A Guide To Primavera P6 Global & Project Data
A Guide To Primavera P6 Global & Project Data
Project Data
I‟ve always had difficulty explaining the concept of global and project
data to new users of Primavera P6 in my training courses. It‟s a bit too
much for some, and why should you even care? You seem to be able
to use Primavera P6 just fine without any knowledge of Global or
Project Data.
You can, but you can also get into trouble once you start moving data
around, especially back and forth between databases. If you‟ve
ever sent or received a Primavera P6 .xer file then this guide is for you.
It will help you to make sure your Primavera P6 project data is making
it to it‟s destination when you send a file. But it‟s also good knowledge
to have for any user of Primavera P6 Professional or EPPM.
Primavera P6, both the Professional version and EPPM, have a more
complex data structure that enables them to be in the realm of
Enterprise software tools. The goal was to design a system that could
be used by an organization‟s many departments. So it would have to
be flexible enough to be configurable for each department‟s needs. But
also, the organization would want some over-arching corporate assets
that could be set up and available to any department.
With Primavera P6, a primary enterprise distinction is that we have this
concept of “Global” data objects and “Project” (or embedded) data
objects.
If you consider that any company that sets up Primavera P6 will want
to reuse and share data objects across their P6 projects, then you
have just revealed the difference between global and project objects.
Global objects can be shared and used on more than one project,
while embedded objects cannot.
When you start to thing about all of the many global objects that can be
linked to a large project, the list starts to look like this:
Global Calendars
Cost Accounts
Global Activity Codes
Project Codes
Resources
Roles
Shift Calendar
User Defined Fields
etc.
If I want to export a project to an .xer or .xml file, and ensure you have
a complete record of the project, then during the export, all the bits of
linked Global objects have to come along for the ride. And that‟s why
happens. Included inside the .xer/.xml file are all of the Global
Resources, Calendars, Activity Codes, Cost Accounts, etc. that are
used in the project. So we now have a combination of Global data
objects and Project data objects in the same file. This isn‟t really a
problem on its own, as during the export this all happens automatically
and there is no way to alter what data goes into an export file from
Primavera P6 Professional.
However, it‟s on the importing of data from a .xer or .xml file that many
users usually run into trouble.
10 Primavera P6 Layouts You Must
Implement
It can get difficult to analyze the mountain of schedules you‟re
responsible for and our good friend Jerome Ijachi Odeh has recently
pulled together a list of 10 Must-Have Primavera P6 Layouts….ones
you probably should be using everyday.
Oh, and don‟t worry – we‟ll show you how to build each P6 layout step-
by-step.
1. Grouping
2. Sorting
3. Filter
4. Columns
1. Grouping
2. Sorting
3. Filters
4. Columns
Layout 3: Analysing Constraints
Constraints are mainly used for the Project Start milestones,
contractual milestones and external milestones. When reviewing
schedules from contractors make sure to check the constraints applied
in the schedule to ensure that constraints are not been used in place of
schedule logic to drive dates.
2. Sorting
3. Filter
4. Columns
11 Ways to Build a Cringe-
Worthy Primavera P6 Schedule
EC2030 – Fix
M5860 – ASCMAC 24
C3100 – Excavate
The Fix.
Make sure to set your Activity ID numbering sequence on the Defaults
tab of your project to increment by 5‟s, 10‟s or 20‟s. 10‟s is the most
common setup. If your project is already built on a sequence
incremented by 1‟s or 2‟s, then highlight your Activities, right-click and
pick “Renumber Activity IDs” from the menu to renumber everything
properly. NOTE: this feature is present in versions 7 of Primavera P6
or later.
So why
bother with relationships if you plan to simply force every Activity to a
set of dates? Constraining %50 of your Activities seems to be an
effective way to get the dates you want….but it will cost you in the end.
With too many constraints, you lose the fluidity of the logic
dependencies (or maybe you didn‟t bother with logic in the first place).
And once you hit F9 to schedule your project, P6 will calculate a start
and finish date for each activity. It‟s why you bought P6 in the first
place.
The fix.
Avoid all of those crazy logic options and stick to using Finish-to-Start
relationships with 0 lag or lead time. If you do, you will have the
cleanest Critical Path possible, assuming you‟re not guilty of #1 above
and are linking everything together.
Maybe you project controls is not for you, or at the meticulous process
of updating a schedule with progress. If your updates are sporadic and
spasmodic your project is going to suffer from giving everyone a major
headache and also from uncertainly of how much work has been done.
