Att 11updated Weekly Live Schedule 20 November 2021
Att 11updated Weekly Live Schedule 20 November 2021
60% Design Package 236 14-Oct-18 A 01-Oct-19 A 11-Sep-18 06-Aug-19 16130 100% 01-Oct-19 A, 60% Design Package
General 236 14-Oct-18 A 16-Jun-19 A 11-Sep-18 06-Aug-19 2500 100% 16-Jun-19 A, General
E1000 Drawing Control List 10 14-Oct-18 A 16-Jun-19 A 11-Sep-18 24-Sep-18 100 100% Drawing Control List
E1010 Scope Of Work 20 01-Nov-18 A 16-Jun-19 A 11-Sep-18 08-Oct-18 100 100% Scope Of Work
E1020 General Arrangement 15 01-Nov-18 A 20-May-19 A 11-Sep-18 01-Oct-18 100 100% General Arrangement
E1080 Site Location Plan 5 11-Dec-18 A 17-Dec-18 A 31-Jul-19 06-Aug-19 50 100% Site Location Plan
E1090 Feed Verification Report 15 11-Nov-18 A 13-Jun-19 A 09-Oct-18 29-Oct-18 400 100% Feed Verification Report
E1100 Metocean Studies Report 20 11-Nov-18 A 13-Jun-19 A 09-Oct-18 05-Nov-18 400 100% Metocean Studies Report
E1110 Basis Of Design 18 11-Nov-18 A 13-Jun-19 A 09-Oct-18 01-Nov-18 400 100% Basis Of Design
E1120 Scope Of Work For Early Pkg. 10 19-May-19 A 16-Jun-19 A 02-Jun-19 13-Jun-19 100 100% Scope Of Work For Early Pkg.
E1130 General Notes 19 01-Dec-18 A 13-Jun-19 A 09-Oct-18 04-Nov-18 150 100% General Notes
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
E1140 Durability Study 25 01-Dec-18 A 13-Jun-19 A 09-Oct-18 12-Nov-18 400 100% Durability Study
E1340 Specification For Concrete For Marine Works 15 01-Dec-18 A 13-Jun-19 A 16-Jan-19 05-Feb-19 100 100% Specification For Concrete For Marine Works
E1360 Specification For Steelwork 15 05-Dec-18 A 13-Jun-19 A 16-Dec-18 03-Jan-19 200 100% Specification For Steelwork
Survey 186 28-Oct-18 A 01-Oct-19 A 11-Oct-18 27-Jun-19 1600 100% 01-Oct-19 A, Survey
Bathymetric & Topographic 100 05-Feb-19 A 13-Jun-19 A 05-Feb-19 24-Jun-19 400 100% 13-Jun-19 A, Bathymetric & Topographic
E1190 Layout Plan 5 29-Apr-19 A 13-Jun-19 A 16-Jun-19 20-Jun-19 100 100% Layout Plan
E1230 Specification 15 05-Feb-19 A 20-May-19 A 05-Feb-19 25-Feb-19 200 100% Specification
E1390 Detailed Drawing 15 30-Apr-19 A 13-Jun-19 A 04-Jun-19 24-Jun-19 100 100% Detailed Drawing
Geotechnical 186 28-Oct-18 A 01-Oct-19 A 11-Oct-18 27-Jun-19 1200 100% 01-Oct-19 A, Geotechnical
E1040 Specification For Geotechnical Invigation 5 28-Oct-18 A 31-Mar-19 A 11-Oct-18 17-Oct-18 200 100% Specification For Geotechnical Invigation
E1070 Geotechnical Report Preparation and Submission 18 12-Feb-19 A 16-Jun-19 A 07-Mar-19 01-Apr-19 1000 100% Geotechnical Report Preparation and Submission
E1310 Review & Approval Cycle of Geotechnical Report 20 02-Jun-19 A 01-Oct-19 A 02-Jun-19 27-Jun-19 0 0% Review & Approval Cycle of Geotechnical Report
Demolition 13 01-Dec-18 A 24-May-19 A 06-Nov-18 22-Nov-18 200 100% 24-May-19 A, Demolition
E1380 Layout Plan 8 01-Dec-18 A 19-May-19 A 06-Nov-18 15-Nov-18 150 100% Layout Plan
E1430 Detailed Drawing 5 01-Dec-18 A 24-May-19 A 18-Nov-18 22-Nov-18 50 100% Detailed Drawing
Dredging & Reclamation 36 15-Nov-18 A 13-Jun-19 A 09-Oct-18 27-Nov-18 1850 100% 13-Jun-19 A, Dredging & Reclamation
E1150 Layout Plan 7 15-Nov-18 A 13-Jun-19 A 09-Oct-18 17-Oct-18 600 100% Layout Plan
E1250 Specification 7 20-Nov-18 A 13-Jun-19 A 18-Oct-18 28-Oct-18 600 100% Specification
E1320 Design report 10 01-Dec-18 A 13-Jun-19 A 29-Oct-18 11-Nov-18 300 100% Design report
E1400 Detailed Drawing 11 01-Dec-18 A 13-Jun-19 A 13-Nov-18 27-Nov-18 350 100% Detailed Drawing
Revetment 28 20-Nov-18 A 25-Jun-19 A 16-Oct-18 22-Nov-18 1450 100% 25-Jun-19 A, Revetment
E1210 Layout Plan 5 20-Nov-18 A 27-May-19 A 16-Oct-18 22-Oct-18 400 100% Layout Plan
E1260 Specification 7 25-Dec-18 A 25-Jun-19 A 23-Oct-18 31-Oct-18 400 100% Specification
E1330 Design report 8 01-Dec-18 A 13-Jun-19 A 01-Nov-18 12-Nov-18 300 100% Design report
E1420 Detailed Drawing 8 01-Dec-18 A 26-May-19 A 13-Nov-18 22-Nov-18 350 100% Detailed Drawing
Access Bridge 40 01-Nov-18 A 13-Jun-19 A 02-Oct-18 26-Nov-18 2050 100% 13-Jun-19 A, Access Bridge
E1050 Layout Plan 5 01-Nov-18 A 21-May-19 A 02-Oct-18 08-Oct-18 700 100% Layout Plan
E1160 Design report 10 10-Nov-18 A 27-May-19 A 09-Oct-18 22-Oct-18 600 100% Design report
E1270 Detailed Drawing 25 10-Nov-18 A 13-Jun-19 A 23-Oct-18 26-Nov-18 750 100% Detailed Drawing
Road 35 01-Nov-18 A 13-Jun-19 A 25-Sep-18 12-Nov-18 2900 100% 13-Jun-19 A, Road
E1030 Layout Plan 5 01-Nov-18 A 27-May-19 A 25-Sep-18 01-Oct-18 1600 100% Layout Plan
E1060 Specification 8 05-Nov-18 A 13-Jun-19 A 02-Oct-18 11-Oct-18 200 100% Specification
E1200 Design report 7 15-Nov-18 A 13-Jun-19 A 14-Oct-18 22-Oct-18 300 100% Design report
E1280 Detailed Drawing 15 15-Nov-18 A 13-Jun-19 A 23-Oct-18 12-Nov-18 800 100% Detailed Drawing
Lighting 25 11-Nov-18 A 13-Jun-19 A 09-Oct-18 12-Nov-18 650 100% 13-Jun-19 A, Lighting
E1170 Layout Plan 5 11-Nov-18 A 14-May-19 A 09-Oct-18 15-Oct-18 250 100% Layout Plan
E1220 Design report 5 20-Nov-18 A 12-Jun-19 A 16-Oct-18 22-Oct-18 300 100% Design report
E1290 Detailed Drawing 15 20-Nov-18 A 13-Jun-19 A 23-Oct-18 12-Nov-18 100 100% Detailed Drawing
Cathodic Protection 14 06-Jan-19 A 12-Jun-19 A 24-Feb-19 13-Mar-19 200 100% 12-Jun-19 A, Cathodic Protection
E1350 Specification 14 06-Jan-19 A 12-Jun-19 A 24-Feb-19 13-Mar-19 200 100% Specification
Fence & Wave Wall 10 01-Dec-18 A 12-Jun-19 A 23-Oct-18 05-Nov-18 200 100% 12-Jun-19 A, Fence & Wave Wall
E1300 Layout Plan 10 01-Dec-18 A 12-Jun-19 A 23-Oct-18 05-Nov-18 200 100% Layout Plan
Escape Jetty 34 10-Nov-18 A 12-Jun-19 A 09-Oct-18 25-Nov-18 2150 100% 12-Jun-19 A, Escape Jetty
E1180 Layout Plan 5 10-Nov-18 A 19-May-19 A 09-Oct-18 15-Oct-18 400 100% Layout Plan
E1240 Specification 14 15-Nov-18 A 12-Jun-19 A 16-Oct-18 04-Nov-18 600 100% Specification
E1370 Design report 5 01-Dec-18 A 19-May-19 A 05-Nov-18 11-Nov-18 300 100% Design report
E1410 Detailed Drawing 10 01-Dec-18 A 12-Jun-19 A 12-Nov-18 25-Nov-18 850 100% Detailed Drawing
Review & Approval Cycle of 60% Design Package 41 03-Feb-19 A 16-Jun-19 A 11-Jun-19 06-Aug-19 380 100% 16-Jun-19 A, Review & Approval Cycle of 60% Design Package
E1440 Submission of 60% design review package 3 03-Feb-19 A 02-Apr-19 A 11-Jun-19 13-Jun-19 30 100% Submission of 60% design review package
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
E1450 Review of 60% design package by Client and receipt of comments 15 21-Mar-19 A 06-May-19 A 08-Jul-19 28-Jul-19 0 0% Review of 60% design package by Client and receipt of comments
E1490 Comments incorporation 7 22-Mar-19 A 16-Jun-19 A 29-Jul-19 06-Aug-19 300 100% Comments incorporation
E1530 Workshop with client to discuss comments and obtain approval 9 21-Apr-19 A 19-May-19 A 07-Jul-19 18-Jul-19 50 100% Workshop with client to discuss comments and obtain approval
GSD Survey Outcomes 30 05-May-19 A 13-Jun-19 A 31-Jul-19 29-Aug-19 0 0% 13-Jun-19 A, GSD Survey Outcomes
