0.75 Backfill exc. mat. ard.
| fdns
0.80
4. Figured Dimensions
a. Sheets should be suitably headed with the title and section of the job at
the top and numbered at the bottom. Example Drawing 10, doors section
can be seen as below.
CONSTRUCTION OF PHYSCIS LABORATORY –Drwgs,,,,,,,,,,,,,,,,,,,,,,,,,
. Site Clearance
1.1
. Doors
10.1
b. At the top of the first dimension sheet for a job, it is good practice to enter
a list of the drawings from which the measurements have been taken with
the precise drawing number of each contract drawing carefully recorded.
17
6. Order or “Taking – off”
The order of “taking off mostly follows the order of construction. In simple
building the order of taking off would probably be as follows:-
a. Site clearance
b. Foundations excavations
concrete footing
blockwork
hard core
Concrete bed
cover bed
c. Blockwork
d. Floors
e. Roof
f. Finishing (Plaster, ceiling & floors )
g. Windows
h. Doors
i. Fittings
j. Plumbing installation
k. Drainage work
l. Other services (electrical etc)
m. External works (roads, paths, fences and grassed areas)
7. Descriptions
18
8. Query Sheet
QUERY SHEET
S/N QUERY ANSWER
19
SUBSTRUCTURES
The Substructure of any building is a base or the underneath or the foundations of that
building. Building construction can be divided into two faces namely,- the Substructure
and the Superstructure. The constructions after the foundations are of the
Superstructure.
A. EXCAVATIONS
In a small building, a satisfactory order of items would be as follows:-
1. Site clearance/site preparation this will include:-
(i) Site preparation generally including anti-termite treatment if any. This is
given in square meters.
(ii) Excavating vegetable soil - This normally forms the first item in the
‘Excavation’ section of the Bill. The area is measured in square meters to
the extremities of the foundations and the average depth, often 150mm, is
included in the description together with the method of disposal on the
site.
15.00 Exc. veg. soil, av.150mm
dp. & dep. on site in
12.00 spoil heaps, av. 20 m
from excavn
20
(iii)(b) Cutting down hedges and grubbing up their roots shall be given in
linear meters stating the nature and height of each hedge or its location.
(iii)(c) Clearing site of bushes, scrub, undergrowth and the like and grubbing
up their roots shall be given in square meters or hectares.
15.00
12.00 Clearing site of bushes,
scrub, undergrowth and
the like and grubbing up
their roots.
Measurement of Earthwork
21
Sloping site excavation
The average depth of excavation over the site is most conveniently found by
suitably weighting the depth at each point on the grid of levels, according to
the area that each level affects. This involves taking the depths at the
extreme corners of the area once, intermediate points on the boundary twice
and all other intermediate points four times. The sum of the weighted depths
is divided by the total number of weightings (number of squares x 4) to give
the average weighted depth for the whole area. This method can only be
used when the levels are spaced the same distance apart in both directions.
22
The volume in this example is now calculated:
Corner depths 2.50-2.00= 0.50
3.00-2.00= 1.00
4.00-2.00= 2.00
3.50-2.00= 1.50
vv
The dimensions would then appear as follows:
(1) Not exceeding 1.50m deep, and (2) Exceeding 1.50m deep and not
exceeding 3.00m deep. It is advisable to separate the trenches to
external and internal walls.
23
Excavation in rock and in silt or running sand shall be given in cubic
meters as extra over all kind of excavations irrespective of the depth.
These are to be separated from normal excavations because they have
different cost implication during pricing.
22.50 Exc. fdn. tr. n.e 1.5m. dp 22.50 Extra over exc.
starting at stripped lev. in rock
0.75 0.75
1.50 1.00 &
&
Backfill exc.
Backfill exc. mtls. ard. mtls. ard. Fdns
Fdns
Girth is a perimeter of a building. This length is required for foundations, external walls
etc. also it is a base to calculate dimensions for trench excavation, planking and
strutting, concrete in foundations, blockwork and damp proof course.
