Module 13 - Project Close (Students)
Module 13 - Project Close (Students)
•2
•3
1
Integration: A project is completed, and products and
services created are integrated into operations; most
common approach
Addition: A project creates a new product or service that
results in a new unit in the organization, such as a
department, division, or company
Extinction: A project ends because it was successful
and achieved its goals, or it was unsuccessful or
superseded; termination by murder is when there is a
sudden end to a project.
Starvation: A project ends by decreasing its budget or
suddenly ending funding; also known as withdrawal of
life support
•4
•5
•6
2
Summary level description of the project or phase
Scope objectives, the criteria used to evaluate the scope, and
evidence that the completion criteria were met
Quality objectives, the criteria used to evaluate the project and
product quality, and the verification and validation information
Schedule objectives including planned and actual milestone delivery
dates and reasons for variances
Cost objectives, including the acceptable cost range, actual costs,
and reasons for variances
Summary of how the final project, service, or result achieved the
benefits that the project was undertaken to address.
Summary of how the final project, service, or result achieved the
business needs identified in the business plan.
Summary of any risks or issues encountered on the project and how
they were addressed
•7
•8
•9
3
Project Name: Just-In-Time Training Project
1. Project Description and Summary of Results
2. Original and Actual Scope
3. Original and Actual Schedule
4. Original and Actual Budget
5. Quality Objectives, Verification, and Validation
6. Risk/Issue Summary
7. Project Assessment
8. Lessons Learned Summary
9. Transition Plan
10. Training Benefits Plan
Attachments:
A. Key Project Management Documentation
Business case
Project charter
Project management plan
Performance reports
B. Product-Related Documentation
Survey and results
Summary of user inputs
Report on research of existing training
Partnership agreements
Course materials
Intranet site training information
Summary of course evaluations
•10
Introduction
The main goal of this project was to develop a new training program at Global Construction to provide
just-in-time training to employees on key topics, including supplier management, negotiating skills,
project management, and software applications. New courses were developed and offered in instructor-
led, CD-ROM, and Web-based formats. These courses will continue to be offered at Global
Construction for the next several years. This transition plan describes the work required to support these
courses.
Assumptions
Support for the just-in-time training will be handled by staff in affected operational departments,
including the training, IT, HR, and contract departments.
Funding for the required support is budgeted at $400,000 per year for three years. These funds will
be used to pay staff in the operational departments supporting this project, experts providing
information for courses, and suppliers providing training materials and courses.
New course topics will be developed under a new project and are not part of this transition plan.
Organization
The Training Director, Lucy Camerena, will lead all efforts to support the Just-In-Time Training courses.
Staff from the training, IT, HR, and contract departments will provide support as required. See the
organizational chart provided in Attachment 1.
Work Required
The main work required to support the training developed from this project includes:
Maintaining related information on the intranet site
Handling course registration
Determining the number of courses offered each year and when they will be offered
Providing classrooms for the instructor-led training
Coordinating with suppliers for all training courses
Planning and managing the internal experts who provide some of the training and expert support for
the courses
Collecting course evaluation information and suggestions for changing the content or format of
courses
Reporting information to senior management on a monthly basis
•11
•12
4
Project Name: Just-In-Time Training Project
Project Sponsor: Lucy Camerena
Project Manager: Kristin Maur
Project Dates: July 1 – June 30
Final Budget: $1, 072,000
1. Did the project meet scope, time, and cost goals?
We did meet scope and time goals, but we had to request an additional $72,000, which the sponsor approved. We actually exceeded
scope goals by having more people take training courses than planned, primarily the Web-based courses.
2. What was the success criteria listed in the project scope statement?
The following statement outlined the project scope and success criteria:
“Our sponsor has stated that the project will be a success if the new training courses are all available within one year, if the average
course evaluations are at least 3.0 on a 1-5 scale, and if the company recoups the cost of the project in reduced training costs within
two years after project completion.”
3. Reflect on whether or not you met the project success criteria.
All of the new training courses were offered within a year, and the course evaluations averaged 3.4 on a 5-point scale. The number
of people who took the Web-based training courses far exceeded our expectations. Because the Web-based training is more cost-
effective than the instructor-led training, we are confident that the cost of the project will be recouped in less than two years.
