Box Culvert Estimate 3/53/0
Box Culvert Estimate 3/53/0
DETAILED ESTIMATE
1x2
Parapet over Body Wall 2 4.000 0.500 0.500 2.00
1x2 (1.20+0.50)/2
Body wall 2 6.000 0.850 1.800 18.36
1x2
Parapet over Body Wall 2 8.000 0.500 0.500 4.00
1x2 (1.50+0.50)/2
Body wall 2 15.000 1.000 1.800 54.00
62.34
or 62.34 Cum
1x7
RCC Pipe 900 mm dia 7 12.500 87.50
or 87.50 Rm
3 Earthwork excavation in all classes of
soils except hard rock requiring
blasting & depositing on bank as
perSS20B with all leads and lifts and
allother incidental charges such
asbailing out water shoring strutting
walling & forming protective bunds
wherever necessary etc.,complete as per
relevent standard specification for
DRESSING THE BED UPTO SILL
LEVEL , BED FLOORING WORKS AND
FLEXIBLE APRON.
0.500av
For River bed 1 18.500 13.850 0.500 128.11
1x2 3.00av
Bund side 2 3.350 12.950 3.000 260.30
0.500av
For Flexible Apron u/s 1 16.860 3.450 0.500 29.08
0.500av
For Flexible Apron d/s 1 16.860 5.450 0.500 45.94
0.500av
For Bed Flooring u/s 1 16.860 2.450 0.500 20.65
1x2 0.500av
For Bed Flooring d/s including Stepped 2 16.860 3.450 0.500 58.17
Bed Flooring
1x2
For Cut off wal Length wise 2 18.500 0.450 2.500 41.63
1x2
For Cut off wal Breadth wise 2 12.950 0.450 2.500 29.14
16.86+2x3.0
Toe wall overall for Flexible Apron u/s 1 22.860 0.450 2.000 20.57
16.86+2x5.0
Toe wall overall for Flexible Apron d/s 1 26.860 0.450 2.500 30.22
16.86+2x2.0
Curtain wall overall for Bed Flooring u/s 1 20.860 0.450 2.000 18.77
1x2 16.86+2x3.0
Curtain wall overall for Bed Flooring d/s 2 22.860 0.450 2.500 51.44
including Stepped Bed Flooring
504.38
or 504.38 / Cum
5 Earthwork excavation in all classes ofsoils
except hard rock requiringblasting
& depositing on bank with all leads & lifts
as per SS20B, including cost of all
labour, equipments and all incidental
chargessuch as providing & maintaining
necessary cofferdams, sheeting, shoring,
bracing and theirsubsequent removal,
removal of all logs, stumps and other
deleteriousmatter and obstructions,
trimming bottom of excavation backfilling,
and clearing the site and disposal of
all surplus materials etc., complete
perrelevent standard specification for
BED FLOORING WORKS BETWEEN
CURTAIN / TOE WALLS AND
FLEXIBLE APRON.
1x2
For Cut off wal Length wise 2 18.500 0.450 2.500 41.63
1x2
For Cut off wal Breadth wise 2 12.950 0.450 2.500 29.14
70.77
or 70.77 / Cum
7 Vibrated Cement Concrete of grade
M15 (nominal mix 1:2:4) using 40mm
HBG metal including cost
andconveyance of all materials to site and
cement at site including cost of
formwork, labour charges for mixing,
transporting, laying and curing concrete
working at depths,Tools & Plants and
incidental charges such as maintaining
of protective bunds, cofferdams, shoring,
struttingetc.,complete as per relevent
standardspecification for FOUNDATION
OF CURTAIN WALL / TOE WALL FOR
BED FLOORING AND FLEXIBLE
APRON.(Below sill level)
16.86+2x3.0
For Toe wall overall u/s 1 22.860 0.450 2.000 20.57
16.86+2x5.0
For Toe wall overall d/s 1 26.860 0.450 2.500 30.22
16.86+2x2.0
For Curtain wal overall u/s 1 20.860 0.450 2.000 18.77
1x2 16.86+2x3.0
For Curtain wal overall d/s 2 22.860 0.450 2.500 51.44
including Stepped Bed Flooring
121.00
or 121.0 / Cum
8 Filling inside the Cut off wall and
Curtain Wall and below Box Culvert
with clean good coarse sand including
cost &conveyance of sand to work
site, laying, handling charges and filling
in layers , tamping under optimum
moisture content to get the maximum
density including watering, with
allleads of water and all other incidental
charges etc. complete .