Example
10.00m
20.00m
24
Girth
l = 20.00
w = 10.00
sum of l & w 2/30.00
sum of all for sides – 60.00
less corners 4/230 - 0.92
girth of bldg 59.08
Fdn depth – 1.20m
Fdn width – 700mm
For insitu plain concrete footing, concrete is poured against the sides of
trenches hence no working space is required.
(a) Working space of 0.30 from the face work requiring the formwork not
exceeding 1m high
(b) 2m for trenches to receive post tensioned concrete ground beams
(c) 1m for work which is over 1m high from below the starting level of
excavation
25
formwork
690mm
Excavating pits to receive columns, isolated piers and the like are given in
cubic meters stating the starting level and the depth. Allowances for
working space are to be considered depending on the depth of pits and
the formwork requirements.
For example, a column of 1.50m height and 1.00m base can be recorded
as follows:-
&
26
3. Disposal of excavated materials
27
20.00 Imported sand to make 20.00 Imported sand
15.00 up levels 15.00 280mm average
0.45 depths to make
up levels
5. Disposal of water
Disposal of water –This is done to keep excavation free from water and is
given as item
Planking and strutting - Earthwork support which include the use of timber
Planking and strutting to uphold the sides of excavation, plywood trench
sheeting and light steel trench sheeting and strutting. It is measured to the
sides of trenches and given as an item. section D19 or can be measured in
square meters
28
excavations
B. MEASUREMENT OF FOUNDATIONS
When the excavation is complete, the excavated trench is filled with foundations
which include:-
Conc.(1:3:6/40mm
20.00 10.00 agg)
Conc.(1:3:6/40mm agg)
0.75 0.75
in fdns. in fdns.
0 .23
0.23 1.725
3.45
& &
Ddt. Backfill Ddt. Backfill
& &
29
20 2.46 4.932 7.398 9.864 12.33 14.79 17.26 19.72 22.19 24.66
6 0 6 2 8 4 0
25 3.85 7.708 11.56 15.41 19.27 23.12 26.97 30.83 34.68 38.54
4 2 6 0 3 8 2 6 0
32 6.31 12.63 18.94 25.26 31.57 37.89 44.20 50.52 56.83 63.15
5 0 5 0 5 0 5 0 5 0
40 9.86 19.73 29.59 39.46 49.33 59.19 69.06 78.92 88.79 98.66
6 2 8 4 0 6 2 8 4 0
30
Example: If the foundation footing is reinforced with mild steel bars, the
measurements and entries will be as follows:-
34.00
4/ 8.50 16.00
34.00 15.20
4/ 4.00 65.20
16.00 12mm dia. Mild steel bars in fdn footing
4/ 3.80
15.20 65.20x 0.888kg/m = 57.8976 Say
58kg
Formwork for most of the surfaces are given in square meters classifying
them in groups according to the position requiring formwork.
31
Example
10.00m
20.00m
Girth
l = 20.00
Less sprd 2/235 0.47
19.53
w = 10.00
Less sprd 2/235 0.47
9.53
32
Example: Measurement of Damp proof course
Solid floors
(a) Ground floor consisting of a concrete bed usually supported on a bed of hardcore
Hardcore – This is measured as equal to the area of the void being filled (D20 in
SMM). It is measured in square meters if it does not exceed 300mm
thick, otherwise it is in cubic meters.
Damp proof membrane – This is laid on top of the hardcore and normally
measured in square meter. The description of Damp
proof membrane must include particulars of materials
used, thickness/gauge, number of layers and the
nature of bedding (section G96 –G97)
&
Polythene hor. Membrane
not less than 0.125 mm th.,
lapped 100mm at jts. & laid
on hardcore
33
Example: Measurement of Concrete bed
(b) Upper floors consisting of suspended concrete slabs. (SMM. section F7 (a))
Suspended floors and the like shall be given in square meters stating the
thickness.
The floors will be measured together with the associated items such as
reinforcements Section F16 and formwork section F19
34
SUPERSTRUCTURES
MEASUREMENTS
It is essential to measure the wall in a sequential order starting with external wall,
internal wall together with their incidental works if any.
