Lean Manufacturing Overview
Lean Manufacturing Overview
Overview
1
Outline
1. Lean Manufacturing
2. 5S & Visual Controls
3. Kaizen
4. Value Streams
5. Pull Manufacturing
6. Mistake Proofing
7. Quick Changeover
8. Six Sigma
9. Lean Accounting
10. Theory of Constraints
11. Human Factors
[email protected] 2
Lean Manufacturing
3
Definitions
[email protected] 4
What is Lean?
[email protected] 5
Thinking Lean
◼ Specify value
◼ can only be defined by the ultimate customer
◼ Identify the value stream
◼ exposes the enormous amounts of waste
◼ Create flow
◼ reduce batch size and WIP
◼ Seek perfection
◼ continuously improve quality and eliminate waste
[email protected] 6
Benefits
◼ Eliminates waste
◼ Improves quality
◼ Improves customer ratings and perceptions
◼ Increases overall customer satisfaction
◼ Improves employee involvement, morale, and company
culture
◼ Helps “transform” manufacturers
[email protected] 7
Toyota Production System (TPS)
◼ Overproduction
◼ Excess inventory
◼ Defects
◼ Non-value added processing
◼ Waiting
◼ Underutilized people
◼ Excess motion
◼ Transportation
[email protected] 9
Lean vs. Traditional Manufacturing
Source: The Machine that Changed the World, Womack, Jones, and Roos, 1990.
[email protected] 10
Lean vs. Traditional Manufacturing
[email protected] 11
Barriers to Lean
[email protected] 12
Implementing Lean
[email protected] 13
Progress Toward Lean
[email protected] 14
Lean Is A Journey
[email protected] 15
5S & Visual Control
16
5S and Visual Control
◼ 5 Elements of 5S
◼ Why 5S?
◼ Waste
◼ Workplace observation
◼ Sort
◼ Straighten
◼ Shine
◼ Standardize
◼ Sustain
◼ Visual Factory
[email protected] 17
5 Elements of 5S
◼ Sort
◼ Straighten
◼ Shine
◼ Standardize
◼ Sustain
[email protected] 18
Why 5S?
[email protected] 19
Types of Waste
◼ Overproduction
◼ Delays (waiting)
◼ Transportation
◼ Process
◼ Inventories
◼ Motions
◼ Defective Products
◼ Untapped Resources
◼ Misused Resources
[email protected] 20
Elimination of Waste
[email protected] 21
Waste Identification
[email protected] 22
After 5S
[email protected] 23
Workplace Observation
[email protected] 24
Sort
[email protected] 25
Straighten
[email protected] 26
Shine
◼ Results in
◼ Fewer breakdowns
◼ Greater safety
◼ Product quality
◼ More satisfying work environment
[email protected] 27
Standardize
[email protected] 28
Sustain
[email protected] 29
Visual Factory Implementation
[email protected] 30
Kaizen
31
What is Kaizen?
◼ Kaizen (Ky’zen)
◼ “Kai” means “change”
◼ “zen” means “good (for the better)”
◼ Gradual, orderly, and continuous improvement
◼ Ongoing improvement involving everyone
[email protected] 32
How to Kaizen
[email protected] 33
Identify the Customer
◼ Legal
[email protected] 34
Types of Waste
◼ Overproduction
◼ Excess inventory
◼ Defects
◼ Non-value added processing
◼ Waiting
◼ Underutilized people
◼ Excess motion
◼ Transportation
[email protected] 35
Identify the Current State
[email protected] 36
Brainstorm and Analyze
◼ Technology
◼ People / Organization
◼ Procedures
◼ Cycle times
[email protected] 37
Implementation Plan
[email protected] 38
Execute
◼ Team members
◼ Customers
[email protected] 39
Check and Sustain
[email protected] 40
Kaizen Blitz
[email protected] 41
Kaizen Blitz - Agenda
[email protected] 42
Roadblocks
[email protected] 43
Value Streams
44
Outline
[email protected] 45
What Are Value Streams?
[email protected] 46
Types of Value Streams
[email protected] 47
Identifying the Value Stream
[email protected] 48
Value Stream Mapping
[email protected] 49
Value Stream Mapping
[email protected] 50
The Current State
Typical Steps to Complete a Current State Drawing
[email protected] 51
The Current State
[email protected] 52
The Current State
[email protected] 53
The Current State
[email protected] 54
The Current State
◼ Typical Results
◼ 80 – 90% of total steps are waste from standpoint of
end customer.