(11.890+11.765)/2
Below Box Culvert 1 17.600 11.828 0.150 31.22
1x2 (0.460+0.325)/2
Below Box Culvert - Sloped Portion 2 17.600 0.393 0.150 2.07
1x2
End Side wall - Vertical 2 12.950 0.520 3.000 40.40
1x2 (0.98+0.30)/2
End Key Portionl 2 12.950 0.640 0.680 11.27
1x2
Intermediate wall - Vertical 2 12.950 0.480 3.000 37.30
1x2x6 0.5(0.15x0.15)
For Haunch portion overall 12 0.011 12.950 1.75
209.24
or 209.24 / Cum
1x2x2x11
For End Side wall 44 0.52 22.88
Rm
13 Vibrated reinforced cement concrete
M30 (Design mix) using ISS graded
hard granite broken metal including
cost and conveyance of all materials to
site & cement at site excluding cost and
fabrication of steel but including
formwork and centering softwater
labour charges for mixing,
transporting,placing in, position
vibrating andcompacting finishing &
curing concrete, working at heights, hire
charges fortools and plants, including
all otherincidental charges etc.,
complete as .per standard specification
for RCC TOP SLAB & DIRT WALL .
(0.610+0.450)/2
For Top slab 1 17.000 12.950 0.530 116.68
1x2
For Dirt wall portion 2 12.950 0.300 0.600 4.66
1x2
For Wedge Portion over Dirt wall portion 2 12.950 0.300 0.180 1.40
1x2 0.300/2
1x2
1x2
For Two portions 2 12.95 25.90
or 25.90 Rm
16 Providing filter media behind the End
Side wall of Box Culvert and Retaing
wall with clean III graded material
53mm to 5.6mm to 600mm and well
compacted in layers with smaller sized
towards the soil and bigger size towards
the wall including cost and conveyance
to work siteincluding all labours and
other incidentalcharges including hire
charges forfor tools and plants employed
etc.,for filter media as per MOST's
(Roads Wing)specifications for Roads
and Bridges Fourth Revision Cl. 309-
3-2-13 and 305-4-4 etc.,complete.
1x 2 (10.50 - 2 x 0.30)
End Vertical wall outter side below
2 9.900 0.600 0.030 0.36
Base course straight
1x 2 (10.500 - 2 x 0.30)
End Vertical wall outter side below 2 9.900 0.600 3.030 36.00
Base course straight portion
Retaining wall Rear Batter side below 4 2.050 0.600 3.381 16.63
bottom of Base course.portion
52.99
or 52.99 / Cum
17 Filling behind End Side wall of Box
Culvert and Retaining wall with
clean gritty gravel including cost
and conveyance of gravel to work site,
laying , handling charges and filling
in layers , tamping under optimum
moisture content to get the maximum
density including watering,withall leads
for water and all other charges etc.,
complete .1- Cum
Fe - 500
1x2
Wedge portion over Dirt wall 2 0.090 0.18
1x2
For Approach slab 2 0.960 1.92
Fe - 240
1x2 0.43/ span
For Wearing Coat over EndTop Slab 2 0.430 0.86
1x2
Base course 2 10.500 3.350 0.150 10.55
or 10.55 / Cum
1x2 (0.43+0.30)/2
Approach slab 2 10.500 3.500 0.365 26.83
or 26.83 /Cum
21 Vibrated Cement Concrete of grade M30
