Att 11updated Weekly Live Schedule 20 November 2021

This document provides a revised schedule for the Berri Drilling Island project from September 2018 through March 2022. It lists key milestones and activities for design and procurement, construction, and project mobilization and management. Some notable milestones include completing the 60% design review by June 2019, awarding all major purchase orders by September 2019, achieving site mobilization and commencing construction by June 2019, and final project completion and demobilization by March 2022. The schedule shows progress of key activities across 2019, 2020 and 2021 for this large offshore construction project in Saudi Arabia.

Uploaded by

Mohammed Misbah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
54 views12 pages

Att 11updated Weekly Live Schedule 20 November 2021

This document provides a revised schedule for the Berri Drilling Island project from September 2018 through March 2022. It lists key milestones and activities for design and procurement, construction, and project mobilization and management. Some notable milestones include completing the 60% design review by June 2019, awarding all major purchase orders by September 2019, achieving site mobilization and commencing construction by June 2019, and final project completion and demobilization by March 2022. The schedule shows progress of key activities across 2019, 2020 and 2021 for this large offshore construction project in Saudi Arabia.

Uploaded by

Mohammed Misbah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

 

BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021


Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021 1295 04-Sep-18 A 31-Mar-22 11-Sep-18 31-Mar-22 1378546 93.09%

MILESTONE 1294 04-Sep-18 A 30-Mar-22 11-Sep-18 31-Mar-22 0 0%

General 16 04-Sep-18 A 16-Sep-18 A 11-Sep-18 27-Sep-18 0 0% 16-Sep-18 A, General


M1000 Award of Contract 0 11-Sep-18 A 11-Sep-18 0 0% Award of Contract
M1010 Contract Effective 0 16-Sep-18 A 16-Sep-18 0 0% Contract Effective
M1020 Kick-Off Meeting 0 04-Sep-18 A 27-Sep-18 0 0% Kick-Off Meeting
Design and Procurement 424 16-Oct-18 A 01-Dec-19 A 11-Oct-18 12-Dec-19 0 0% 01-Dec-19 A, Design and Procurement
M1030 Complete CONTRACTOR Design Office Mobilization and Receive Approval 0 16-Oct-18 A 11-Oct-18 0 0% Complete CONTRACTOR Design Office Mobilization and Receive Approval
M1040 Submit Work Schedule 0 16-Nov-18 A 10-Nov-18 0 0% Submit Work Schedule
M1050 Complete Geotechnical Reports,Geophysical Reports,and Receive Approval 0 10-Nov-19 A 10-Nov-19 0 0% Complete Geotechnical Reports,Geophysical Reports,and Receive Approval
M1060 Complete 60% Design Review and Receive Approval 0 13-Jun-19 A 18-Jul-19 0 0% Complete 60% Design Review and Receive Approval
M1070 Award all Major POs 0 30-Sep-19 A 10-Nov-19 0 0% Award all Major POs
M1090 Complete 90% Design Review and Receive Approval 0 09-Nov-19 A 10-Nov-19 0 0% Complete 90% Design Review and Receive Approval
M1100 Award all POs for Bulk Materials 0 30-Jun-19 A 31-Jul-19 0 0% Award all POs for Bulk Materials
M1110 Receive Approval and Distribute Issued- for-Construction (IFC) Drawings and Related Documents
0 01-Dec-19 A 12-Dec-19 0 0% Receive Approval and Distribute Issued- for-Construction (IFC) Drawings and Relat
Construction 974 13-Jun-19 A 30-Mar-22 31-Jul-19 31-Mar-22 0 0%
M1080 Achieve Site Mobilization Completion and Commence Construction 0 13-Jun-19 A 31-Jul-19 0 0% Achieve Site Mobilization Completion and Commence Construction
M1120 Complete the Construction of the South Island 0 20-Nov-21 05-Apr-21 0 0%
M1130 Complete the construction of the North Island 0 03-Jan-22 10-Aug-21 0 0%
M1140 Complete the construction of the Access Bridge connecting to KFIP Causeway 0 29-Jan-22 09-Nov-21 0 0%
M1150 Final Mechanical Completion 0 29-Jan-22 31-Dec-21 0 0%
M1160 Provide Remaining Project Reocord Books and Other Required Documents including As-Building
0 Drawings 30-Mar-22 31-Mar-22 0 0%
M1170 Project Completion and Demobilization 0 30-Mar-22 31-Mar-22 0 0%
M1180 Project Close-out 0 30-Mar-22 31-Mar-22 0 0%
MOBILIZATION & MANAGEMENT 300 11-Sep-18 A 08-Jul-19 A 11-Sep-18 07-Jul-19 0 0% 08-Jul-19 A, MOBILIZATION & MANAGEMENT
MM1000 Kick-Off Meeting preparation 11 16-Sep-18 A 26-Sep-18 A 11-Sep-18 21-Sep-18 0 0% Kick-Off Meeting preparation
MM1010 Geotechnical Investigation Mobilization 30 27-Sep-18 A 02-Feb-19 A 11-Sep-18 10-Oct-18 0 0% Geotechnical Investigation Mobilization
MM1020 Design Office Mobilization 20 27-Sep-18 A 16-Oct-18 A 11-Sep-18 30-Sep-18 0 0% Design Office Mobilization
MM1030 Submit Work Schedule 50 27-Sep-18 A 15-Nov-18 A 11-Sep-18 30-Oct-18 0 0% Submit Work Schedule
MM1040 Land Use Permit Issue by Aramco 33 16-Sep-18 A 29-Oct-18 A 11-Sep-18 13-Oct-18 0 0% Land Use Permit Issue by Aramco
MM1050 Engineering Mobilization 17 11-Sep-18 A 27-Sep-18 A 11-Sep-18 27-Sep-18 0 0% Engineering Mobilization
MM1060 Major Equipment Mobilization on shore 20 30-Oct-18 A 07-May-19 A 11-Sep-18 30-Sep-18 0 0% Major Equipment Mobilization on shore
MM1070 Equipment mobilization for pipeline works 60 31-Mar-19 A 10-May-19 A 31-Mar-19 29-May-19 0 0% Equipment mobilization for pipeline works
MM1080 Major Equipment Mobilization for dredging -Stage 1 ( Clearance , permits -Outside kingdom100
) 01-Jan-19 A 18-Jun-19 A 01-Jan-19 10-Apr-19 0 0% Major Equipment Mobilization for dredging -Stage 1 ( Clearance , permits -Outside kingdom )
MM1090 Major Equipment Mobilization for dredging -Stage 2 ( Clearance ,mobilization , inspection - Inside
40 03-Feb-19
kingdom)A 08-Jul-19 A 29-May-19 07-Jul-19 0 0% Major Equipment Mobilization for dredging -Stage 2 ( Clearance ,mobilization , inspection - Inside
ENGINEERING 455 14-Oct-18 A 01-Dec-19 A 11-Sep-18 12-Dec-19 19500 100% 01-Dec-19 A, ENGINEERING

60% Design Package 236 14-Oct-18 A 01-Oct-19 A 11-Sep-18 06-Aug-19 16130 100% 01-Oct-19 A, 60% Design Package
General 236 14-Oct-18 A 16-Jun-19 A 11-Sep-18 06-Aug-19 2500 100% 16-Jun-19 A, General
E1000 Drawing Control List 10 14-Oct-18 A 16-Jun-19 A 11-Sep-18 24-Sep-18 100 100% Drawing Control List
E1010 Scope Of Work 20 01-Nov-18 A 16-Jun-19 A 11-Sep-18 08-Oct-18 100 100% Scope Of Work
E1020 General Arrangement 15 01-Nov-18 A 20-May-19 A 11-Sep-18 01-Oct-18 100 100% General Arrangement
E1080 Site Location Plan 5 11-Dec-18 A 17-Dec-18 A 31-Jul-19 06-Aug-19 50 100% Site Location Plan
E1090 Feed Verification Report 15 11-Nov-18 A 13-Jun-19 A 09-Oct-18 29-Oct-18 400 100% Feed Verification Report
E1100 Metocean Studies Report 20 11-Nov-18 A 13-Jun-19 A 09-Oct-18 05-Nov-18 400 100% Metocean Studies Report
E1110 Basis Of Design 18 11-Nov-18 A 13-Jun-19 A 09-Oct-18 01-Nov-18 400 100% Basis Of Design
E1120 Scope Of Work For Early Pkg. 10 19-May-19 A 16-Jun-19 A 02-Jun-19 13-Jun-19 100 100% Scope Of Work For Early Pkg.
E1130 General Notes 19 01-Dec-18 A 13-Jun-19 A 09-Oct-18 04-Nov-18 150 100% General Notes

