The objective
Kolej Profesional MARA Indera Mahkota (KPMIM) offers diploma programs. The
KPM curriculum is developed by experts in the relevant fields. It is continuously
improved to ensure KPM students are equipped with the latest knowledge and are
prepared with career readiness for the current national industrial needs. Kolej
Profesional MARA Indera Mahkota is doing a constructor to install network cabling in
FYP Lab this is because the current lab is not provided with Ethernet/network port.
Need 1: The contractor must use Cat6 UTP cables.
Need 2: The installation process should begin on 1st June 2020 until 15th June 2020
Need 3: Contractor must ensure the port is working and follow the standard of
structured cabling
Need 4: Cable should be pulled from the telecommunication Room to FYP Lab
Need 5: The management did not specify the tools of devices to be used. The best
quality with low Price is the priority
The Opportunity
After meeting with Haji Suwandi Bin Sanusi we believe that KPMIM goals are as
follows
Goal 1: Give the student the best facilities and more comfortable
Goal 2: The Project is going well and the project will complete and will be ready on
time
The solution
KPMIM is a company that grows from cabling and technical installations provider.
We already installed network for more than 300 companies. So basically our
company has that experience. We are 100% focused on designing installing and
maintaining systems.
27/01/2020
Haji Suwandi Bin Sanusi
MR Director
Kolej Profesional Mara
Indera Mahkota
Kuantan Pahang.
Dear Mr. Haji Suwandi ,
We would be most pleased to design and install network cabling in FYP Lab in Kolej
Profesional Mara Indera Mahkota.
HighTech Computer Cabling, Inc. is located in Pekan Pahang , but we travel
throughout the state of Malaysia to install computer networks. We have designed
and installed networks for more than 300 companies of all sizes.
Please find enclosed our proposal and cost estimates for KPMIM FYP lab’s new
network cabling. The prices listed are good for 15 days. We hope to be working with
you soon.
Sincerely,
Zara Nazaruddin
Lead Designer
HighTech Computer Cabling, Inc.
6592-590-016
[email protected]
www.hightechnw.com
Company Background
• HighTech Enterprise started business at 2015.
• We’re a well-established and growing cabling and technical installations provider
based in Pekan , Pahang.
• We’ve already installed networks for more than 300 companies.
• We work on a ‘right-first-time’ ethos and our professionalism is one of our key
strengths. Our company is staffed by industry-trained installers who all take great
pride in their quality of work, presentation, and the ability to build strong and long-
lasting customer relationships.
• We are 100% focused on designing, installing and maintaining systems that deliver
optimum performance for our customers.
• We’re approachable and practical, cost efficient and experienced, and we focus on
your challenges to help you succeed with exactly the right cabling or technical
solution. Over years we have built an enviable reputation in the industry by providing
a second-to-none, rapid and reliable service across all Malaysia.
Estimated
Material Cost
Before any work can begin, all computer devices in FYP Lab need to be accounted
for and have a space reserved for them on the architectural blueprints for the new
building.
Designing new path for the cabling by Lead 1 June One days
Designer 2020
Install all the UTP cable throughout FYP Lab as 2 June Approximately one
needed by Network Cabling Technician 2020 week
Install Patch Panel on TR Rack and Pull all cable 9 June Three days
from FYP to TR and connect to Patch Panel 2020
This project is legally required to obtain the following permits and to be performed by
individuals licensed to complete the project.
Permits Required:
• Permit #1 – Class Licence - NFP, NSP, ASP & CASP
Authority: MCMC
This permit must be Registration of a class license is valid for one calendar year
only. Prior to the expiry of the same, the class licensee must submit a fresh
application to the Malaysian Communications and Multimedia Commission together
with the relevant fees and documents.A registration fee of RM1,000.00.
Types of fees
Fees(RM)
Initial registration fee and annual registration fee (per year)
1,000.00
Application for certified true copy of class licence registration notice
10.00 per page
Application for certified true copy of class licence
10.00 per page
Fee for change of particulars in the registration notice of class licence
50.00
Fee for making a copy of, or taking extracts from, the register
1.00 per page
Qualification of tech staff
In high tech Enterprise we always using workers that have skills, knowledge and
ideas. So from that our workers always have a good qualification so that our
THIS AGREEMENT is made this 13th day of April, 2020 by and between HighTech
Enterprise (“Company”) and Kolej Profesional MARA(KPMIM) (“Customer”).
Recitals
B. Customers desire to have the Company develop a Network Cabling for them.
C. Company desires to develop Customer’s Network on the terms and conditions set
forth herein (the “Network”).
Agreements
In consideration of the mutual covenants set forth in this Agreement, Customer and
1. Development of Network.
2. Specifications.
Company agrees to develop the Network pursuant to the Specifications that have listed.
LAYOUT IN FYP LAB
14 CAT6 cable
10m
23m 25m 5m 5m
References
- DC6PP24UKY1U - Category 6 UTP 24-port Patch Panel, loaded: Schneider
Electric. (n.d.). Retrieved from
https://www.se.com/my/en/product/DC6PP24UKY1U/category-6-utp-24-port-patch-
panel,-loaded/
- DC6CAUTP4P3X - Category 6 4 pair UTP Cable 305m: Schneider Electric. (n.d.).
Retrieved from https://www.se.com/my/en/product/DC6CAUTP4P3X/category-6-4-
pair-utp-cable-305m/
- STC-Philadelphia Metro Chapter Follow. (2013, October 18). Proposals - What to
Say, How to Say It, and How Much to Charge. Retrieved from
https://www.slideshare.net/stc-pmc/stc-2013