Estimating The Effort of Development of A Django Application
Estimating The Effort of Development of A Django Application
I'm a passionate software developer and researcher. I write about Python, Django and
Web Development on a weekly basis. Read more.
ARTICLE
Global scale on a
startup budget. Built
on Apache
Cassandra™ in the
cloud. Get $300 free
credit.
ads via Carbon
(Picture: https://www.pexels.com/photo/sky-wind-north-weather-vane-36882/)
This is a very common problem that every developer will eventually face at some point. Your boss or a client
comes with a set of requirements and asks you to estimate how long it will take to implement them.
How to precisely (as possible) estimate the effort of development of a Web application? That’s a really tough
question. People in the academia have being conducting research on that topic for at least the past 40 years, and
yet we fail to get it right.
I wanted to write a little bit on that subject to try to highlight the challenges of making an accurate estimation and
perhaps share some of my experience about it.
Check this numbers in relation to the time overruns of the original estimates, from the Chaos Report 2015:
Time Overruns
For the same combined challenged and impaired projects, over one-third also experienced time overruns of 200
to 300%. The average overrun is 222% of the original time estimate. For large companies, the average is 230%;
for medium companies, the average is 202%; and for small companies, the average is 239%.
21 - 50% 18.3%
51 - 100% 20.0%
Scary, right?
Now, why does that happen? Mainly because every estimation involves uncertainty. An estimation is different from
the reality because of the uncertainties. Make no mistake, every estimation will fail.
The software domain is plagued by uncertainties: incomplete requirements, volatile requirements, incomplete
understanding of the scope, human aspects, external factors, etc.
We can’t help ourselves, we are not very good on forecasting things we don’t know.
To illustrate that phenomena, I will quote the article How Uncertainty Works published by Kevin Thompson:
There is more room, in a mathematical sense, for work to grow beyond expectation than to shrink below
expectation.
Mathematically speaking, the effort the accomplish one task can’t go below zero hours. But in the other hand, it
can grow…
Sorry for the silly joke. Anyway, check the example Kevin Thompson gave in his article:
Assume we estimate this work at three days. The actual time may be more than three days over this estimate,
but cannot be more than three days under the estimate!
In mathematical terms, we cannot estimate a task as requiring “X plus or minus Y days,” because the estimate
becomes meaningless if Y is greater than X. What we can do is replace the concept of an increment of
uncertainty with that of an uncertainty factor, F. This means that we think that X is the most likely duration, but
the range of values is between X divided by F, and X times F. For example, suppose we estimate “Paint
Bedroom” at 3 days, with an uncertainty factor of 2.
Besides that, still, why are we so bad at making estimations? When it comes to estimating the effort of software
development, we are over-optimistic. This is just one of the cognitive bias that affect our work.
I grabbed the information below from a great presentation by Julia Clavien on Cognitive Bias in Software
Development.
Cognitive Bias
Systematic errors in judgment and decision making common to all human beings.
– Daniel Kahneman
The tendency of individuals to display an optimism bias and underestimate the time and resource required to
complete a project.
The plan is usually very different from the reality because of the difficulties to estimate what we don’t know, and
even worse, to estimate things we don’t know we don’t know.
There are known knowns. These are things we know that we know. There are known unknowns. That is to say,
there are things that we know we don’t know. But there are also unknown unknowns. There are things we don’t
know we don’t know.
– Donald Rumsfeld
On the Wikipedia I found a very interesting citation of Jørgensen and Grimstad’s work, The Impact of Irrelevant and
Misleading Information on Software Development Effort Estimates: A Randomized Controlled Field Experiment:
It’s hard to estimate what you know you don’t know. (known unknowns)
It’s very hard to estimate things that you don’t know you don’t know. (unknown unknowns)
There is more room for work to grow beyond expectation than to shrink below expectation;
It is all about uncertainty. We certainly can’t eliminate it, but sure thing we can reduce it.
Decompose the tasks into smaller ones. Try to look at them in great detail. Think about the underlying implications
of the implementation of a given requirement.
We can decompose this task into several smaller tasks, and then estimate the effort of the small tasks. Naturally,
putting them all together would give us the overall estimation of the initial task.
The challenge here is to keep the smaller tasks in a level of granularity that actually makes sense, there is no point
in reducing the size below a level where the relative uncertainty does not improve.
As stated by Kevin Thompson, the important thing is to pick a granularity that (1) enables a tolerable level of
uncertainty, and (2) produces a set of things to estimate that is small enough to be practical.
It is what it is. That’s what requirements do. They change. All the time. If they don’t change during the
development, they will during the usage.
There is only one circumstance where the requirements won’t change: It is when the software is no longer being
used.
The requirements will change and I will not cry about that.
What we can do about it? Deliver fast. You certainly have at least heard about Scrum, Minimum Viable Product
(MVP) or Agile Development before.
Break the whole project into small valuable deliverables. Get the client involved. Learn faster. The development of
a software product should be dynamic.
Besides all the benefits of a MVP, it will enable a more accurate estimation, because you will be dealing with a
small chunk of the whole problem, and you will also be learning faster about the requirements and the domain.