GS1000 Revision of partial 60% design drawings 30 05-May-19 A 13-Jun-19 A 31-Jul-19 29-Aug-19 0 0% Revision of partial 60% design drawings
90% Design Package 114 28-Nov-18 A 09-Nov-19 A 12-Jun-19 18-Nov-19 3150 100% 09-Nov-19 A, 90% Design Package
Dredging & Reclamation 15 28-Nov-18 A 20-Jun-19 A 07-Jul-19 25-Jul-19 50 100% 20-Jun-19 A, Dredging & Reclamation
E1500 Navigation Aids - Typical Detail 15 28-Nov-18 A 20-Jun-19 A 07-Jul-19 25-Jul-19 50 100% Navigation Aids - Typical Detail
Lighting 15 03-Feb-19 A 02-Jun-19 A 16-Jun-19 04-Jul-19 200 100% 02-Jun-19 A, Lighting
E1470 Specification 15 03-Feb-19 A 02-Jun-19 A 16-Jun-19 04-Jul-19 200 100% Specification
Cathodic Protection 48 18-May-19 A 15-Sep-19 A 12-Jun-19 18-Aug-19 2050 100% 15-Sep-19 A, Cathodic Protection
E1460 Layout Plan 5 18-May-19 A 28-Jul-19 A 12-Jun-19 18-Jun-19 700 100% Layout Plan
E1480 Design report 7 20-May-19 A 04-Aug-19 A 07-Aug-19 15-Aug-19 900 100% Design report
E1520 Detailed Drawing 8 16-Jun-19 A 15-Sep-19 A 07-Aug-19 18-Aug-19 450 100% Detailed Drawing
Fence & Wave Wall 28 03-Feb-19 A 30-Sep-19 A 03-Jul-19 11-Aug-19 400 100% 30-Sep-19 A, Fence & Wave Wall
E1510 Design report 10 01-May-19 A 24-Sep-19 A 03-Jul-19 16-Jul-19 300 100% Design report
E1540 Detailed Drawing 10 03-Feb-19 A 30-Sep-19 A 29-Jul-19 11-Aug-19 100 100% Detailed Drawing
Missalaneous (If Any ) 7 02-Jun-19 A 03-Jun-19 A 07-Aug-19 15-Aug-19 100 100% 03-Jun-19 A, Missalaneous (If Any )
E1550 Missalaneous items - (If any ) 7 02-Jun-19 A 03-Jun-19 A 07-Aug-19 15-Aug-19 100 100% Missalaneous items - (If any )
Review & Approval Cycle of 90% Design 107 15-Jun-19 A 09-Nov-19 A 23-Jun-19 18-Nov-19 350 100% 09-Nov-19 A, Review & Approval Cycle of 90% Design
E1560 Submission of 90% design review package 3 15-Jun-19 A 16-Jun-19 A 23-Jun-19 25-Jun-19 30 100% Submission of 90% design review package
E1570 Review of 90% design package by Client and receipt of comments 10 23-Jun-19 A 02-Sep-19 A 26-Jun-19 09-Jul-19 150 100% Review of 90% design package by Client and receipt of comments
E1580 Comments in-corporation 10 30-Jun-19 A 15-Oct-19 A 11-Aug-19 22-Aug-19 70 100% Comments in-corporation
E1590 Workshop with client to discuss comments and obtain approval 15 29-Oct-19 A 09-Nov-19 A 29-Oct-19 18-Nov-19 100 100% Workshop with client to discuss comments and obtain approval
Issue 100% IFC(Issue for Construction) Drawing 186 06-Jun-19 A 01-Dec-19 A 06-Jun-19 12-Dec-19 220 100% 01-Dec-19 A, Issue 100% IFC(Issue for Construction) Drawing
Review Cycle of IFC 186 06-Jun-19 A 01-Dec-19 A 06-Jun-19 12-Dec-19 220 100% 01-Dec-19 A, Review Cycle of IFC
A1010 Submission & Approval of Early IFC ( Land filling & preparation ) 10 06-Jun-19 A 12-Jun-19 A 06-Jun-19 16-Jun-19 0 0% Submission & Approval of Early IFC ( Land filling & preparation )
E1600 100% Submission of IFC 9 04-Nov-19 A 23-Nov-19 A 10-Nov-19 20-Nov-19 30 100% 100% Submission of IFC
E1610 100%- Client Review of IFC 8 01-Jul-19 A 24-Nov-19 A 21-Nov-19 02-Dec-19 150 100% 100%- Client Review of IFC
E1620 100%- Receipt of Approval from Client 8 26-Nov-19 A 01-Dec-19 A 03-Dec-19 12-Dec-19 40 100% 100%- Receipt of Approval from Client
PROCUREMENT 837 01-Oct-18 A 28-Nov-21 11-Oct-18 15-Oct-20 14000 98.64%
Steel Tubular Pipe 397 27-Nov-18 A 12-Mar-20 A 22-Nov-18 29-Feb-20 1000 100% 12-Mar-20 A, Steel Tubular Pipe
P1110 Issue RFQ, 15 27-Nov-18 A 10-Dec-18 A 22-Nov-18 10-Dec-18 100 100% Issue RFQ,
P1240 Tender Bid Evaluation 25 03-Mar-19 A 08-Mar-19 A 18-Jun-19 17-Jul-19 150 100% Tender Bid Evaluation
P1490 Award PO 3 13-Jun-19 A 17-Jul-19 A 13-Jun-19 17-Jun-19 150 100% Award PO
P1510 Completion of NMR 601 7 21-Jul-19 A 22-Jul-19 A 17-Jun-19 25-Jun-19 100 100% Completion of NMR 601
P1520 Completion of NMR 602 7 25-Jun-19 A 25-Jun-19 A 25-Jun-19 03-Jul-19 100 100% Completion of NMR 602
P1580 Delivery To Site 100% 20 04-Jan-20 A 12-Mar-20 A 05-Jan-20 28-Jan-20 300 100% Delivery To Site 100%
P1760 Receipt of Final NMR 603 3 20-Feb-20 A 06-Mar-20 A 26-Feb-20 29-Feb-20 100 100% Receipt of Final NMR 603
Concrete 483 29-Nov-18 A 28-Nov-21 22-Nov-18 22-Mar-20 1000 99.75%
P1100 Issue RFQ, 15 29-Nov-18 A 24-Dec-18 A 22-Nov-18 10-Dec-18 100 100% Issue RFQ,
P1230 Tender Bid Evaluation 15 12-Feb-19 A 19-Feb-19 A 14-May-19 01-Jun-19 150 100% Tender Bid Evaluation
P1430 Award PO 27 07-Jul-19 A 03-Sep-19 A 31-Jul-19 31-Aug-19 150 100% Award PO
P1500 Delivery To Site 1st Batch 30 05-Sep-19 A 06-Sep-19 A 16-Sep-19 20-Oct-19 250 100% Delivery To Site 1st Batch
P1530 Receipt of Final NMR 603 20 05-Sep-19 A 06-Sep-19 A 21-Oct-19 12-Nov-19 100 100% Receipt of Final NMR 603
P1540 Delivery To Site 100% 100 14-Dec-19 A 28-Nov-21 14-Dec-19 22-Mar-20 250 99%
Reinforcement 485 27-Nov-18 A 07-Feb-20 A 22-Nov-18 24-Mar-20 1000 100% 07-Feb-20 A, Reinforcement
P1120 Issue RFQ, 15 27-Nov-18 A 02-Dec-18 A 22-Nov-18 10-Dec-18 100 100% Issue RFQ,
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
P1250 Tender Bid Evaluation 15 09-Feb-19 A 25-Feb-19 A 10-Jun-19 27-Jun-19 150 100% Tender Bid Evaluation
P1440 Award PO 3 07-May-19 A 11-May-19 A 13-Jun-19 17-Jun-19 150 100% Award PO
P1480 Delivery To Site 1st Batch 80 21-Oct-19 A 03-Nov-19 A 20-Oct-19 20-Jan-20 250 100% Delivery To Site 1st Batch
P1740 Receipt of Final NMR 603 8 03-Nov-19 A 09-Nov-19 A 03-Nov-19 12-Nov-19 100 100% Receipt of Final NMR 603
P1750 Delivery To Site 100% 90 10-Nov-19 A 07-Feb-20 A 26-Dec-19 24-Mar-20 250 100% Delivery To Site 100%
Geotextile 451 01-Oct-18 A 26-Dec-19 A 31-Oct-18 28-Jan-20 1000 100% 26-Dec-19 A, Geotextile
P1080 Issue RFQ, 15 01-Oct-18 A 18-Dec-18 A 31-Oct-18 18-Nov-18 100 100% Issue RFQ,
P1210 Tender Bid Evaluation 15 13-Feb-19 A 16-Feb-19 A 29-Apr-19 16-May-19 150 100% Tender Bid Evaluation
P1410 Award PO 3 21-Mar-19 A 25-Mar-19 A 13-May-19 16-May-19 150 100% Award PO
P1460 Delivery To Site 1st Batch 50 26-Mar-19 A 26-Jul-19 A 01-Jul-19 28-Aug-19 250 100% Delivery To Site 1st Batch
P1610 Receipt of Final NMR 603 7 06-Sep-19 A 08-Sep-19 A 31-Jul-19 07-Aug-19 100 100% Receipt of Final NMR 603
P1620 Delivery To Site 100% 80 20-Sep-19 A 26-Dec-19 A 10-Nov-19 28-Jan-20 250 100% Delivery To Site 100%
Steel Road Barrier 333 08-Jan-19 A 07-Feb-20 A 31-Jan-19 24-Feb-20 1000 100% 07-Feb-20 A, Steel Road Barrier
P1010 Issue RFQ, 15 08-Jan-19 A 20-Jan-19 A 31-Jan-19 18-Feb-19 100 100% Issue RFQ,
P1140 Tender Bid Evaluation 15 23-May-19 A 23-May-19 A 02-Jul-19 20-Jul-19 150 100% Tender Bid Evaluation
P1270 Award PO 3 14-Jul-19 A 14-Jul-19 A 25-Jun-19 29-Jun-19 150 100% Award PO
P1340 Delivery To Site 100% 10 23-Jan-20 A 05-Feb-20 A 13-Feb-20 24-Feb-20 500 100% Delivery To Site 100%
P1840 Receipt of Final NMR 603 3 06-Feb-20 A 07-Feb-20 A 12-Feb-20 15-Feb-20 100 100% Receipt of Final NMR 603
Expansion Joint for Bridge 306 11-Apr-19 A 03-Apr-20 A 11-Apr-19 02-Apr-20 1000 100% 03-Apr-20 A, Expansion Joint for Bridge