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
 
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
E1140 Durability Study 25 01-Dec-18 A 13-Jun-19 A 09-Oct-18 12-Nov-18 400 100% Durability Study
E1340 Specification For Concrete For Marine Works 15 01-Dec-18 A 13-Jun-19 A 16-Jan-19 05-Feb-19 100 100% Specification For Concrete For Marine Works
E1360 Specification For Steelwork 15 05-Dec-18 A 13-Jun-19 A 16-Dec-18 03-Jan-19 200 100% Specification For Steelwork
Survey 186 28-Oct-18 A 01-Oct-19 A 11-Oct-18 27-Jun-19 1600 100% 01-Oct-19 A, Survey
Bathymetric & Topographic 100 05-Feb-19 A 13-Jun-19 A 05-Feb-19 24-Jun-19 400 100% 13-Jun-19 A, Bathymetric & Topographic
E1190 Layout Plan 5 29-Apr-19 A 13-Jun-19 A 16-Jun-19 20-Jun-19 100 100% Layout Plan
E1230 Specification 15 05-Feb-19 A 20-May-19 A 05-Feb-19 25-Feb-19 200 100% Specification
E1390 Detailed Drawing 15 30-Apr-19 A 13-Jun-19 A 04-Jun-19 24-Jun-19 100 100% Detailed Drawing
Geotechnical 186 28-Oct-18 A 01-Oct-19 A 11-Oct-18 27-Jun-19 1200 100% 01-Oct-19 A, Geotechnical
E1040 Specification For Geotechnical Invigation 5 28-Oct-18 A 31-Mar-19 A 11-Oct-18 17-Oct-18 200 100% Specification For Geotechnical Invigation
E1070 Geotechnical Report Preparation and Submission 18 12-Feb-19 A 16-Jun-19 A 07-Mar-19 01-Apr-19 1000 100% Geotechnical Report Preparation and Submission
E1310 Review & Approval Cycle of Geotechnical Report 20 02-Jun-19 A 01-Oct-19 A 02-Jun-19 27-Jun-19 0 0% Review & Approval Cycle of Geotechnical Report
Demolition 13 01-Dec-18 A 24-May-19 A 06-Nov-18 22-Nov-18 200 100% 24-May-19 A, Demolition
E1380 Layout Plan 8 01-Dec-18 A 19-May-19 A 06-Nov-18 15-Nov-18 150 100% Layout Plan
E1430 Detailed Drawing 5 01-Dec-18 A 24-May-19 A 18-Nov-18 22-Nov-18 50 100% Detailed Drawing
Dredging & Reclamation 36 15-Nov-18 A 13-Jun-19 A 09-Oct-18 27-Nov-18 1850 100% 13-Jun-19 A, Dredging & Reclamation
E1150 Layout Plan 7 15-Nov-18 A 13-Jun-19 A 09-Oct-18 17-Oct-18 600 100% Layout Plan
E1250 Specification 7 20-Nov-18 A 13-Jun-19 A 18-Oct-18 28-Oct-18 600 100% Specification
E1320 Design report 10 01-Dec-18 A 13-Jun-19 A 29-Oct-18 11-Nov-18 300 100% Design report
E1400 Detailed Drawing 11 01-Dec-18 A 13-Jun-19 A 13-Nov-18 27-Nov-18 350 100% Detailed Drawing
Revetment 28 20-Nov-18 A 25-Jun-19 A 16-Oct-18 22-Nov-18 1450 100% 25-Jun-19 A, Revetment
E1210 Layout Plan 5 20-Nov-18 A 27-May-19 A 16-Oct-18 22-Oct-18 400 100% Layout Plan
E1260 Specification 7 25-Dec-18 A 25-Jun-19 A 23-Oct-18 31-Oct-18 400 100% Specification
E1330 Design report 8 01-Dec-18 A 13-Jun-19 A 01-Nov-18 12-Nov-18 300 100% Design report
E1420 Detailed Drawing 8 01-Dec-18 A 26-May-19 A 13-Nov-18 22-Nov-18 350 100% Detailed Drawing
Access Bridge 40 01-Nov-18 A 13-Jun-19 A 02-Oct-18 26-Nov-18 2050 100% 13-Jun-19 A, Access Bridge
E1050 Layout Plan 5 01-Nov-18 A 21-May-19 A 02-Oct-18 08-Oct-18 700 100% Layout Plan
E1160 Design report 10 10-Nov-18 A 27-May-19 A 09-Oct-18 22-Oct-18 600 100% Design report
E1270 Detailed Drawing 25 10-Nov-18 A 13-Jun-19 A 23-Oct-18 26-Nov-18 750 100% Detailed Drawing
Road 35 01-Nov-18 A 13-Jun-19 A 25-Sep-18 12-Nov-18 2900 100% 13-Jun-19 A, Road
E1030 Layout Plan 5 01-Nov-18 A 27-May-19 A 25-Sep-18 01-Oct-18 1600 100% Layout Plan
E1060 Specification 8 05-Nov-18 A 13-Jun-19 A 02-Oct-18 11-Oct-18 200 100% Specification
E1200 Design report 7 15-Nov-18 A 13-Jun-19 A 14-Oct-18 22-Oct-18 300 100% Design report
E1280 Detailed Drawing 15 15-Nov-18 A 13-Jun-19 A 23-Oct-18 12-Nov-18 800 100% Detailed Drawing
Lighting 25 11-Nov-18 A 13-Jun-19 A 09-Oct-18 12-Nov-18 650 100% 13-Jun-19 A, Lighting
E1170 Layout Plan 5 11-Nov-18 A 14-May-19 A 09-Oct-18 15-Oct-18 250 100% Layout Plan
E1220 Design report 5 20-Nov-18 A 12-Jun-19 A 16-Oct-18 22-Oct-18 300 100% Design report
E1290 Detailed Drawing 15 20-Nov-18 A 13-Jun-19 A 23-Oct-18 12-Nov-18 100 100% Detailed Drawing
Cathodic Protection 14 06-Jan-19 A 12-Jun-19 A 24-Feb-19 13-Mar-19 200 100% 12-Jun-19 A, Cathodic Protection
E1350 Specification 14 06-Jan-19 A 12-Jun-19 A 24-Feb-19 13-Mar-19 200 100% Specification
Fence & Wave Wall 10 01-Dec-18 A 12-Jun-19 A 23-Oct-18 05-Nov-18 200 100% 12-Jun-19 A, Fence & Wave Wall
E1300 Layout Plan 10 01-Dec-18 A 12-Jun-19 A 23-Oct-18 05-Nov-18 200 100% Layout Plan
Escape Jetty 34 10-Nov-18 A 12-Jun-19 A 09-Oct-18 25-Nov-18 2150 100% 12-Jun-19 A, Escape Jetty
E1180 Layout Plan 5 10-Nov-18 A 19-May-19 A 09-Oct-18 15-Oct-18 400 100% Layout Plan
E1240 Specification 14 15-Nov-18 A 12-Jun-19 A 16-Oct-18 04-Nov-18 600 100% Specification
E1370 Design report 5 01-Dec-18 A 19-May-19 A 05-Nov-18 11-Nov-18 300 100% Design report
E1410 Detailed Drawing 10 01-Dec-18 A 12-Jun-19 A 12-Nov-18 25-Nov-18 850 100% Detailed Drawing
Review & Approval Cycle of 60% Design Package 41 03-Feb-19 A 16-Jun-19 A 11-Jun-19 06-Aug-19 380 100% 16-Jun-19 A, Review & Approval Cycle of 60% Design Package
E1440 Submission of 60% design review package 3 03-Feb-19 A 02-Apr-19 A 11-Jun-19 13-Jun-19 30 100% Submission of 60% design review package

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
 
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
E1450 Review of 60% design package by Client and receipt of comments 15 21-Mar-19 A 06-May-19 A 08-Jul-19 28-Jul-19 0 0% Review of 60% design package by Client and receipt of comments
E1490 Comments incorporation 7 22-Mar-19 A 16-Jun-19 A 29-Jul-19 06-Aug-19 300 100% Comments incorporation
E1530 Workshop with client to discuss comments and obtain approval 9 21-Apr-19 A 19-May-19 A 07-Jul-19 18-Jul-19 50 100% Workshop with client to discuss comments and obtain approval
GSD Survey Outcomes 30 05-May-19 A 13-Jun-19 A 31-Jul-19 29-Aug-19 0 0% 13-Jun-19 A, GSD Survey Outcomes
GS1000 Revision of partial 60% design drawings 30 05-May-19 A 13-Jun-19 A 31-Jul-19 29-Aug-19 0 0% Revision of partial 60% design drawings
90% Design Package 114 28-Nov-18 A 09-Nov-19 A 12-Jun-19 18-Nov-19 3150 100% 09-Nov-19 A, 90% Design Package
Dredging & Reclamation 15 28-Nov-18 A 20-Jun-19 A 07-Jul-19 25-Jul-19 50 100% 20-Jun-19 A, Dredging & Reclamation
E1500 Navigation Aids - Typical Detail 15 28-Nov-18 A 20-Jun-19 A 07-Jul-19 25-Jul-19 50 100% Navigation Aids - Typical Detail
Lighting 15 03-Feb-19 A 02-Jun-19 A 16-Jun-19 04-Jul-19 200 100% 02-Jun-19 A, Lighting
E1470 Specification 15 03-Feb-19 A 02-Jun-19 A 16-Jun-19 04-Jul-19 200 100% Specification
Cathodic Protection 48 18-May-19 A 15-Sep-19 A 12-Jun-19 18-Aug-19 2050 100% 15-Sep-19 A, Cathodic Protection
E1460 Layout Plan 5 18-May-19 A 28-Jul-19 A 12-Jun-19 18-Jun-19 700 100% Layout Plan
E1480 Design report 7 20-May-19 A 04-Aug-19 A 07-Aug-19 15-Aug-19 900 100% Design report
E1520 Detailed Drawing 8 16-Jun-19 A 15-Sep-19 A 07-Aug-19 18-Aug-19 450 100% Detailed Drawing
Fence & Wave Wall 28 03-Feb-19 A 30-Sep-19 A 03-Jul-19 11-Aug-19 400 100% 30-Sep-19 A, Fence & Wave Wall
E1510 Design report 10 01-May-19 A 24-Sep-19 A 03-Jul-19 16-Jul-19 300 100% Design report
E1540 Detailed Drawing 10 03-Feb-19 A 30-Sep-19 A 29-Jul-19 11-Aug-19 100 100% Detailed Drawing
Missalaneous (If Any ) 7 02-Jun-19 A 03-Jun-19 A 07-Aug-19 15-Aug-19 100 100% 03-Jun-19 A, Missalaneous (If Any )
E1550 Missalaneous items - (If any ) 7 02-Jun-19 A 03-Jun-19 A 07-Aug-19 15-Aug-19 100 100% Missalaneous items - (If any )
Review & Approval Cycle of 90% Design 107 15-Jun-19 A 09-Nov-19 A 23-Jun-19 18-Nov-19 350 100% 09-Nov-19 A, Review & Approval Cycle of 90% Design
E1560 Submission of 90% design review package 3 15-Jun-19 A 16-Jun-19 A 23-Jun-19 25-Jun-19 30 100% Submission of 90% design review package
E1570 Review of 90% design package by Client and receipt of comments 10 23-Jun-19 A 02-Sep-19 A 26-Jun-19 09-Jul-19 150 100% Review of 90% design package by Client and receipt of comments
E1580 Comments in-corporation 10 30-Jun-19 A 15-Oct-19 A 11-Aug-19 22-Aug-19 70 100% Comments in-corporation
E1590 Workshop with client to discuss comments and obtain approval 15 29-Oct-19 A 09-Nov-19 A 29-Oct-19 18-Nov-19 100 100% Workshop with client to discuss comments and obtain approval
Issue 100% IFC(Issue for Construction) Drawing 186 06-Jun-19 A 01-Dec-19 A 06-Jun-19 12-Dec-19 220 100% 01-Dec-19 A, Issue 100% IFC(Issue for Construction) Drawing
Review Cycle of IFC 186 06-Jun-19 A 01-Dec-19 A 06-Jun-19 12-Dec-19 220 100% 01-Dec-19 A, Review Cycle of IFC
A1010 Submission & Approval of Early IFC ( Land filling & preparation ) 10 06-Jun-19 A 12-Jun-19 A 06-Jun-19 16-Jun-19 0 0% Submission & Approval of Early IFC ( Land filling & preparation )
E1600 100% Submission of IFC 9 04-Nov-19 A 23-Nov-19 A 10-Nov-19 20-Nov-19 30 100% 100% Submission of IFC
E1610 100%- Client Review of IFC 8 01-Jul-19 A 24-Nov-19 A 21-Nov-19 02-Dec-19 150 100% 100%- Client Review of IFC
E1620 100%- Receipt of Approval from Client 8 26-Nov-19 A 01-Dec-19 A 03-Dec-19 12-Dec-19 40 100% 100%- Receipt of Approval from Client
PROCUREMENT 837 01-Oct-18 A 28-Nov-21 11-Oct-18 15-Oct-20 14000 98.64%