◼ 99.9% of throughput time is wasted time.
◼ Demand becomes more and more erratic as it moves
upstream, imposing major inventory, capacity, and
management costs at every level.
◼ Quality becomes worse and worse as we move upstream,
imposing major costs downstream.
◼ Most managers and many production associates expend
the majority of their efforts on hand-offs, work-arounds,
and logistical complexity.
[email protected] 55
The Future State
[email protected] 56
The Future State
[email protected] 57
The Future State
[email protected] 58
Implementing Change
Don’t Wait!
You need a plan!
• Tie it to your business objectives.
• Make a VS Plan: What to do by when.
• Establish an appropriate review frequency.
[email protected] 59
Implementing Change
[email protected] 60
Implementing Change
Kaizen
[email protected] 61
Implementing Change
Typical Results
◼ Throughput time falls from 44 days to 6 (87%)
◼ Wasted steps fall from 65 to 27 (60%)
[email protected] 62
Roadblocks
[email protected] 63
Roadblocks
[email protected] 64
Roadblocks
[email protected] 65
Wrong Ways to Address Roadblocks
[email protected] 66
Pull Manufacturing
67
Outline
[email protected] 68
Why Pull Manufacturing?
[email protected] 69
Push Vs. Pull Scheduling
◼ Push Scheduling
• traditional approach
• “move the job on when finished”
• problems - creates excessive inventory
◼ Pull scheduling
• coordinated production
• driven by demand (pulled through system)
• extensive use of visual triggers
(production/withdrawal kanbans)
[email protected] 70
Inventory Hides Problems
Unreliable Capacity
Scrap
Vendors Imbalances
[email protected] 71
Lowering Inventory Reveals Problems
•Reducing variability
•Eliminating waste
•Streamlining production and material flows
•Accurate information
[email protected] 72
What is Just-in-Time?
[email protected] 73
Objective of JIT
[email protected] 74
JIT Principles
[email protected] 75
Quality enables JIT
[email protected] 76
How to accomplish JIT production
1) Design Flow Process
7) Improve Product Design -Link operations
-Standard product configuration -Balance workstation
-Standardize and reduce capacities
number of parts -Re-layout for flow
-Process design with -Emphasize preventive 2) Total Quality Control
product design maintenance -Worker responsibility
-Quality expectations -Reduce lot size -Measure: SQC
-Reduce setup/changeover time -Enforce compliance
-Fail-safe methods
-Automatic inspection
[email protected] 77
Kanban
[email protected] 78
Kanban Squares
X X X
X
X X
Flow of work
Flow of information
[email protected] 79
Kanban Card
Unique Part #
46-281247p1 Description
27” Al Rim
Qty
Where to find
part when bin 23 Kanban Qty
is empty Where to return
Stock Loc: Line Loc: filled Kanban
RIP 1 Asm. 1
[email protected] 80
Quality at the Source
[email protected] 81
One Piece Flow
[email protected] 82
Continuous Flow
• Line up all of the steps that truly create value so they occur
in a rapid sequence
[email protected] 83
Pull Production
[email protected] 84
Pull Production
[email protected] 85
Pull System
Leveled assembly
instructions
Production A Fab Vendor
C
Schedule A
B Sub
A
Fab Vendor
Customers Final Assy
Fab Vendor
86
[email protected]
....
Standardized Work
◼ Standardized work consists of three elements:
◼ Takt time
Matches the time to produce a part or finished product
with the rate of sales. It is the basis for determining
workforce size and work allocation.
◼ Standard in-process inventory
The minimum number of parts, including units in
machines, required to keep a cell or process moving.
◼ Standard work sequence
The order in which a worker performs tasks for various
processes.
◼ Once a standard work is set, performance is measured and
continuously improved
[email protected] 87
Work Balancing / TAKT Time
[email protected] 88
Production Smoothing / Leveling
[email protected] 89
Production Smoothing / Leveling
[email protected] 90
Production Smoothing / Leveling
Toyota solved the problem by production leveling.
If customers are buying nine convertibles, nine hardtops, and nine
SUVs each day, Toyota assembles three of each in the morning,
three of each in the afternoon, and three of each in the evening. It
also distributes the production of convertibles, hard tops, and SUVs
as evenly as possible through each shift: convertible, hard top, SUV,
convertible, hard top, SUV, and so on.
[email protected] 91
Wrap-up - Pull Manufacturing
[email protected] 92
Mistake Proofing
(Poka Yoke and Error Proofing)
93
Outline
[email protected] 94
What is Mistake Proofing?