P1090 Issue RFQ, 15 11-Apr-19 A 29-Apr-19 A 11-Apr-19 29-Apr-19 100 100% Issue RFQ,
P1220 Tender Bid Evaluation 15 26-May-19 A 30-Jun-19 A 13-Jun-19 01-Jul-19 150 100% Tender Bid Evaluation
P1420 Award PO 3 22-Jul-19 A 28-Jul-19 A 01-Jul-19 04-Jul-19 150 100% Award PO
P1470 Completion of NMR 601 20 28-Jul-19 A 28-Jul-19 A 04-Jul-19 28-Jul-19 100 100% Completion of NMR 601
P1590 Completion of NMR 602 20 28-Jul-19 A 28-Jul-19 A 28-Jul-19 20-Aug-19 100 100% Completion of NMR 602
P1700 Delivery To Site 100% 4 28-Mar-20 A 30-Mar-20 A 28-Mar-20 31-Mar-20 300 100% Delivery To Site 100%
P1830 Receipt of Final NMR 603 2 30-Mar-20 A 03-Apr-20 A 01-Apr-20 02-Apr-20 100 100% Receipt of Final NMR 603
Navigation Aids 475 06-Jan-19 A 22-Aug-20 A 17-Feb-19 24-Aug-20 1000 100% 22-Aug-20 A, Navigation Aids
P1050 Issue RFQ, 15 06-Jan-19 A 21-Jan-19 A 17-Feb-19 06-Mar-19 100 100% Issue RFQ,
P1180 Tender Bid Evaluation 15 22-Mar-19 A 04-Apr-19 A 03-Jul-19 21-Jul-19 150 100% Tender Bid Evaluation
P1310 Award PO 3 03-Jun-19 A 05-Jun-19 A 03-Jul-19 07-Jul-19 150 100% Award PO
P1380 Completion of NMR 601 24 05-Jun-19 A 05-Jun-19 A 07-Jul-19 04-Aug-19 100 100% Completion of NMR 601
P1550 Completion of NMR 602 24 05-Jun-19 A 05-Jun-19 A 04-Aug-19 01-Sep-19 100 100% Completion of NMR 602
P1640 Delivery To Site 100% 8 20-Aug-20 A 21-Aug-20 A 15-Aug-20 23-Aug-20 300 100% Delivery To Site 100%
P1800 Receipt of Final NMR 603 1 21-Aug-20 A 22-Aug-20 A 24-Aug-20 24-Aug-20 100 100% Receipt of Final NMR 603
Lighting 401 12-Dec-18 A 04-May-20 A 06-Mar-19 16-Jun-20 1000 100% 04-May-20 A, Lighting
P1020 Issue RFQ, 7 12-Dec-18 A 20-Dec-18 A 06-Mar-19 14-Mar-19 100 100% Issue RFQ,
P1150 Tender Bid Evaluation 10 26-Feb-19 A 01-Mar-19 A 16-Jul-19 28-Jul-19 150 100% Tender Bid Evaluation
P1280 Award PO 9 28-Jul-19 A 28-Jul-19 A 04-Jul-19 15-Jul-19 150 100% Award PO
P1350 Completion of NMR 601 25 28-Jul-19 A 28-Jul-19 A 15-Jul-19 13-Aug-19 100 100% Completion of NMR 601
P1560 Completion of NMR 602 25 28-Jul-19 A 28-Jul-19 A 13-Aug-19 12-Sep-19 100 100% Completion of NMR 602
P1660 Delivery To Site 100% 8 08-Jan-20 A 02-May-20 A 24-Feb-20 04-Mar-20 300 100% Delivery To Site 100%
P1790 Receipt of Final NMR 603 2 03-May-20 A 04-May-20 A 15-Jun-20 16-Jun-20 100 100% Receipt of Final NMR 603
Cathodic protection 499 02-Dec-18 A 03-Jun-20 A 21-Nov-18 25-Jun-20 1000 100% 03-Jun-20 A, Cathodic protection
P1030 Issue RFQ, 15 02-Dec-18 A 09-Dec-18 A 21-Nov-18 09-Dec-18 100 100% Issue RFQ,
P1160 Tender Bid Evaluation 15 17-Apr-19 A 18-Jul-19 A 19-Jun-19 07-Jul-19 150 100% Tender Bid Evaluation
P1290 Award PO 3 21-Jul-19 A 24-Jul-19 A 07-Jul-19 10-Jul-19 150 100% Award PO
P1360 Completion of NMR 601 30 24-Jul-19 A 24-Jul-19 A 10-Jul-19 14-Aug-19 100 100% Completion of NMR 601
P1600 Completion of NMR 602 20 12-Oct-19 A 18-Oct-19 A 01-Oct-19 23-Oct-19 100 100% Completion of NMR 602
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
P1650 Delivery To Site 100% 15 30-Jan-20 A 01-Jun-20 A 13-Feb-20 01-Mar-20 300 100% Delivery To Site 100%
P1770 Receipt of Final NMR 603 3 02-Jun-20 A 03-Jun-20 A 23-Jun-20 25-Jun-20 100 100% Receipt of Final NMR 603
Escape Jetty Facilities 391 08-Jan-19 A 22-May-20 A 24-Feb-19 25-May-20 1000 100% 22-May-20 A, Escape Jetty Facilities
P1040 Issue RFQ, 15 08-Jan-19 A 20-Jan-19 A 24-Feb-19 13-Mar-19 100 100% Issue RFQ,
P1170 Tender Bid Evaluation 15 28-May-19 A 03-Jun-19 A 19-Jun-19 07-Jul-19 150 100% Tender Bid Evaluation
P1300 Award PO 3 05-Jun-19 A 06-Jun-19 A 07-Jul-19 10-Jul-19 150 100% Award PO
P1370 Completion of NMR 601 20 28-Jul-19 A 30-Jul-19 A 31-Jul-19 22-Aug-19 100 100% Completion of NMR 601
P1570 Completion of NMR 602 20 17-Oct-19 A 09-Nov-19 A 13-Oct-19 04-Nov-19 100 100% Completion of NMR 602
P1670 Delivery To Site 100% 6 03-May-20 A 21-May-20 A 02-May-20 07-May-20 300 100% Delivery To Site 100%
P1850 Receipt of Final NMR 603 3 21-May-20 A 22-May-20 A 23-May-20 25-May-20 100 100% Receipt of Final NMR 603
Rocks 575 02-Dec-18 A 02-May-20 A 31-Oct-18 31-May-20 1000 100% 02-May-20 A, Rocks
P1070 Issue RFQ, 15 02-Dec-18 A 09-Dec-18 A 31-Oct-18 18-Nov-18 100 100% Issue RFQ,
P1200 Tender Bid Evaluation 15 25-Apr-19 A 28-Apr-19 A 24-Jun-19 11-Jul-19 150 100% Tender Bid Evaluation
P1400 Award PO 3 15-May-19 A 16-May-19 A 18-Jul-19 22-Jul-19 150 100% Award PO
P1450 Delivery To Site 1st Batch 51 14-Jul-19 A 28-Jul-19 A 11-Jul-19 09-Sep-19 250 100% Delivery To Site 1st Batch
P1680 Receipt of Final NMR 603 8 05-Sep-19 A 24-Sep-19 A 31-Jul-19 10-Aug-19 100 100% Receipt of Final NMR 603
P1690 Delivery To Site 100% 170 18-Sep-19 A 02-May-20 A 14-Dec-19 31-May-20 250 100% Delivery To Site 100%
Road-asphalt 720 09-Dec-18 A 23-Nov-21 11-Oct-18 15-Oct-20 1000 81.25%
P1060 Issue RFQ, 15 09-Dec-18 A 23-Dec-18 A 11-Oct-18 29-Oct-18 100 100% Issue RFQ,
P1190 Tender Bid Evaluation 15 05-May-19 A 07-Jul-19 A 02-Jul-19 20-Jul-19 150 100% Tender Bid Evaluation
P1320 Award PO 40 25-Aug-19 A 21-Oct-19 A 31-Jul-19 15-Sep-19 150 100% Award PO
P1390 Delivery To Site 100% 4 29-Jan-21 A 23-Nov-21 10-Oct-20 13-Oct-20 500 62.5%
P1820 Receipt of Final NMR 603 2 27-Jan-21 A 30-Jan-21 A 14-Oct-20 15-Oct-20 100 100% Receipt of Final NMR 603
Road-base Course 439 09-Dec-18 A 17-Jan-20 A 11-Oct-18 07-Mar-20 1000 100% 17-Jan-20 A, Road-base Course
P1000 Issue RFQ, 15 09-Dec-18 A 23-Dec-18 A 11-Oct-18 29-Oct-18 100 100% Issue RFQ,
P1130 Tender Bid Evaluation 15 05-May-19 A 10-May-19 A 02-Jul-19 20-Jul-19 150 100% Tender Bid Evaluation
P1260 Award PO 3 15-May-19 A 16-May-19 A 20-Jul-19 23-Jul-19 150 100% Award PO
P1330 Delivery To Site 100% 28 22-Dec-19 A 16-Jan-20 A 01-Feb-20 04-Mar-20 500 100% Delivery To Site 100%
P1810 Receipt of Final NMR 603 2 16-Jan-20 A 17-Jan-20 A 04-Mar-20 07-Mar-20 100 100% Receipt of Final NMR 603
Marl 425 02-Dec-18 A 17-Jan-20 A 28-Oct-18 07-Mar-20 1000 100% 17-Jan-20 A, Marl
P1630 Issue RFQ, 15 02-Dec-18 A 09-Dec-18 A 28-Oct-18 14-Nov-18 100 100% Issue RFQ,
P1710 Tender Bid Evaluation 12 17-Apr-19 A 18-Apr-19 A 03-Jul-19 17-Jul-19 150 100% Tender Bid Evaluation
P1720 Award PO 3 07-May-19 A 10-May-19 A 17-Jul-19 21-Jul-19 150 100% Award PO
P1730 Delivery To Site 1st Batch 30 22-Dec-19 A 26-Dec-19 A 28-Jan-20 03-Mar-20 500 100% Delivery To Site 1st Batch
P1780 Receipt of Final NMR 603 3 17-Jan-20 A 17-Jan-20 A 03-Mar-20 07-Mar-20 100 100% Receipt of Final NMR 603
CONSTRUCTION 1214 19-Nov-18 A 29-Jan-22 01-Oct-18 31-Dec-21 1333296 93.71%
Temporary Facilities 330 19-Nov-18 A 14-Sep-19 A 01-Oct-18 29-Aug-19 52720 100% 14-Sep-19 A, Temporary Facilities
Site Preperation 15 19-Nov-18 A 20-Jan-19 A 01-Oct-18 15-Oct-18 5000 100% 20-Jan-19 A, Site Preperation
C2020 Leveling/Compaction for Laydown Area 15 19-Nov-18 A 20-Jan-19 A 01-Oct-18 15-Oct-18 5000 100% Leveling/Compaction for Laydown Area