I know I’m deviating a little bit from the original subject of this article, but the point is: it is easier to give a better
estimate when the scope is small.
Your client will always need an overall estimation. After all, they need to plan the schedule and the budget.
Besides, there are many factors to take into account when planning a release: the time-to-market, the return on
investment, the end-user needs, etc.
You can always give an overall estimation. But agree with the client that it’s an imperfect and error-prone
estimation. Decompose the requirements into several small and valuable deliverables. Smaller scope means better
estimate. After each interaction, each delivery, review the requirements with the client and update the overall
estimation.
Without mentioning it will improve the client’s understanding of the software needs. Also, they will eventually get to
know some of the technical challenges.
Despite all the effort you are putting to make things work, that’s how the client will perceive you and your work:
Haha! Got the monkey idea from Julia Clavien’s presentation on Cognitive Bias in Software Development.
Sometimes when we are doing estimates, it is common that we forget to take into account the time to write
documentation, unit tests, functional tests, and so on.
Bear in mind it is not only about code. And also important to note, the development estimate is different from a
project estimate.
After reducing the level of uncertainty to a minimum practical level, it’s time to cope with the remaining uncertainty.
If it is a project with a real fixed scope, the client deeply understands what he wants to be done, ideally you already
have some proof of concepts and prototypes – what you want to do is to add a buffer time to the schedule.
How much is enough depends. Depends on how big, what’s the complexity of the project, your experience, how
familiar you are with the domain.
Ask developers about the time they will take to implement the features (T). Multiply it by 2.5. If it is a very
complex algorithmic type project multiply it by 3.0.
In my experience that’s a pretty good approximation for total project time. Usually coding time is only 40% of
total project time.
Nitin Bhide
Thursday, March 25, 2004
Reference: http://discuss.fogcreek.com/askjoel/default.asp?cmd=show&ixPost=4164
Now, if we compare with the data from Chaos Report 2015, where the average overrun is 222% of the original time
estimate. The numbers suggested by Nitin Bhide are about right.
So this velocity concept will eventually be impacted by the team’s experience, the framework that’s being used
(Django ir our case) and all other technologies being used in the development.
Nevertheless, I like to take a few factors into account when estimating the effort of the Django applications I
develop. It is important to have a look in all the Python/Django Ecosystem to better understand what you can
reuse, what can be integrated and what will need to be developed from scratch.
Take a look at the requirements list and first try to think of what can be used out-of-the-box? That is, you can
simply use what the Django framework offers as it is.
Authentication system
Login
Logout
Password reset
Permissions
User groups
Store flat HTML pages in the database (and manage from Admin interface)
Redirects app
Store simple redirects in the database (and manage from Admin interface)
RSS
Atom
Sitemap framework
Now a special case is the Django Admin. If the Django Admin interface can be used without many customizations,
then that means you will be saving lots of hours of development.
Keep in mind that the Django Admin is not meant to be used by the end-users of a website. So don’t try to push it
as a “member’s area”. It is meant for the administrator of the website to manage its content.
Comments
Local Flavors
Form Tools
Channels
After that, try to find Third-Party Packages that solve your problems. The Django Packages is a great resource.
Also don’t forget to look at PyPI and of course Google.
Django Haystack
Django Celery
The key concept here is to explore. Even if you are not gonna use, it is good to know what is out there. It is also
important to note that you shouldn’t deliberately just add new dependencies to the project. It is always a trade-off.
You must check if the third party app offers a suitable license, if it is being maintained, if the community is active,
and so on.
It is not only about installing packages and using stuff out-of-the-box. When estimating the effort in a Django
project, try also to think how the framework can assist in the development.
For example, here is a few resources that Django offers that saves lots of implementation time:
Pagination
Middlewares
Cache system
Messages framework
Forms
Django ORM
Email interface
Internationalization
Localization
Geographic framework
The views are a big part of a Django application. If you are able to use the Generic Class-Based Views, it will
certainly reduce the implementation time:
DetailView
ListView
FormView
CreateView
UpdateView
DeleteView
Actually when I’m developing a new Django application, I use my old projects all the time. I reuse lots of work I’ve
done in the past. Actually I have a repository of easy-to-reuse snippets, like pagination controls HTMLs, some
reusable template filters, etc. From time to time I share them in the blog.
More than reusing existing resource, compare the new requirements to things you have built in the past. This will
give you insights of how long each tasks takes to be implemented. Measure everything that’s possible. After the
project is delivered, review your initial estimates. Update it with the actual time.
Even if you are working on a personal project, estimate first the effort. It is a good exercise, and it will help you in
future estimates.
Conclusions
I wanted to share some of my experience with effort estimation and also some valuable resources. Mainly because
for me, the worst thing is having to work under time-pressure because of bad estimations.
Don’t be so optimistic;
While it is easier to estimate things you know, it is hard to estimate the things you don’t know;
Things that you don’t know you don’t know will happen, and it will affect your schedule;
Break down big requirements so you can minimize the level of uncertainty;
It’s not only about code, consider also the time to create documentation and testing;
The team experience and knowledge about the development tools and resources are very important!
I hope you have enjoyed this post, and found it somehow helpful. If you want to discuss further, please leave a
comment below.