The length of external walling will be obtained by the method of girthing and the
height will normally be taken up to some convenient level, such as the general
eaves line. Any additional areas of the external wall such as gables parapets, wall
up to higher eaves level, etc, will be then taken off.
In measuring the wall the measurer takes the whole area regardless that there are
some voids and the adjustment of wall for window and doors openings will be made
when measuring the windows and doors.
35
The measurement of areas of external walls will be followed by incidental labours,
etc, such as rough cutting, eaves-filling, projecting courses etc.
The measurement of external wall is usually followed by the internal walls. A careful
check should be made on the type and thickness of each partition, and where there
are a number of different types of partition it is often helpful to color each type in a
different color on the floor plan. Internal wall is also measured in square meters
stating all essential particulars as before described.
Roofs are of two types namely; Pitched roofs and flat roofs. Both types can
conveniently be subdivided into two main sections for purposes of measurement, i.e.
construction and coverings. The order of measurement of these two sections varies in
practice, but on balance it is probably better to take the construction first as this follows
the order of construction on site.
PITCHED ROOFS
(a) Construction
The order of items should follow a logical sequence such as plates, rafters, ceiling joist,
collars, purlins, struts, ridge boards, and hip and valley rafters.
36
25X250mm
60 hardwood/softwood timber
Fascia board
18m
18m
No of Trusses =
Gable ends L/S + 1
18/1.5 +1 = 13
37
18m
If the length of rafters is calculated as 5m in each side, then the ‘taking off’ will be as
follows:-
Where roof sections are drawn to a sufficiently large scale, the easiest method is
to scale the length of rafter off the drawing, taking the length from one extremity
to other of the rafter.
The use of four figure mathematical table for values of natural secants is
recommended.
38
40°
4.175m
Half total span of roof is 4.175m, and the secant 40° is 1.305, therefore,
(b) Coverings
Roof covering are of various types such as slates or tiles, corrugated or toughed
sheets, thatch, bitumen felt , etc.
39
Square cutting around openings, raking cuttings , curved cuttings, valleys, hips
and vertical angles shall be given in linear meter separately.
Corrugated or troughed sheets SMM K16 –K26
Measurements:-
Square cutting around openings, raking cuttings , curved cuttings, valleys, hips
and vertical angles shall be given in linear meter separately.
(a) Asphalt (SMM SECTION J)– The main areas of asphalt are measured in square
meters stating the thickness and number coats of asphalt. Furthermore, the asphalt
item is to include the underlay of felt, cork, fiberboard or similar material and any
reinforcement.
(b) Bitumen felt (SMM K36) – The unit of measurement is the square meter and it is
classified by slope. Full particulars of felt are to be given such as extent of laps, nature
40
of base and method of securing felt to it and the nature of surface treatment if any. The
measurement of the main areas of roof covering will be followed by such linear items.
FINISHING (SECTION S)
Major Finishing classifications are walls, floors and ceiling. The classifications depend
on which kind of materials eg.
-Cement sand screed
-Terrazo
-Ceramic floor tiles etc
INSITU FINISHINGS
41
Typical description
40mm Thick cement and sand screed (1:3) steel trowelled smooth laid to floor to
keyed concrete base.
B) TERRAZO FINISHING
(i) Composition and mix ratio
1st coat consist of cement and sand screed (1: 3), (1: 4), (1: 6)
2nd coat consist of cement marble chipping white or any color 1 :21/2
(ii) Thickness 20 – 60mm thick ( minimum thickness is 16)
(iii) Number of coats – 2coat or 1coat it the thickness is less than 30mm
(iv) Nature of surface treatment
- Grind the surface
- Polish the surface
(v) Nature of base – concrete, blockwork or brickwork
(vi) Special curing
Typical description
40mm Thick terrazzo to floor to keyed concrete base in two coats 1st coat of
20mm thick (sand and cement 1:3) 2nd coat of 20mm coloured and marble
chipping 1:21/2) includind grinding the surface and polishing.