[email protected] 95
Everyday Examples
3.5 inch diskettes cannot be inserted unless diskette
is oriented correctly. This is as far as a disk can be
inserted upside-down. The beveled corner of the
diskette along with the fact that the diskette is not
square, prohibit incorrect orientation.
[email protected] 96
Evidence of the Effectiveness
◼ AT&T Power Systems is first US manufacturer to win the Deming
prize. Average outgoing defects reduced by 70%.
◼ A washing machine drain pipe assembly line produced 180,000 units
without a single defect (6 months).
◼ TRW reduced customer PPM’s from 288 to 2.
◼ Federal Mogul: 99.6% less customer defects and 60% productivity
increase
◼ DE-STA-CO: reduced omitted parts 800 to 10 ppm with a 15-30%
productivity increase.
[email protected] 97
Mistake Proofing ROI
[email protected] 98
1-10-100 Rule
Activity Cost
Order entered correctly $1
Error detected in billing $ 10
Error detected by customer $ 100
[email protected] 99
The difficulties with human error
Why existing tools are not enough
Motorola findings:
[email protected] 100
Error proofing & SPC
[email protected] 101
“Be more careful” not effective
◼ “The old way of dealing with human error was to scold people, retrain them, and
tell them to be more careful … My view is that you can’t do much to change
human nature, and people are going to make mistakes. If you can’t tolerate
them ... you should remove the opportunities for error.”
◼ “Training and motivation work best when the physical part of the system is well-
designed. If you train people to use poorly designed systems, they’ll be OK for
awhile. Eventually, they’ll go back to what they’re used to or what’s easy,
instead of what’s safe.”
◼ “You’re not going to become world class through just training, you have to
improve the system so that the easy way to do a job is also the safe, right way.
The potential for human error can be dramatically reduced.”
Chappell, L. 1996. The Pokayoke Solution. Automotive News Insights, (August 5): 24i.
LaBar, G. 1996. Can Ergonomics Cure ‘Human Error’? Occupational Hazards 58(4): 48-51.
[email protected] 102
What Causes Defects?
[email protected] 103
Inspection techniques
[email protected] 104
Poka yoke
Mistake-proofing systems
Does not rely on operators catching mistakes
Inexpensive Point of Origin inspection
Quick feedback 100% of the time
[email protected] 105
Seven Guidelines to Poka Yoke Attainment
[email protected] 106
Poka Yoke Systems Govern the Process
[email protected] 107
Common Mistake proofing Devices
◼ Guide Pins
◼ Blinking lights and alarms
◼ Limit switches
◼ Proximity switches
◼ Counters
◼ Checklists
[email protected] 108
Methods for Using Poka yoke
[email protected] 109
Contact Methods
[email protected] 110
Counting Method
[email protected] 111
Motion-Sequence Method
[email protected] 112
Types of Sensing Devices
3. Warning Sensors
[email protected] 113
3 Rules of POKA YOKE
114
Quick Changeover
Single Minute Exchange of Dies
115
Outline
[email protected] 116
Changeover Defined
[email protected] 117
Changeover Time Defined
[email protected] 118
Traditional approach
◼ Combine lots
[email protected] 119
Another way
[email protected] 120
Benefits of setup reduction
◼ Better quality
◼ Lower cost
◼ Less inventory
◼ Better flexibility
◼ Better worker utilization
◼ Shorter lead time and more capacity
◼ Less process variability
[email protected] 121
Classification of setup activities
◼ Type 1
◼ Gathering, preparing, and returning tools, fixtures, etc.
◼ Type 2
◼ Removing previous setup, mounting next setup on machine
◼ Type 3
◼ Measuring, calibrating, adjusting
◼ Type 4
◼ Producing test pieces, further adjustment until parts are good
[email protected] 122
What is SMED?
[email protected] 123
Single Minute Exchange of Dies
[email protected] 124
Why SMED?
◼ Reduced inventories.
◼ Improved productivity.
◼ Higher quality levels.
◼ Increased safety.
◼ Improved flexibility.
◼ Reduction in throughput time.
◼ Improve operator capabilities.
◼ Lower manufacturing costs.
[email protected] 125
SMED Methodology
[email protected] 126
The SMED Process
[email protected] 127
Preliminary Stage
Observe and record
◼ Team-work
◼ Recorder
◼ Overall duration (from last product to first good product).
◼ Describe the change (from what to what?).
◼ Record the equipment used.
◼ Timers
◼ Time each step
◼ Fact collectors
◼ Breakdown the steps into actions – as much detail as possible.