Temporary Fence & Road 119 25-Nov-18 A 27-Apr-19 A 16-Oct-18 11-Feb-19 5000 100% 27-Apr-19 A, Temporary Fence & Road
C2030 Temporary Road 15 10-Dec-18 A 13-Feb-19 A 16-Oct-18 30-Oct-18 3000 100% Temporary Road
C2050 Temporary Fence 7 25-Nov-18 A 27-Apr-19 A 05-Feb-19 11-Feb-19 2000 100% Temporary Fence
Temporary Building 25 10-Jan-19 A 19-Mar-19 A 27-Feb-19 24-Mar-19 16720 100% 19-Mar-19 A, Temporary Building
C2060 SAPMTSite Office Installation 25 02-Feb-19 A 17-Feb-19 A 27-Feb-19 24-Mar-19 9000 100% SAPMTSite Office Installation
C2070 CONTRACTOR Site Office Installation 25 15-Feb-19 A 13-Mar-19 A 27-Feb-19 24-Mar-19 1360 100% CONTRACTOR Site Office Installation
C2080 Warehouse Construction 15 19-Feb-19 A 13-Mar-19 A 27-Feb-19 14-Mar-19 1360 100% Warehouse Construction
C2090 Clinic/prayer Room/Guard Room installation 20 27-Feb-19 A 19-Mar-19 A 27-Feb-19 19-Mar-19 1000 100% Clinic/prayer Room/Guard Room installation
C2140 Workshop Construction 20 10-Jan-19 A 13-Mar-19 A 27-Feb-19 18-Mar-19 4000 100% Workshop Construction
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
Temporary Sewage Facilities 30 11-Mar-19 A 04-May-19 A 04-Apr-19 04-May-19 1500 100% 04-May-19 A, Temporary Sewage Facilities
C2100 Sewage Facilites Installation 30 11-Mar-19 A 04-May-19 A 04-Apr-19 04-May-19 1500 100% Sewage Facilites Installation
Temporary Water Supplying Facilities 18 15-Feb-19 A 04-May-19 A 09-Mar-19 27-Mar-19 1500 100% 04-May-19 A, Temporary Water Supplying Facilities
C2120 Water Supplying Facilities Installation 18 15-Feb-19 A 04-May-19 A 09-Mar-19 27-Mar-19 1500 100% Water Supplying Facilities Installation
Temporary Electrical Works 18 15-Feb-19 A 04-May-19 A 09-Mar-19 27-Mar-19 1500 100% 04-May-19 A, Temporary Electrical Works
C2110 Electrical Facilities Construction 18 15-Feb-19 A 04-May-19 A 09-Mar-19 27-Mar-19 1500 100% Electrical Facilities Construction
Laydown Area 8 10-Mar-19 A 04-May-19 A 29-Apr-19 07-May-19 2500 100% 04-May-19 A, Laydown Area
C2160 Finishing Works 8 10-Mar-19 A 04-May-19 A 29-Apr-19 07-May-19 2500 100% Finishing Works
Temporary Fire Protection Facilities 30 31-Mar-19 A 22-May-19 A 31-Mar-19 29-Apr-19 1500 100% 22-May-19 A, Temporary Fire Protection Facilities
C2170 Fire Protection Facilities Construction 30 31-Mar-19 A 22-May-19 A 31-Mar-19 29-Apr-19 1500 100% Fire Protection Facilities Construction
Precast Yard 30 11-Feb-19 A 04-May-19 A 03-Apr-19 03-May-19 7500 100% 04-May-19 A, Precast Yard
C2180 Precast Yard Construction 30 11-Feb-19 A 04-May-19 A 03-Apr-19 03-May-19 7500 100% Precast Yard Construction
Temporary Jetty 30 06-Aug-19 A 14-Sep-19 A 31-Jul-19 29-Aug-19 10000 100% 14-Sep-19 A, Temporary Jetty
C2300 South Island TJ - Stage 1 15 06-Aug-19 A 16-Aug-19 A 31-Jul-19 14-Aug-19 6000 100% South Island TJ - Stage 1
C2440 South Island TJ - Stage 2 15 18-Aug-19 A 14-Sep-19 A 15-Aug-19 29-Aug-19 4000 100% South Island TJ - Stage 2
General Demolition Activities 143 31-Mar-19 A 18-Jul-19 A 31-Mar-19 23-Aug-19 16750 100% 18-Jul-19 A, General Demolition Activities
Remove and Dispose of Existing Pipeline 108 31-Mar-19 A 08-Jul-19 A 31-Mar-19 19-Jul-19 12250 100% 08-Jul-19 A, Remove and Dispose of Existing Pipeline
C2010 Pipeline Exploration 12 31-Mar-19 A 08-Apr-19 A 31-Mar-19 11-Apr-19 2250 100% Pipeline Exploration
C2040 Pipeline Cut Off 30 18-May-19 A 28-May-19 A 17-Jun-19 19-Jul-19 6250 100% Pipeline Cut Off
C2130 Pipeline Lifting and Transportation 20 24-May-19 A 08-Jul-19 A 17-Jun-19 06-Jul-19 3750 100% Pipeline Lifting and Transportation
Remove and Dispose of Existing Facilities In The Park 54 09-May-19 A 18-Jul-19 A 27-Jun-19 23-Aug-19 4500 100% 18-Jul-19 A, Remove and Dispose of Existing Facilities In The Park
C2150 Above Ground Facilities Demolition 30 09-May-19 A 08-Jul-19 A 27-Jun-19 30-Jul-19 2250 100% Above Ground Facilities Demolition
C2190 Under Ground Facilities Demolition 42 09-May-19 A 18-Jul-19 A 09-Jul-19 23-Aug-19 2250 100% Under Ground Facilities Demolition
Causeway to South Island 839 13-Jun-19 A 28-Oct-21 A 16-Jun-19 05-Mar-21 134600 100%
South Island Causeway Reclamation 180 13-Jun-19 A 20-Nov-19 A 16-Jun-19 16-Dec-19 26250 100% 20-Nov-19 A, South Island Causeway Reclamation
C2210 South Island Causeway Infill 25% 24 13-Jun-19 A 15-Jul-19 A 16-Jun-19 10-Jul-19 7500 100% South Island Causeway Infill 25%
C2240 South Island Causeway Infill 50% 24 15-Jul-19 A 28-Jul-19 A 15-Jul-19 07-Aug-19 6250 100% South Island Causeway Infill 50%
C2330 South Island Causeway Infill 75% 24 28-Jul-19 A 17-Aug-19 A 06-Jul-19 02-Aug-19 6250 100% South Island Causeway Infill 75%
C2450 South Island Causeway Infill 100% 12 19-Nov-19 A 20-Nov-19 A 05-Dec-19 16-Dec-19 6250 100% South Island Causeway Infill 100%
Revetment (L=1532m) 80 07-Oct-19 A 29-Jan-20 A 10-Nov-19 28-Jan-20 79480 100% 29-Jan-20 A, Revetment (L=1532m)
C2310 Sand Slope Trimming (below +2.5m CD) 72 07-Oct-19 A 16-Nov-19 A 10-Nov-19 20-Jan-20 4600 100% Sand Slope Trimming (below +2.5m CD)
C2320 Geotextile Laying (below +2.5m CD) 72 07-Oct-19 A 17-Nov-19 A 10-Nov-19 20-Jan-20 10350 100% Geotextile Laying (below +2.5m CD)
C2340 Rock Under Layer (Below +2.5m CD) 72 07-Oct-19 A 23-Nov-19 A 10-Nov-19 20-Jan-20 10350 100% Rock Under Layer (Below +2.5m CD)
C2510 Rock Armour Layer (below +2.5m CD) 72 07-Oct-19 A 06-Dec-19 A 10-Nov-19 20-Jan-20 9450 100% Rock Armour Layer (below +2.5m CD)
C2520 Rock Armour Layer at toe (below +2.5m CD) 59 07-Oct-19 A 06-Dec-19 A 01-Dec-19 28-Jan-20 9450 100% Rock Armour Layer at toe (below +2.5m CD)
C2860 Geotextile Laying (+2.5m~ +4m CD) 59 01-Dec-19 A 04-Jan-20 A 01-Dec-19 28-Jan-20 4410 100% Geotextile Laying (+2.5m~ +4m CD)
C2870 Rock Under Layer (+2.5m~ +4m CD) 40 01-Dec-19 A 04-Jan-20 A 01-Dec-19 09-Jan-20 4410 100% Rock Under Layer (+2.5m~ +4m CD)
C2880 Sand Slope Trimming (+2.5m~ +4m CD) 33 01-Dec-19 A 17-Jan-20 A 01-Dec-19 02-Jan-20 4410 100% Sand Slope Trimming (+2.5m~ +4m CD)
C3110 Rock Armour Layer (+2.5m~ +4m CD) 33 01-Dec-19 A 17-Jan-20 A 01-Dec-19 02-Jan-20 4410 100% Rock Armour Layer (+2.5m~ +4m CD)
C3640 Geotextile Laying (+4m~top CD) 33 21-Dec-19 A 17-Jan-20 A 14-Dec-19 15-Jan-20 4410 100% Geotextile Laying (+4m~top CD)
C3650 Sand Slope Trimming (+4m~top CD) 33 14-Dec-19 A 17-Jan-20 A 14-Dec-19 15-Jan-20 4410 100% Sand Slope Trimming (+4m~top CD)
C3660 Rock Under Layer (+4m~top CD) 33 14-Dec-19 A 17-Jan-20 A 14-Dec-19 15-Jan-20 4410 100% Rock Under Layer (+4m~top CD)
C4010 Rock Armour Layer (+4m~top CD) 33 14-Dec-19 A 29-Jan-20 A 14-Dec-19 15-Jan-20 4410 100% Rock Armour Layer (+4m~top CD)
Soil Improvement 37 08-Dec-19 A 11-Jan-20 A 26-Dec-19 31-Jan-20 10500 100% 11-Jan-20 A, Soil Improvement
C6520 Soil Improvement 50% 10 08-Dec-19 A 28-Dec-19 A 26-Dec-19 04-Jan-20 5250 100% Soil Improvement 50%
C7140 Soil Improvement 100% 35 28-Dec-19 A 11-Jan-20 A 28-Dec-19 31-Jan-20 5250 100% Soil Improvement 100%