Ceiling Finishing (S 4)
Work to walls and ceilings shall each be given separately in square meters describing if
to battering walls, to sloping walls etc.
The area of ceiling is measured between wall surfaces in square meters, followed by
any associated labor such as arises to beams.
42
Wall Finishing (S 4)
The measurement is taken from the floor to ceiling. Work behind wood skirting and the
like shall be dealt with the work of walls disregarding any ground.
Dividing strips S. 7
Dividing strips are given in linear meters stating end, angles and intersections shall be
deemed to be included with the item.
Schedule of finishings
150X20
RI 40mm Terrazzo Terrazzo Plaster Plaster
43
230 3000 230 3500 230 4000 230 4000 230
R1 R2 R3 R4
44
FLOOR FINISHING SKIRTING
WALL FINISHINGS
CEILING
(R(1& 2) FINISHING
ht = 3.00
Less floor 0.04 15 mm thick plaster
Less Skirting 0.15 0.19 to concrete ceiling
in two coat 1st coat
Finishing ht 2.81 12mm thick in
cement, sand and
(R(1& 2) line ( 1: 4: 5); 2nd
Ht = 3.70 coast 2mm thick in
Less 0.19 cement sand and
3.51 line putty (1: 1: 5)
with wood floated
surface internally.
45
2/ 3.00 15mm thick plaster to
2.81 blockwork/ concrete work or
brickwork walls in two coats,
2/ 5.00 1st coat 12mm thick in
2.81 cement, sand and lime
(1:4:5) 2nd coat 3mm thick.
&
2/ 3.50
2.81 3mm thick in cement, sand
and lime putty ( 1:1:5) with
2/ 5.00 wood floated surface
2.81 internally
2/2 4.00
3.51
2/2 5.00
3.51
46
DOORS AND WINDOWS - SECTION M
A. DOORS
Door shutters
The measurement of doors can be subdivided into internal and external doors, and the
dimensions of each of these two classes of door broken down into;
1. Door
2. Adjustment of opening
Measurements
Doors shall be given in square meters stating the thickness and the number of
doors (each leaf being counted as one door).
Classification
(i) Flash doors stating the construction of the core, the finished thickness of the
door, the kind, quality and the thickness of the facing materials and the method
of fixing of facing material to the core.
(ii) Boarded doors stating the thickness of the boarding, ledges, braces and
framing and the method of jointing the board covering or filling.
(iii) Panelled doors stating the nominal thickness of the framing, the number and
nominal thickness of the panels and where molded stating whether the moldings
are worked on the solid or planted on and whether on one or both side.
Pannelled doors with open panels for glass shall be so described.
47
Door frames and linings
Door frames and linings are measure in linear meters giving full description of all the
labours and the size of the member.
Adjustments
When adjusting the opening for care must be taken to cover all the appropriate items
by adopting a logical order of ‘taking off’ such as deduction of walls, external and
internal finishings, - skirting, and flooring
Sundries
Plugging - Plugging to concrete, blockwork and stonework shall be given in squire
meters or enumerated or may be given in the description.
Holes in timber – Holes for bolts and the like shall each be enumerated separately
stating the size of bolts and the thickness of timber.
Iron-mongery
48
FIXTURES AND FITTINGS - SECTION M28
Internal work
External work
Generally, work on surface over 300mm girth shall be given in square meters.
Those not exceeding 300mm girth shall be in linear meters
Those not exceeding 0.10 square meter shall be enumerated
49
Measured on groups according to the nature of the background such as:-
On general surfaces
On wood, frames, wood windows and glazed wood doors
On metal windows and glazed metal doors
On structural steelwork
On grilles, balustrades, railing and mesh
On gutters
On pipes
On bars, cables, conduits, straps and ducting
50
BILLS OF QUANTITIES
Bills of quantities is a fully described and accurately representation of the works to be
executed. Bills of quantities consist of preliminaries, prime cost sums, provisional sums
and measured works.