Steel Tubular Pipe 397 27-Nov-18 A 12-Mar-20 A 22-Nov-18 29-Feb-20 1000 100% 12-Mar-20 A, Steel Tubular Pipe
P1110 Issue RFQ, 15 27-Nov-18 A 10-Dec-18 A 22-Nov-18 10-Dec-18 100 100% Issue RFQ,
P1240 Tender Bid Evaluation 25 03-Mar-19 A 08-Mar-19 A 18-Jun-19 17-Jul-19 150 100% Tender Bid Evaluation
P1490 Award PO 3 13-Jun-19 A 17-Jul-19 A 13-Jun-19 17-Jun-19 150 100% Award PO
P1510 Completion of NMR 601 7 21-Jul-19 A 22-Jul-19 A 17-Jun-19 25-Jun-19 100 100% Completion of NMR 601
P1520 Completion of NMR 602 7 25-Jun-19 A 25-Jun-19 A 25-Jun-19 03-Jul-19 100 100% Completion of NMR 602
P1580 Delivery To Site 100% 20 04-Jan-20 A 12-Mar-20 A 05-Jan-20 28-Jan-20 300 100% Delivery To Site 100%
P1760 Receipt of Final NMR 603 3 20-Feb-20 A 06-Mar-20 A 26-Feb-20 29-Feb-20 100 100% Receipt of Final NMR 603
Concrete 483 29-Nov-18 A 28-Nov-21 22-Nov-18 22-Mar-20 1000 99.75%
P1100 Issue RFQ, 15 29-Nov-18 A 24-Dec-18 A 22-Nov-18 10-Dec-18 100 100% Issue RFQ,
P1230 Tender Bid Evaluation 15 12-Feb-19 A 19-Feb-19 A 14-May-19 01-Jun-19 150 100% Tender Bid Evaluation
P1430 Award PO 27 07-Jul-19 A 03-Sep-19 A 31-Jul-19 31-Aug-19 150 100% Award PO
P1500 Delivery To Site 1st Batch 30 05-Sep-19 A 06-Sep-19 A 16-Sep-19 20-Oct-19 250 100% Delivery To Site 1st Batch
P1530 Receipt of Final NMR 603 20 05-Sep-19 A 06-Sep-19 A 21-Oct-19 12-Nov-19 100 100% Receipt of Final NMR 603
P1540 Delivery To Site 100% 100 14-Dec-19 A 28-Nov-21 14-Dec-19 22-Mar-20 250 99%
Reinforcement 485 27-Nov-18 A 07-Feb-20 A 22-Nov-18 24-Mar-20 1000 100% 07-Feb-20 A, Reinforcement
P1120 Issue RFQ, 15 27-Nov-18 A 02-Dec-18 A 22-Nov-18 10-Dec-18 100 100% Issue RFQ,

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
 
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
P1250 Tender Bid Evaluation 15 09-Feb-19 A 25-Feb-19 A 10-Jun-19 27-Jun-19 150 100% Tender Bid Evaluation
P1440 Award PO 3 07-May-19 A 11-May-19 A 13-Jun-19 17-Jun-19 150 100% Award PO
P1480 Delivery To Site 1st Batch 80 21-Oct-19 A 03-Nov-19 A 20-Oct-19 20-Jan-20 250 100% Delivery To Site 1st Batch
P1740 Receipt of Final NMR 603 8 03-Nov-19 A 09-Nov-19 A 03-Nov-19 12-Nov-19 100 100% Receipt of Final NMR 603
P1750 Delivery To Site 100% 90 10-Nov-19 A 07-Feb-20 A 26-Dec-19 24-Mar-20 250 100% Delivery To Site 100%
Geotextile 451 01-Oct-18 A 26-Dec-19 A 31-Oct-18 28-Jan-20 1000 100% 26-Dec-19 A, Geotextile
P1080 Issue RFQ, 15 01-Oct-18 A 18-Dec-18 A 31-Oct-18 18-Nov-18 100 100% Issue RFQ,
P1210 Tender Bid Evaluation 15 13-Feb-19 A 16-Feb-19 A 29-Apr-19 16-May-19 150 100% Tender Bid Evaluation
P1410 Award PO 3 21-Mar-19 A 25-Mar-19 A 13-May-19 16-May-19 150 100% Award PO
P1460 Delivery To Site 1st Batch 50 26-Mar-19 A 26-Jul-19 A 01-Jul-19 28-Aug-19 250 100% Delivery To Site 1st Batch
P1610 Receipt of Final NMR 603 7 06-Sep-19 A 08-Sep-19 A 31-Jul-19 07-Aug-19 100 100% Receipt of Final NMR 603
P1620 Delivery To Site 100% 80 20-Sep-19 A 26-Dec-19 A 10-Nov-19 28-Jan-20 250 100% Delivery To Site 100%
Steel Road Barrier 333 08-Jan-19 A 07-Feb-20 A 31-Jan-19 24-Feb-20 1000 100% 07-Feb-20 A, Steel Road Barrier
P1010 Issue RFQ, 15 08-Jan-19 A 20-Jan-19 A 31-Jan-19 18-Feb-19 100 100% Issue RFQ,
P1140 Tender Bid Evaluation 15 23-May-19 A 23-May-19 A 02-Jul-19 20-Jul-19 150 100% Tender Bid Evaluation
P1270 Award PO 3 14-Jul-19 A 14-Jul-19 A 25-Jun-19 29-Jun-19 150 100% Award PO
P1340 Delivery To Site 100% 10 23-Jan-20 A 05-Feb-20 A 13-Feb-20 24-Feb-20 500 100% Delivery To Site 100%
P1840 Receipt of Final NMR 603 3 06-Feb-20 A 07-Feb-20 A 12-Feb-20 15-Feb-20 100 100% Receipt of Final NMR 603
Expansion Joint for Bridge 306 11-Apr-19 A 03-Apr-20 A 11-Apr-19 02-Apr-20 1000 100% 03-Apr-20 A, Expansion Joint for Bridge
P1090 Issue RFQ, 15 11-Apr-19 A 29-Apr-19 A 11-Apr-19 29-Apr-19 100 100% Issue RFQ,
P1220 Tender Bid Evaluation 15 26-May-19 A 30-Jun-19 A 13-Jun-19 01-Jul-19 150 100% Tender Bid Evaluation
P1420 Award PO 3 22-Jul-19 A 28-Jul-19 A 01-Jul-19 04-Jul-19 150 100% Award PO
P1470 Completion of NMR 601 20 28-Jul-19 A 28-Jul-19 A 04-Jul-19 28-Jul-19 100 100% Completion of NMR 601
P1590 Completion of NMR 602 20 28-Jul-19 A 28-Jul-19 A 28-Jul-19 20-Aug-19 100 100% Completion of NMR 602
P1700 Delivery To Site 100% 4 28-Mar-20 A 30-Mar-20 A 28-Mar-20 31-Mar-20 300 100% Delivery To Site 100%
P1830 Receipt of Final NMR 603 2 30-Mar-20 A 03-Apr-20 A 01-Apr-20 02-Apr-20 100 100% Receipt of Final NMR 603
Navigation Aids 475 06-Jan-19 A 22-Aug-20 A 17-Feb-19 24-Aug-20 1000 100% 22-Aug-20 A, Navigation Aids
P1050 Issue RFQ, 15 06-Jan-19 A 21-Jan-19 A 17-Feb-19 06-Mar-19 100 100% Issue RFQ,
P1180 Tender Bid Evaluation 15 22-Mar-19 A 04-Apr-19 A 03-Jul-19 21-Jul-19 150 100% Tender Bid Evaluation
P1310 Award PO 3 03-Jun-19 A 05-Jun-19 A 03-Jul-19 07-Jul-19 150 100% Award PO
P1380 Completion of NMR 601 24 05-Jun-19 A 05-Jun-19 A 07-Jul-19 04-Aug-19 100 100% Completion of NMR 601
P1550 Completion of NMR 602 24 05-Jun-19 A 05-Jun-19 A 04-Aug-19 01-Sep-19 100 100% Completion of NMR 602
P1640 Delivery To Site 100% 8 20-Aug-20 A 21-Aug-20 A 15-Aug-20 23-Aug-20 300 100% Delivery To Site 100%
P1800 Receipt of Final NMR 603 1 21-Aug-20 A 22-Aug-20 A 24-Aug-20 24-Aug-20 100 100% Receipt of Final NMR 603
Lighting 401 12-Dec-18 A 04-May-20 A 06-Mar-19 16-Jun-20 1000 100% 04-May-20 A, Lighting
P1020 Issue RFQ, 7 12-Dec-18 A 20-Dec-18 A 06-Mar-19 14-Mar-19 100 100% Issue RFQ,
P1150 Tender Bid Evaluation 10 26-Feb-19 A 01-Mar-19 A 16-Jul-19 28-Jul-19 150 100% Tender Bid Evaluation
P1280 Award PO 9 28-Jul-19 A 28-Jul-19 A 04-Jul-19 15-Jul-19 150 100% Award PO
P1350 Completion of NMR 601 25 28-Jul-19 A 28-Jul-19 A 15-Jul-19 13-Aug-19 100 100% Completion of NMR 601
P1560 Completion of NMR 602 25 28-Jul-19 A 28-Jul-19 A 13-Aug-19 12-Sep-19 100 100% Completion of NMR 602
P1660 Delivery To Site 100% 8 08-Jan-20 A 02-May-20 A 24-Feb-20 04-Mar-20 300 100% Delivery To Site 100%
P1790 Receipt of Final NMR 603 2 03-May-20 A 04-May-20 A 15-Jun-20 16-Jun-20 100 100% Receipt of Final NMR 603
Cathodic protection 499 02-Dec-18 A 03-Jun-20 A 21-Nov-18 25-Jun-20 1000 100% 03-Jun-20 A, Cathodic protection
P1030 Issue RFQ, 15 02-Dec-18 A 09-Dec-18 A 21-Nov-18 09-Dec-18 100 100% Issue RFQ,
P1160 Tender Bid Evaluation 15 17-Apr-19 A 18-Jul-19 A 19-Jun-19 07-Jul-19 150 100% Tender Bid Evaluation
P1290 Award PO 3 21-Jul-19 A 24-Jul-19 A 07-Jul-19 10-Jul-19 150 100% Award PO
P1360 Completion of NMR 601 30 24-Jul-19 A 24-Jul-19 A 10-Jul-19 14-Aug-19 100 100% Completion of NMR 601
P1600 Completion of NMR 602 20 12-Oct-19 A 18-Oct-19 A 01-Oct-19 23-Oct-19 100 100% Completion of NMR 602