Marl Cap Installation 20 23-Dec-19 A 05-Feb-20 A 01-Feb-20 20-Feb-20 17500 100% 05-Feb-20 A, Marl Cap Installation
C7590 Marl Cap 50% 20 23-Dec-19 A 30-Jan-20 A 01-Feb-20 20-Feb-20 8750 100% Marl Cap 50%
C7990 Marl Cap 100% 20 01-Feb-20 A 05-Feb-20 A 01-Feb-20 20-Feb-20 8750 100% Marl Cap 100%
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
Construction of Road 543 22-Mar-20 A 28-Oct-21 A 11-Apr-20 05-Mar-21 870 100%
C7580 Lighting Pole Foundation construction 5 11-Apr-20 A 07-May-20 A 11-Apr-20 15-Apr-20 250 100% Lighting Pole Foundation construction
C7980 Base Layer of Road Construction 15 22-Mar-20 A 11-Apr-20 A 11-Apr-20 25-Apr-20 250 100% Base Layer of Road Construction
C8400 Armour Layer of Road Construction 39 28-Jan-21 A 22-Mar-21 A 01-Jan-21 08-Feb-21 150 100% Armour Layer of Road Const
C8610 Road Marking 5 01-Oct-21 A 28-Oct-21 A 09-Feb-21 18-Feb-21 70 100%
C8650 Road Barrier Installation 15 18-Apr-21 A 16-May-21 A 19-Feb-21 05-Mar-21 150 100%
South Island 656 31-Jul-19 A 24-Sep-21 A 31-Jul-19 23-Mar-21 398020 100%
Civil / Structural 656 31-Jul-19 A 24-Sep-21 A 31-Jul-19 23-Mar-21 398020 100%
Dredging and Reclamation 226 31-Jul-19 A 23-Apr-20 A 31-Jul-19 12-Mar-20 107500 100% 23-Apr-20 A, Dredging and Reclamation
C2250 Reclamation of South Island 10% 34 31-Jul-19 A 31-Aug-19 A 31-Jul-19 02-Sep-19 10750 100% Reclamation of South Island 10%
C2290 Reclamation of South Island 20% 15 31-Aug-19 A 22-Sep-19 A 03-Sep-19 17-Sep-19 10750 100% Reclamation of South Island 20%
C2400 Reclamation of South Island 30% 15 23-Sep-19 A 27-Oct-19 A 18-Sep-19 02-Oct-19 10750 100% Reclamation of South Island 30%
C2760 Reclamation of South Island 40% 15 27-Oct-19 A 09-Nov-19 A 04-Nov-19 18-Nov-19 10750 100% Reclamation of South Island 40%
C3240 Reclamation of South Island 50% 15 15-Nov-19 A 30-Nov-19 A 15-Nov-19 29-Nov-19 10750 100% Reclamation of South Island 50%
C3790 Reclamation of South Island 60% 15 23-Dec-19 A 02-Jan-20 A 14-Dec-19 28-Dec-19 10750 100% Reclamation of South Island 60%
C4300 Reclamation of South Island 70% 20 03-Jan-20 A 12-Jan-20 A 29-Dec-19 17-Jan-20 10750 100% Reclamation of South Island 70%
C4790 Reclamation of South Island 80% 20 13-Jan-20 A 28-Jan-20 A 18-Jan-20 06-Feb-20 10750 100% Reclamation of South Island 80%
C5350 Reclamation of South Island 90% 20 28-Jan-20 A 21-Feb-20 A 18-Jan-20 06-Feb-20 10750 100% Reclamation of South Island 90%
C5920 Reclamation of South Island 100% 20 22-Feb-20 A 23-Apr-20 A 22-Feb-20 12-Mar-20 10750 100% Reclamation of South Island 100%
South Drilling Island (A) Civil Work 534 07-Oct-19 A 24-Sep-21 A 30-Nov-19 23-Mar-21 290520 100%
Revetment (L=2957m) 103 07-Oct-19 A 24-Sep-21 A 30-Nov-19 11-Mar-20 143520 100%
C2410 Sand Slope Trimming (below +2.5m CD) 50 07-Oct-19 A 24-Feb-20 A 30-Nov-19 18-Jan-20 7800 100% Sand Slope Trimming (below +2.5m CD)
C2420 Geotextile Laying (below +2.5m CD) 15 08-Oct-19 A 20-Oct-20 A 15-Dec-19 29-Dec-19 17550 100% Geotextile Laying (below +2.5m CD)
C2430 Rock Under Layer (Below +2.5m CD) 15 08-Oct-19 A 14-Oct-20 A 30-Dec-19 13-Jan-20 17550 100% Rock Under Layer (Below +2.5m CD)
C2570 Rock Armour Layer (below +2.5m CD) 15 05-Nov-19 A 23-Sep-21 A 14-Jan-20 28-Jan-20 17550 100%
C2580 Rock Armour Layer at toe (below +2.5m CD) 15 23-Dec-19 A 23-Sep-21 A 14-Dec-19 28-Dec-19 17550 100%
C2780 Sand Slope Trimming (+2.5m~ +4m CD) 8 26-Jan-20 A 24-Sep-21 A 02-Feb-20 09-Feb-20 8190 100%
C2790 Geotextile Laying (+2.5m~ +4m CD) 8 27-Jan-20 A 23-Sep-21 A 10-Feb-20 17-Feb-20 8190 100%
C2800 Rock Under Layer (+2.5m~ +4m CD) 8 27-Jan-20 A 23-Sep-21 A 18-Feb-20 25-Feb-20 8190 100%
C3010 Rock Armour Layer (+2.5m~ +4m CD) 8 26-Jan-20 A 23-Sep-21 A 02-Mar-20 09-Mar-20 8190 100%
C3310 Sand Slope Trimming (+4m~top CD) 8 05-Feb-20 A 23-Sep-21 A 09-Feb-20 16-Feb-20 8190 100%
C3320 Geotextile Laying (+4m~top CD) 8 06-Feb-20 A 23-Sep-21 A 17-Feb-20 24-Feb-20 8190 100%
C3330 Rock Under Layer (+4m~top CD) 8 02-Feb-20 A 23-Sep-21 A 25-Feb-20 03-Mar-20 8190 100%
C3350 Rock Armour Layer (+4m~top CD) 8 04-Feb-20 A 23-Sep-21 A 04-Mar-20 11-Mar-20 8190 100%
Soil Improvement 478 02-Jan-20 A 17-Apr-21 A 10-Jan-20 08-Mar-21 105000 100% 17-Apr-21 A, Soil Improvem
C3250 Soil Improvement 10% 10 02-Jan-20 A 03-Apr-20 A 10-Jan-20 19-Jan-20 10500 100% Soil Improvement 10%
C3630 Soil Improvement 20% 5 04-Apr-20 A 23-Apr-20 A 04-Apr-20 08-Apr-20 10500 100% Soil Improvement 20%
C4160 Soil Improvement 30% 5 25-Apr-20 A 06-May-20 A 25-Apr-20 29-Apr-20 10500 100% Soil Improvement 30%
C4520 Soil Improvement 40% 5 07-May-20 A 28-May-20 A 02-May-20 06-May-20 10500 100% Soil Improvement 40%
C4850 Soil Improvement 50% 5 28-May-20 A 09-Oct-20 A 28-May-20 01-Jun-20 10500 100% Soil Improvement 50%
C5360 Soil Improvement 60% 30 31-Oct-20 A 16-Dec-20 A 10-Oct-20 08-Nov-20 10500 100% Soil Improvement 60%
C5780 Soil Improvement 70% 30 17-Dec-20 A 14-Jan-21 A 09-Nov-20 08-Dec-20 9500 100% Soil Improvement 70%
C6310 Soil Improvement 80% 30 15-Jan-21 A 29-Jan-21 A 09-Dec-20 07-Jan-21 10500 100% Soil Improvement 80%
C6750 Soil Improvement 90% 30 30-Jan-21 A 07-Mar-21 A 08-Jan-21 06-Feb-21 10500 100% Soil Improvement 90%
C7170 Soil Improvement 100% 27 08-Mar-21 A 17-Apr-21 A 07-Feb-21 08-Mar-21 11500 100% Soil Improvement 100%
Marl Cap Installation 79 27-Feb-21 A 24-May-21 A 08-Jan-21 23-Mar-21 42000 100%
C4860 Marl Cap 20% 15 27-Feb-21 A 22-Mar-21 A 08-Jan-21 22-Jan-21 7400 100% Marl Cap 20%
C5430 Marl Cap 40% 15 21-Mar-21 A 17-Apr-21 A 23-Jan-21 06-Feb-21 7400 100% Marl Cap 40%
C6050 Marl Cap 60% 15 11-Mar-21 A 11-Apr-21 A 07-Feb-21 21-Feb-21 9400 100% Marl Cap 60%
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
C6670 Marl Cap 80% 15 12-Apr-21 A 27-Apr-21 A 22-Feb-21 08-Mar-21 9400 100%
C7180 Marl Cap 100% 8 28-Apr-21 A 24-May-21 A 09-Mar-21 23-Mar-21 8400 100%
South Island Escape Jetty 285 21-Feb-21 A 09-Dec-21 01-Jan-21 09-Jul-21 1610 80.69%
C8130 Piles Installation 30 21-Feb-21 A 15-May-21 A 01-Jan-21 30-Jan-21 300 100%
C8790 Cross Beam Installation 30 01-Jun-21 A 29-Jun-21 A 31-Jan-21 01-Mar-21 210 100%
C8880 I-Beam Installation 27 01-Aug-21 A 20-Aug-21 A 02-Mar-21 31-Mar-21 300 100%
C8900 P/C Plank Installation 10 21-Aug-21 A 31-Aug-21 A 01-Apr-21 30-Apr-21 100 100%
C8950 Cast In-situ of Deck 31 18-Sep-21 A 30-Sep-21 A 01-May-21 30-May-21 400 100%
C8990 Facilities Installation (Life boat etc) 20 13-Nov-21 A 09-Dec-21 31-May-21 09-Jul-21 300 10%
KFIP Expansion 735 19-Aug-19 A 02-Jan-22 30-Dec-19 12-Dec-21 76260 81.73%
KFIP Causeway Expansion Reclaimation 197 23-Sep-19 A 10-Jan-20 A 30-Dec-19 13-Jul-20 4920 100% 10-Jan-20 A, KFIP Causeway Expansion Reclaimation
C2200 Reclamation of KFIP Causeway Expansion 25% 20 23-Sep-19 A 26-Dec-19 A 30-Dec-19 18-Jan-20 1230 100% Reclamation of KFIP Causeway Expansion 25%