design mix using ISS size graded HBG
metal including cost & conveyance of all
materials to site and cement at site with
nominal reinforcement as per MORT&H
specification , including all labour charges
for mixing concrete laying, vibrating
Hirecharges for Tools and Plants,
compacting, curing with all leads of soft
water,including and all other incidental
charges form work cost of premoulded
expansion joints and fixing the same in
position etc.,complete for wearing coat
of 75mm uniform .thickness over Top
slab and Approach slab
1x1
Over Top slab 1 17.000 10.500 178.50
1x4
Deduct expansion jpint 4 0.020 10.500 0.84
1x2
Over approach slab 2 3.500 10.500 73.50
252.84
or 252.84 / sqm
1x2 17-4*0.02
Over Top slab over all 2.000 16.920 0.450 0.100 1.52
1x2 17-4*0.02 (0.45+0.225)/2
Over Top slab over all 2 16.920 0.338 0.25 2.86
1x2 17-4*0.02 (0.225+0.175)/2
Over Top slab over all 2 16.920 0.200 0.700 4.74
9.12
or 9.12 /Cum
23 Vibrated Cement Concrete of grade
M15(nominal mix 1:2:4) using 40mm ISS
HBG metal including cost and
conveyance of all materials to site and
cement at site including cost of formwork,
lead for soft water,labour charges for
mixing, transporting,laying and curing
concrete working at heights hire charges
for Tools and Plants including all other
incidental charges etc. complete as per
standard specification for PCC CRASH
BARRIER PARAPET OVER WING
WALL CUM RETAINING WALL
Over wings
1x2x2
Base 4 3.500 0.475 0.350 2.33
1x2x2 (0.30+0.45)/2
Bottom portion 4 3.500 0.375 0.600 3.15
1x2x2
Top portion 4 3.500 0.300 0.300 1.26
6.74
or 6.74 / Cum
24 Providing and fixing of cast iron
drainage spouts 100mm dia as
per MOST drawings SD/205 with grating
arrangements at top as shown in
thedrawing using 12mmx25mm flats for
grating arrangements,and 100mm dia
drainage spout projecting beyond the
bottom of deck slab as shown in
thedrawing including cost & conveyance
of cast iron pipes and flats and fixing
them in position etc., complete.
1x3x2
For Three Cells 6 6 Nos
or 6 Nos
25 Granite rough stone dry packing for
Flexible Apron using good size granite
Rough stone , properly wedged with
quarry spals including cost and
conveyance of all materials to site ,
labour charges for packing the same in
positions including all other incidental
charges etc., complete.
1x2x2x2
Over Approach slab 8 3.500 28.00
96.00
or 96.00 RM
27 Retaining Wall cum Wing Wall for Approach portion (Sub-Estimate)
31 Dewatering (Sub-Estimate)
L.S provisions:
33 Provision for shifting of EB post , Telegraph post , waterpipe line and cables etc.
1 Scaffolding and Centering charges for the structural components of Cut off wall ,
Curtain wall , Top Slab,Bottom Slab, Side and Middle Wall and cost and conveyance
all materials to site including labour charges and incidental charge etc., complete.