4. In terms of managing the project, what were the main lessons your team learned from this project?
The main lessons we learned include the following:
Having good communications was instrumental to project success. We had a separate item in the WBS for stakeholder
communications, which was very important. Moving from traditional to primarily Web-based training was a big change for
Global Construction, so the strong communications was crucial. The intranet site information was excellent, thanks to support
from the IT department. It was also very effective to have different departments create project description posters to hang in
their work areas. They showed creativity and team spirit.
Teamwork and supplier partnerships were essential. It was extremely helpful to take time to develop and follow a team
contract for the project team and to focus on developing good partnerships with suppliers. Everyone was very supportive of
each other.
•13
•Good planning paid off in when plans were executed. We spent a fair amount of time developing a good project
charter, scope statement, WBS, schedules, and so on. Everyone worked together to develop these planning documents,
and there was strong buy-in. We kept the plans up-to-date and made key project information available for everyone on
a secure Web site.
•Creativity and innovation are infectious: Many creative and innovative ideas were used on this project. After
departments had so much fun making their posters in their work areas, people picked up on the idea of being creative
and innovative throughout the project. Everyone realized that training and learning could be enjoyable.
•The project steering committee was very effective. It was extremely helpful to meet regularly with the project steering
committee. Having members from different departments in the company was very important and helped in promoting
the training created as part of this project.
5. Describe one example of what went right on this project.
We were skeptical about hiring an outside consultant to help us develop a short list of potential suppliers for the
training courses, but it was well worth the money. We gained a good deal of useful information very quickly, and the
consultant made excellent recommendations and helped us develop partnerships that benefited suppliers and us.
6. Describe one example of what went wrong on this project.
The senior supplier management specialist assigned to the team at the beginning of the project was not a good fit. The
project manager should have more involvement in selecting project team members.
7. What will you do differently on the next project based on your experience working on this project?
For future training projects it would be helpful to line up experts and mentors further in advance. We underestimated
the number of people who would take the Web-based courses, and participants liked the interactive features, such as
getting expert advice and having a list of people willing to mentor them on various topics. We were scrambling to get
people and had to figure out how to organize them in an effective manner.
•14
•15
5
[Project Name]
Project Lessons Learned
Department: Document Owner:
Focus Area: Project or Organization Role:
Product or Process:
Version Date Author Change Description
•16
•17
•18
6
Assign a project manager from operations to lead
projects that affect operations.
Form a steering committee with key managers from
various departments for projects that will cause major
organizational change.
Provide mentoring and training for project managers and
other stakeholders.
Document action items at meetings, and set the next
meeting time.
Document meeting with minutes, focusing on key
decisions and action items, and send them out quickly.
Use more than one approach for creating cost estimates.
•19
•20
•21
7
Popular television shows likes American Idol and The Voice
have great closing shows. For example, in 2016, several
famous celebrities (Kelly Clarkson, Jennifer Hudson, etc.)
performed before ending the fifteenth season of American
Idol and announcing the new winner, Trent Harmon.
Many viewers get tears in their eyes watching the last few
minutes of Extreme Home Makeover episodes. Ty
Pennington and his team of designers, builders, volunteers,
friends, family, and neighbors gather to see the new home
built quickly for a family in need. Everyone enjoys the
tradition of shouting, “Move that bus!”
•22
The key takeaways at each phase of the project ( Align to each process
group and key deliverables created by your team): Consider:
◦ What worked well—or didn’t work well—either for this project or for
the project team?
◦ What needs to be done over or differently?
◦ What surprises did the team have to deal with?
◦ What project circumstances were not anticipated?
Use the team checklist provided as input into this presentation.
(Consider Tuckman’s stages of group development)
Use examples graphics/illustrations to support your analysis
Examples/Anecdotes encouraged
Cont’d
•23
•24
8
This will be a team presentation. You
should not exceed12 minutes.
You are free to select a format of your
choice e.g. PowerPoint presentation, role
play, panel discussion etc.
Be creative!
All team members are required to
participate!
Upload a copy of your presentation to
Blackboard (a simply summary/script if role
play format is selected for Part B)
Copyright 2017 Kathy Schwalbe LLC
•25
•26