C2220 Reclamation of KFIP Causeway Expansion 50% 30 27-Dec-19 A 31-Dec-19 A 13-Jan-20 11-Feb-20 1230 100% Reclamation of KFIP Causeway Expansion 50%
C2260 Reclamation of KFIP Causeway Expansion 75% 30 31-Dec-19 A 02-Jan-20 A 30-May-20 28-Jun-20 1230 100% Reclamation of KFIP Causeway Expansion 75%
C2270 Reclamation of KFIP Causeway Expansion 100% 15 02-Jan-20 A 10-Jan-20 A 29-Jun-20 13-Jul-20 1230 100% Reclamation of KFIP Causeway Expansion 100%
Revetment 712 31-Dec-19 A 30-Dec-21 13-Jan-20 13-Jun-21 32240 90.75%
C2360 Sand Slope Trimming (below +2.5m CD) 20 31-Dec-19 A 07-May-20 A 13-Jan-20 01-Feb-20 1800 100% Sand Slope Trimming (below +2.5m CD)
C2370 Geotextile Laying (below +2.5m CD) 20 31-Dec-19 A 07-May-20 A 02-Feb-20 21-Feb-20 1800 100% Geotextile Laying (below +2.5m CD)
C2380 Rock Under Layer (Below +2.5m CD) 20 31-Dec-19 A 15-Dec-21 02-Feb-20 21-Feb-20 4050 89.02%
C2460 Armour Layer (below +2.5m CD) 12 01-May-20 A 15-Dec-21 22-May-20 02-Jun-20 4500 87.79%
C2470 Armour Layer at toe (below +2.5m CD) 12 01-May-20 A 15-Dec-21 03-Jun-20 14-Jun-20 4500 94.45%
C2620 Sand Slope Trimming (+2.5m~ +4m CD) 12 04-May-20 A 15-Dec-21 03-Jun-20 14-Jun-20 1800 94.3%
C2630 Geotextile Laying (+2.5m~ +4m CD) 12 04-May-20 A 15-Dec-21 15-Jun-20 26-Jun-20 1800 91.84%
C2640 Rock Under Layer (+2.5m~ +4m CD) 12 05-May-20 A 15-Dec-21 28-May-20 08-Jun-20 1800 94.39%
C2900 Armour Layer (+2.5m~ +4m CD) 12 10-Feb-21 A 15-Dec-21 16-May-21 21-May-21 2250 94.47%
C3170 Sand Slope Trimming (+4m~top CD) 10 24-Oct-21 A 16-Dec-21 22-May-21 27-May-21 1900 93.46%
C3180 Geotextile Laying (+4m~top CD) 10 24-Oct-21 A 16-Dec-21 28-May-21 02-Jun-21 1900 94.53%
C3190 Rock Under Layer (+4m~top CD) 5 24-Oct-21 A 25-Dec-21 03-Jun-21 08-Jun-21 1890 72.17%
C3500 Armour Layer (+4m~top CD) 5 24-Oct-21 A 30-Dec-21 09-Jun-21 13-Jun-21 2250 78.35%
Soil Improvement 15 18-Jan-20 A 23-Dec-21 18-Jan-20 01-Feb-20 10500 89.52%
C4500 Soil Improvement 50% 8 18-Jan-20 A 26-Jan-20 A 18-Jan-20 25-Jan-20 5250 100% Soil Improvement 50%
C4920 Soil Improvement 100% 7 26-Jan-20 A 23-Dec-21 26-Jan-20 01-Feb-20 5250 78.77%
Marl Cap Installation 32 15-Sep-21 A 05-Dec-21 01-Oct-21 30-Oct-21 9000 64.84%
C5460 Marl Cap 50% 8 15-Sep-21 A 11-Nov-21 A 01-Oct-21 15-Oct-21 4500 100%
C5940 Marl Cap 100% 16 11-Nov-21 A 05-Dec-21 16-Oct-21 30-Oct-21 4500 29.94%
New Road Construction (KFIP Causeway Expansion) 20 20-Nov-21 09-Dec-21 16-Oct-21 04-Nov-21 0 0%
C7480 Base Layer of Road Construction 11 20-Nov-21 30-Nov-21 16-Oct-21 25-Oct-21 0 0%
C7950 Armour Layer of Road Construction 9 01-Dec-21 09-Dec-21 26-Oct-21 04-Nov-21 0 0%
Modification of Existing Wave Wall 88 19-Aug-19 A 09-Nov-19 A 21-May-20 17-Aug-20 13500 100% 09-Nov-19 A, Modification of Existing Wave Wall
C6500 Modification of existing wave wall 50% 15 19-Aug-19 A 05-Oct-19 A 21-May-20 05-Jun-20 6750 100% Modification of existing wave wall 50%
C7030 Modification of existing wave wall 100% 12 04-Oct-19 A 09-Nov-19 A 05-Aug-20 17-Aug-20 6750 100% Modification of existing wave wall 100%
New Access Road (KFIP Causeway Expansion) 51 13-Nov-21 A 02-Jan-22 26-Oct-21 12-Dec-21 6100 5.28%
C7450 Lighting Pole Foundation construction 10 13-Nov-21 A 29-Nov-21 26-Oct-21 02-Nov-21 1250 30%
C7850 Base Layer of Road Construction 10 20-Nov-21 29-Nov-21 03-Nov-21 12-Nov-21 1250 0%
C7860 Lighting Pole Installation 10 25-Nov-21 04-Dec-21 03-Nov-21 12-Nov-21 1250 0%
C8300 Armour Layer of Road Construction 10 05-Dec-21 14-Dec-21 13-Nov-21 22-Nov-21 650 0%
C8480 Road Marking 10 15-Dec-21 24-Dec-21 23-Nov-21 02-Dec-21 350 0%
C8560 Road Barrier Installation 9 25-Dec-21 02-Jan-22 03-Dec-21 12-Dec-21 1350 0%
New Pipelines Culvert structure (KFIP Causeway Expansion) 62 03-Oct-21 A 23-Dec-21 16-Jul-21 13-Sep-21 0 0%
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
C7460 Leveling and compaction 9 03-Oct-21 A 06-Oct-21 A 16-Jul-21 25-Jul-21 0 0%
C7600 Subgrade Soil compaction 9 07-Nov-21 A 10-Nov-21 A 26-Jul-21 09-Aug-21 0 0%
C7720 Concrete Casting for Culvert 26 20-Nov-21 15-Dec-21 26-Jul-21 14-Aug-21 0 0%
C8100 Coating Work 3 16-Dec-21 18-Dec-21 15-Aug-21 29-Aug-21 0 0%
C8290 Back Filling 5 19-Dec-21 23-Dec-21 30-Aug-21 13-Sep-21 0 0%
North island 633 12-Jan-20 A 20-Dec-21 18-Jan-20 26-Jul-21 329366 99.36%
North Island Reclamation 131 12-Jan-20 A 04-Jun-20 A 18-Jan-20 27-May-20 107500 100% 04-Jun-20 A, North Island Reclamation
C2350 Reclamation of NorthIsland 10% 10 12-Jan-20 A 03-Feb-20 A 18-Jan-20 27-Jan-20 10750 100% Reclamation of NorthIsland 10%
C2560 Reclamation of NorthIsland 20% 8 04-Feb-20 A 21-Feb-20 A 11-Feb-20 18-Feb-20 10750 100% Reclamation of NorthIsland 20%
C3000 Reclamation of NorthIsland 30% 8 20-Feb-20 A 27-Mar-20 A 23-Feb-20 01-Mar-20 10750 100% Reclamation of NorthIsland 30%
C3480 Reclamation of NorthIsland 40% 6 27-Mar-20 A 23-Apr-20 A 27-Mar-20 01-Apr-20 10750 100% Reclamation of NorthIsland 40%
C4060 Reclamation of NorthIsland 50% 4 24-Apr-20 A 06-May-20 A 24-Apr-20 27-Apr-20 10750 100% Reclamation of NorthIsland 50%
C4540 Reclamation of NorthIsland 60% 4 06-May-20 A 12-May-20 A 06-May-20 09-May-20 10750 100% Reclamation of NorthIsland 60%
C5040 Reclamation of NorthIsland 70% 4 13-May-20 A 19-May-20 A 13-May-20 16-May-20 10750 100% Reclamation of NorthIsland 70%
C5590 Reclamation of NorthIsland 80% 4 20-May-20 A 21-May-20 A 20-May-20 23-May-20 10750 100% Reclamation of NorthIsland 80%
C6190 Reclamation of NorthIsland 90% 4 21-May-20 A 26-May-20 A 24-May-20 27-May-20 10750 100% Reclamation of NorthIsland 90%
C6830 Reclamation of NorthIsland 100% 4 23-May-20 A 04-Jun-20 A 23-May-20 26-May-20 10750 100% Reclamation of NorthIsland 100%
North Drilling Island (B) Civil Work 577 17-Mar-20 A 20-Dec-21 14-Mar-20 26-Jul-21 221866 99.06%
Revetment 534 17-Mar-20 A 20-Dec-21 14-Mar-20 30-May-21 115826 98.2%
C5050 Sand Slope Trimming (below +2.5m CD) 9 17-Mar-20 A 20-Oct-20 A 14-Mar-20 22-Mar-20 6600 100% Sand Slope Trimming (below +2.5m CD)
C5060 Geotextile Laying (below +2.5m CD) 9 19-Mar-20 A 26-Oct-20 A 19-Mar-20 27-Mar-20 6600 100% Geotextile Laying (below +2.5m CD)
C5070 Rock Under Layer (Below +2.5m CD) 5 28-Mar-20 A 15-Dec-21 28-Mar-20 01-Apr-20 14726 98.51%
C5150 Armour Layer (below +2.5m CD) 5 21-May-20 A 15-Dec-21 21-May-20 25-May-20 15500 96.9%
C5160 Armour Layer at toe (below +2.5m CD) 5 21-May-20 A 15-Dec-21 21-May-20 25-May-20 15500 96.97%
C5510 Sand Slope Trimming (+2.5m~ +4m CD) 5 21-May-20 A 20-Dec-21 21-May-20 25-May-20 6900 97.67%
C5520 Geotextile Laying (+2.5m~ +4m CD) 5 22-May-20 A 20-Dec-21 26-May-20 30-May-20 6800 98.31%
C5530 Rock Under Layer (+2.5m~ +4m CD) 5 22-May-20 A 15-Dec-21 31-May-20 04-Jun-20 6800 98.29%
C5710 Armour Layer (+2.5m~ +4m CD) 12 24-Nov-20 A 15-Dec-21 01-Apr-21 12-Apr-21 8000 98.19%
C6060 Sand Slope Trimming (+4m~top CD) 12 21-Feb-21 A 26-Nov-21 13-Apr-21 24-Apr-21 6800 98.41%
C6070 Geotextile Laying (+4m~top CD) 12 25-Feb-21 A 26-Nov-21 25-Apr-21 06-May-21 6800 98.57%