[email protected] 128
Stage 1
[email protected] 129
Stage 2
[email protected] 130
Stage 3
[email protected] 131
Stage 4
[email protected] 132
The SMED System - Results
C ompany Machine Before improvement After improvement Red’n
T Manufacturing 1 80t single shot press 4 hours 0 mins 4 mins 18 sec 98%
Expanded Metal Co. 4’6” lath press 4 hours 30 mins 11 mins (note: NOT 96%
SMED)
[email protected] 133
Six Sigma
134
Outline
◼ Measure
◼ Evaluate / Analyze
◼ Improve
◼ Control
◼ Design for Six Sigma
◼ Green Belts & Black Belts
[email protected] 135
What is Six Sigma?
[email protected] 136
Why Companies Need Six Sigma
5. Improves profits!
[email protected] 137
How good is good enough?
But what could happen at a quality level of 99.9% (i.e., 1000 ppm),
[email protected] 138
Six Sigma as a Metric
Sigma = = Deviation
( Square root of variance )
1
2
3
5
6
7
0
4
between + / - 1 68.27 % result: 317300 ppm outside
(deviation)
between + / - 2 95.45 % 45500 ppm
[email protected] 139
3 Sigma Vs. 6 Sigma
◼ Spends 15~25% of sales dollars on cost of ◼ Spends 5% of sales dollars on cost of failure
failure
◼ Relies on inspection to find defects ◼ Relies on capable process that don’t produce
defects
◼ Does not have a disciplined approach to ◼ Use Measure, Analyze, Improve, Control and
gather and analyze data Measure, Analyze, Design
[email protected] 140
Six Sigma ROI
Motorola ROI
1987-1994
• Reduced in-process defect levels by a factor of 200.
• Reduced manufacturing costs by $1.4 billion.
• Increased employee production on a dollar basis by 126%.
• Increased stockholders share value fourfold.
AlliedSignal ROI
1992-1996
• $1.4 Billion cost reduction.
• 14% growth per quarter.
• 520% price/share growth.
• Reduced new product introduction time by 16%.
• 24% bill/cycle reduction.
[email protected] 141
Six Sigma as a Philosophy
Old Belief
4 High Quality = High Cost
Quality
Internal & Prevention &
External Appraisal
Costs Failure Costs Costs
New Belief 4
New Belief
5
High Quality = Low Cost
6
Quality
[email protected] 142
Six Sigma Tools
Baselining SPC
[email protected] 143
Problem Solving Methodology
Phase 1:
Define
Phase 2:
Characterization
Measure
Phase 3:
Breakthrough
Analyze
Strategy
Phase 4:
Improve
Optimization
Phase 5:
Control
◼ Define Process
◼ Define Customer requirement
[email protected] 145
Define Phase
[email protected] 146
Measure
Characterize Process
Evaluate Control
Understand Process Maintain New Process
Improve
Improve and Verify Process
[email protected] 147
Measure Phase
[email protected] 148
Measure
Characterize Process
Evaluate Control
Understand Process Maintain New Process
Improve
Improve and Verify Process
[email protected] 149
Evaluate / Analysis Phase
◼ Data Analysis
◼ Process Analysis
◼ Formulate Hypothesis
◼ Test Hypothesis
[email protected] 150
Measure
Characterize Process
Evaluate Control
Understand Process Maintain New Process
Improve
Improve and Verify Process
[email protected] 151
Improvement Phase
[email protected] 152
Design of Experiments (DOE)
◼ To estimate the effects of independent Variables on Responses.
◼ Terminology
➢ Factor – An independent variable
➢ Level – A value for the factor.