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
 
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
P1650 Delivery To Site 100% 15 30-Jan-20 A 01-Jun-20 A 13-Feb-20 01-Mar-20 300 100% Delivery To Site 100%
P1770 Receipt of Final NMR 603 3 02-Jun-20 A 03-Jun-20 A 23-Jun-20 25-Jun-20 100 100% Receipt of Final NMR 603
Escape Jetty Facilities 391 08-Jan-19 A 22-May-20 A 24-Feb-19 25-May-20 1000 100% 22-May-20 A, Escape Jetty Facilities
P1040 Issue RFQ, 15 08-Jan-19 A 20-Jan-19 A 24-Feb-19 13-Mar-19 100 100% Issue RFQ,
P1170 Tender Bid Evaluation 15 28-May-19 A 03-Jun-19 A 19-Jun-19 07-Jul-19 150 100% Tender Bid Evaluation
P1300 Award PO 3 05-Jun-19 A 06-Jun-19 A 07-Jul-19 10-Jul-19 150 100% Award PO
P1370 Completion of NMR 601 20 28-Jul-19 A 30-Jul-19 A 31-Jul-19 22-Aug-19 100 100% Completion of NMR 601
P1570 Completion of NMR 602 20 17-Oct-19 A 09-Nov-19 A 13-Oct-19 04-Nov-19 100 100% Completion of NMR 602
P1670 Delivery To Site 100% 6 03-May-20 A 21-May-20 A 02-May-20 07-May-20 300 100% Delivery To Site 100%
P1850 Receipt of Final NMR 603 3 21-May-20 A 22-May-20 A 23-May-20 25-May-20 100 100% Receipt of Final NMR 603
Rocks 575 02-Dec-18 A 02-May-20 A 31-Oct-18 31-May-20 1000 100% 02-May-20 A, Rocks
P1070 Issue RFQ, 15 02-Dec-18 A 09-Dec-18 A 31-Oct-18 18-Nov-18 100 100% Issue RFQ,
P1200 Tender Bid Evaluation 15 25-Apr-19 A 28-Apr-19 A 24-Jun-19 11-Jul-19 150 100% Tender Bid Evaluation
P1400 Award PO 3 15-May-19 A 16-May-19 A 18-Jul-19 22-Jul-19 150 100% Award PO
P1450 Delivery To Site 1st Batch 51 14-Jul-19 A 28-Jul-19 A 11-Jul-19 09-Sep-19 250 100% Delivery To Site 1st Batch
P1680 Receipt of Final NMR 603 8 05-Sep-19 A 24-Sep-19 A 31-Jul-19 10-Aug-19 100 100% Receipt of Final NMR 603
P1690 Delivery To Site 100% 170 18-Sep-19 A 02-May-20 A 14-Dec-19 31-May-20 250 100% Delivery To Site 100%
Road-asphalt 720 09-Dec-18 A 23-Nov-21 11-Oct-18 15-Oct-20 1000 81.25%
P1060 Issue RFQ, 15 09-Dec-18 A 23-Dec-18 A 11-Oct-18 29-Oct-18 100 100% Issue RFQ,
P1190 Tender Bid Evaluation 15 05-May-19 A 07-Jul-19 A 02-Jul-19 20-Jul-19 150 100% Tender Bid Evaluation
P1320 Award PO 40 25-Aug-19 A 21-Oct-19 A 31-Jul-19 15-Sep-19 150 100% Award PO
P1390 Delivery To Site 100% 4 29-Jan-21 A 23-Nov-21 10-Oct-20 13-Oct-20 500 62.5%
P1820 Receipt of Final NMR 603 2 27-Jan-21 A 30-Jan-21 A 14-Oct-20 15-Oct-20 100 100% Receipt of Final NMR 603
Road-base Course 439 09-Dec-18 A 17-Jan-20 A 11-Oct-18 07-Mar-20 1000 100% 17-Jan-20 A, Road-base Course
P1000 Issue RFQ, 15 09-Dec-18 A 23-Dec-18 A 11-Oct-18 29-Oct-18 100 100% Issue RFQ,
P1130 Tender Bid Evaluation 15 05-May-19 A 10-May-19 A 02-Jul-19 20-Jul-19 150 100% Tender Bid Evaluation
P1260 Award PO 3 15-May-19 A 16-May-19 A 20-Jul-19 23-Jul-19 150 100% Award PO
P1330 Delivery To Site 100% 28 22-Dec-19 A 16-Jan-20 A 01-Feb-20 04-Mar-20 500 100% Delivery To Site 100%
P1810 Receipt of Final NMR 603 2 16-Jan-20 A 17-Jan-20 A 04-Mar-20 07-Mar-20 100 100% Receipt of Final NMR 603
Marl 425 02-Dec-18 A 17-Jan-20 A 28-Oct-18 07-Mar-20 1000 100% 17-Jan-20 A, Marl
P1630 Issue RFQ, 15 02-Dec-18 A 09-Dec-18 A 28-Oct-18 14-Nov-18 100 100% Issue RFQ,
P1710 Tender Bid Evaluation 12 17-Apr-19 A 18-Apr-19 A 03-Jul-19 17-Jul-19 150 100% Tender Bid Evaluation
P1720 Award PO 3 07-May-19 A 10-May-19 A 17-Jul-19 21-Jul-19 150 100% Award PO
P1730 Delivery To Site 1st Batch 30 22-Dec-19 A 26-Dec-19 A 28-Jan-20 03-Mar-20 500 100% Delivery To Site 1st Batch
P1780 Receipt of Final NMR 603 3 17-Jan-20 A 17-Jan-20 A 03-Mar-20 07-Mar-20 100 100% Receipt of Final NMR 603
CONSTRUCTION 1214 19-Nov-18 A 29-Jan-22 01-Oct-18 31-Dec-21 1333296 93.71%

Temporary Facilities 330 19-Nov-18 A 14-Sep-19 A 01-Oct-18 29-Aug-19 52720 100% 14-Sep-19 A, Temporary Facilities
Site Preperation 15 19-Nov-18 A 20-Jan-19 A 01-Oct-18 15-Oct-18 5000 100% 20-Jan-19 A, Site Preperation
C2020 Leveling/Compaction for Laydown Area 15 19-Nov-18 A 20-Jan-19 A 01-Oct-18 15-Oct-18 5000 100% Leveling/Compaction for Laydown Area
Temporary Fence & Road 119 25-Nov-18 A 27-Apr-19 A 16-Oct-18 11-Feb-19 5000 100% 27-Apr-19 A, Temporary Fence & Road
C2030 Temporary Road 15 10-Dec-18 A 13-Feb-19 A 16-Oct-18 30-Oct-18 3000 100% Temporary Road
C2050 Temporary Fence 7 25-Nov-18 A 27-Apr-19 A 05-Feb-19 11-Feb-19 2000 100% Temporary Fence
Temporary Building 25 10-Jan-19 A 19-Mar-19 A 27-Feb-19 24-Mar-19 16720 100% 19-Mar-19 A, Temporary Building
C2060 SAPMTSite Office Installation 25 02-Feb-19 A 17-Feb-19 A 27-Feb-19 24-Mar-19 9000 100% SAPMTSite Office Installation
C2070 CONTRACTOR Site Office Installation 25 15-Feb-19 A 13-Mar-19 A 27-Feb-19 24-Mar-19 1360 100% CONTRACTOR Site Office Installation
C2080 Warehouse Construction 15 19-Feb-19 A 13-Mar-19 A 27-Feb-19 14-Mar-19 1360 100% Warehouse Construction
C2090 Clinic/prayer Room/Guard Room installation 20 27-Feb-19 A 19-Mar-19 A 27-Feb-19 19-Mar-19 1000 100% Clinic/prayer Room/Guard Room installation
C2140 Workshop Construction 20 10-Jan-19 A 13-Mar-19 A 27-Feb-19 18-Mar-19 4000 100% Workshop Construction

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
 
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
Temporary Sewage Facilities 30 11-Mar-19 A 04-May-19 A 04-Apr-19 04-May-19 1500 100% 04-May-19 A, Temporary Sewage Facilities
C2100 Sewage Facilites Installation 30 11-Mar-19 A 04-May-19 A 04-Apr-19 04-May-19 1500 100% Sewage Facilites Installation
Temporary Water Supplying Facilities 18 15-Feb-19 A 04-May-19 A 09-Mar-19 27-Mar-19 1500 100% 04-May-19 A, Temporary Water Supplying Facilities
C2120 Water Supplying Facilities Installation 18 15-Feb-19 A 04-May-19 A 09-Mar-19 27-Mar-19 1500 100% Water Supplying Facilities Installation
Temporary Electrical Works 18 15-Feb-19 A 04-May-19 A 09-Mar-19 27-Mar-19 1500 100% 04-May-19 A, Temporary Electrical Works
C2110 Electrical Facilities Construction 18 15-Feb-19 A 04-May-19 A 09-Mar-19 27-Mar-19 1500 100% Electrical Facilities Construction
Laydown Area 8 10-Mar-19 A 04-May-19 A 29-Apr-19 07-May-19 2500 100% 04-May-19 A, Laydown Area
C2160 Finishing Works 8 10-Mar-19 A 04-May-19 A 29-Apr-19 07-May-19 2500 100% Finishing Works
Temporary Fire Protection Facilities 30 31-Mar-19 A 22-May-19 A 31-Mar-19 29-Apr-19 1500 100% 22-May-19 A, Temporary Fire Protection Facilities
C2170 Fire Protection Facilities Construction 30 31-Mar-19 A 22-May-19 A 31-Mar-19 29-Apr-19 1500 100% Fire Protection Facilities Construction
Precast Yard 30 11-Feb-19 A 04-May-19 A 03-Apr-19 03-May-19 7500 100% 04-May-19 A, Precast Yard
C2180 Precast Yard Construction 30 11-Feb-19 A 04-May-19 A 03-Apr-19 03-May-19 7500 100% Precast Yard Construction
Temporary Jetty 30 06-Aug-19 A 14-Sep-19 A 31-Jul-19 29-Aug-19 10000 100% 14-Sep-19 A, Temporary Jetty
C2300 South Island TJ - Stage 1 15 06-Aug-19 A 16-Aug-19 A 31-Jul-19 14-Aug-19 6000 100% South Island TJ - Stage 1
C2440 South Island TJ - Stage 2 15 18-Aug-19 A 14-Sep-19 A 15-Aug-19 29-Aug-19 4000 100% South Island TJ - Stage 2
General Demolition Activities 143 31-Mar-19 A 18-Jul-19 A 31-Mar-19 23-Aug-19 16750 100% 18-Jul-19 A, General Demolition Activities
Remove and Dispose of Existing Pipeline 108 31-Mar-19 A 08-Jul-19 A 31-Mar-19 19-Jul-19 12250 100% 08-Jul-19 A, Remove and Dispose of Existing Pipeline
C2010 Pipeline Exploration 12 31-Mar-19 A 08-Apr-19 A 31-Mar-19 11-Apr-19 2250 100% Pipeline Exploration
C2040 Pipeline Cut Off 30 18-May-19 A 28-May-19 A 17-Jun-19 19-Jul-19 6250 100% Pipeline Cut Off
C2130 Pipeline Lifting and Transportation 20 24-May-19 A 08-Jul-19 A 17-Jun-19 06-Jul-19 3750 100% Pipeline Lifting and Transportation
Remove and Dispose of Existing Facilities In The Park 54 09-May-19 A 18-Jul-19 A 27-Jun-19 23-Aug-19 4500 100% 18-Jul-19 A, Remove and Dispose of Existing Facilities In The Park
C2150 Above Ground Facilities Demolition 30 09-May-19 A 08-Jul-19 A 27-Jun-19 30-Jul-19 2250 100% Above Ground Facilities Demolition
C2190 Under Ground Facilities Demolition 42 09-May-19 A 18-Jul-19 A 09-Jul-19 23-Aug-19 2250 100% Under Ground Facilities Demolition
Causeway to South Island 839 13-Jun-19 A 28-Oct-21 A 16-Jun-19 05-Mar-21 134600 100%
South Island Causeway Reclamation 180 13-Jun-19 A 20-Nov-19 A 16-Jun-19 16-Dec-19 26250 100% 20-Nov-19 A, South Island Causeway Reclamation
C2210 South Island Causeway Infill 25% 24 13-Jun-19 A 15-Jul-19 A 16-Jun-19 10-Jul-19 7500 100% South Island Causeway Infill 25%
C2240 South Island Causeway Infill 50% 24 15-Jul-19 A 28-Jul-19 A 15-Jul-19 07-Aug-19 6250 100% South Island Causeway Infill 50%
C2330 South Island Causeway Infill 75% 24 28-Jul-19 A 17-Aug-19 A 06-Jul-19 02-Aug-19 6250 100% South Island Causeway Infill 75%
C2450 South Island Causeway Infill 100% 12 19-Nov-19 A 20-Nov-19 A 05-Dec-19 16-Dec-19 6250 100% South Island Causeway Infill 100%
Revetment (L=1532m) 80 07-Oct-19 A 29-Jan-20 A 10-Nov-19 28-Jan-20 79480 100% 29-Jan-20 A, Revetment (L=1532m)
C2310 Sand Slope Trimming (below +2.5m CD) 72 07-Oct-19 A 16-Nov-19 A 10-Nov-19 20-Jan-20 4600 100% Sand Slope Trimming (below +2.5m CD)
C2320 Geotextile Laying (below +2.5m CD) 72 07-Oct-19 A 17-Nov-19 A 10-Nov-19 20-Jan-20 10350 100% Geotextile Laying (below +2.5m CD)
C2340 Rock Under Layer (Below +2.5m CD) 72 07-Oct-19 A 23-Nov-19 A 10-Nov-19 20-Jan-20 10350 100% Rock Under Layer (Below +2.5m CD)
C2510 Rock Armour Layer (below +2.5m CD) 72 07-Oct-19 A 06-Dec-19 A 10-Nov-19 20-Jan-20 9450 100% Rock Armour Layer (below +2.5m CD)
C2520 Rock Armour Layer at toe (below +2.5m CD) 59 07-Oct-19 A 06-Dec-19 A 01-Dec-19 28-Jan-20 9450 100% Rock Armour Layer at toe (below +2.5m CD)
C2860 Geotextile Laying (+2.5m~ +4m CD) 59 01-Dec-19 A 04-Jan-20 A 01-Dec-19 28-Jan-20 4410 100% Geotextile Laying (+2.5m~ +4m CD)
C2870 Rock Under Layer (+2.5m~ +4m CD) 40 01-Dec-19 A 04-Jan-20 A 01-Dec-19 09-Jan-20 4410 100% Rock Under Layer (+2.5m~ +4m CD)
C2880 Sand Slope Trimming (+2.5m~ +4m CD) 33 01-Dec-19 A 17-Jan-20 A 01-Dec-19 02-Jan-20 4410 100% Sand Slope Trimming (+2.5m~ +4m CD)
C3110 Rock Armour Layer (+2.5m~ +4m CD) 33 01-Dec-19 A 17-Jan-20 A 01-Dec-19 02-Jan-20 4410 100% Rock Armour Layer (+2.5m~ +4m CD)
C3640 Geotextile Laying (+4m~top CD) 33 21-Dec-19 A 17-Jan-20 A 14-Dec-19 15-Jan-20 4410 100% Geotextile Laying (+4m~top CD)
C3650 Sand Slope Trimming (+4m~top CD) 33 14-Dec-19 A 17-Jan-20 A 14-Dec-19 15-Jan-20 4410 100% Sand Slope Trimming (+4m~top CD)
C3660 Rock Under Layer (+4m~top CD) 33 14-Dec-19 A 17-Jan-20 A 14-Dec-19 15-Jan-20 4410 100% Rock Under Layer (+4m~top CD)
C4010 Rock Armour Layer (+4m~top CD) 33 14-Dec-19 A 29-Jan-20 A 14-Dec-19 15-Jan-20 4410 100% Rock Armour Layer (+4m~top CD)
Soil Improvement 37 08-Dec-19 A 11-Jan-20 A 26-Dec-19 31-Jan-20 10500 100% 11-Jan-20 A, Soil Improvement
C6520 Soil Improvement 50% 10 08-Dec-19 A 28-Dec-19 A 26-Dec-19 04-Jan-20 5250 100% Soil Improvement 50%
C7140 Soil Improvement 100% 35 28-Dec-19 A 11-Jan-20 A 28-Dec-19 31-Jan-20 5250 100% Soil Improvement 100%
Marl Cap Installation 20 23-Dec-19 A 05-Feb-20 A 01-Feb-20 20-Feb-20 17500 100% 05-Feb-20 A, Marl Cap Installation
C7590 Marl Cap 50% 20 23-Dec-19 A 30-Jan-20 A 01-Feb-20 20-Feb-20 8750 100% Marl Cap 50%
C7990 Marl Cap 100% 20 01-Feb-20 A 05-Feb-20 A 01-Feb-20 20-Feb-20 8750 100% Marl Cap 100%

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
 
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
Construction of Road 543 22-Mar-20 A 28-Oct-21 A 11-Apr-20 05-Mar-21 870 100%
C7580 Lighting Pole Foundation construction 5 11-Apr-20 A 07-May-20 A 11-Apr-20 15-Apr-20 250 100% Lighting Pole Foundation construction
C7980 Base Layer of Road Construction 15 22-Mar-20 A 11-Apr-20 A 11-Apr-20 25-Apr-20 250 100% Base Layer of Road Construction
C8400 Armour Layer of Road Construction 39 28-Jan-21 A 22-Mar-21 A 01-Jan-21 08-Feb-21 150 100% Armour Layer of Road Const
C8610 Road Marking 5 01-Oct-21 A 28-Oct-21 A 09-Feb-21 18-Feb-21 70 100%
C8650 Road Barrier Installation 15 18-Apr-21 A 16-May-21 A 19-Feb-21 05-Mar-21 150 100%
South Island 656 31-Jul-19 A 24-Sep-21 A 31-Jul-19 23-Mar-21 398020 100%
Civil / Structural 656 31-Jul-19 A 24-Sep-21 A 31-Jul-19 23-Mar-21 398020 100%
Dredging and Reclamation 226 31-Jul-19 A 23-Apr-20 A 31-Jul-19 12-Mar-20 107500 100% 23-Apr-20 A, Dredging and Reclamation
C2250 Reclamation of South Island 10% 34 31-Jul-19 A 31-Aug-19 A 31-Jul-19 02-Sep-19 10750 100% Reclamation of South Island 10%
C2290 Reclamation of South Island 20% 15 31-Aug-19 A 22-Sep-19 A 03-Sep-19 17-Sep-19 10750 100% Reclamation of South Island 20%
C2400 Reclamation of South Island 30% 15 23-Sep-19 A 27-Oct-19 A 18-Sep-19 02-Oct-19 10750 100% Reclamation of South Island 30%
C2760 Reclamation of South Island 40% 15 27-Oct-19 A 09-Nov-19 A 04-Nov-19 18-Nov-19 10750 100% Reclamation of South Island 40%
C3240 Reclamation of South Island 50% 15 15-Nov-19 A 30-Nov-19 A 15-Nov-19 29-Nov-19 10750 100% Reclamation of South Island 50%
C3790 Reclamation of South Island 60% 15 23-Dec-19 A 02-Jan-20 A 14-Dec-19 28-Dec-19 10750 100% Reclamation of South Island 60%
C4300 Reclamation of South Island 70% 20 03-Jan-20 A 12-Jan-20 A 29-Dec-19 17-Jan-20 10750 100% Reclamation of South Island 70%
C4790 Reclamation of South Island 80% 20 13-Jan-20 A 28-Jan-20 A 18-Jan-20 06-Feb-20 10750 100% Reclamation of South Island 80%
C5350 Reclamation of South Island 90% 20 28-Jan-20 A 21-Feb-20 A 18-Jan-20 06-Feb-20 10750 100% Reclamation of South Island 90%
C5920 Reclamation of South Island 100% 20 22-Feb-20 A 23-Apr-20 A 22-Feb-20 12-Mar-20 10750 100% Reclamation of South Island 100%
South Drilling Island (A) Civil Work 534 07-Oct-19 A 24-Sep-21 A 30-Nov-19 23-Mar-21 290520 100%
Revetment (L=2957m) 103 07-Oct-19 A 24-Sep-21 A 30-Nov-19 11-Mar-20 143520 100%
C2410 Sand Slope Trimming (below +2.5m CD) 50 07-Oct-19 A 24-Feb-20 A 30-Nov-19 18-Jan-20 7800 100% Sand Slope Trimming (below +2.5m CD)
C2420 Geotextile Laying (below +2.5m CD) 15 08-Oct-19 A 20-Oct-20 A 15-Dec-19 29-Dec-19 17550 100% Geotextile Laying (below +2.5m CD)
C2430 Rock Under Layer (Below +2.5m CD) 15 08-Oct-19 A 14-Oct-20 A 30-Dec-19 13-Jan-20 17550 100% Rock Under Layer (Below +2.5m CD)
C2570 Rock Armour Layer (below +2.5m CD) 15 05-Nov-19 A 23-Sep-21 A 14-Jan-20 28-Jan-20 17550 100%
C2580 Rock Armour Layer at toe (below +2.5m CD) 15 23-Dec-19 A 23-Sep-21 A 14-Dec-19 28-Dec-19 17550 100%
C2780 Sand Slope Trimming (+2.5m~ +4m CD) 8 26-Jan-20 A 24-Sep-21 A 02-Feb-20 09-Feb-20 8190 100%
C2790 Geotextile Laying (+2.5m~ +4m CD) 8 27-Jan-20 A 23-Sep-21 A 10-Feb-20 17-Feb-20 8190 100%
C2800 Rock Under Layer (+2.5m~ +4m CD) 8 27-Jan-20 A 23-Sep-21 A 18-Feb-20 25-Feb-20 8190 100%
C3010 Rock Armour Layer (+2.5m~ +4m CD) 8 26-Jan-20 A 23-Sep-21 A 02-Mar-20 09-Mar-20 8190 100%
C3310 Sand Slope Trimming (+4m~top CD) 8 05-Feb-20 A 23-Sep-21 A 09-Feb-20 16-Feb-20 8190 100%
C3320 Geotextile Laying (+4m~top CD) 8 06-Feb-20 A 23-Sep-21 A 17-Feb-20 24-Feb-20 8190 100%
C3330 Rock Under Layer (+4m~top CD) 8 02-Feb-20 A 23-Sep-21 A 25-Feb-20 03-Mar-20 8190 100%
C3350 Rock Armour Layer (+4m~top CD) 8 04-Feb-20 A 23-Sep-21 A 04-Mar-20 11-Mar-20 8190 100%
Soil Improvement 478 02-Jan-20 A 17-Apr-21 A 10-Jan-20 08-Mar-21 105000 100% 17-Apr-21 A, Soil Improvem
C3250 Soil Improvement 10% 10 02-Jan-20 A 03-Apr-20 A 10-Jan-20 19-Jan-20 10500 100% Soil Improvement 10%
C3630 Soil Improvement 20% 5 04-Apr-20 A 23-Apr-20 A 04-Apr-20 08-Apr-20 10500 100% Soil Improvement 20%
C4160 Soil Improvement 30% 5 25-Apr-20 A 06-May-20 A 25-Apr-20 29-Apr-20 10500 100% Soil Improvement 30%
C4520 Soil Improvement 40% 5 07-May-20 A 28-May-20 A 02-May-20 06-May-20 10500 100% Soil Improvement 40%
C4850 Soil Improvement 50% 5 28-May-20 A 09-Oct-20 A 28-May-20 01-Jun-20 10500 100% Soil Improvement 50%
C5360 Soil Improvement 60% 30 31-Oct-20 A 16-Dec-20 A 10-Oct-20 08-Nov-20 10500 100% Soil Improvement 60%
C5780 Soil Improvement 70% 30 17-Dec-20 A 14-Jan-21 A 09-Nov-20 08-Dec-20 9500 100% Soil Improvement 70%
C6310 Soil Improvement 80% 30 15-Jan-21 A 29-Jan-21 A 09-Dec-20 07-Jan-21 10500 100% Soil Improvement 80%
C6750 Soil Improvement 90% 30 30-Jan-21 A 07-Mar-21 A 08-Jan-21 06-Feb-21 10500 100% Soil Improvement 90%
C7170 Soil Improvement 100% 27 08-Mar-21 A 17-Apr-21 A 07-Feb-21 08-Mar-21 11500 100% Soil Improvement 100%
Marl Cap Installation 79 27-Feb-21 A 24-May-21 A 08-Jan-21 23-Mar-21 42000 100%
C4860 Marl Cap 20% 15 27-Feb-21 A 22-Mar-21 A 08-Jan-21 22-Jan-21 7400 100% Marl Cap 20%
C5430 Marl Cap 40% 15 21-Mar-21 A 17-Apr-21 A 23-Jan-21 06-Feb-21 7400 100% Marl Cap 40%
C6050 Marl Cap 60% 15 11-Mar-21 A 11-Apr-21 A 07-Feb-21 21-Feb-21 9400 100% Marl Cap 60%

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
 
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
C6670 Marl Cap 80% 15 12-Apr-21 A 27-Apr-21 A 22-Feb-21 08-Mar-21 9400 100%
C7180 Marl Cap 100% 8 28-Apr-21 A 24-May-21 A 09-Mar-21 23-Mar-21 8400 100%
South Island Escape Jetty 285 21-Feb-21 A 09-Dec-21 01-Jan-21 09-Jul-21 1610 80.69%
C8130 Piles Installation 30 21-Feb-21 A 15-May-21 A 01-Jan-21 30-Jan-21 300 100%
C8790 Cross Beam Installation 30 01-Jun-21 A 29-Jun-21 A 31-Jan-21 01-Mar-21 210 100%
C8880 I-Beam Installation 27 01-Aug-21 A 20-Aug-21 A 02-Mar-21 31-Mar-21 300 100%
C8900 P/C Plank Installation 10 21-Aug-21 A 31-Aug-21 A 01-Apr-21 30-Apr-21 100 100%
C8950 Cast In-situ of Deck 31 18-Sep-21 A 30-Sep-21 A 01-May-21 30-May-21 400 100%
C8990 Facilities Installation (Life boat etc) 20 13-Nov-21 A 09-Dec-21 31-May-21 09-Jul-21 300 10%
KFIP Expansion 735 19-Aug-19 A 02-Jan-22 30-Dec-19 12-Dec-21 76260 81.73%
KFIP Causeway Expansion Reclaimation 197 23-Sep-19 A 10-Jan-20 A 30-Dec-19 13-Jul-20 4920 100% 10-Jan-20 A, KFIP Causeway Expansion Reclaimation
C2200 Reclamation of KFIP Causeway Expansion 25% 20 23-Sep-19 A 26-Dec-19 A 30-Dec-19 18-Jan-20 1230 100% Reclamation of KFIP Causeway Expansion 25%
C2220 Reclamation of KFIP Causeway Expansion 50% 30 27-Dec-19 A 31-Dec-19 A 13-Jan-20 11-Feb-20 1230 100% Reclamation of KFIP Causeway Expansion 50%
C2260 Reclamation of KFIP Causeway Expansion 75% 30 31-Dec-19 A 02-Jan-20 A 30-May-20 28-Jun-20 1230 100% Reclamation of KFIP Causeway Expansion 75%
C2270 Reclamation of KFIP Causeway Expansion 100% 15 02-Jan-20 A 10-Jan-20 A 29-Jun-20 13-Jul-20 1230 100% Reclamation of KFIP Causeway Expansion 100%
Revetment 712 31-Dec-19 A 30-Dec-21 13-Jan-20 13-Jun-21 32240 90.75%
C2360 Sand Slope Trimming (below +2.5m CD) 20 31-Dec-19 A 07-May-20 A 13-Jan-20 01-Feb-20 1800 100% Sand Slope Trimming (below +2.5m CD)
C2370 Geotextile Laying (below +2.5m CD) 20 31-Dec-19 A 07-May-20 A 02-Feb-20 21-Feb-20 1800 100% Geotextile Laying (below +2.5m CD)
C2380 Rock Under Layer (Below +2.5m CD) 20 31-Dec-19 A 15-Dec-21 02-Feb-20 21-Feb-20 4050 89.02%
C2460 Armour Layer (below +2.5m CD) 12 01-May-20 A 15-Dec-21 22-May-20 02-Jun-20 4500 87.79%
C2470 Armour Layer at toe (below +2.5m CD) 12 01-May-20 A 15-Dec-21 03-Jun-20 14-Jun-20 4500 94.45%
C2620 Sand Slope Trimming (+2.5m~ +4m CD) 12 04-May-20 A 15-Dec-21 03-Jun-20 14-Jun-20 1800 94.3%
C2630 Geotextile Laying (+2.5m~ +4m CD) 12 04-May-20 A 15-Dec-21 15-Jun-20 26-Jun-20 1800 91.84%
C2640 Rock Under Layer (+2.5m~ +4m CD) 12 05-May-20 A 15-Dec-21 28-May-20 08-Jun-20 1800 94.39%
C2900 Armour Layer (+2.5m~ +4m CD) 12 10-Feb-21 A 15-Dec-21 16-May-21 21-May-21 2250 94.47%
C3170 Sand Slope Trimming (+4m~top CD) 10 24-Oct-21 A 16-Dec-21 22-May-21 27-May-21 1900 93.46%
C3180 Geotextile Laying (+4m~top CD) 10 24-Oct-21 A 16-Dec-21 28-May-21 02-Jun-21 1900 94.53%
C3190 Rock Under Layer (+4m~top CD) 5 24-Oct-21 A 25-Dec-21 03-Jun-21 08-Jun-21 1890 72.17%
C3500 Armour Layer (+4m~top CD) 5 24-Oct-21 A 30-Dec-21 09-Jun-21 13-Jun-21 2250 78.35%
Soil Improvement 15 18-Jan-20 A 23-Dec-21 18-Jan-20 01-Feb-20 10500 89.52%
C4500 Soil Improvement 50% 8 18-Jan-20 A 26-Jan-20 A 18-Jan-20 25-Jan-20 5250 100% Soil Improvement 50%
C4920 Soil Improvement 100% 7 26-Jan-20 A 23-Dec-21 26-Jan-20 01-Feb-20 5250 78.77%
Marl Cap Installation 32 15-Sep-21 A 05-Dec-21 01-Oct-21 30-Oct-21 9000 64.84%
C5460 Marl Cap 50% 8 15-Sep-21 A 11-Nov-21 A 01-Oct-21 15-Oct-21 4500 100%
C5940 Marl Cap 100% 16 11-Nov-21 A 05-Dec-21 16-Oct-21 30-Oct-21 4500 29.94%
New Road Construction (KFIP Causeway Expansion) 20 20-Nov-21 09-Dec-21 16-Oct-21 04-Nov-21 0 0%
C7480 Base Layer of Road Construction 11 20-Nov-21 30-Nov-21 16-Oct-21 25-Oct-21 0 0%
C7950 Armour Layer of Road Construction 9 01-Dec-21 09-Dec-21 26-Oct-21 04-Nov-21 0 0%
Modification of Existing Wave Wall 88 19-Aug-19 A 09-Nov-19 A 21-May-20 17-Aug-20 13500 100% 09-Nov-19 A, Modification of Existing Wave Wall
C6500 Modification of existing wave wall 50% 15 19-Aug-19 A 05-Oct-19 A 21-May-20 05-Jun-20 6750 100% Modification of existing wave wall 50%
C7030 Modification of existing wave wall 100% 12 04-Oct-19 A 09-Nov-19 A 05-Aug-20 17-Aug-20 6750 100% Modification of existing wave wall 100%
New Access Road (KFIP Causeway Expansion) 51 13-Nov-21 A 02-Jan-22 26-Oct-21 12-Dec-21 6100 5.28%
C7450 Lighting Pole Foundation construction 10 13-Nov-21 A 29-Nov-21 26-Oct-21 02-Nov-21 1250 30%
C7850 Base Layer of Road Construction 10 20-Nov-21 29-Nov-21 03-Nov-21 12-Nov-21 1250 0%
C7860 Lighting Pole Installation 10 25-Nov-21 04-Dec-21 03-Nov-21 12-Nov-21 1250 0%
C8300 Armour Layer of Road Construction 10 05-Dec-21 14-Dec-21 13-Nov-21 22-Nov-21 650 0%
C8480 Road Marking 10 15-Dec-21 24-Dec-21 23-Nov-21 02-Dec-21 350 0%
C8560 Road Barrier Installation 9 25-Dec-21 02-Jan-22 03-Dec-21 12-Dec-21 1350 0%
New Pipelines Culvert structure (KFIP Causeway Expansion) 62 03-Oct-21 A 23-Dec-21 16-Jul-21 13-Sep-21 0 0%

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
 
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
C7460 Leveling and compaction 9 03-Oct-21 A 06-Oct-21 A 16-Jul-21 25-Jul-21 0 0%
C7600 Subgrade Soil compaction 9 07-Nov-21 A 10-Nov-21 A 26-Jul-21 09-Aug-21 0 0%
C7720 Concrete Casting for Culvert 26 20-Nov-21 15-Dec-21 26-Jul-21 14-Aug-21 0 0%
C8100 Coating Work 3 16-Dec-21 18-Dec-21 15-Aug-21 29-Aug-21 0 0%
C8290 Back Filling 5 19-Dec-21 23-Dec-21 30-Aug-21 13-Sep-21 0 0%
North island 633 12-Jan-20 A 20-Dec-21 18-Jan-20 26-Jul-21 329366 99.36%
North Island Reclamation 131 12-Jan-20 A 04-Jun-20 A 18-Jan-20 27-May-20 107500 100% 04-Jun-20 A, North Island Reclamation
C2350 Reclamation of NorthIsland 10% 10 12-Jan-20 A 03-Feb-20 A 18-Jan-20 27-Jan-20 10750 100% Reclamation of NorthIsland 10%
C2560 Reclamation of NorthIsland 20% 8 04-Feb-20 A 21-Feb-20 A 11-Feb-20 18-Feb-20 10750 100% Reclamation of NorthIsland 20%
C3000 Reclamation of NorthIsland 30% 8 20-Feb-20 A 27-Mar-20 A 23-Feb-20 01-Mar-20 10750 100% Reclamation of NorthIsland 30%
C3480 Reclamation of NorthIsland 40% 6 27-Mar-20 A 23-Apr-20 A 27-Mar-20 01-Apr-20 10750 100% Reclamation of NorthIsland 40%
C4060 Reclamation of NorthIsland 50% 4 24-Apr-20 A 06-May-20 A 24-Apr-20 27-Apr-20 10750 100% Reclamation of NorthIsland 50%
C4540 Reclamation of NorthIsland 60% 4 06-May-20 A 12-May-20 A 06-May-20 09-May-20 10750 100% Reclamation of NorthIsland 60%
C5040 Reclamation of NorthIsland 70% 4 13-May-20 A 19-May-20 A 13-May-20 16-May-20 10750 100% Reclamation of NorthIsland 70%
C5590 Reclamation of NorthIsland 80% 4 20-May-20 A 21-May-20 A 20-May-20 23-May-20 10750 100% Reclamation of NorthIsland 80%
C6190 Reclamation of NorthIsland 90% 4 21-May-20 A 26-May-20 A 24-May-20 27-May-20 10750 100% Reclamation of NorthIsland 90%
C6830 Reclamation of NorthIsland 100% 4 23-May-20 A 04-Jun-20 A 23-May-20 26-May-20 10750 100% Reclamation of NorthIsland 100%
North Drilling Island (B) Civil Work 577 17-Mar-20 A 20-Dec-21 14-Mar-20 26-Jul-21 221866 99.06%
Revetment 534 17-Mar-20 A 20-Dec-21 14-Mar-20 30-May-21 115826 98.2%
C5050 Sand Slope Trimming (below +2.5m CD) 9 17-Mar-20 A 20-Oct-20 A 14-Mar-20 22-Mar-20 6600 100% Sand Slope Trimming (below +2.5m CD)
C5060 Geotextile Laying (below +2.5m CD) 9 19-Mar-20 A 26-Oct-20 A 19-Mar-20 27-Mar-20 6600 100% Geotextile Laying (below +2.5m CD)
C5070 Rock Under Layer (Below +2.5m CD) 5 28-Mar-20 A 15-Dec-21 28-Mar-20 01-Apr-20 14726 98.51%
C5150 Armour Layer (below +2.5m CD) 5 21-May-20 A 15-Dec-21 21-May-20 25-May-20 15500 96.9%
C5160 Armour Layer at toe (below +2.5m CD) 5 21-May-20 A 15-Dec-21 21-May-20 25-May-20 15500 96.97%
C5510 Sand Slope Trimming (+2.5m~ +4m CD) 5 21-May-20 A 20-Dec-21 21-May-20 25-May-20 6900 97.67%
C5520 Geotextile Laying (+2.5m~ +4m CD) 5 22-May-20 A 20-Dec-21 26-May-20 30-May-20 6800 98.31%
C5530 Rock Under Layer (+2.5m~ +4m CD) 5 22-May-20 A 15-Dec-21 31-May-20 04-Jun-20 6800 98.29%
C5710 Armour Layer (+2.5m~ +4m CD) 12 24-Nov-20 A 15-Dec-21 01-Apr-21 12-Apr-21 8000 98.19%
C6060 Sand Slope Trimming (+4m~top CD) 12 21-Feb-21 A 26-Nov-21 13-Apr-21 24-Apr-21 6800 98.41%
C6070 Geotextile Laying (+4m~top CD) 12 25-Feb-21 A 26-Nov-21 25-Apr-21 06-May-21 6800 98.57%
C6080 Rock Under Layer (+4m~top CD) 12 28-Feb-21 A 27-Nov-21 07-May-21 18-May-21 6800 98.58%
C6250 Armour Layer (+4m~top CD) 12 02-Mar-21 A 25-Nov-21 19-May-21 30-May-21 8000 98.9%
Soil Improvemtn 213 25-Jan-21 A 15-Jul-21 A 29-Nov-20 16-Jun-21 105000 100%
C6240 Soil Improvement 20% 40 25-Jan-21 A 04-May-21 A 29-Nov-20 07-Jan-21 21000 100%
C7300 Soil Improvement 40% 40 07-May-21 A 16-May-21 A 08-Jan-21 16-Feb-21 21000 100%
C7840 Soil Improvement 60% 40 17-May-21 A 03-Jun-21 A 17-Feb-21 28-Mar-21 21000 100%
C8330 Soil Improvement 80% 40 04-Jun-21 A 09-Jun-21 A 29-Mar-21 07-May-21 21000 100%
C8760 Soil Improvement 100% 40 10-Jun-21 A 15-Jul-21 A 08-May-21 16-Jun-21 21000 100%
Marl Cap Installation 87 17-Jul-21 A 19-Dec-21 08-May-21 26-Jul-21 1040 97.94%
C8110 Marl Cap 50% 35 17-Jul-21 A 31-Aug-21 A 08-May-21 16-Jun-21 520 100%
C8780 Marl Cap 100% 30 01-Sep-21 A 19-Dec-21 17-Jun-21 26-Jul-21 520 91.11%
North Island Escape Jetty 208 08-May-21 A 01-Dec-21 02-Apr-21 28-Sep-21 1320 77.14%
C7750 Piles Installation 30 08-May-21 A 18-Jun-21 A 02-Apr-21 01-May-21 10 100%
C8140 Cross Beam Installation 30 14-Aug-21 A 23-Aug-21 A 01-Jun-21 30-Jun-21 210 100%
C8410 I-Beam Installation 13 11-Sep-21 A 21-Oct-21 A 01-Jul-21 30-Jul-21 300 100%
C8520 P/C Plank Installation 15 14-Sep-21 A 26-Oct-21 A 01-Jul-21 30-Jul-21 100 100%
C8660 Cast In-situ of Deck 15 24-Oct-21 A 09-Nov-21 A 01-Jul-21 30-Jul-21 400 100%
C8800 Facilities Installation 12 20-Nov-21 01-Dec-21 31-Jul-21 28-Sep-21 300 0%

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
 
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
Access Bridge 675 09-Feb-20 A 14-Jan-22 11-Mar-20 30-Oct-21 97080 72.94%
Access Bridge 675 09-Feb-20 A 14-Jan-22 11-Mar-20 30-Oct-21 97080 72.94%
Piles Installation 391 09-Feb-20 A 24-May-21 A 11-Mar-20 05-Apr-21 6250 100%
C2770 Piles Installation preparation 20 18-Feb-20 A 27-Feb-20 A 11-Mar-20 30-Mar-20 0 0% Piles Installation preparation
C3260 Piles Installation 100% 90 09-Feb-20 A 24-May-21 A 06-Jan-21 05-Apr-21 6250 100%
Cross Beam Installation 72 05-Jun-21 A 05-Aug-21 A 05-Feb-21 04-Jun-21 20800 100%
C3800 Cross Beam Construction 50% 55 05-Jun-21 A 30-Jun-21 A 05-Feb-21 05-Apr-21 10400 100%
C6880 Cross Beam Construction 100% 47 30-Jun-21 A 05-Aug-21 A 06-Apr-21 04-Jun-21 10400 100%
I-Beams Installation 38 21-Aug-21 A 07-Sep-21 A 06-Apr-21 30-Jun-21 21520 100%
C5200 I-Beam Installation 50% 17 21-Aug-21 A 30-Aug-21 A 06-Apr-21 18-May-21 10600 100%
C7610 I-Beam Installation 100% 14 31-Aug-21 A 07-Sep-21 A 19-May-21 30-Jun-21 10920 100%
Cast In-situ of Partition Wall 99 25-Sep-21 A 01-Jan-22 06-Apr-21 30-Jun-21 13440 13.38%
C5630 Cast In-situ of Partition Wall 50% 22 25-Sep-21 A 11-Dec-21 06-Apr-21 18-May-21 6720 26.76%
C7940 Cast In-situ of Partition Wall 100% 21 12-Dec-21 01-Jan-22 19-May-21 30-Jun-21 6720 0%
P/C Planks Installation 14 02-Sep-21 A 20-Oct-21 A 06-Apr-21 30-Jun-21 8400 100%
C6690 P/C Plank Installation 50% 11 02-Sep-21 A 15-Sep-21 A 06-Apr-21 18-May-21 4200 100%
C8420 P/C Plank Installation 100% 10 16-Sep-21 A 20-Oct-21 A 19-May-21 30-Jun-21 4200 100%
Decks Construction 80 25-Sep-21 A 13-Dec-21 06-Jun-21 01-Sep-21 24060 50%
C7960 Cast In-situ of Deck 50% 19 25-Sep-21 A 19-Nov-21 A 06-Jun-21 19-Jul-21 12030 100%
C8740 Cast In-situ of Deck 100% 15 29-Nov-21 13-Dec-21 20-Jul-21 01-Sep-21 12030 0%
Asphalt Surfacing 10 14-Dec-21 23-Dec-21 17-Sep-21 11-Oct-21 1050 0%
C8910 Asphalt Layer laying 10 14-Dec-21 23-Dec-21 17-Sep-21 11-Oct-21 1050 0%
Facilities Installation 56 20-Nov-21 14-Jan-22 05-Jul-21 30-Oct-21 1560 0%
A1000 Other Facilities Installation 10 24-Dec-21 02-Jan-22 20-Jul-21 28-Aug-21 0 0%
C8750 Expansion Joint 12 03-Jan-22 14-Jan-22 26-Sep-21 17-Oct-21 300 0%
C8920 Pipe Support 15 20-Nov-21 04-Dec-21 05-Jul-21 25-Sep-21 560 0%
C8930 Telecom/HV/LV Electric Support and Cable Tray 15 16-Dec-21 30-Dec-21 26-Sep-21 30-Oct-21 700 0%
Cathodic Protection 164 01-Aug-21 A 11-Jan-22 06-Feb-21 29-May-21 5500 15.91%
C3810 CP for Access Bridge 105 01-Aug-21 A 15-Dec-21 06-Feb-21 21-May-21 2500 35%
C8150 CP for Access NorthIsland Escape Jetty 26 17-Dec-21 11-Jan-22 04-May-21 29-May-21 1500 0%
C8470 CP for Access Sorth Island Escape Jetty 25 20-Nov-21 14-Dec-21 03-Mar-21 27-Mar-21 1500 0%
Pre-cast works ( South & North Island ) 385 05-Sep-19 A 15-Nov-20 A 10-Nov-19 28-Nov-20 163030 100% 15-Nov-20 A, Pre-cast works ( South & North
Precast Work 385 05-Sep-19 A 15-Nov-20 A 10-Nov-19 28-Nov-20 163030 100% 15-Nov-20 A, Precast Work
Precast Armour block 89 05-Sep-19 A 11-Jan-20 A 10-Nov-19 06-Feb-20 87750 100% 11-Jan-20 A, Precast Armour block
C2230 PrecastArmour Block 8% 12 05-Sep-19 A 13-Oct-19 A 13-Nov-19 24-Nov-19 6750 100% PrecastArmour Block 8%
C2280 PrecastArmour Block 16% 12 12-Oct-19 A 27-Oct-19 A 20-Dec-19 01-Jan-20 6750 100% PrecastArmour Block 16%
C2390 PrecastArmour Block 24% 12 27-Oct-19 A 30-Oct-19 A 06-Jan-20 18-Jan-20 6750 100% PrecastArmour Block 24%
C2750 PrecastArmour Block 32% 12 07-Nov-19 A 10-Nov-19 A 18-Dec-19 30-Dec-19 6750 100% PrecastArmour Block 32%
C3160 PrecastArmour Block 40% 12 30-Oct-19 A 08-Nov-19 A 25-Jan-20 06-Feb-20 6750 100% PrecastArmour Block 40%
C3680 PrecastArmour Block 48% 12 10-Nov-19 A 13-Dec-19 A 10-Nov-19 21-Nov-19 6750 100% PrecastArmour Block 48%
C4250 PrecastArmour Block 56% 12 22-Oct-19 A 26-Nov-19 A 22-Nov-19 03-Dec-19 6750 100% PrecastArmour Block 56%
C4780 PrecastArmour Block 64% 12 26-Nov-19 A 07-Dec-19 A 04-Dec-19 15-Dec-19 6750 100% PrecastArmour Block 64%
C5260 PrecastArmour Block 72% 12 06-Dec-19 A 13-Dec-19 A 16-Dec-19 27-Dec-19 6750 100% PrecastArmour Block 72%
C5810 PrecastArmour Block 80% 12 22-Dec-19 A 26-Dec-19 A 14-Dec-19 25-Dec-19 5750 100% PrecastArmour Block 80%
C6490 PrecastArmour Block 88% 12 26-Dec-19 A 29-Dec-19 A 26-Dec-19 06-Jan-20 6750 100% PrecastArmour Block 88%
C7020 PrecastArmour Block 96% 12 29-Dec-19 A 04-Jan-20 A 07-Jan-20 18-Jan-20 6750 100% PrecastArmour Block 96%
C7470 PrecastArmour Block 100% 12 04-Jan-20 A 11-Jan-20 A 19-Jan-20 30-Jan-20 7750 100% PrecastArmour Block 100%
Plank Precasting 120 04-Jan-20 A 20-Feb-20 A 12-Jan-20 11-May-20 17000 100% 20-Feb-20 A, Plank Precasting
C2740 Plank Precast 10% 15 04-Jan-20 A 12-Jan-20 A 12-Jan-20 27-Jan-20 1700 100% Plank Precast 10%

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
 
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
C3020 Plank Precast 20% 15 12-Jan-20 A 16-Jan-20 A 27-Jan-20 11-Feb-20 1700 100% Plank Precast 20%
C3490 Plank Precast 30% 15 13-Jan-20 A 17-Jan-20 A 02-Feb-20 16-Feb-20 1700 100% Plank Precast 30%
C3940 Plank Precast 40% 15 14-Jan-20 A 18-Jan-20 A 17-Feb-20 02-Mar-20 1700 100% Plank Precast 40%
C4350 Plank Precast 50% 15 19-Jan-20 A 26-Jan-20 A 03-Mar-20 17-Mar-20 1700 100% Plank Precast 50%
C4770 Plank Precast 60% 15 22-Jan-20 A 02-Feb-20 A 18-Mar-20 01-Apr-20 1700 100% Plank Precast 60%
C5090 Plank Precast 70% 15 01-Feb-20 A 07-Feb-20 A 16-Feb-20 01-Mar-20 1700 100% Plank Precast 70%
C5600 Plank Precast 80% 15 06-Feb-20 A 07-Feb-20 A 27-Apr-20 11-May-20 1700 100% Plank Precast 80%
C6140 Plank Precast 90% 15 06-Feb-20 A 12-Feb-20 A 23-Feb-20 08-Mar-20 1700 100% Plank Precast 90%
C6530 Plank Precast 100% 10 13-Feb-20 A 20-Feb-20 A 09-Mar-20 18-Mar-20 1700 100% Plank Precast 100%
I Beam Precasting 267 07-Mar-20 A 15-Nov-20 A 07-Mar-20 28-Nov-20 53280 100% 15-Nov-20 A, I Beam Precasting
C3690 I Beam Precast #1 8 07-Mar-20 A 31-Mar-20 A 07-Mar-20 14-Mar-20 4440 100% I Beam Precast #1
C3990 I Beam Precast #2 7 31-Mar-20 A 05-Apr-20 A 05-Apr-20 11-Apr-20 4440 100% I Beam Precast #2
C4220 I Beam Precast #3 7 06-Apr-20 A 24-Apr-20 A 11-Apr-20 17-Apr-20 4440 100% I Beam Precast #3
C4510 I Beam Precast #4 7 25-Apr-20 A 07-May-20 A 25-Apr-20 01-May-20 4440 100% I Beam Precast #4
C4650 I Beam Precast #5 6 07-May-20 A 15-May-20 A 09-May-20 14-May-20 4440 100% I Beam Precast #5
C4910 I Beam Precast #6 6 16-May-20 A 28-May-20 A 16-May-20 21-May-20 4440 100% I Beam Precast #6
C5140 I Beam Precast #7 20 06-May-20 A 16-Aug-20 A 06-Jun-20 25-Jun-20 4440 100% I Beam Precast #7
C5420 I Beam Precast #8 20 17-Aug-20 A 01-Sep-20 A 04-Sep-20 23-Sep-20 4440 100% I Beam Precast #8
C5770 I Beam Precast #9 20 01-Sep-20 A 19-Sep-20 A 20-Sep-20 09-Oct-20 4440 100% I Beam Precast #9
C5970 I Beam Precast #10 20 19-Sep-20 A 09-Oct-20 A 19-Sep-20 08-Oct-20 4440 100% I Beam Precast #10
C6320 I Beam Precast #11 25 10-Oct-20 A 16-Oct-20 A 10-Oct-20 03-Nov-20 4440 100% I Beam Precast #11
C6600 I Beam Precast #12 25 17-Oct-20 A 15-Nov-20 A 04-Nov-20 28-Nov-20 4440 100% I Beam Precast #12
Lighting Pole Foundation 30 05-Feb-20 A 29-Feb-20 A 23-Feb-20 24-Mar-20 5000 100% 29-Feb-20 A, Lighting Pole Foundation
C6870 Lighting Pole Foundation Precast 50% 15 05-Feb-20 A 20-Feb-20 A 23-Feb-20 09-Mar-20 2500 100% Lighting Pole Foundation Precast 50%
C7160 Lighting Pole Foundation Precast 100% 15 20-Feb-20 A 29-Feb-20 A 09-Mar-20 24-Mar-20 2500 100% Lighting Pole Foundation Precast 100%
Electrical 218 15-May-21 A 18-Dec-21 10-Oct-20 09-Nov-21 2720 43.77%
Lighting 218 15-May-21 A 18-Dec-21 10-Oct-20 09-Nov-21 2720 43.77%
C8000 Lighting Accessories Installation for South Island Causeway 30 15-May-21 A 28-May-21 A 10-Oct-20 08-Nov-20 1200 100%
C8310 Lighting Accessories Installation for KFIP Causeway Expansion 7 30-Nov-21 06-Dec-21 03-Nov-21 09-Nov-21 960 0%
C8830 Lighting Accessories Installation for Access Bridge 3 16-Dec-21 18-Dec-21 26-Sep-21 15-Oct-21 560 0%
Navigation Aids 383 01-Oct-20 A 29-Nov-20 A 29-Oct-20 15-Nov-21 7000 100% 29-Nov-20 A, Navigation Aids
C7310 Navigation Aids Installation for South Island 29 01-Oct-20 A 09-Oct-20 A 18-Oct-21 15-Nov-21 3500 100% Navigation Aids Installation for South Island
C7570 Navigation Aids Installation for North Island 30 10-Oct-20 A 29-Nov-20 A 29-Oct-20 27-Nov-20 3500 100% Navigation Aids Installation for North Island
Mechanical Completion 140 22-Aug-21 A 29-Jan-22 28-Nov-20 31-Dec-21 47320 21.6%
Clearing of Exception "Yes" Items 140 22-Aug-21 A 29-Jan-22 13-Dec-20 31-Dec-21 47320 21.6%
C7740 Clearning of Exception "Yes" Items At South Island 10 23-Aug-21 A 05-Sep-21 A 06-Apr-21 15-Apr-21 2520 100%
C7970 Clearning of Exception "Yes" Items At Navigation 10 22-Aug-21 A 25-Aug-21 A 13-Dec-20 22-Dec-20 700 100%
C8850 Clearning of Exception "Yes" Items At South Island Causeway 15 26-Sep-21 A 07-Nov-21 A 05-Apr-21 14-Apr-21 7000 100%
C8870 Clearning of Exception "Yes" Items At KFIP Causeway Expansion 6 31-Dec-21 05-Jan-22 10-Nov-21 19-Nov-21 3500 0%
C8890 Clearning of Exception "Yes" Items At North Island 10 20-Dec-21 29-Dec-21 27-Jul-21 05-Aug-21 14000 0%
C9000 Clearning of Exception "Yes" Items At Access Bridge 15 15-Jan-22 29-Jan-22 31-Oct-21 09-Nov-21 14000 0%
C9030 Clearning of Exception "Yes" Items At North & South Escape Jetty 13 03-Jan-22 15-Jan-22 13-Dec-21 31-Dec-21 5600 0%
Walkthrough and PMCC 66 20-Nov-21 24-Jan-22 28-Nov-20 22-Nov-21 0 0%
C7830 Walkthrough for Navigation Aids 15 20-Nov-21 04-Dec-21 28-Nov-20 12-Dec-20 0 0%
C8820 Walkthrough for South Island Causeway 15 20-Nov-21 04-Dec-21 19-Feb-21 05-Mar-21 0 0%
C8840 Walkthrough for KFIP Causeway Expansion 14 31-Dec-21 13-Jan-22 31-Oct-21 14-Nov-21 0 0%
C8860 Walkthrough for North Island 15 20-Dec-21 03-Jan-22 27-Jul-21 10-Aug-21 0 0%
C8960 Walkthrough for Access Bridge 10 15-Jan-22 24-Jan-22 31-Oct-21 09-Nov-21 0 0%

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone
 
BERRI DRILLING ISLAND- Revised chedule - Live schedule Dec 2021
Activity ID Activity Name Original Start Finish BL Project Start BL Project BLU Units % Complete 2019 2020 2021
Duration Finish
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AM
C9010 Walkthrough for North & South Escape Jetty 12 19-Dec-21 30-Dec-21 08-Nov-21 22-Nov-21 0 0%
PMCC 71 20-Nov-21 29-Jan-22 22-Dec-20 31-Dec-21 0 0%
C8010 PMCC for South Island 0 20-Nov-21 05-Apr-21 0 0%
C8460 PMCC for Navigation Aids 0 04-Dec-21 22-Dec-20 0 0%
C8940 PMCC for North Island 0 03-Jan-22 10-Aug-21 0 0%
C8970 PMCC for South Island Causeway 0 03-Jan-22 14-Apr-21 0 0%
C8980 PMCC for KFIP Causeway Expansion 0 13-Jan-22 14-Nov-21 0 0%
C9020 PMCC for Access Bridge 0 29-Jan-22 09-Nov-21 0 0%
C9040 PMCC for North & South Escape Jetty 0 29-Jan-22 31-Dec-21 0 0%
C9050 Final Mechanical Completion (FMCC) 0 29-Jan-22 31-Dec-21 0 0%
PROJECT CLOSE-OUT 145 08-Aug-21 A 31-Mar-22 13-Dec-20 31-Mar-22 11750 4.05%

Clearning of Exception "No" Items 92 08-Aug-21 A 06-Feb-22 13-Dec-20 10-Dec-21 1750 28.57%
O1000 Clearning of Exception "NO" Items At South Island 20 20-Nov-21 09-Dec-21 06-Apr-21 25-Apr-21 250 0%
O1010 Clearning of Exception "NO" Items At South Island Causeway 20 05-Dec-21 24-Dec-21 06-Mar-21 25-Mar-21 250 0%
O1020 Clearning of Exception "NO" Items At KFIP Causeway Expansion 10 14-Jan-22 23-Jan-22 15-Nov-21 04-Dec-21 250 0%
O1030 Clearning of Exception "NO" Items At North Island 20 08-Aug-21 A 16-Aug-21 A 11-Aug-21 30-Aug-21 250 100%
O1040 Clearning of Exception "NO" Items At Access Bridge 13 25-Jan-22 06-Feb-22 10-Nov-21 29-Nov-21 250 0%
O1050 Clearning of Exception "NO" Items At Navigation 20 26-Aug-21 A 31-Aug-21 A 13-Dec-20 01-Jan-21 250 100%
O1060 Clearning of Exception "NO" Items At North & South Escape Jetty 18 31-Dec-21 17-Jan-22 23-Nov-21 10-Dec-21 250 0%
Project Close-out 61 30-Jan-22 31-Mar-22 01-Jan-22 31-Mar-22 10000 0%
O1070 Facilities Demolition & Manpower Demobilization 1st Batch 20 30-Jan-22 18-Feb-22 01-Jan-22 25-Jan-22 2500 0%
O1080 Complete As-Built Drawing 12 07-Feb-22 18-Feb-22 01-Jan-22 23-Jan-22 1250 0%
O1090 Facilities Demolition & Manpower Demobilization 2nd Batch 15 19-Feb-22 05-Mar-22 26-Jan-22 19-Feb-22 2000 0%
O1100 Review Cycle of As-Built Drawing 13 19-Feb-22 03-Mar-22 24-Jan-22 15-Feb-22 1000 0%
O1110 Facilities Demolition & Manpower Demobilization 3rd Batch 15 04-Mar-22 18-Mar-22 16-Feb-22 09-Mar-22 2000 0%
O1120 Complete Project Record Books 13 19-Mar-22 31-Mar-22 10-Mar-22 31-Mar-22 1250 0%

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
20-Nov-21
Remaining Work Milestone