1x2
Length wise - inner 2 17.600 2.500 88.00
1x2
Breadth wise - outter 2 13.850 2.500 69.25
1x2
Breadth wise - inner 2 12.950 2.500 64.75
314.50
Sqm
Concrete quantity as per detailed estimate = 70.77 Cum
b Centering for Curtain Wall and Toe Wall below Sill Level
15.96+2x2.00
Length wise over all - inner u/s 1 19.960 2.000 39.92
1x2 16.86+2x3.45
Length wise over all- outer d/s 2 23.760 2.500 118.80
1x2 15.96+2x3.00
Length wise over all - inner d/s 2 21.960 2.500 109.80
15.96+2x3.00
Length wise over all - inner u/s 1 21.960 2.000 43.92
16.86+2x5.45
Length wise over all- outer d/s 1 27.760 2.500 69.40
15.96+2x5.00
Length wise over all - inner d/s 1 25.960 2.500 64.90
537.78
Sqm
Concrete quantity as per detailed estimate = 121.00 Cum
c Centering for Bottom Slab, Side and Intermediate wall -below & aboveSill level
Bottom Slab
1x2
Length wise - u/s & d/s 2 17.600 0.520 18.30
1x2
Breadth wise behind Side wall 2 12.950 0.520 13.47
1x2 (0.68+1.414x0.68)
Key Portion Length wise 2 12.950 1.642 42.52
1x2 (0.98+0.30)/2x0.68
Key Portion End 2 12.950 0.435 11.27
Side Wall
1x2
Outter 2 12.950 3.000 77.70
1x2
Inner 2 12.950 2.700 69.93
Intermediate wall
1x4
Both sides 4 12.950 2.700 139.86
1x2x3x4 0.15/2
Haunch portion overall- side 24 0.150 0.075 0.27
1x3x4 0.15x1.4142
Haunch Tappering portion 12 12.950 0.212 32.97
Top Slab
1x3
Bottom 3 4.700 12.950 182.60
1x2
Span Side over all 2 12.950 0.450 11.66
1x2 (0.45+0.610)/2
Ends 2 12.950 0.530 13.73
1x2
Kerb outter 2 17.000 0.350 11.90
1x2x2
Kerb ends 4 0.475 0.350 0.67
1x2
Safety Kerb- Road side 2 17.000 0.300 10.20
1x2x2 (0.325+0.30)/2
Safety Kerb- Ends 4 0.750 0.313 0.94
1x2 0.30+1.414*0.3
Dirtwall - overall 2 10.500 0.724 15.21
1x2x2
End straight 4 0.300 0.300 0.36
1x2 2x0.3+10.50
Side Wedge portion overall 2 11.100 0.180 4.00
1x2x2 0.30/2
End Tappering portion 4 0.300 0.150 0.18
251.45
Sqm
Concrete quantity as per detailed estimate = 121.57 Cum
1x2
Ends 2 10.500 0.150 3.15
1x2x2 (0.325+0)/2
Ramp for Approach slab 4 3.500 0.163 2.28
f Approach Slab
1x2 (0.43+0.30)/2
Ends 2 10.500 0.365 7.67
1x4
Over Deck Slab - Cross Portion 4 10.500 0.075 3.150
1x2
Over Approch Slab - Cross Portion 2 10.500 0.075 1.575
4.725
252.84 x0.075 Sqm
Concrete quantity as per detailed estimate = 18.96 Cum
1x2 √.1752+0.252
Middle Portion - Inner 2 17.000 0.305 10.37
1x2 √0.052+0.702
Top Portion - Inner 2 17.000 0.702 23.87
1x2 √.052+1.052
Whole Portion - Outter 2 17.000 1.051 35.74
1x2x2x2
Ends 8 0.2690 2.15
Total centering Area 75.53
Sqm
1x2x2x2
Base - Inner & Outter 8 3.500 0.350 9.80
1x2x2x2
Base - Ends 8 0.475 0.350 1.33
1x2x2 √0.152+0.602
Bottom Portion - Inner 4 3.500 0.618 8.65
1x2x2
Top Portion - Inner 4 3.500 0.300 4.20
1x2x2
Whole Portion -outter 4 3.500 0.900 12.60
1x2x4 (0.45+0.3)/2x0.60+0.3x0.3
Ends 8 0.315 2.52
39.10
Sqm
Concrete quantity as per detailed estimate = 6.74 Cum
NAME OF WORK:
CONSTRUCTION OF MINOR BRIDGE AT KM 6 / 2 OF
COST OF MATERIALS
1 Lead (Kms) 80 80 80 80 80
1 Lead (Kms) 80 80 80
Source of Supply
2.Gravel:From
: KM 65/8
Vanathirapuram
of SH-71 Quarry
COST OF LABOUR
1. Cement
1 M.T Price of Non-Levy Cement including all 5960.00 1 M.T
taxes and transportation charges upto destination
and loading and unloading and stacking
Sundries
Total per 10 Cum
Rate per Cum
Rs. Rs= 8439.20
Sundries
Total per 10 Cum
Sundries
Total per 10 Cum
sundries
Rate per RM = Rs 340.00 For 900 mm dia
3 Earth work excavation in all classes of soils except hard rockrequiring
blasting and depositing on bank as per SS20B with allleads and lifts
and all other incidental charges such as bailingout water shoring
strutting, walling & forming protective bundswherever necessary etc
complete as per relevent standardspecification for DRESSING THE
BED UPTO SILL LEVEL AND BED FLOORING WORK -1 Cum
Sundries L.S
Total
Rate per Cum Rs 11836.65
7 Vibrated Cement Concrete of grade M15(nominal mix 1:2:4)
using40mm HBG metal including cost and conveyance of all
materialsto site and cement at site including cost of formwork, soft
water,labour charges for mixing, transporting, laying and curing
concreteworking at depths, Tools and Plants and incidental charges
such as maintaining of protective bunds, cofferdams, shoring,
struttingetc., complete as per relevent standard specification
forFOUNDATION FOR CURTAIN WALL FOR BED FLOORING AND
TOE WALL FOR FLEXIBLE APRON -1 Cum(Below sill level)
Sundries L.S
Total
Rate per Cum Rs 9691.00
8 Filling inside the Cut off wall ,Curtain wall and below Box Culvert
with clean good sand including cost and conveyance of sand to work
site, laying, handling charges andfilling in layers , tamping under
optimum moisture content to get the maximum density including
watering,with all leads of water andall other incidental charges etc.
complete-1cum
Sundries
Sundries L.S
Total
Rate per Cum Rs 6337.00
Sundries L.S
Total
Rate per Cum Rs 6550.00 /m3
11 Reinforced cement concrete M30 design mix using ISS graded hard
granite crushed stone including cost and conveyance of allmaterials to
site and cement at site excluding cost and fabrication of steel but
including formwork and centering, softwater, labour charges for mixing,
transporting and placingin position, vibrating and compacting, finishing
and curing,working at heights, hire charges for tools and plants
including all other incidental charges etc., complete as per specification
for BOX CELL STRUCTURES OVER BASE SLAB -1CUM (Below
Sill and Above Sill level)
Sundries L.S
Total
Rate per Cum Rs 10561.00 /m3
Sundries L.S
Total
Rate per Cum Rs 11051.00 /m3
14
Providing and fixing KRAFT paper for full width of seating of
deckslab and including cost and conveyance to worksite, labour for
fixing the same in correct position and all other incidental charges etc.,
complete-1 Sqm
Sundries LS
18 Supply and fabrication of Fe- 500 and Fe- 240 steel required for all
RCC items of works involved in the schedule including cost of steel at
site including cost of fabrication, labour charges for cleaning the rods
strengthening, cutting,bending,tying grills, including overlaping to the
required length wherever necessary and placing the reinforcement in
position as specified in the drawings, including cost of binding
wire,provision of spacer bars, cover blocks and all other incidental
charges etc complete, -1 MT
Sundries L.S
Total
Rate per Cum Rs. 7052.00
Sundries L.S
Total
Rate per Cum Rs. 8879.00
21 Vibrated Cement Concrete of grade M30 design mix using ISS size
graded HBG metal with nominal reinforcement as per MORT&H
specification including cost and conveyance of all materials to siteand
cement at site including all labour charges for mixing concrete
laying,vibrating Hire charges for Tools and Plants, compacting, curing
withall leads of soft water,including and all other incidental charges
form work cost of premoulded expansion joints and fixing the same in
position etc., complete for wearing coat of 75mm uniform thickness
over deck slab and approach slab
Sundries L.S
Total for 10 Sqm
Total
Rate per Cum Rs. 19807.00
Sundries L.S
Total
Rate per Cum Rs. 10636.00
24 Providing and fixing of GI iron drainage spouts 100mm dia as per
MOSTdrawings SD/205 with grating arrangements at top as shown in
the drawing using 12mm x 25mm flats for grating arrangements, and
100mm dia drainage spout projecting beyond the bottom of deck slab
as shownin the drawing including cost and conveyance of GI iron pipes
and flats and fixing them in position etc., complete -1 No.
Sundries
10.00 cum
26 Supply and fixing of High quality of PVC pipes of 160mm dia 6kg/cm^2 inclu
including cost and conveyance of pipes to the site and fixing in 566.70 /Rm
position to proper grade and level including labour charges for S.I No:213(l) P62
fixing and including all other incidental charges etc., complete for
providing utility services in foot path / safety kerb
80
982.25
678.10
1660.35
Amount
5960.00
-260.50
5699.50
284.98
6244.98
51750.00
-260.50
51489.50
2574.48
54324.48
2248.35
5551.78
7800.13
2248.35
5832.81
8081.16
2248.35
4077.97
6326.32
2248.35
4327.77
6576.12
2248.35
5277.01
7525.36
15363.90
28468.43
1447.20
9947.40
6500.10
61727.03
15363.90
28468.43
1447.20
9947.40
6500.10
602.00
62329.03
15363.90
29592.53
1447.20
9947.40
6500.10
602.00
63453.13
13293.63
5419.17
33864.14
2814.00
11914.40
16273.30
813.00
0.36
84392.00
13293.63
5419.17
35100.60
2814.00
11914.40
16273.30
813.00
85628.09
13293.63
5419.170
36365.22
2814.00
11914.40
16273.30
813.00
0.00
86892.72
381.00
16.86
322.70
339.56
0.44
340.00
96.60
96.60
96.60
96.60
28.00
30.00
30.00
25.00
25.00
20.00
0.00
0.80
352.00
96.60
96.60
28.00
30.00
25.00
0.80
277.00
8439.20
3292.98
20.00
84.00
0.47
11836.65
6232.90
3293.33
20.00
84.00
30.00
30.00
0.76
9691.00
2248.35
29.50
0.15
2278.00
6172.70
20.00
84.00
30.00
30.00
0.30
6337.00
6345.31
100.00
20.00
84.00
0.69
6550.00
8562.81
1893.45
20.00
84.00
0.74
10561.00
100.62
0.38
101.00
8562.81
2383.49
20.00
84.00
0.70
11051.00
100.00
580.00
1660.35
33.60
0.05
1694.00
586.80
33.60
0.60
621.00
54324.48
2716.22
503.00
26145.00
4500.00
0.30
88189.00
6232.90
714.32
20.00
84.00
0.77
7052.00
8562.81
211.93
20.00
84.00
0.27
8879.00
760.095
309.67
95.42
764.44
1873.49
1056.56
534.76
362.06
309.96
20.00
34.00
60.98
63.00
0.57
6245.00
8689.27
11013.73
20.00
84.00
19807.00
6232.90
4298.90
20.00
84.00
0.20
10636.00
2163.00
11694.10
1946.00
5957.20
3273.10
0.60
22871.00
566.70
0.3
567.00
NAME OF WORK:
CONSTRUCTION OF MINOR BRIDGE AT KM 6 / 2 OF
ABSTRACT ESTIMATE
16. Providing filter media behind the End Side wall of Box
Culvert and Retaing wall with clean III graded material 53mm to
5.6mm to 600mm and well compacted in layers with smaller sized
towards the soil and bigger size towards the wall including cost and
conveyance to work site including all labours and other incidental
charges including hire charges for tools and plants employed etc.,
for filter media as per MOST's ( Roads Wing) specifications for
Roads and Bridges " Fourth Revision Cl. 309-3-2-13 and 305-4-4
etc., complete
6 2163.00 12978
Nos Each
Total 15685932
33 Provision for shifting of EB post , Telegraph post , waterpipe line and cables etc. 250000
L.S
34 Provision for Advertisement charged for calling tender. 100000
20000000