Rate Analysis
Rate Analysis
Excavation for foundation upto 1.5 m depth including disposal excavated material upto 50
m
I.Material Cost Analysis :
Rate Amount
Material Quantity Per
Rs. P. Rs. P.
- - - - - Nil -
Total Rs. -
II.Labour Cost Analysis :
Rate Amount
Labour No. Per
Rs. P. Rs. P.
Male 1/3 60 0 day 20 0
R.C.C.(1:2:4) Column (400 mm * 250 mm) and their formwork excluding reinforcement
I.Material Cost Analysis :
Rate Amount
Material Quantity Per
Rs. P. Rs. P.
Cement 1/7*1.54*28.8 6.336 140 0 bag 887.04
R.C.C.(1:2:4) Beam (250 mm * 300 mm) and their formwork excluding reinforcement
I.Material Cost Analysis :
Rate Amount
Material Quantity Per
Rs. P. Rs. P.
Cement 1/7*1.54*28.8 6.336 140 0 bag 887.04
2 nd Coat 20 30 0 Kg 600.00
Total Rs. 1500.00
II.Labour Cost Analysis :
Rate Amount
Labour No. Per
Rs. P. Rs. P.
Painter 5 100 0 day 500.00 0
Refilling of material
I.Material Cost Analysis :
Rate Amount
Material Quantity Per
Rs. P. Rs. P.
Nil - - - - - -
Tor Steel
I.Material Cost Analysis :
Rate Amount
Material Quantity Per
Rs. P. Rs. P.
Tor Steel 1000 15.8 0 Kg 15800.0 -
Add 5% towards westage 50 15.8 0 Kg 790.00
Distemper ( 100 m2 )
I.Material Cost Analysis :
Rate Amount
Material Quantity Per
Rs. P. Rs. P.
( I ) Prime Coating
( 1 ) Distemper primer 8 94.00 0 Lit. 752.00 0
( 2 ) Putty 5 5.00 0 Kg. 25.00 0
( 3 ) Sand Paper 1 18.00 0 Dozen 18.00 0
( II ) Top Coat
( 1 )Dry Distemper 10 50.00 0 Lit. 500.00 0
( 2 ) Putty 5 5.00 0 Kg. 25.00 0
( 3 ) Sand Paper 1 18.00 0 Dozen 18.00 0
Total Rs. 1338.00
II.Labour Cost Analysis :
Rate Amount
Labour No. Per
Rs. P. Rs. P.
( I ) Prime Coat
Painter 2.5 100.00 0 day 250.00 0
Mazdoor 2.5 60.00 0 day 150.00 0
( II ) Top Coat
Painter 6 100.00 0 day 600.00 0
Mazdoor 3 60.00 0 day 180.00 0
mild Steel
I.Material Cost Analysis :
Rate Amount
Material Quantity Per
Rs. P. Rs. P.
mild Steel 1050 16.00 0 Kg 16800.0 -
Add 5% towards westage 20 16.00 0 Kg 320.00