C6080 Rock Under Layer (+4m~top CD) 12 28-Feb-21 A 27-Nov-21 07-May-21 18-May-21 6800 98.58%
C6250 Armour Layer (+4m~top CD) 12 02-Mar-21 A 25-Nov-21 19-May-21 30-May-21 8000 98.9%
Soil Improvemtn 213 25-Jan-21 A 15-Jul-21 A 29-Nov-20 16-Jun-21 105000 100%
C6240 Soil Improvement 20% 40 25-Jan-21 A 04-May-21 A 29-Nov-20 07-Jan-21 21000 100%
C7300 Soil Improvement 40% 40 07-May-21 A 16-May-21 A 08-Jan-21 16-Feb-21 21000 100%
C7840 Soil Improvement 60% 40 17-May-21 A 03-Jun-21 A 17-Feb-21 28-Mar-21 21000 100%
C8330 Soil Improvement 80% 40 04-Jun-21 A 09-Jun-21 A 29-Mar-21 07-May-21 21000 100%
C8760 Soil Improvement 100% 40 10-Jun-21 A 15-Jul-21 A 08-May-21 16-Jun-21 21000 100%
Marl Cap Installation 87 17-Jul-21 A 19-Dec-21 08-May-21 26-Jul-21 1040 97.94%
C8110 Marl Cap 50% 35 17-Jul-21 A 31-Aug-21 A 08-May-21 16-Jun-21 520 100%
C8780 Marl Cap 100% 30 01-Sep-21 A 19-Dec-21 17-Jun-21 26-Jul-21 520 91.11%
North Island Escape Jetty 208 08-May-21 A 01-Dec-21 02-Apr-21 28-Sep-21 1320 77.14%
C7750 Piles Installation 30 08-May-21 A 18-Jun-21 A 02-Apr-21 01-May-21 10 100%
C8140 Cross Beam Installation 30 14-Aug-21 A 23-Aug-21 A 01-Jun-21 30-Jun-21 210 100%
C8410 I-Beam Installation 13 11-Sep-21 A 21-Oct-21 A 01-Jul-21 30-Jul-21 300 100%
C8520 P/C Plank Installation 15 14-Sep-21 A 26-Oct-21 A 01-Jul-21 30-Jul-21 100 100%
C8660 Cast In-situ of Deck 15 24-Oct-21 A 09-Nov-21 A 01-Jul-21 30-Jul-21 400 100%
C8800 Facilities Installation 12 20-Nov-21 01-Dec-21 31-Jul-21 28-Sep-21 300 0%
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
Access Bridge 675 09-Feb-20 A 14-Jan-22 11-Mar-20 30-Oct-21 97080 72.94%
Access Bridge 675 09-Feb-20 A 14-Jan-22 11-Mar-20 30-Oct-21 97080 72.94%
Piles Installation 391 09-Feb-20 A 24-May-21 A 11-Mar-20 05-Apr-21 6250 100%
C2770 Piles Installation preparation 20 18-Feb-20 A 27-Feb-20 A 11-Mar-20 30-Mar-20 0 0% Piles Installation preparation
C3260 Piles Installation 100% 90 09-Feb-20 A 24-May-21 A 06-Jan-21 05-Apr-21 6250 100%
Cross Beam Installation 72 05-Jun-21 A 05-Aug-21 A 05-Feb-21 04-Jun-21 20800 100%
C3800 Cross Beam Construction 50% 55 05-Jun-21 A 30-Jun-21 A 05-Feb-21 05-Apr-21 10400 100%
C6880 Cross Beam Construction 100% 47 30-Jun-21 A 05-Aug-21 A 06-Apr-21 04-Jun-21 10400 100%
I-Beams Installation 38 21-Aug-21 A 07-Sep-21 A 06-Apr-21 30-Jun-21 21520 100%
C5200 I-Beam Installation 50% 17 21-Aug-21 A 30-Aug-21 A 06-Apr-21 18-May-21 10600 100%
C7610 I-Beam Installation 100% 14 31-Aug-21 A 07-Sep-21 A 19-May-21 30-Jun-21 10920 100%
Cast In-situ of Partition Wall 99 25-Sep-21 A 01-Jan-22 06-Apr-21 30-Jun-21 13440 13.38%
C5630 Cast In-situ of Partition Wall 50% 22 25-Sep-21 A 11-Dec-21 06-Apr-21 18-May-21 6720 26.76%
C7940 Cast In-situ of Partition Wall 100% 21 12-Dec-21 01-Jan-22 19-May-21 30-Jun-21 6720 0%
P/C Planks Installation 14 02-Sep-21 A 20-Oct-21 A 06-Apr-21 30-Jun-21 8400 100%
C6690 P/C Plank Installation 50% 11 02-Sep-21 A 15-Sep-21 A 06-Apr-21 18-May-21 4200 100%
C8420 P/C Plank Installation 100% 10 16-Sep-21 A 20-Oct-21 A 19-May-21 30-Jun-21 4200 100%
Decks Construction 80 25-Sep-21 A 13-Dec-21 06-Jun-21 01-Sep-21 24060 50%
C7960 Cast In-situ of Deck 50% 19 25-Sep-21 A 19-Nov-21 A 06-Jun-21 19-Jul-21 12030 100%
C8740 Cast In-situ of Deck 100% 15 29-Nov-21 13-Dec-21 20-Jul-21 01-Sep-21 12030 0%
Asphalt Surfacing 10 14-Dec-21 23-Dec-21 17-Sep-21 11-Oct-21 1050 0%
C8910 Asphalt Layer laying 10 14-Dec-21 23-Dec-21 17-Sep-21 11-Oct-21 1050 0%
Facilities Installation 56 20-Nov-21 14-Jan-22 05-Jul-21 30-Oct-21 1560 0%
A1000 Other Facilities Installation 10 24-Dec-21 02-Jan-22 20-Jul-21 28-Aug-21 0 0%
C8750 Expansion Joint 12 03-Jan-22 14-Jan-22 26-Sep-21 17-Oct-21 300 0%
C8920 Pipe Support 15 20-Nov-21 04-Dec-21 05-Jul-21 25-Sep-21 560 0%
C8930 Telecom/HV/LV Electric Support and Cable Tray 15 16-Dec-21 30-Dec-21 26-Sep-21 30-Oct-21 700 0%
Cathodic Protection 164 01-Aug-21 A 11-Jan-22 06-Feb-21 29-May-21 5500 15.91%
C3810 CP for Access Bridge 105 01-Aug-21 A 15-Dec-21 06-Feb-21 21-May-21 2500 35%
C8150 CP for Access NorthIsland Escape Jetty 26 17-Dec-21 11-Jan-22 04-May-21 29-May-21 1500 0%
C8470 CP for Access Sorth Island Escape Jetty 25 20-Nov-21 14-Dec-21 03-Mar-21 27-Mar-21 1500 0%
Pre-cast works ( South & North Island ) 385 05-Sep-19 A 15-Nov-20 A 10-Nov-19 28-Nov-20 163030 100% 15-Nov-20 A, Pre-cast works ( South & North
Precast Work 385 05-Sep-19 A 15-Nov-20 A 10-Nov-19 28-Nov-20 163030 100% 15-Nov-20 A, Precast Work
Precast Armour block 89 05-Sep-19 A 11-Jan-20 A 10-Nov-19 06-Feb-20 87750 100% 11-Jan-20 A, Precast Armour block
C2230 PrecastArmour Block 8% 12 05-Sep-19 A 13-Oct-19 A 13-Nov-19 24-Nov-19 6750 100% PrecastArmour Block 8%
C2280 PrecastArmour Block 16% 12 12-Oct-19 A 27-Oct-19 A 20-Dec-19 01-Jan-20 6750 100% PrecastArmour Block 16%
C2390 PrecastArmour Block 24% 12 27-Oct-19 A 30-Oct-19 A 06-Jan-20 18-Jan-20 6750 100% PrecastArmour Block 24%
C2750 PrecastArmour Block 32% 12 07-Nov-19 A 10-Nov-19 A 18-Dec-19 30-Dec-19 6750 100% PrecastArmour Block 32%
C3160 PrecastArmour Block 40% 12 30-Oct-19 A 08-Nov-19 A 25-Jan-20 06-Feb-20 6750 100% PrecastArmour Block 40%
C3680 PrecastArmour Block 48% 12 10-Nov-19 A 13-Dec-19 A 10-Nov-19 21-Nov-19 6750 100% PrecastArmour Block 48%
C4250 PrecastArmour Block 56% 12 22-Oct-19 A 26-Nov-19 A 22-Nov-19 03-Dec-19 6750 100% PrecastArmour Block 56%
C4780 PrecastArmour Block 64% 12 26-Nov-19 A 07-Dec-19 A 04-Dec-19 15-Dec-19 6750 100% PrecastArmour Block 64%
C5260 PrecastArmour Block 72% 12 06-Dec-19 A 13-Dec-19 A 16-Dec-19 27-Dec-19 6750 100% PrecastArmour Block 72%
C5810 PrecastArmour Block 80% 12 22-Dec-19 A 26-Dec-19 A 14-Dec-19 25-Dec-19 5750 100% PrecastArmour Block 80%
C6490 PrecastArmour Block 88% 12 26-Dec-19 A 29-Dec-19 A 26-Dec-19 06-Jan-20 6750 100% PrecastArmour Block 88%
C7020 PrecastArmour Block 96% 12 29-Dec-19 A 04-Jan-20 A 07-Jan-20 18-Jan-20 6750 100% PrecastArmour Block 96%
C7470 PrecastArmour Block 100% 12 04-Jan-20 A 11-Jan-20 A 19-Jan-20 30-Jan-20 7750 100% PrecastArmour Block 100%
Plank Precasting 120 04-Jan-20 A 20-Feb-20 A 12-Jan-20 11-May-20 17000 100% 20-Feb-20 A, Plank Precasting
C2740 Plank Precast 10% 15 04-Jan-20 A 12-Jan-20 A 12-Jan-20 27-Jan-20 1700 100% Plank Precast 10%
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
C3020 Plank Precast 20% 15 12-Jan-20 A 16-Jan-20 A 27-Jan-20 11-Feb-20 1700 100% Plank Precast 20%
C3490 Plank Precast 30% 15 13-Jan-20 A 17-Jan-20 A 02-Feb-20 16-Feb-20 1700 100% Plank Precast 30%
C3940 Plank Precast 40% 15 14-Jan-20 A 18-Jan-20 A 17-Feb-20 02-Mar-20 1700 100% Plank Precast 40%
C4350 Plank Precast 50% 15 19-Jan-20 A 26-Jan-20 A 03-Mar-20 17-Mar-20 1700 100% Plank Precast 50%
C4770 Plank Precast 60% 15 22-Jan-20 A 02-Feb-20 A 18-Mar-20 01-Apr-20 1700 100% Plank Precast 60%