(a) It enables all contractors tendering for a job to price on exactly the same
information with a minimum effort. In the absence of a bill of quantities being
prepared by the building owner each contractor would have to preparing his own
Bill of Quantities in the limited amount of time allowed for tendering. These
places a heavy burden on each contractor and also involve him, in additional
costs.
(b) It provides a basis for the valuation of variations which often occur during the
progress of the work.
(c) It gives an itemized list of the component parts of the building, with a full
description and the quantity of each part, and this may assist the successful
contractor in ordering materials and assessing his labour requirements for the
job.
(d) After being priced, it provides a good basic for “cost planning and cost analysis
work”.
Elemental bills
In Elemental bills, items are grouped according to their position in the building. Each
element comprises an integral part of the building such as external walls, roofs or
floors, which each perform a certain design of function. Within each element, the items,
may be billed in trade order or grouped in building sequence.
51
Trade bills
In Trade bills, items are arranged in trade order under the main headings of the
separate trades.
Operational bills
The description of the billed work follows the actual building process, with materials
shown separately from labour, all described in terms of the operations necessary for
the construction of the building. An operation for the purpose of the operational bill is
the work performed by a man or gang between definite breaks in the pattern, such as
bricklaying from damp-proof course to first floor joists in housing work.
Working – up
After the ‘taking - off’ the quantities, squaring the dimensions and entering the resultant
lengths, areas and volumes in the third or squaring column on the dimension paper
follows. The next stage is transferring the squared dimensions to the abstract or
transferring the items directly from the dimension sheet to the bill. In the bill of
quantities, the various items of work making up the job are listed under the appropriate
trade or section headings, with descriptions printed in full and quantities given in
recognized units of measurement as per SMM. The above narrated process is known
as ‘working – up’.
52
Ruling of Bill of Quantities
1 2 3 4 5 6
SUBSTRUCTURE
Vegetable soil
Excavation of vegetable. soil, average150mm
A deep and deposit. on site in spoil heaps, average. 20 M2 20,000 400,000
20 metres away from excavations
E ………………………..
TO COLLECTION
Pg. 8/3/1/1
53
Item Description Quantity Unit Rate Amount
ELEMENT NO 1: SUBSTRUCTURE
Trench excavation and Disposal
Excavation of foundation trenches.. not
A exceeing 1.5 meter deep starting at 20 M3 ……… …………
stripped levels.
C ……………………..
D …………………….
Concrete bed
E 100mm Thick concrete bed (1:2:4) mix
30
ratio 20) aggregate. M2 ………… ………….
TO COLLECTION
COLLECTION
Pg. 8/3/1/2
54
Item Description Quantity Unit Rate Amount
ELEMENT NO 2: ROOFING
Roof structure
…………………………………
A … M ……… ……….
…..
B ………………………………… …… ………..
C …………………….. …. M
….. ………..
D …………………….
Roof coverings
E ………………………………. ………. ………..
… M2
Pg. 8/3/2/1
Units of Measurement
The commonly used in the Bills of Quantities are Linear, Square and cubic respectively
They are abbreviated as M, M2, M3, Kg, Prs
Quantities are to be billed to the nearest whole unit. Fractions of units which are
less than one – half are. Disregarded
When the above application causes an entire item to be eliminated, the item is to
be enumerated stating the size or weight.
55
General Rule of Billing
Items will be grouped under suitable section and sub-section headings and will
follow the order and terms adopted in the SMM.
The preamble clauses will be inserted at the head of each section
Each item to be priced in the bill is indexed by letters and or numbers in the first
column
Words in the bill will written in full without any abbreviation
Provision is made for the total sum on each page of the bill relating to a given
section of work to be transferred to a collection at the end of the section
The total of each of the collections is transferred to a summary at the end of the
bill
Note: On completion of the draft bill must be very carefully checked against the
abstract or the squared items and those items suitably marked in colored
ink or pencil as each item is dealt with.
Numbering of the pages in the Bill of Quantities follows the sequence of section; bill
No., Element No and the page No.
For example the page below indicate that, fencing work is placed at section number 9,
it is in bill number 3, Element No. 1 on page 1.
Here below is an example of the Bill of Quantities
56