➢ Response - Outcome
X Y
PROCESS
[email protected] 153
Measure
Characterize Process
Evaluate Control
Understand Process Maintain New Process
Improve
Improve and Verify Process
[email protected] 154
Control Phase
- Confirmation of Improvement
- Confirmation you solved the practical problem
- Benefit validation
- Buy into the Control plan
- Quality plan implementation
- Procedural changes
- System changes
- Statistical process control implementation
- “Mistake-proofing” the process
- Closure documentation
- Audit process
- Scoping next project
[email protected] 155
Control Phase
[email protected] 157
DFSS Methodology & Tools
DELIVERABLES
TOOLS
[email protected] 158
Green Belts & Black Belts
◼ GE has very successfully instituted this program
◼ 4,000 trained Black Belts by YE 1997
◼ 10,000 trained Black Belts by YE 2000
◼ “You haven’t much future at GE unless they are selected to
become Black Belts” - Jack Welch
◼ Kodak has instituted this program
◼ CEO and COO driven process
◼ Training includes both written and oral exams
◼ Minimum requirements: a college education, basic statistics,
presentation skills, computer skills
◼ Other companies include:
◼ Allied Signal -Texas Instruments
◼ IBM - ABB
◼ Navistar - Citibank
[email protected] 159
Green Belts & Black Belts
Time on
Consulting/ Related
Task Mentoring
Projects
Training
Utilize
Green Belt Statistical/Quality
technique Find one new
2%~5% 2 / year
green belt
Lead use of
technique and
communicate new
ones
Master Consulting/Mentor
80~100% Five Black Belts 10 / year
ing/Training
Black Belt
[email protected] 160
Activity Based Costing
and
Lean Accounting
161
Outline
[email protected] 162
What is Cost Accounting?
[email protected] 163
Traditional Cost Systems
[email protected] 164
Overhead Costs
[email protected] 165
Activity-Based Costing
[email protected] 166
Activity-Based Costing
[email protected] 167
Activity-Based Costing
[email protected] 168
Unit Costs under ABC
[email protected] 169
Benefits of Activity-Based Costing
◼ ABC leads to more activity cost pools with more relevant cost
drivers
◼ ABC leads to enhanced control of overhead costs since
overhead costs can be more often traced directly to activities
◼ ABC leads to better management decisions by providing more
accurate product costs, which contributes to setting selling
prices that will achieve desired product profitability levels
[email protected] 170
Benefits of ABC
[email protected] 171
Limitations of ABC
[email protected] 172
When to Use ABC
[email protected] 173
Activity-Based Management
[email protected] 174
Lean Accounting
[email protected] 175
Lean Accounting – The Lean Transition
[email protected] 176
Lean Accounting – Management Accounting
[email protected] 177
Lean Accounting – Business Management
[email protected] 178
Lean Accounting – Operational Accounting
[email protected] 179
Lean Accounting – Financial Accounting
[email protected] 180
Theory of Constraints
181
Outline
1. Introduction to Constraints
2. Five Steps Of Theory of Constraints
3. Drum Buffer Rope
4. Issues with TOC
5. Measurements
[email protected] 182
Constraints
Constraint
[email protected] 183
Significance of Bottlenecks
[email protected] 184
Theory of Constraints
[email protected] 185
Theory of Constraints
[email protected] 186
Theory of Constraints
[email protected] 187
Theory of Constraints
◼ Buffer
◼ Stockpile of work in process in front of constraint
◼ Precaution to keep constraint running if upstream operations
are interrupted
◼ Ropes
◼ Limitations placed on production in upstream operations
◼ Necessary to prevent flooding the constraint
[email protected] 188
What is the Theory of Constraints?
[email protected] 189
What is TOC? (continued)
Noreen, Smith, and Mackey, The Theory of Constraints and its Implecations for Management Accounting (North River Press, 1995)
[email protected] 190
How does TOC help companies?
[email protected] 191
Five Steps Of TOC
[email protected] 192
Theory of Constraints
[email protected] 194
Steps in the TOC Process
[email protected] 195
Steps in the TOC Process
[email protected] 196
Steps in the TOC Process
[email protected] 197
Drum Buffer Rope
A Pull System
Buffer
60 70 40 60
Rope Constraint
(Drum)
[email protected] 198
Lean: How DBR Supports it
Fundamentally, Don’t Build Until Needed
◼ Defects avoided because of “small lot”, non conformance, and corrective action
[email protected] 199
Issues with TOC
[email protected] 201
Issues with TOC
◼ Advantages
◼ Improves capacity decisions in the short-run
◼ Avoids build up of inventory
◼ Aids in process understanding
◼ Avoids local optimization
◼ Improves communication between departments
[email protected] 202
Issues with TOC
◼ Disadvantages
◼ Negative impact on non-constrained areas
◼ Diverts attention from other areas that may be the next constraint
◼ Temptation to reduce capacity
[email protected] 203
Issues with TOC
[email protected] 204
Measurements
Conventional Wisdom
◼ Net profit?
◼ Efficiency?
◼ Utilization?
◼ Return on Investment?
◼ Cash Flow?
[email protected] 205
Measurements
TOC Wisdom
◼ Throughput
◼ Inventory
◼ Operating Expense
[email protected] 206
Traditional vs JIT, TQM and TOC
All Three methods attack the underlying assumption that crated a problem related to
inventory levels. They ask:
[email protected] 207
The “Cost World”
[email protected] 208
The “Throughput World”
[email protected] 209
Financial Issues
[email protected] 210
Conclusion
[email protected] 211
Human Factors
212
Outline
1. Ergonomics
2. Knowledge Management
3. Rewards & Recognition
4. Safety & Health
5. Effective Teams
6. Conducting Effective Meetings
[email protected] 213
Ergonomics
214
WHAT IS ERGONOMICS?
[email protected] 215
WHAT MAKES AN EFFECTIVE PROGRAM?
[email protected] 216
CAUSES & CONTRIBUTING FACTORS
[email protected] 217
HAZARD PREVENTION & CONTROL
ENGINEERING CONTROLS
- Eliminate the task or unnecessary movement.
- Reduce weights of loads, increase handling capacity of
equipment.
- Workspace modifications.
- Use handles or “easy grip” surfaces.
- Investigate quality problems that may cause stresses.
- Lift properly, keeping loads close to body.
- Logical, convenient controls and displays.
[email protected] 218
HAZARD PREVENTION & CONTROL
CONTINUED
ADMINISTRATIVE & PROCESS CONTROLS
- Work rest or break scheduling.
- Training in proper lifting techniques & ergonomics.
- Job orientation, training and follow up.
- Rotation between high & low stress tasks.
- Housekeeping.
- Video study and evaluation of job tasks.
- Use of effective job safety analysis program.
- Enforcement of existing procedures.
[email protected] 219
ERGONOMIC MODIFICATION PROCESS
[email protected] 220
WORK PRACTICE CONTROLS
[email protected] 221
WORK AT WORKING SAFELY
[email protected] 222
Knowledge Management
223
Why Knowledge Management?
[email protected] 226
Rewards & Recognition
227
Rewards & Recognition
[email protected] 228
Rewards & Recognition
[email protected] 229
Rewards & Recognition
[email protected] 230
Rewards & Recognition
[email protected] 231
Rewards & Recognition
[email protected] 232
Rewards & Recognition
[email protected] 233
Rewards & Recognition
[email protected] 234
Safety & Health
235
Cost of Accidents
◼ Direct Costs
◼ Medical Costs (including worker’s comp)
◼ Indemnity Payments
◼ Indirect costs
◼ Time Lost (by worker and supervisor)
◼ Schedule delays
◼ Training new employees
◼ Legal fees
[email protected] 236
Legal Issues and Liability
[email protected] 237
Accident Causes
◼ Unsafe Conditions
◼ Easiest to correct (and very cost effective)
◼ Easiest to prevent
◼ Safety audits
◼ Safety inspections
◼ Maintenance schedules for equipment
◼ Encouraging employee reporting
◼ Good housekeeping
[email protected] 238
Accident Causes
◼ Unsafe Acts
◼ Most difficult to address
◼ Changing behavior isn’t easy
◼ Best prevented by developing a “safety culture”
[email protected] 239
Establishing Accountability
[email protected] 240
Defining Responsibilities
◼ Working safely
[email protected] 241
Defining Responsibilities
[email protected] 242
Defining Responsibilities
[email protected] 243
Effective Teams
244
Your Organization Can Benefit from Teams
[email protected] 245
The Importance of Creating High
Performance Teams
◼ Common Purpose
◼ Specific Goals
◼ Mutual Accountability
[email protected] 246
The Five Stages of
Team Development
◼ Forming
◼ Storming
◼ Norming
◼ Performing
◼ Adjourning
[email protected] 247
Conducting Effective Meetings
248
Conducting Effective Meetings
◼ Preparing for the Meeting
◼ Set Objectives – problems to solve, issues to
address, decisions to be made
◼ Select Participants
◼ Set a Time and Place
◼ Plan the Agenda
◼ Distribute the Agenda and Relevant Materials in
Advance
◼ Consult with Participants
Before the Meeting
[email protected] 249
Conducting Effective Meetings
[email protected] 250
Conducting Effective Meetings
◼ Reach a Consensus
◼ End the Meeting by
Clarifying What
Happens Next
[email protected] 251
Conducting Effective Meetings
◼ Follow Up after the Meeting
◼ Spend the Last Five Minutes Debriefing the
Meeting Process.
◼ The Best Time to Share Your Reactions to
the Meeting Is Right After It Has Ended
◼ Brief Memo Summarizing
Discussions, Decisions, and Commitments
(minutes)
[email protected] 252
The End
(or really only the beginning…)
253