Customer Meetings
Project Management tasks
Maintenance of equipment
Clerical work
How much project management did you do? VS. How many lamp
posts did you install?
You can see what the Defence Contract Management Agency has to
say about discrete tasks versus Level of Effort tasks and how they
relate to earned value.
Level of Effort activities get their dates and durations from their
predecessors and successors. It‟s most common to assign a
predecessor with an SS relationship and a successor with an FF
relationship (however you aren‟t limited to those as in P3‟s
hammocks”). Then you assign a resource to the activity and his/her
effort is will be spread over the activity‟s duration.
How is a Level of Effort Activity’s
Duration calculated in Primavera P6?
The Level of Effort Activity gets it‟s start date from the Early Start date
of it‟s predecessor. It gets it‟s finish date from the Early Finish of it‟s
successor. Then it‟s own calendar is used to calculate the duration
between the start and finish dates.
All of this happens when you reschedule your project. After you
reschedule, the Level of Effort‟s duration will be calculated.
Wrap-Up
Level of Effort activities are an essential component in building
complete schedules, for displaying and representing supportive, non-
discrete work. Make sure you familiar with them but don‟t overuse
them. Like most things in planning and scheduling, a little goes a long
way.
5 Tips to Improve Your Primavera P6
Activity Names
Newer versions of Primavera P6 and beyond allow many more
characters in the activity description field. Follow these 5 simple tips to
improve the overall quality of your schedule network and respective
activity descriptions.
try
3. Be descriptive!
The activity description needs to be as descriptive and detailed as
possible. For construction activities consider adding the location,
utilizing column references, direction, room numbers, and floor
elevation.
Example: “Install North Lower Base Slab Col 1 – Col 5, Floor 1”.
This type of description will give your reader vital information about
where this activity is physically located. Always assume that your
reader will not be using your code grouping & sorting when reading
yours schedule. Make sure each activity can stand on its own without
any coding headers.
4. Uniformity
Developing standard activity descriptions, similar to activity IDs, will
help standardize your schedule. Try to come up with a standard
structure that can be conveyed to the entire planning team. This is
especially good practice when working with multiple users in the same
program.
5. Don’t scream!
THERE IS NO NEED FOR ALL OF YOUR ACTIVITIES
DESCRIPTIONS TO BE CAPTILIZED! For some reason there are
several planners that prefer to work in all-caps. Do us all a favor and
please turn the caps lock off. There is no need to scream and it adds
no value to the final product.
Schedule % Complete in Oracle
Primavera
Schedule % Complete is one of the many percent completes you have
in Primavera P6 and we‟re going to have a complete look at what it is
and how it is calculated. Two important products of maintaining
schedules are planned progress and actual progress of a given time;
you want to know how much you‟ve done so far and compare it with
how much you were supposed to do so far, in order to reach project
targets.
The second thing is that this field is calculated differently for Activities
than for WBS Elements. This is the source of the most common
problems people have with this field.
When the Data Date is earlier than the Baseline Start date, Schedule
% Complete is zero, when it‟s after the Baseline Finish data, Schedule
% Complete is 100%. Otherwise, Schedule % Complete would show
what percentage of the Baseline duration is passed by the Data Date.
Here‟s a formula to calculate Activity Schedule % Complete:
And that‟s all for the activities; it has nothing to do with the current
schedule, the resource curves, the costs, etc. For Activities, Schedule
% Complete is strictly calculated based on:
1. Data Date
2. Activity‟s Baseline Start
3. Activity‟s Baseline Finish
Scenario 1
How are these calculations possible? The Sample WBS Element has
three Activities, they all have Schedule % Completes greater than
zero, but the value for Sample WBS Element is 0! Before I reveal the
answer, here‟s a contrasting scenario.
Scenario 2
In this scenario, the Sample WBS Element has three Activities with
Schedule % Completes less than 50%, but the Schedule % Complete
of the WBS Element is 75%.
The Schedule %
Complete of the WBS Element will be the ratio of the Baseline Costs
before the Data Date to the Total Baseline Cost.
In the world of Earned Value, the costs before the Data Date are called
the Planned Value, or PV for short (Also called BCWS – Budgeted
Cost of Work Scheduled). The total baseline cost is called Budget At
Completion or BAC for short. We can now formulate the calculation of
Schedule % Complete for WBS Elements as:
Schedule % Completed (WBS) = PV / BAC
Please have this in mind that all the mentioned parameters are derived
from baseline and not from current schedule; the WBS bar shown in
these figures is the baseline schedule of the WBS Element and the
costs are the baseline costs of the WBS Element.
1. Data Date
2. Baseline Costs before the Data Date (PV)
3. Total Baseline Costs (BAC)
Examine the sample plan below. This plan has four WBS Elements in
two levels and seven Activities. Activities have sample durations and
relationships and you can see the current schedule in the Gantt chart.
Each Activity has a resource assignment and that‟s why we have costs
in the plan. Some Activities have uniform resource curves, while others
use At-Start, At-Finish or Bell-Shaped resource curves.
The project baseline is maintained and assigned. The baseline
schedule is shown by the yellow bars in Gantt chart. The current
schedule and the baseline are the same now.
2. PV – Planned Value
Planned Value (PV) is bit trickier as it related to how your schedule is
cost-loaded in a time-phased manner.
Planned Value….elaborated
Planned Value taked into account Resource Curves. Let‟s explore
Activity A6.
A6 has a uniform curve and it has only two working days, $80 planned
for each one. $80 for the first day, and the cumulative value remains
80$ for the next two nonworking days, then increases to $160 in the
last day.
The Layout Options Bar is used to create customized layouts that fulfill
your project reporting requirements. The Layout Options Bar is located
in the Activities Window.
Bars
Columns
Table Font & Row
Group & Sort
Filters
Step 1: Open the layout that you want to print using the Layout
Options Bar. The layout displayed below is: X – Current vs. Baseline
Bars. This layout includes the Activity Table on the left and the Gantt
chart on the right. The Gantt chart includes both current and baseline
bars. Click the Print Preview icon on the toolbar (see yellow arrow).
Step 2: In the Print Preview Dialog Box, you can use the toolbar at the
top left to access various print/view options.
Step 3: We will access the “Page Setup” option, which is the first icon
from the left. “Page Setup” consists of 5 tabs, and we will review each
of those tabs. The first tab is the Page tab, which can be used to select
page orientation, scaling and paper size.
Step 4: The Margins tab allows you to establish the top, bottom, left
and right margins.
Step 5: The Header tab enables you to select the appearance of the
Header. You can divide the header (see yellow arrow) into up to 5
sections and can control the contents of each section. You can also
identify on which pages you would like to include the Header, as well
as the height of the Header. In our example, we will divide the Header
into 3 sections. We will put a logo in the first section, insert the Project
Name & Layout Name in the second section, and the Date/Time in the
third section.
To insert the logo into section 1, click the drop-down list for section 1
and select Picture (see red arrow below),
Step 6: Use the browse button to select the filename of the logo (see
yellow arrow) . Click the Apply button on the right to preview the layout
with the new modifications. Notice that the logo is barely visible (see
green arrow below) because the Header height is only .25.
Step 7: Increase the Header height to 1 and click Apply to view the
result. Notice that the logo is now more prominent.
Step 8: Let‟s work on the 2nd Section of the Header. Currently, the
2nd section is set to display the Layout Name (see Red arrow). We
would like to display the Project Name in addition to the Layout Name
and would also like the Project Name to be displayed as red text.
Step 9: In section 2, select Text/Logo (see yellow arrow) to identify the
desired contents. Click the drop-down list at the bottom left to pick
Project Name (see red arrow).
Step 10: Use the text formatting tools to format the text for the
contents of section 2 (see red arrow). Click the Apply button to view
the results. You can see that the text for Project Name has been set to
red using the text formatting tools.
Step 11: We will let Section 3 of the Header reflect Date/Time (see red
arrow).
Step 12: The Footer Tab works exactly as the Header tab.
Step 13: The Options tab will be available if your Layout includes a
Gantt chart, Profile, Spreadsheet, or Trace Logic. You can identify the
Timescale Start and Timescale Finish. These can be predefined dates
or you can specify a custom date. We have selected DD (Earliest Data
Date) for the Timescale Start and PF (Latest Project Finish) for the
Timescale Finish. Of course, you‟ll want to ensure you descrunch the
Gantt chart if you‟re printing it with this trick.
Notice the other print options that can be selected. We will explore
those options with the subsequent images.
Step 14: The preview displayed below depicts printing the Gantt chart,
only without the Activity Table.
Step 15: The preview below selects to print the Activity Table, displays
all columns on the Activity Table, as well as the Gantt chart.
Step 16: The preview below displays only those Activity Table columns
visible on the layout versus all columns.
Step 17: This preview displays only the Activity Table (ie. No Gantt
chart).
Step 18: View the finished product. Use arrows on the toolbar to
navigate through the preview. Use the print setup & print icons to
establish printer options. You can also publish the layout to an HTML
file (red arrow identifies the print preview dialog box options).