C5090 Plank Precast 70% 15 01-Feb-20 A 07-Feb-20 A 16-Feb-20 01-Mar-20 1700 100% Plank Precast 70%
C5600 Plank Precast 80% 15 06-Feb-20 A 07-Feb-20 A 27-Apr-20 11-May-20 1700 100% Plank Precast 80%
C6140 Plank Precast 90% 15 06-Feb-20 A 12-Feb-20 A 23-Feb-20 08-Mar-20 1700 100% Plank Precast 90%
C6530 Plank Precast 100% 10 13-Feb-20 A 20-Feb-20 A 09-Mar-20 18-Mar-20 1700 100% Plank Precast 100%
I Beam Precasting 267 07-Mar-20 A 15-Nov-20 A 07-Mar-20 28-Nov-20 53280 100% 15-Nov-20 A, I Beam Precasting
C3690 I Beam Precast #1 8 07-Mar-20 A 31-Mar-20 A 07-Mar-20 14-Mar-20 4440 100% I Beam Precast #1
C3990 I Beam Precast #2 7 31-Mar-20 A 05-Apr-20 A 05-Apr-20 11-Apr-20 4440 100% I Beam Precast #2
C4220 I Beam Precast #3 7 06-Apr-20 A 24-Apr-20 A 11-Apr-20 17-Apr-20 4440 100% I Beam Precast #3
C4510 I Beam Precast #4 7 25-Apr-20 A 07-May-20 A 25-Apr-20 01-May-20 4440 100% I Beam Precast #4
C4650 I Beam Precast #5 6 07-May-20 A 15-May-20 A 09-May-20 14-May-20 4440 100% I Beam Precast #5
C4910 I Beam Precast #6 6 16-May-20 A 28-May-20 A 16-May-20 21-May-20 4440 100% I Beam Precast #6
C5140 I Beam Precast #7 20 06-May-20 A 16-Aug-20 A 06-Jun-20 25-Jun-20 4440 100% I Beam Precast #7
C5420 I Beam Precast #8 20 17-Aug-20 A 01-Sep-20 A 04-Sep-20 23-Sep-20 4440 100% I Beam Precast #8
C5770 I Beam Precast #9 20 01-Sep-20 A 19-Sep-20 A 20-Sep-20 09-Oct-20 4440 100% I Beam Precast #9
C5970 I Beam Precast #10 20 19-Sep-20 A 09-Oct-20 A 19-Sep-20 08-Oct-20 4440 100% I Beam Precast #10
C6320 I Beam Precast #11 25 10-Oct-20 A 16-Oct-20 A 10-Oct-20 03-Nov-20 4440 100% I Beam Precast #11
C6600 I Beam Precast #12 25 17-Oct-20 A 15-Nov-20 A 04-Nov-20 28-Nov-20 4440 100% I Beam Precast #12
Lighting Pole Foundation 30 05-Feb-20 A 29-Feb-20 A 23-Feb-20 24-Mar-20 5000 100% 29-Feb-20 A, Lighting Pole Foundation
C6870 Lighting Pole Foundation Precast 50% 15 05-Feb-20 A 20-Feb-20 A 23-Feb-20 09-Mar-20 2500 100% Lighting Pole Foundation Precast 50%
C7160 Lighting Pole Foundation Precast 100% 15 20-Feb-20 A 29-Feb-20 A 09-Mar-20 24-Mar-20 2500 100% Lighting Pole Foundation Precast 100%
Electrical 218 15-May-21 A 18-Dec-21 10-Oct-20 09-Nov-21 2720 43.77%
Lighting 218 15-May-21 A 18-Dec-21 10-Oct-20 09-Nov-21 2720 43.77%
C8000 Lighting Accessories Installation for South Island Causeway 30 15-May-21 A 28-May-21 A 10-Oct-20 08-Nov-20 1200 100%
C8310 Lighting Accessories Installation for KFIP Causeway Expansion 7 30-Nov-21 06-Dec-21 03-Nov-21 09-Nov-21 960 0%
C8830 Lighting Accessories Installation for Access Bridge 3 16-Dec-21 18-Dec-21 26-Sep-21 15-Oct-21 560 0%
Navigation Aids 383 01-Oct-20 A 29-Nov-20 A 29-Oct-20 15-Nov-21 7000 100% 29-Nov-20 A, Navigation Aids
C7310 Navigation Aids Installation for South Island 29 01-Oct-20 A 09-Oct-20 A 18-Oct-21 15-Nov-21 3500 100% Navigation Aids Installation for South Island
C7570 Navigation Aids Installation for North Island 30 10-Oct-20 A 29-Nov-20 A 29-Oct-20 27-Nov-20 3500 100% Navigation Aids Installation for North Island
Mechanical Completion 140 22-Aug-21 A 29-Jan-22 28-Nov-20 31-Dec-21 47320 21.6%
Clearing of Exception "Yes" Items 140 22-Aug-21 A 29-Jan-22 13-Dec-20 31-Dec-21 47320 21.6%
C7740 Clearning of Exception "Yes" Items At South Island 10 23-Aug-21 A 05-Sep-21 A 06-Apr-21 15-Apr-21 2520 100%
C7970 Clearning of Exception "Yes" Items At Navigation 10 22-Aug-21 A 25-Aug-21 A 13-Dec-20 22-Dec-20 700 100%
C8850 Clearning of Exception "Yes" Items At South Island Causeway 15 26-Sep-21 A 07-Nov-21 A 05-Apr-21 14-Apr-21 7000 100%
C8870 Clearning of Exception "Yes" Items At KFIP Causeway Expansion 6 31-Dec-21 05-Jan-22 10-Nov-21 19-Nov-21 3500 0%
C8890 Clearning of Exception "Yes" Items At North Island 10 20-Dec-21 29-Dec-21 27-Jul-21 05-Aug-21 14000 0%
C9000 Clearning of Exception "Yes" Items At Access Bridge 15 15-Jan-22 29-Jan-22 31-Oct-21 09-Nov-21 14000 0%
C9030 Clearning of Exception "Yes" Items At North & South Escape Jetty 13 03-Jan-22 15-Jan-22 13-Dec-21 31-Dec-21 5600 0%
Walkthrough and PMCC 66 20-Nov-21 24-Jan-22 28-Nov-20 22-Nov-21 0 0%
C7830 Walkthrough for Navigation Aids 15 20-Nov-21 04-Dec-21 28-Nov-20 12-Dec-20 0 0%
C8820 Walkthrough for South Island Causeway 15 20-Nov-21 04-Dec-21 19-Feb-21 05-Mar-21 0 0%
C8840 Walkthrough for KFIP Causeway Expansion 14 31-Dec-21 13-Jan-22 31-Oct-21 14-Nov-21 0 0%
C8860 Walkthrough for North Island 15 20-Dec-21 03-Jan-22 27-Jul-21 10-Aug-21 0 0%
C8960 Walkthrough for Access Bridge 10 15-Jan-22 24-Jan-22 31-Oct-21 09-Nov-21 0 0%
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
C9010 Walkthrough for North & South Escape Jetty 12 19-Dec-21 30-Dec-21 08-Nov-21 22-Nov-21 0 0%
PMCC 71 20-Nov-21 29-Jan-22 22-Dec-20 31-Dec-21 0 0%
C8010 PMCC for South Island 0 20-Nov-21 05-Apr-21 0 0%
C8460 PMCC for Navigation Aids 0 04-Dec-21 22-Dec-20 0 0%
C8940 PMCC for North Island 0 03-Jan-22 10-Aug-21 0 0%
C8970 PMCC for South Island Causeway 0 03-Jan-22 14-Apr-21 0 0%
C8980 PMCC for KFIP Causeway Expansion 0 13-Jan-22 14-Nov-21 0 0%
C9020 PMCC for Access Bridge 0 29-Jan-22 09-Nov-21 0 0%
C9040 PMCC for North & South Escape Jetty 0 29-Jan-22 31-Dec-21 0 0%
C9050 Final Mechanical Completion (FMCC) 0 29-Jan-22 31-Dec-21 0 0%
PROJECT CLOSE-OUT 145 08-Aug-21 A 31-Mar-22 13-Dec-20 31-Mar-22 11750 4.05%
Clearning of Exception "No" Items 92 08-Aug-21 A 06-Feb-22 13-Dec-20 10-Dec-21 1750 28.57%
O1000 Clearning of Exception "NO" Items At South Island 20 20-Nov-21 09-Dec-21 06-Apr-21 25-Apr-21 250 0%
O1010 Clearning of Exception "NO" Items At South Island Causeway 20 05-Dec-21 24-Dec-21 06-Mar-21 25-Mar-21 250 0%
O1020 Clearning of Exception "NO" Items At KFIP Causeway Expansion 10 14-Jan-22 23-Jan-22 15-Nov-21 04-Dec-21 250 0%
O1030 Clearning of Exception "NO" Items At North Island 20 08-Aug-21 A 16-Aug-21 A 11-Aug-21 30-Aug-21 250 100%
O1040 Clearning of Exception "NO" Items At Access Bridge 13 25-Jan-22 06-Feb-22 10-Nov-21 29-Nov-21 250 0%
O1050 Clearning of Exception "NO" Items At Navigation 20 26-Aug-21 A 31-Aug-21 A 13-Dec-20 01-Jan-21 250 100%
O1060 Clearning of Exception "NO" Items At North & South Escape Jetty 18 31-Dec-21 17-Jan-22 23-Nov-21 10-Dec-21 250 0%
Project Close-out 61 30-Jan-22 31-Mar-22 01-Jan-22 31-Mar-22 10000 0%
O1070 Facilities Demolition & Manpower Demobilization 1st Batch 20 30-Jan-22 18-Feb-22 01-Jan-22 25-Jan-22 2500 0%
O1080 Complete As-Built Drawing 12 07-Feb-22 18-Feb-22 01-Jan-22 23-Jan-22 1250 0%
O1090 Facilities Demolition & Manpower Demobilization 2nd Batch 15 19-Feb-22 05-Mar-22 26-Jan-22 19-Feb-22 2000 0%
O1100 Review Cycle of As-Built Drawing 13 19-Feb-22 03-Mar-22 24-Jan-22 15-Feb-22 1000 0%
O1110 Facilities Demolition & Manpower Demobilization 3rd Batch 15 04-Mar-22 18-Mar-22 16-Feb-22 09-Mar-22 2000 0%
O1120 Complete Project Record Books 13 19-Mar-22 31-Mar-22 10-Mar-22 31-Mar-22 1250 0%
Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone