Spring 2011 Outline
Spring 2011 Outline
NO MATTER HOW IT READS ON EXAM, IT WILL MEAN ***HOW MANY ARGUMENTS CAN YOU
MAKE TO DEFEND AGAINST ENFORCING THIS CONTRACT?***
I. PERFORMANCE
A. THE PAROL EVIDENCE RULE (PER)– Supplemental Materials: U.C.C. § 202 (CS)
1. What is Parol Evidence?
a) It is extrinsic evidence; anything not inside the four corners of the contract.
b) Parol Evidence arguments will most likely come up concerning --
i. What the contract says
ii. What the parties said prior to contract formation (preliminary negotiations
2. Parol Evidence Rule:
a) RULE: Prevents a party to a written contract from presenting evidence that contradicts or
adds to the written terms of the contract that appears to be whole
b) What do we do with extrinsic evidence?
i. Either use it or do not use it.
ii. Generally, the rule states that extrinsic evidence should not be used in contracts;
iii. Generally, we do not look at evidence that is extrinsic to the 4 corners of the Contract.
iv. Only applies to fully integrated contracts
i. parties intend for this to be the full embodiment of the agreement)
v. The parol evidence rule operates in situations where there is a writing that represents the final
embodiment of the contract or some of its terms. The rule governs whether parties may
introduce evidence of extrinsic agreements to prove the existence of additional or modified
terms.
3. Rationale for Rule:
a) Prevent Fraud/People may lie
b) Can't trust people's memory – Memories fade and distort things
c) Creates more fairness & equity – If don’t have a parol evidence rule juries may be inclined to listen
to it even though it’s not good evidence & it contradicts other good evidence (oral testimony plays
on emotions)
d)
4. Issues:
a) Varies vs. Supplements – Determines whether Parol evidence can be used in partially integrated K.
i. Varies – Contradicts / Negates
i. Parol evidence that varies the terms of the contract
ii. Not allowed
iii. RULE: Using parole evidence not allowed if it contradicts or negates the
partially integrated contract.
(1) Based more on 4 corners – needs a starting point
iv. CASES:
(1) Alaska Northern Development, Inc. v. Pipeline Service Co. (Supreme
Court of Alaska, 1983) (Caterpillar part purchase) (page 665)
a. FACTS: Caterpillar part purchase w/ blank price then later price
entered w/ “subject to final approval owner committee”
b. ISSUE: Can extrinsic evidence be used to determine what "subject
to approval by the owner" means by it's use in the contract
c. P used the "explains" argument b/c it is one of the exceptions that
allows parol evidence to be used.
i. Court rejects this argument b/c while it doesn't
negate/contradict, it doesn't do anything to explain it.
ii. No reasonable person would interpret the words to interpret
them what you said they mean.
d. Court finds the contract to be partial integration and does not allow
the parol evidence.
e. Court says it varied earlier term applied a “Reasonable
Harmony” Test:
i. Absence of reasonable harmony & inconsistency.
ii. They could not read it in reasonable harmony with the
contract.
f. Judges probably like the parol evidence rule b/c they have discretion
in either allowing in the parol evidence or not.
i. Generally, lawyers are probably able to get evidence past
the parol evidence rule.
g. NOTE:
i. if had not been a price, ct would likely have gone with fmv
or something
h. Easiest approach: go with contract and say contradicts/negates =
less slippery slope.
ii. Supplements – Whether it can be read in reasonable harmony
i. Parol evidence that supplements the terms of the contract.
(1) Can it be read in reasonable harmony w/ the K?
ii. Maybe allowed
iii. RULE: Can only allow PE if supplements the partially integrated K, or can be
read in reasonable harmony.
(1) Can only use for definition explanation if there’s ambiguity in first place.
(2) Cannot allow if varies.
(3) Not as stringent – doesn’t necessarily need a starting point.
b) Full Integration vs. Partial Integration
i. Is the contract final (versus a draft)?
ii. RULE: If ALL of intended obligations in written K, K is fully integrated and must
follow Parole Evidence Rule – no extrinsic evidence is allowed. (exceptions below).
iii. Full Integration – of the terms and full understanding of each parties responsibilities is a
complete contract
i. Parol Evidence Rule applies – extrinsic evidence is not allowed
ii. How to best integrate a K:
(1) put integration/merger clause (i.e., “this is the full extent of our K, prior
considerations, etc. are not to be considered…”)
(2) Look for all essential terms – (i.e., price, quantity, etc.)
iii. Cases:
(1) Mitchill v. Lath (Court of Appeals of New York, 1928) (icehouse
removal) (page 656)
a. (boathouse removal) – commercial real estate sale, collateral
agreement, formal long canadi. (“Collateral agreement”)
iv. Partial Integration – of the terms of a contract
i. If what the parties are obligated to do is only partially in K, then is partially
integrated..
ii. Maybe allowed
iii. Cases:
(1) Masterson v. Sine (Supreme Court of California, 1968) (family option to
repurchase) (p.660)
a. (family **option to repurchase) – family real estate sale, no
professionals, informal short deed. (Option K incl terms, how
long/exercise period, price). No integration clause BUT would not
expect to see one in a contract between family members.
b. **option = 1) consideration, 2) can be accepted, updated, rejected
until option period ends. MUST have price term.
v. Two Tests:
i. Majority:
(1) look at the 4 corners of the K (i.e., the explicit language) to determine full
vs. partial,
(2) Is there an integration clause?
ii. Others:
(1) Look to the K plus something else:
a. intent of parties,
b. preliminary negotiations,
c. conduct of parties,
d. PE evidence itself,
e. surrounding circumstances.
(2) Looks at the surrounding circumstances
5. Sub-RULES::
The parol evidence rule does not bar extrinsic evidence offered for the following purposes:
a) to aid in the interpretation of existing terms
b) to show that a writing is or is not an integration
c) to establish that an integration is complete or partial
d) to establish subsequent agreements or modifications between the parties (post-contract negotiations)
e) to show that terms were the product of illegality, fraud, duress, mistake, lack of consideration or other
invalidating cause
6. Exceptions:
a) Arguments Against Parol Evidence Use (i.e., Parol Evidence does NOT apply in these scenarios):
i. Post-Contract Negotiations
i. (PER applies if evidence is prior to or contemporaneous to the K) RULE: Extrinsic
parol evidence is allowed regarding post-contract negotiations. (ex. oral, scribbles
on a contract)
ii. Definition / Explanation of Meaning Issues
i. RULE: May use PE for exclusively determining what an ambiguous term means. -
Courts usually permit it
iii. Contract Formation Issues/Questions (i.e., Offer/Acceptance/Consideration)
i. (if they don’t contradict). RULE: PER does not apply to an oral agreement that is
related to but separate from the integrated writing. If you can prove to ct. that
you’re just proving two agreements, PER doesn’t apply. Two contracts, same
subject. (Mitchill)
iv. CASE:
i. Luther Williams v. Johnson (unintegrated finance condition)
(1) Homeowners thought it was only an estimate,
(2) contractor thought it was a K.
(3) ct. held no contract in first place b/c the writing was not intended to be a
complete statement of the agreement of the parties.
B. CONTRACT INTERPRETATION (RULE, TOOLKIT) – Heirarchy U.C.C. 1-205 (CS)
1. Express terms (e.g. definitions section of the contract itself, dictionaries to determine common
usage of a term, cross-references)
2. Course of Performance (e.g. Rest. 2-208) – what occurs after the contract has been formed…what
did you do post-formation so far, how did you perform so far?
3. Course of Dealings (UCC 1-205) – how the parties dealt with each other prior to this contract
formation (usually suggests repeated interactions, i.e. previous contracts and dealings between the parties)
4. Trade Usage (UCC 1-205, etc.) – is there a custom or trade usage?
5. Reasonableness of one interpretation over the other = “justice” = the catch-all when nothing else
has worked! Therefore, usually don’t even get to the following:
6. Other aids
a) **Construe Against Drafter (common! when there’s a contract case w/ a true interpretation issue)
b) Expression of One Excludes the Other (“we’re buying all on floors 2 and 3…so by definition not
buying what’s on 1, 4, 5)
c) Specific over General (see below)
d) **Negotiated over Non-Negotiated (lengthy and detailed language vs. boilerplate generic
language/form contract)
e) No Surplusage (every part of contract has to have some meaning, no duplication
7. CASES:
a) A. Kemp Fisheries, Inc. v. Castle & Cooke, Inc., 852 F. 2d 493 (9th Cir. 1988) (United States Court
of Appeals, Ninth Circuit, 1988) (unseaworthy boat - City of San Diego) (TWEN)
i. FACTS: P contracted to charter D’s boat; P noticed contract differed from “letter of intent”
previously signed in that it disclaimed all warranties; P didn’t say anything & signed
contract; later the boat’s freezing system malfunctioned & cost the P his fishing profits
ii. Court found contract was fully integrated & parol evidence rule bars extrinsic evidence
iii. When contract is fully integrated don’t have to determine if extrinsic evidence varies or
supplements, but court looked anyway & found it would contradict the explicit disclaimer in
the contract
iv. parol evidence rule requires that courts consider extrinsic evidence to determine whether the
contract is ambiguous…But if the extrinsic evidence advances an interpretation to which the
language of the contract is not reasonably susceptible, the evidence is not admissible.
v. Not going to allow extrinsic evidence to define the term “good condition” b/c it would create
an unreasonable construction of the term- extrinsic evidence will not go to reasonable
interpretation of the term
b) Frigaliment Importing Co. v. B.N.S. International Sales Corp. (United States District Court, S.D.
New York, 1960) (what is chicken?) (page 690)
i. FACTS: P wants smaller chicken (for broiling & frying) & gets the larger chicken (for
stewing)- smaller chicken is more valuable
ii. P argues on face of contract that only young chicken come in small size & since adult
chicken doesn’t come in small size the larger chicken must also be young chicken
iii. Court looks at contract itself which references the Department of Agriculture, Grade A,
Government Inspection
iv. Pre-contractual correspondence- negotiation between the parties
v. Custom usage or trade
vi. Performance- Conduct of parties
i. Post-contract formation = not barred by parol evidence
vii. Dictionary definition of “chicken” = still not helpful
viii. Course of prior business dealings = 1st time these parties have done business
ix. Market price for broilers v. fowl
i. Market price for broiler was between 35 & 37 cents (info was known by P)- would
be unrealistic for D to sell chicken at a lower than market price (33 cents) & suffer
loses – people will make profitable contracts!
(1) Really only decent evidence the Court has
x. Court is NOT using parol evidence here- it is looking at all sorts of extrinsic evidence
xi. Neither points of view are unreasonable so will permit extrinsic evidence- similar to Peerless
except this is an interpretation case not a mistake case. So, difference in the remedy.
i. Mistake:
(1) Remedy = non-enforcement
a. Leaves parties as it finds them.
b. Void the contract.
ii. Interpretation:
(1) Remedy = pick a side & enforce the contract with the interpreted terms;
a. Court should enforce – courts have a natural preference to enforce
the contract than to void.
xii. Other Rules of interpretation
i. Construe against drafter last on hierarchy
(1) If Court here decides to construe against the drafter; it looks like P is the
drafter (D made 1st offer) & case would turn out the same
ii. Separately negotiated terms are going to trump standardized terms
iii. Duty to take an affirmative act such that the contract can be performed by both
sides (i.e. looking for financing if contract to buy a house)
C. SCOPE AND CONTENT OF THE DUTY OF GOOD FAITH – Supp. Material: U.C.C. Secs. 2-708 and 2-306 (CS)
1. 4.1 Rules of Professional Conduct: “Truthfulness In statements to Others: In the course of
representing a client a lawyer shall not knowingly:
(a) make a false statement of material fact or law to a third person; or
(b) fail to disclose a material fact to a third person when disclosure is necessary to avoid assisting a
criminal or fraudulent act by a client, unless disclosure is prohibited
Truthfulness requirement DOES NOT include price and value, settlement negotiations!
2. RULE: A duty of Good Faith is implied in all contracts, to deal with each other fairly and
ensure each gets the benefit of the bargain.
a) Timing
i. After Formation vs. Prior to Forming
i. Pre-contract? No – No OGF prior to contract formation
ii. Pre- Contract and Lawyers? No OGF (handout RPC 4.1)
iii. Cannot lie about material facts BUT price and value are not considered to be facts
iv. Post-Contract – OGF in all contracts, including modifications.
b) Type
i. All? – Yes, implied in all contracts and
i. RULE: OGF in a contract cannot be disclaimed
ii. Mandatory vs Default (UCC 1-302 & 1-304) – generally, standards/rules/principals of K’s
are governed by default rules that can contract around if so agree. OGF mandatory per 1-
302. However, hard to successfully contract around OGF – although lawyers try to do it;
even if put language in a contract trying to contract around OGF by putting in conditions,
those conditions must still be “reasonable”
iii. Employment Agreement? Sometimes – see below
iv. Modifications? Yes – modification is essentially a new-formation contract occurring after
the formation of the first contract. See JC Penney case below
c) Requirements of Duty of Good Faith in all Contracts = essentially “truthfulness”
i. Less than Best Efforts required (“best efforts” MUCH stronger than “good faith”)
ii. Duty to Refrain from misrepresentation
iii. Duty to Act/Disclose
d) Two Tests: Evidence of good/bad faith
i. Objective test
i. Predominant rule.
(1) RULE: Evidence that reasonable person in that situation would be
dissatisfied is the objective test for good faith.
ii. ***Abuse of Discretion main test - Whether one party has discretion, and whether
or not the party vested w/ discretion vested it unreasonably/unfairly – if they have
used it unreasonably, then they’ve violated
(1) OGF RULE: When one party has discretion and abuses it by using it
unreasonably/unfairly, they have breached the duty of good faith.
Objective evidence of bad faith can be proof.
iii. Burton test. applies objective criteria to identify the unstated economic
opportunities intended to be bargained away by a promisor as a cost of
performance (attempt to renegotiate and take stuff already agreed to, “negotiate
bygone opportunities”)
(1) RULE: the Burton test for good faith applies objective criteria to
identify whether a party has attempted to renegotiate and take back
what they had already bargained away.
ii. Subjective test –
i. Minority rule exception to Objective Test: Evidence that my client is really
dissatisfied.
(1) RULE: the minority test for good faith requires honesty in fact from
an individual.
ii. Personal Fancy Contracts (ex. for massage)
iii. Merchants vs. non-merchants - ct may let non-merchant use subjective test (ex.
returning something to Wal-Mart).
iii. Cases
i. Centronics (unreleased escrow) –
(1) D acted in good faith in refusing to release a portion of the escrow fund
during arbitration- there was no breach of duty of good faith
ii. Market St/JC Penney (Judge Posner’s take on Good Faith) –
(1) “Good faith” is a compact reference to an implied undertaking not to take
opportunistic advantage in a way that could not have been contemplated at
the time of drafting, & which therefore was not resolved explicitly by the
parties.
(2) Posner says parties at pre-contract stage are naturally wary so there is no
deception (or duty to disclose all this info)
iii. Neumiller Farms (potato chipping pretext)
e) Types of Contracts and Good Faith
i. Modifications –
i. RULE: Modification of a contract requires good faith and fair dealings.
ii. Output contracts – UCC 2-306 – 2-306(1):
i. RULE: An output contract requires best efforts by the parties to the contract.
ii. Motive – the “best efforts” requirement stronger than OGF;
(1) RULE: motive is element of bad faith
iii. RULE: UNLESS Bankruptcy (close business, liquidate assets, & pay debts) or
genuine business peril- Can only stop/reduce production under 1 circumstance=
when business itself is in genuine peril (bankruptcy)
iv. CASE:
(1) Feld v. Henry Levy (bread crumb supply)
a. D stopped crumb production w/o giving P-buyer 6 months notice).
b. Good faith required continued production until cancellation, even if
there be no profit.
c. This was only small part of D’s business.
iii. At-Will Employment – RULE: At-will employment agreements generally can be
terminated for any reason unless contract states specifically otherwise. OGF IS in
specific term employment contracts.
i. Vast majority of employment agreements are employment at will contracts
ii. Employer’s interest in running his business as he sees fit must be balanced against
his interest of the employee in maintaining his employment & this exception does
not strike the proper balance.
iii. Default rule: RULE: employment contract silent as to whether at-will employment
vs. employment for “specific term” = employment is at will and employee can be
fired for any cause whatsoever.
(1) Argument that default should be different because employees mistakenly
think can only be fired “for cause,” whereas employers know reality of
legal landscape. BUT – if change default, employers can just put 2 – 3
sentences expressly into a written K that “I can fire you for whatever
reason I want.” So, no big change.
iv. Limitations to no OGF in “at will” contracts: RULE: OGF may exist in an at-
will contract when:
(1) Public policy requires it. (as determined by judges – e.g. spite/malice,
revenge, notice is suspect)
(2) Statutory protections exist. (e.g. discrimination on race, sex)
(3) Some states req. Good Faith, limits discretion of employer
a. Requires cause (ex. a progressive state)
b. Requires cause-plus (ex. long length of employment, other evidence
of a company policy that “we keep people around,” etc.)
c. Requires compliance w/ public policy (i.e. notice, no spite/malice,
no revenge)
(4) Company handbooks/manuals
v. Cases:
(1) Hillesland v. Federal Land Bank (dismissal for conflict of interest)
Misunderstanding
Ambiguous term: Where a contract term is ambiguous and one party should know the meaning
understood by the other party, a contract is formed based on the other party's understanding.
Example: In October, C, an art collector, telephones A, an artist, and says, "In February I saw
your painting of Sunflowers. Is it still available, and, if so, how much do you want for it?" The
contract they later sign states: "A hereby sells to C A's sunflower painting …" C was referring to a
painting entitled "Sunflowers." In July A had painted another picture of sunflowers entitled
"Sunflowers II," and A subjectively was referring to this painting in the contract. C had the first
"Sunflowers" in mind. Since C mentioned that he had seen the painting in February, A should have
known that C was referring to the first "Sunflowers." Therefore, a contract exists, and for the first
Sunflowers.
On the other hand, if neither party was at fault in the misunderstanding, the lack of agreement
on which painting was intended would be great enough to cause the contract to be void for
misunderstanding.
I. Exam Tips on MISTAKE
Mistakes as to Existing Fact
Use the term "mistake," and the analysis in this chapter, only to cover those situations involving a
mistake as to the facts as they existed just prior to the contract. Where the parties are operating under
a mistaken assumption about future events (e.g., future market prices), use the
Impossibility/Impracticability analysis given in Ch. 12.
Mutual Mistake
The topic most frequently tested from this chapter concerns a mistaken assumption made by both
parties to the contract (mutual mistake). Before concluding that there has been a mutual mistake—and
that the contract can therefore be avoided by a party who is injured by the mistake—make sure that all
3 requirements are met:
(1) Mutuality. Make sure that both parties made the same (ultimately wrong) assumption when
entering into the agreement.
(2) Materiality. Make sure the assumption was "basic" to the bargain, and that the mistake had a
material effect on the agreed-upon exchanges. Watch for these situations:
Real estate transactions. Look out for a sale where there has been a mistaken acreage
count and the total acreage contained in the contract can't be conveyed by the seller.
If the portion of land that cannot be conveyed is large or otherwise significant, then
its inclusion was probably a basic assumption of the contract. But if the parcel that
cannot be conveyed is insignificant (e.g., a 3-foot-wide strip along one end of a 50
acre parcel), then it probably would not be considered a basic assumption of the
contract.
Purchase of a unique good. Look for the purchase of a unique work of art where the
parties are mistaken as to its origin or creator. These will probably be basic assumptions.
Example: D, an art dealer, receives from one of her purchasing agents a painting entitled
"Sunset" which she is informed was painted by Van Goon. C, an art collector, sees the
painting at D's gallery and says to D, "What an interesting Van Goon." D responds
(honestly believing that he's telling the truth), "Yes, it is." C pays $50,000 for the painting,
its worth had it been a genuine Van Goon. C later finds out that the painting is a forgery
worth only a few hundred dollars and stops payment on her check. The assumption about
authorship was almost certainly a basic assumption, so C's nonperformance is probably not
a breach.
(3) Allocation of risk. Make sure the parties did not explicitly or implicitly allocate the risk of
the mistake to the party who is now trying to avoid the contract. (If they did so allocate the
risk, that party can't use the doctrine.) Also, remember that the court can allocate the risk of
mistakes wherever it is "reasonable" to do so.
Examples of situations where courts usually find an implicit allocation of risk of mistake:
Minerals in the land: The risk that there will turn out to be valuable mineral deposits is
allocated to the seller. (Example: S and B enter into an agreement for the sale of Farmland
for $8 an acre. Oil is then discovered under the land. S may not avoid the contract, because
he'll be found to have implicitly borne this risk, assuming the contract is silent.)
Auctions with object of unknown characteristics: At an auction, the risk that the item
won't have some desired attribute—where both the auctioneer and the buyer know that the
existence of that attribute is unknown—is allocated to the buyer.
Example: Auctioneer offers a 2-month-old calf at auction. Breed buys the calf for
$1,000, believing that the calf will prove fertile (as most calves are). No express
warranty is made about fertility. Two years later, the calf is conclusively shown to
have been born sterile, making it useless for Breed's purposes (of which Auctioneer
was aware). Had this fact been known at auction-time, the calf would have been
worth $150. Both parties knew at auction time that the fertility of a calf can't be
measured until it is at least 1 year old.
Breed can't rescind for mutual mistake. That's because both sides knew that the
fertility of the item couldn't be known, and the circumstances implicitly allocated to
the buyer the risk of a mistake on this point.
Building conditions: In a construction contract, the risk of undiscovered
unfavorable building conditions is normally allocated to the contractor.
Example: X is hired to drill a well for Y, to be completed by June 1. Two
hundred feet down X's drill strikes a solid layer of rock and breaks, plugging
the hole. It's no longer possible for X to complete the drilling of the well by
the agreed-upon date. Even though the accident may have been unavoidable and
neither party was aware of the rock which caused the drill to break, X may not
rescind the contract, because the contractor implicitly bears the risk of such
conditions if the contract is silent.
However, always make sure that the contract language or surrounding circumstances
don't effectively allocate the risk in a different way.
Unilateral Mistake
Where only one party has made a mistake (unilateral mistake), he is excused from performance only
if the other party knew or should have known of the mistake.
If you don't know whether the other party knew or should have known of the mistake, argue the
evidence in support of each view, and then state that the result depends on which way the
"knew/should have known" issue is resolved.
Most common scenario: A unduly low bid is submitted by a sub-contractor to a general
contractor, on account of the sub's computational error. If the general contractor should have
realized that an error was made, the sub can get discharged.
Example: C, a contractor, solicits bids from sub-contractors for a construction job to be
performed for X. S, a sub-contractor, delivers a bid for the foundation work in the amount
of $140,000. The next lowest bid that is submitted to C is $150,000. Relying on S's bid, C
immediately submits its overall bid to X. Fifteen minutes later, S telephones C and says
that there was a mistake in the calculation and revises its bid to $170,000. Since the next
lowest bid was only $10,000 more than S's bid, C probably did not have reason to know
that S's bid was a mistake, in which case S will be not be able to avoid the contract based
upon unilateral mistake.
Reformation
If there is a clerical error and a written agreement doesn't accurately reflect the parties' agreement, the
aggrieved party can have the contract reformed to reflect the prior agreement. This usually occurs regarding
price: the contract states a different price than the one agreed upon, or leaves out the agreed-upon price
altogether.
Liquidated damages available: Remember the majority rule that the existence of a liquidated damages
award does not bar the remedy of specific performance.
Example: Buyer, a corporate transferee from out of town, contracts with Seller for the purchase
of Seller's house. Because Buyer plans to move her family on April 20, the contract provides that
the house is to be vacant and ready for occupancy by that date. The contract also contains a
liquidated damages clause and provides for payment to Buyer of $75 for each day after April 20
that the house isn't ready for occupancy. On April 20, Buyer moves her family into town and the
house isn't vacant, so they stay at a motel. On May 1, Seller informs her that he doesn't intend to
go through with the contract. Buyer may sue both for specific performance of the land contract
and for liquidated damages—since specific performance would be otherwise appropriate (it's a
contract for the sale of land), the court won't deny that remedy merely because Seller is also
subject to a liquidated damages clause.
Expectation Damages
This is the standard measure of damages for breach of contract. Expectation damages are awarded to
put the plaintiff in the position she would have been in had the contract been performed.
Formula: Expectation damages are usually calculated as:
the value of defendant's promised performance (generally the contract price) less
the benefits to plaintiff (i.e., money saved) from not having to perform her end of the
contract.
Hint: You should always discuss expectation damages in any fact pattern where the contract
was valid and one party materially breached.
Common scenario: A contractor partially performs, and either the hiring party obtains a substitute
performance, or the contractor wants to be reimbursed for his partial work.
Substitute performance example: Owner owns a farm in County. She hires Driller to drill
a water well. The contract provides for a guaranteed completion by June 1. The contract
price is $10 a foot and Driller is to be paid $3,500 in advance, with any refund or
additional payment to be made on completion. Two hundred feet down, Driller's drill
strikes rock and breaks, plugging the hole. Driller refuses to start a new hole. Owner hires
Dan to drill the well for $4,500. Dan strikes water at 300 feet.
Because of Driller's repudiation of the contract, Owner may recover the $3,500
advanced to Driller (since she got no value for that advance) and the $1,500 difference
between the price for the substitute performance and the contract price (which would have
been $3,000 for a 300-foot well).
Reimbursement example: Contractor, a building contractor, enters into a contract with
Manco, a manufacturer, for the construction of a two-story factory on Manco's parcel of
realty for $250,000, to be paid upon completion. When the factory is partially completed,
Manco decides to retire from the manufacturing business, and tells Contractor to stop
work. Contractor has already spent $180,000 on the construction and would need to spend
another $35,000 to complete the building.
Contractor can collect expectation damages of $215,000, calculated as the contract
price ($250,000) minus the cost to him of completion ($35,000).
Reliance Damages
Reliance damages come into play when expectation damages would not adequately compensate the
plaintiff, or where there is no enforceable contract, but plaintiff is entitled to some protection anyway.
Most commonly, reliance damages generally appear on exams in questions involving promissory
estoppel.
Example: Buyer and Seller orally agree that Seller will sell Blackacre to Buyer for $200,000, with
Seller to deliver the property with a presently-existing unsightly shed at the back removed. Seller
spends $5,000 to remove the shed. At the time for closing, Buyer fails to tender the purchase
price. Seller won't be able to recover contract damages, since the contract is for the sale of an
interest in land, and thus was required to be in writing. However, Seller will probably be able to
recover on a promissory estoppel theory, in which case he'll recover the $5,000 spend on shed-
removal, since that cost was incurred in direct and reasonable reliance on the oral agreement.
Restitution Damages
Restitution damages are defined as the value to the defendant of the plaintiff's performance. (Think
unjust enrichment.) Restitution damages can be awarded in a suit on the contract, or in a suit brought
in quasi-contract.
Example (suit on the contract): Duster, the owner of crop-dusting planes, enters into a contract
with Farmer, a farmer, for the dusting of Farmer's crop four times a year for four years for a total
of $10,000, which is paid upon the signing of the contract. After two years, Duster sells her
business to Newco, assigning the contract with Farmer to Newco.
If Newco fails to perform, Farmer may collect as damages from Duster the $5,000 unearned
portion of the money paid to Duster, since Duster has been enriched by not performing the final
two years. (Alternatively, Farmer could try to recover the "benefit of her bargain" —the amount, if
any, by which the $10,000 contract price was less than Farmer's total payments would be by the
time she procured a substitute duster for the last 2 years. But the point is that even without proof
of cost-of-substitution, Farmer can recover the unpaid deposit on a restitution-damages theory.)
Quasi-contract
Quasi-contract recovery is an important possibility to keep in mind whenever you are discussing
the possible remedies available. Always consider relief based on quasi-contract when the aggrieved party
is not entitled to damages for breach of contract. Remember that recovery will be the reasonable value
of the services rendered. Watch for these situations:
Contract never formed: Look for a fact pattern where an enforceable contract was never formed.
The party providing the services may be entitled to recover in quasi-contract if he had a
reasonable expectation of payment for those services (i.e., he did not intend them as a gift).
Common trick scenario: A party performs emergency services for a person in peril.
Usual conclusion: The savior has performed without an expectation of payment for
services or for losses incurred as a result, and therefore may not recover in quasi-contract.
Contract rendered unenforceable: Look for an originally-enforceable contract that only later
becomes unenforceable, i.e., where a party is excused from performing for some reason. Although
the performing party isn't entitled to contract damages, he may still be able to recover in quasi-
contract. This is most likely in cases of impossibility/impracticability and frustration of purpose.
Example: Owner owns a piece of undeveloped land adjacent to City Airport. On January
2, Owner enters into a contract with Architect, an architect, whereby Architect agrees to
produce and deliver by May 1 a design of a ten-story hotel which Owner wishes to build
on that land. On March 31, it's announced that City Airport flight operations will cease at
the end of the year, making it pointless for Owner to build the hotel. Owner refuses to
accept the completed hotel design from Architect on May 1.
If Owner is excused from performing because of frustration of purpose, Architect will
still be able recover the reasonable value of services rendered up until March 31, when the
event excusing Owner's performance occurred.
Building destroyed before completion: Look for a fact pattern where, through no fault of
either party, the structure that is being built is destroyed and the contractor refuses to begin
work again:
If the construction is of a new structure, the contractor is usually allocated the risk,
so he isn't excused from performing, and therefore may not collect damages in
quasi-contract for the value of the services performed through the time of
destruction.
If the construction involves a repair of an existing structure, then the contractor will
probably be excused from performing because of frustration of purpose and/or
impossibility, since the continued existence of the building is a basic assumption
upon which the contract is based. The contractor may, in that case, recover in
quasi-contract for the value of the work performed up until the time of the
destruction.
Partial performance, then breach: Quasi-contract remedies are frequently used by the party who
has partially performed but then breaches a contract, as a way to set-off the damages it owes to
the nonbreaching party. Look for a breaching contractor who hasn't substantially performed but
has nonetheless provided the owner with something of value.
Example: O contracts to have C, a contractor, build O a house on O's land. The contract price
is $300,000. C does about half the work, then defaults. The reasonable value to O of the work
done is $125,000. C has received a $60,000 deposit. It will cost O $225,000 to get another
contractor to finish the job (meaning that if O has to pay the full value of C's work less the
deposit, O will be $50,000 worse off than had C fully performed). C can recover $15,000,
calculated as follows:
Reasonable value of work done, less deposit received and less O's damages for the breach,
or
$125,000 minus ($60,000?+?$50,000)?=?$15,000
Extra damages: If the standard expectation measure doesn't fully compensate a party for her losses,
remember that the additional damages can also be recovered. These are often called "consequential"
damages.
Example: C agrees to renovate O's house for $50,000, by March 1. C gets a $25,000 deposit,
does half the work, then defaults. O hires a replacement, X, who finishes the job for $25,000. The
standard expectation "benefit of the bargain" measure would give O $0 recovery, because there is
no difference between the contract and market price. But if X can't finish the job until April 30,
and O can't move in during the month of April, O will probably be able to recover the cost of
procuring substitute lodging for that month—the lodging costs will be "consequential" damages,
and will be on top of the contract/market differential.
Foreseeability: But remember that consequential damages are subject to an important limitation:
the requirement of foreseeability. Determine whether the additional losses were either: (1)
reasonably foreseeable to an objective observer in D's shoes, based on general principles; or (2)
foreseeable based on the plaintiff's special requirements, of which D had notice. (Remember that
this is basically the rule of Hadley v. Baxendale.) If the losses don't fall into either category,
they're not recoverable.
Example: Seller and Buyer enter into a contract for the sale of 10,000 pounds of
specifically described bolts each month for a period of ten months beginning March 1; the
contract has a total value of $40,000. On March 1, Seller informs Buyer that he will not
deliver any bolts to Buyer because he has just contracted to sell his entire output to another
buyer for a higher price. It takes Buyer 61 days to find a new supplier; the new supplier
charges the same price. Because of the delay in finding a new supplier, Buyer is late in
delivering motors to End User, a company with which Buyer has a contract containing a
valid liquidated damages clause providing for damages of $10,000 a day for delays in
delivery of motors. Although Seller knew that Buyer sold motors, Seller didn't know about
Buyer's specific contract with End User. May Buyer recover from Seller the $610,000 he is
required to pay End User under the liquidated damages clause?
Probably not, because it probably wasn't foreseeable to Seller that a 2-month delay in
delivery on a $40,000 contract would bring about $610,000 in losses. Buyer's needs—in
particular his need to avoid heavy liquidated damages—were probably "special
requirements" that cannot be the basis for recovery unless Seller knew about them at the
time of contracting.
Mitigation
Be sure to discuss whether the nonbreaching party has attempted to mitigate damages in a situation
where the loss was partially or totally avoidable—if she didn't, any damages that would probably have
been avoided by such an attempt are non-recoverable.
Look for a terminated employee, who fails to make reasonable efforts to find a suitable
replacement job.
Look for a disappointed buyer or recipient of services.
Example: B, the owner of a furnace-repair company, maintains a fleet of personal trucks
for his employees' use and drives his personal station wagon when visiting customers'
homes. On February 15, B orders a new station wagon from S, a car dealer, to be delivered
by March 5. On March 4, B sells his old station wagon because of the expected delivery of
the new car the following day. However, the new car isn't delivered to S until March 30. B
sues S for lost profits because of his inability to travel to customers. B won't recover for
this: although business losses were foreseeable at the time of contracting, B could have
mitigated his damages by renting a car or using one of the company's trucks.
Liquidated Damages
Reasonableness: Remember that the liquidated damages amount will be deemed (in most courts)
reasonable if it is a reasonable estimate as of either the time of contracting or the time of the actual
loss. Normally, you should try to analyze the reasonableness as of each time frame.
Other points to watch for:
Pay attention to what the clause remedies. Even where the clause is enforceable, other types of
damages can still be awarded to address problems not covered by the clause.
Example: O and C, a contractor, enter into an agreement for various repairs to be made to O's
home. The contract provides that the repairs are to be completed within sixty days, and that if
C fails to complete the job on time, C will pay O$50 per day as liquidated damages. After the
repairs are finished, O discovers that C did a faulty job on one aspect, the roof; she has another
contractor redo the repair for $1,000. Since the liquidated damages clause only redresses late
performance, it doesn't eliminate the possibility of O's collecting damages for defective
performance in the amount of $1,000.
Damages in Sales Contracts
Buyer's damages: This area is more heavily tested than that of seller's damages. Several reminders:
Standard "contract/market" differential: If a buyer returns defective goods (or fails to receive
any shipment of goods from the seller) and doesn't purchase replacement goods elsewhere, she is
entitled to the difference between the contract price and the market price at the time of breach.
Cover: If a buyer returns defective goods (or fails to receive any shipment of goods from the
seller) and purchases them elsewhere, she is entitled to the difference between the contract price
and the cover price.
The buyer's cover price paid by the buyer must be reasonable in the circumstances. Look
the buyer's attempts to find a good price (or at least to verify the true "market" price)—if
these are absent, discuss the possibility that the buyer may have behaved unreasonably and
should be denied the full contract/cover differential.
Remember that if the market price (or the cover price) and the contract price are the same, there
are no damages to collect, except consequential or incidental ones.
Note: Where the market price or cover price is less than the contract price, the buyer gets
the benefit of the difference with no off-setting to what the seller owes for consequential or
incidental damages.
Breach of warranty: If a buyer accepts defective goods the damages are calculated as the
difference between the value which the delivered goods had at the time of acceptance and the
value which conforming goods would have had at the time.
Specific Performance: The buyer can only get specific performance if the goods are unique.
Seller's damages: The most testable issue in this area is whether a seller can be compensated for lost
profits. Trick: The seller appears to have suffered no damage because he resold the item or items for the
contract price or for an amount in excess of the contract price. Your inquiry should not end there,
however.
"Lost volume" seller: Look for a seller who has a supply of goods in excess of the level of
demand (the "lost volume" seller). He has lost a sale and is entitled to his lost profits—even if he
resold the goods in question—because he could have had both sales but for the breach.
Example: S, a computer reseller, contracts to sell a Model 101 Xtra personal computer
(made by Xtra Corp.) to B, for $3,000, delivery to occur Oct. 1. (The price from Xtra to S
will be $2,200.) On Oct. 1, B unjustifiably repudiates. S resells the same computer to T for
the same $3,000. The Model 101 is a popular computer, and S can get as many of it as he
wants from Xtra, with rapid delivery. What are S's damages?
S is a lost volume seller—although he's sold the computer in question to a different
buyer for the same price, he's lost one net sale due to B's breach, since S could have a
different copy of the 101 to T if B had honored the contract. Therefore, S is entitled to
$800 (plus any incidental damages), representing the profit that S would have made on the
sale to B if it had occurred.
Limited supply: But if the seller resells all the available goods of the type that is the
subject of the contract, then he is not a lost-volume seller and cannot collect lost profits for
the breach.
Deduct costs: Remember to deduct from all recoveries the costs that the aggrieved buyer or seller
didn't incur as a result of not having to complete his performance.
Punitive Damages
Remember that punitive damages are ordinarily not recoverable in breach-of-contract actions.
(However, if the breach was also independently a tort—as in fraud—punitives may be recoverable.)
VII. Exam Tips on CONTRACTS INVOLVING MORE THAN TWO PARTIES
Material from this chapter is heavily tested. Look for a fact pattern where rights or duties are created in a
third person either when or after the contract has been executed.
Assignment and Delegation
Remember that an assignment is a transfer of contract rights, and a delegation is a transfer of contract
duties.
Be sure to check whether the contract may be assigned, and/or delegated:
When assignment is allowed:
Consideration: Don't worry if the assignment isn't supported by consideration. Consideration is
unnecessary where there's a present transfer of rights.
Generally permissible: Where the contract is silent on whether assignment is allowed, the
contract is assignable, even without the obligor's consent.
Anti-assignment clause: If a contract contains an anti-assignment clause, an act of assignment
gives the obligor a right to damages against the assignor for breach, but does not render the
assignment ineffective (unless the assignment imposes an material additional burden on the
obligor, or would be void for some other reason independent of the anti-assignment clause).
When delegation is allowed:
Nondelegable duties: In delegation cases, check that the duties are in fact delegable. Remember
that the main rule is that delegation is permitted unless the obligee (the one to whom the delegated
performance is due) has a "substantial interest in having the delegator perform."
Personal services: Contracts for performance of personal services are generally not
delegable by the person who would do the work.
Example 1: Contracts of employment, which are not be delegable by the employee.
Example 2: Contracts with independent contractors possessing special personal skills,
such as musical performers, interior decorators, architects, computer programmers, etc.
Note: In these personal-service circumstances, the delegation may be deemed an
anticipatory repudiation, in which case the obligee can immediately cancel the contract
and sue the delegator for breach.
Construction contracts: Generally, an obligation under a construction contract is not
considered a personal service and may be assigned.
Important distinction: A delegation of the duty to perform personal services is more likely
prohibited than an assignment of the right to receive the services (which is prohibited only
if it materially alters the duty of the obligor).
Example 1: The rights to receive the benefits of a one-year contract for gardening
services performed for an owner of a condominium may probably be transferred to the
party to whom he sells the condominium. (The duty to make payment may also be
assigned, though the assignor remains liable as guarantor.)
Example 2: The rights to a musical performance at one party's wedding may be
transferred to another party having a wedding, if all the contract terms (place, time, date,
contract price) are the same.
Waiver: Remember that even if the contract is nondelegable, the right to object may be waived.
Example: Ohn, the owner of a piece of undeveloped land, enters into a contract with
Arch, an architect, whereby Arch agrees to produce and deliver by May 1 a design of a
ten-story hotel to be built on the land. On January 15, because of health problems, Arch is
ordered to take a six-month break from work by his physician. Arch signs a documents
"assigning" to Bench—a well-known architect with whom Arch has sometimes
collaborated—all Arch's rights and duties under the contract with Ohn. One week later,
Bench meets with Ohn to discuss preliminary plans with him. Thereafter, he communicates
with Ohn by phone. When Bench submits the completed design on May 1, Ohn refuses to
accept it.
Ohn, by failing to object to the assignment during his initial encounters with Bench,
has probably waived his right to object.
Demand for assurances: When the party who is owed the performance receives notice of a
delegation of duties, she may demand assurances of performance from the delegatee, and may
suspend her own performance until assurances are furnished.
Rights and obligations on assignor/delegator side: Remember to evaluate the rights and obligations of
the assignor or delegator.
Assignor's right to revoke:
Assignor relinquishes rights: In an assignment, an assignor's rights are extinguished once there
has been an effective assignment. Therefore, don't make the mistake of allowing the assignor to
sue to enforce rights previously held by her.
Assignments for consideration are irrevocable: Also, watch for an assignment that is supported
by consideration—such an assignment is irrevocable, so the assignor can't change her mind and
cancel the assignment.
Gratuitous assignment: By contrast, a gratuitous assignment is revocable by the
assignor, unless one of the following happens:
the assignor delivers a symbolic document evidencing the rights (e.g., hands over a
bankbook, which would make assignment of the bank account irrevocable);
the assignor puts the assignment in writing;
the assignee foreseeably relies to his detriment on the assignment; or
the obligor gives performance to the assignee.
Delegator's ongoing liability:
A delegation of contract duties doesn't divest the delegator of her obligations to the obligor.
Thus, the delegator can be sued if the delegatee breaches.
Example: Store, a retailer of home gardening supplies, enters into a one-year contract
with Seedco, a wholesaler of seeds, whereby Seedco will supply Store with all of its
requirements for rye grass seeds on a monthly basis. After delivering one delivery of rye
grass seeds to Store, Seedco sells its business to Byer, who fulfills Store's next month's
requirement of seeds. Store pays Byer for the seeds, but also demands that Byer assure it
that it will be able to meet Store's future rye grass seed needs. Five weeks later Store has
still not heard from Byer and notifies Seedco and Byer that it's canceling the contract.
Store may successfully sue Seedco for breach of contract—the delegation by Seedco to
Byer did not relieve Seedco of liability if Byer should not perform.
Trap: A fact pattern may indicate that an obligee has consented to the delegation. This
consent does not relieve the delegator of liability, unless the obligee explicitly agrees
to release the delegator (in which case there is said to be a "novation." )
Rights and obligations of assignee: Also, analyze the rights of the assignee.
Assignee's rights: The assignee is entitled to enforce the contract rights to the same extent that
the assignor could have—the assignee "steps in to the assignor's shoes."
Subject to defenses: However, the assignee's right to enforce the contract is subject to any
defenses which could have been asserted against the assignor, such as breach of the assignor's
return promise, lack of consideration, or occurrence of a condition to the defendant's duty.
Example: Pawn, a pawnbroker, sells to Jewel, owner of a jewelry store, a ring for
$2,500, representing it to contain a diamond. The following month, Pawn sells Jewel a
pearl necklace for $2,200, to be paid for within thirty days. Before Jewel pays for the
necklace, he learns that the ring he previously purchased contains a cubic zirconia and
is worth only $300. A day later, Pawn assigns his rights to payment for the necklace to
Art. Since Art steps into Pawn's shoes, if Art sues Jewel for payment on the necklace,
Jewel can successfully assert against Art (at least as a set-off to reduce Art's recovery)
the breach-of-contract claim regarding the ring.
Warranty of no defenses: An assignor (at least one who assigns for value, rather
than as a gift) makes an implied warranty that at the time of the assignment, the
obligor has no defenses.
Example: Thus in the above example, if Pawn assigns to Art for value his right to
payment from Jewel, Pawn has impliedly warranted to Art that Jewel has no
defenses. Since Jewel has a defense against Pawn, Pawn has breached the implied
warranty and is liable to Art for any amount by which Art's claim against Jewel is
reduced.
Modification of assignee's rights by original parties: In assignment scenarios, profs love to
test whether/when the two original parties (the obligor [who owes the duty] and the assignor)
may modify the assignee's rights. Remember that the assignee's rights depend on whether the
modification took place before or after the assignee got notice of the assignment:
Modification before notice: If the modification takes place before the assignee gets
notice of the assignment (not the scenario that's usually tested), the modification is
binding no matter what.
Modification after notice: But if the modification occurs after the assignee has received
notice of the assignment, the modification is binding only if the assignor has not yet fully
performed.
Example: Conti, a contractor, agrees to build a house for Owen, at a price of $300,000. Since Conti owes
$400,000 to Bert, Conti's brother, Conti assigns to Bert Conti's right to receive payment from Owen, and
immediately notifies Bert of the assignment. Then, Owen and Conti agree to a price reduction to $250,000. If
the price reduction occurred before Conti finished the work, Bert is bound. But if the reduction
occurred after Conti finished, the reduction is not binding on Bert, and Bert can sue for the
whole $300,000.
Multiple assignments: Also, look for a fact pattern where there have been two
assignments of the same right. If the first assignment is irrevocable, then, generally, that
first assignee has priority.
Prior payment as defense: Remember that timing also counts where the obligor pays (or gives
performance to) the assignor instead of the assignee. If the obligor pays the assignor (in part or in
full) or gives the required performance before he has received notice of the assignment, he may
use this as a defense against the assignee. But if the obligor renders payment/performance to the
assignor after learning of the assignment, she may not use this as a defense vis-á-vis the assignee.
Example: In the above example, suppose Owen paid $200,000 to Conti (rather than to
Bert) after Owen got notice of the assignment. Owen would not be able to use this
payment as a set-off in an action for the $300,000 brought against him by Bert.
Assignee's obligations: Typically, the assignee will have obligations to both the assignor and to
the original promisee, since the latter will be a third-party beneficiary. So either can sue the
assignee if he breaches.
Example: Chef hires Delegator, a famous interior designor, to have Delegator design
Chef's new restaurant. Delegator hires Newdes, another designer, to take over the project.
Chef allows the deligation to take place (notice that he doesn't have to, since the contract
involves Deligator's unique personal skills). Newdes fails to do the work properly.
Newdes can be sued by both Chef and Delegator. First, Chef can sue Newdes—Chef
was almost certainly an intended beneficiary of the Delegator-Newdes contract (Chef was
to receive Newdes' performance, and Delegator clearly intended that Chef be benefitted by
Newdes' taking over Delegator's role—see the discussion of third-party beneficiaries
immediately infra). If, instead, Chef chooses to sue Delegator (which he can do because
the delegation did not let Delegator off the hook), Delegator can sue Newdes to be made
whole—Newdes owed the obligation of performance both to Delegator (the promisee of
Newdes' promise to perform) and to Chef (the third-party beneficiary of that promise).
Third Party Beneficiaries
This topic is always a favorite on exams. The two most important issues to concentrate on are the
distinction between intended and incidental beneficiaries, and the analysis of whether an intended
beneficiary's rights have vested.
Intended vs. incidental: You must distinguish between these two types of beneficiaries, because
the intended beneficiary may enforce the contract whereas the incidental beneficiary cannot.
Creditor: If the agreement is to pay money that one of the original parties owes to a third
party, that third party is an intended beneficiary, and may sue. (This is the classic "creditor
beneficiary" situation).
Example: Own hires Gard to landscape Own's property for $90,000. The contract
provides that Own is to pay $80,000 to Gard and the balance is to paid to Cred, to whom
Gard owes money. Cred is an intended beneficiary of the contract between Own and Gard.
Therefore, Cred may sue if Own doesn't pay.
To whom performance runs: Look at whether the performance runs directly from the
promisor to the third party. If it does, the beneficiary is probably "intended." If not, the
beneficiary is probably incidental.
Example: Whole, a wholesaler, agrees to supply to Ret, a retailer, 100 bicycles made by
Manco. Ret is to pay Whole, who will then order from, and pay, Manco. Because Ret's
performance (payment) is to run to Whole, not to Manco, Manco is not an intended
beneficiary, and may not sue Ret if Ret cancels the contract.
Promisee's intent: Pay the closest attention to the intent of the promisee, not the promisor
—if the promisee didn't intend to benefit the third party, the latter is not an intended
beneficiary.
Trap: The mere fact that a third party is mentioned in a contract doesn't automatically
mean that he's an intended beneficiary. Analyze whether the promisee really intended to
benefit the third party.
Example: Cli owes Lawr money for legal services. Lawr suggests to Cli, "I'd like you to
pay me off by buying my nephew Neff a Goldray Special from the Zebra Car Agency—
they've got good prices there." Cli responds, "If that's what you want, I'll be glad to do it."
Neff is an intended beneficiary, because it's clear that Lawr (the promisee, to whom Cli
owes money) intends to benefit Neff. (The fact that Cli has no particular desire to benefit
Neff is irrelevant). On the other hand, there's no indication that Lawr intended to benefit
Zebra—Lawr seems to have suggested Zebra by name merely because she wanted a good
price, not because she had an affirmative desire to benefit Zebra. Therefore, Zebra is
merely an incidental beneficiary.
Vesting as a bar to modification or discharge: In exam fact patterns the two original parties
often try to modify or discharge the obligation after it comes into existence. The general rule is
that they may do this, but only until the beneficiary's rights have "vested." Vesting occurs when
the beneficiary does one of these 3 things:
she manifests assent to the promise,
she brings suit on the promise, or
she materially changes her position in justifiable reliance on the promise.
Examples of justifiable reliance: (1) A freelance book illustrator who is the
beneficiary of full-time employment for a year notifies her other clients that she
can't work for them. (2) A person who is the beneficiary of a promise to convey
land cancels a contract for the purchase of a different parcel.
Beneficiary doesn't know of contract: A common exam situation is that the beneficiary
doesn't know of the contract prior to the time it's discharged or modified. In this situation,
the beneficiary obviously can't do any of the 3 vesting events (manifest assent to the
promise, bring suit on it, or materially change her position). Therefore, the original parties
can modify or discharge the contract with impunity.
Example: Frank, owner of a house, hires Paynt, a painting contractor, to paint Frank's
residence. The contract price is $5,000, provided that Paynt delivers a "satisfactory result."
A provision in the contract directs that payment be made to Paynt's daughter, Dot
(intended as a wedding gift). When the job is completed, Frank says he doesn't find it
"satisfactory." Paynt agrees to settle for a lower price of $4,500, provided the money's paid
directly to him. Paynt doesn't give any of the money to Dot. Shortly thereafter, Dot finds
out about the promise, and sues both Paynt and Frank for breach of the agreement. Dot will
lose, because prior to the settlement (a modification), Dot didn't manifest assent to
receiving the money, didn't bring suit on the agreement, and didn't materially change her
position in reliance. Therefore, Dot's rights never vested.
VIII. Exam Tips on IMPOSSIBILITY, IMPRACTICABILITY AND
FRUSTRATION
Exams often hint at the possibility of a defense based on Impossibility/Impracticability/Frustration (we'll
call this "I/I/F" for short). Usually, your fact pattern won't mention any of these defenses—it'll be up to
you to spot the issue, based on the fact that some unlikely event has occurred that makes it difficult or
senseless for one party to perform.
Issues Common to Impossibility, Impracticability and Frustration
Failure of basic assumption: Remember the basic standard for when I/I/F applies: it applies only
when the parties made the contract on the basic assumption that the contingency in question would
not occur. When you try to decide whether this test is met, focus on three sub-issues:
(1) Assumptions shared by both parties: Look first to see if both parties made this underlying
basic assumption—if the party who's trying to avoid a discharge (i.e., who's trying to enforce
the contract) didn't know that the contract was predicated on that assumption, I/I/F won't
apply.
Example 1: Stu, a high school senior, interviews with Count, an accountant, for a position
in his firm in January. Count then writes to Stu: "I offer you employment with my firm,
beginning August 1, at $25,000 a year." Stu accepts the offer several days later. In March,
Count sends Stu a letter stating: "It was my intention in hiring you to have you work with
my International Union account. However, the Union no longer retains my firm. Therefore,
I lack the funds and will not hire you. Good luck in securing other employment."
If Count asserts the defense of frustration, Stu can successfully contend that he wasn't
apprised of the special reason for hiring him. Therefore, the keeping of the account wasn't
a "basic assumption" of the contract, and Count can't be excused on grounds of frustration.
Example 2: In January, O and A enter into a contract under which A will design a ten-
story hotel to be built on a piece of land owned by O adjacent to City Airport. The design
is to be delivered on or before May 1. A is aware that O's interest in building a hotel is on
account of the business that will come from travelers using the airport. In March, the
government announces that the airport will shut down at the end of the year.
O will probably be able to argue successfully that the continuation of the airport's
operation was a basic assumption under both parties made the design contract. If he can
show this, he'll probably be able to have the contract excused on frustration grounds.
(2) Foreseeability: Remember that the more foreseeable the contingency was, the less like it is
that that contingency represents the failure of a basic assumption.
Circumstances which are usually foreseeable, and that therefore probably won't lead to
discharge:
Increase in costs. Look for a sudden large increase in the cost of labor or materials
which the seller of goods or services claims makes it impossible to perform.
Usually, such difficulties were relatively foreseeable when the contract was made,
in which case they probably won't excuse performance. (But this won't always be
true: if the cost increase is due to a truly unforeseen type of event—a sudden
industry-wide strike, outbreak of war, etc.—impossibility will generally apply.)
Circumstance which may or may not be deemed foreseeable:
Weather conditions. Look for bad storms that either push off the date of
completion of performance or destroy a crop. Note in your answer that
foreseeability probably depends upon whether that type of weather was usual for
that time of year in that region.
(3) Risk allocation: The last step in determining whether a party's obligations have been
discharged because of I/I/F is to make sure that the risk of one of these outcomes wasn't
implicitly allocated to that party by the contract.
F.O.B. contracts: Watch for "F.O.B." and the name of a location in an agreement for the
sale of goods. The phrase means that the parties agreed that the risk of loss would not pass
to the buyer until the goods were delivered to a carrier at the location specified. Thus if the
location specified is the buyer's factory ( "F.O.B. buyer's plant" ), the buyer does not
assume the risk until the goods arrive at her factory.
Example: B agrees to purchase fifty gallons of chemicals from S at $5 a gallon "F.O.B.
B's factory." S delivers the chemicals to T, a trucking company, which loads it onto its
truck. While en route to the city where B's facto truly unforeseen many-fold market-price
increase (e.g., 10x) might be sufficient.
Technology breakthroughs: If S agrees to develop a customized product for B, and both
parties understand that the product will need to develop or use new, unproven, technology,
the court will almost certainly find that the parties allocated to S the risk of an inability to
develop the needed technology. (Example: CompCo agrees to develop a new type of
computer to meet Bank's special needs. If CompCo can't develop the new computer, it
can't rely on impracticability to escape the deal, even if CompCo's failure comes despite its
having made all reasonable development efforts.)
Supervening illegality: When you find a fact pattern where parties have entered into an illegal contract,
pay attention to when it became illegal. If it became illegal because of a change in law that took effect
after the formation of the contract, then the frustration or impossibility defenses may apply. But if the
illegality existed before the contract was signed, and one or both parties were unaware, analyze the
problem under illegality (next chapter), not I/I/F.
Example: In February, L, a landlord, and T, a tenant, enter into a written lease agreement for two
years beginning April 1 whereby T is to rent a building for use as a "sports book," an
establishment where bets are made on horse races and other sporting events. The rent is $1,000 per
month and 20 percent of T's gross profits. T gives L a $2,000 deposit. Between the time of the
signing of the lease and April 1, a law is passed which makes the operation of sports books illegal.
T may sue for the refund of his deposit and the parties will be excused from performing. This
is so because T's purpose, of which L was aware, has been frustrated by the supervening illegality.
Frustration of Purpose—Special Issue
When dealing with a fact pattern where one party claims frustration of purpose, make sure the purpose
is totally (not just partially) frustrated.
Illness: For instance, in cases not involving personal services, a party's serious illness may not
lead to total frustration, in which case it probably won't lead to excuse for frustration.
Example: Sol, a homeowner, enters into a written contract with Byer for the sale of Sol's
house in Illinois. Three months later Byer informs Sol that he's retiring down South
because he has suffered a heart attack, and that he therefore won't be going through with
the deal. If Sol sues Byer for breach of contract, Byer won't be excused from performing
because of frustration—Byer could still buy the house and re-sell it, so his illness and
retirement probably haven't totally deprived him of all possible benefits from the
transaction.
Impossibility—Special Issues
When you're dealing with a fact pattern where one party claims impossibility, make sure performance
is totally impossible, and that the event creating the impossibility was unforeseeable at the time of
formation.
Destruction of subject matter: Destruction isn't always an excuse.
First, determine whether the parties allocated the risk to the party seeking to be
excused—if it was, then impossibility/impracticability won't apply.
Example: Where a builder agrees to build a new structure, most courts say that the
builder implicitly assumes the risk of total destruction of the structure during
construction (unless the contract expressly says otherwise).
Next, if the risk remained with the party claiming impossibility, determine whether
the subject matter is replaceable on a commercially sensible basis—if so,
impossibility won't apply.
Example: B enters into a written agreement to purchase 100 standard air
conditioning units from S, F.O.B. B's warehouse. While the truck carrying the units
is en route to B's warehouse, it overturns and the shipment is destroyed. Because S
could readily obtain replacement units, S won't be excused on account of the
destruction. (But S would be excused if what was being delivered was, say, a one-
of-a-kind painting.)
Also, make sure that the impossibility isn't due to the fault of the party claiming
impossibility.
Impracticability—Special Issues
Increased expense: Although an increased expense generally doesn't rise to the level of fulfilling the
requirements for an impossibility defense, some jurisdictions sometimes allow a party to use the
increased costs as an impracticability defense.
Extreme increase: In addition to ensuring that the parties didn't allocate the risk (e.g., an
explicitly fixed-price sales contract), make sure that the impracticality is extreme. Probably the
cost of performance should be a minimum of five times the anticipated cost.
Example: Fischco, a wholesaler of fish, enters into a one-year contract with Rest, a
restaurant, to provide Rest with 250 pounds of salmon per week at $4 per pound. One
month into the contract, Fischco announces that because of an oil spill that has reduced the
catch of salmon, Fischco's costs have gone from $3/pound to $8/pound, and that Rest must
now pay $9/pound. Fischco is very unlikely to succeed on an impracticability defense,
because: (1) a fixed-price contract for a commodity usually means an implied allocation to
the seller of an increase in market prices; and (2) the less-than-3x cost increase is not so
extreme as to be the kind of unforeseeable event that might justify use of the doctrine.
Slight reduction in profitability: Also, make sure that the increase wouldn't just make
performing slightly unprofitable. (For instance, even a 10x increase in the cost of one
component wouldn't suffice, if the component was only a very small percentage of the
seller's overall costs.)
Consequence of Excuse
Remember that if parties are excused from performing, contract damages aren't awarded, because
there hasn't been a breach.
However, quasi-contractual remedies for the value of work performed (or benefits rendered) may
be appropriate. (See the chapter on Remedies).
IX. Exam Tips on WARRANTIES
Express warranty: Be on the lookout for descriptions of goods or services to be furnished, since such
descriptions are usually express warranties. For instance, a description of goods in a sales contract is an
express warranty that the goods will have those qualities.
Example: B agrees to purchase 250 2??×?4? "construction grade" wooden studs from S by a
written contract in which she agrees to tender payment on delivery prior to inspection. After
paying for the studs, B inspects them and discovers that they're utility grade instead of
construction grade. B sends a letter notifying S that the studs are defective, but keeps them and
uses them anyway. B is entitled to damages for breach of express warranty, since the description
of the goods as "construction grade" amounted to an express warranty that the goods would have
this feature, and B's use of the goods after inspection did not serve as a waiver of the warranty.
Implied warranty: Remember that a contract providing that goods are to be sold "as is" serves to
impliedly disclaim all implied warranties (including the warranty of merchantability and the warranty of
fitness for a particular purpose). But such language does not exclude express warranties.
Example: Seller offers, on e-bay.com, a "1951 Barbie & Ken matching 'Beach Party' doll set,
sold as is." The words "as is" would prevent the buyer from suing on account of the poor condition
of the set, even if a sale of dolls on e-bay would normally include an implied warranty that the
goods were in good enough condition to be worth collecting. However, the words would not
prevent the buyer from suing if the dolls turned out to be a 1980 set, because the description
"1950" constituted an express warranty that the dolls were from that year, and the words "as is" do
not modify or disclaim express warranties, only implied ones.
X. ESSAY EXAM
QUESTIONS AND ANSWERS
The following questions were adapted from various Harvard Law School First-Year Contracts examinations
of the past. The questions are reproduced almost exactly as they actually appeared, with only slight changes
to the facts. The sample answers are not "official" and represent merely one approach to handling the
questions.
XI. QUESTION 1
David Dole, owner of 75,000 acres of forest land in Dover County, Maine, had attempted for several years
without success to persuade state and local authorities to purchase the tract as a wildlife refuge. He was
approached by Paul Pinsky, a prominent producer of motion pictures and creator of an entertainment park in
California known as Pinsky Land. Pinsky said that he saw great possibilities in Dole's tract of land as a ski
area if properly developed with access roads, motels and a summer resort, and if several hundred cottages
were built for rental. However, extensive surveys would be needed before he would want to buy. Dole
explained that the taxes assessed against the property were delinquent, and that the 2007 tax would be
payable Dec. 11, 2007. Dole added: "I simply have to bail out by then." Dole then prepared and gave Pinsky
the following document:
Oct. 9, 2007
I hereby give Paul Pinsky the privilege of entering my land in Dover County, Maine to survey and
map it as a recreation area. I will sell him the whole tract of 75,000 acres for $7.5 million, provided he
accepts this offer by giving me a certified check for $750,000 on or before Dec. 4, 2007.
/s/ Paul Dole
Pinsky sent a crew of surveyors and architects to the Dover County tract, where they worked for four
weeks, at a cost to Pinsky of $100,000. Their activities became widely known and on Nov. 12, a group of five
wealthy owners of land in Maine approached Dole, who informed them of his offer to Pinsky. They
persuaded Dole that the land should be preserved unspoiled if possible. During the next two weeks the five
secured pledges totaling $10 million from 500 persons, and on Nov. 30 the five gave Dole a check for $1
million and jointly signed a promissory note for the remaining $9 million. Dole then executed a conveyance
of the 75,000 acre tract to the Wilderness Society, a non-profit corporation whose charter authorizes it "to
receive and hold land that is still preserved in or can revert to its natural state and to dispose of such holdings
only on such terms as will insure that its natural state is preserved so far as possible."
On Dec. 1, 2007, Pinsky called from California to Dole's home in Webster, Mass., gave his name, and said, "I
have a $750,000 check for Mr. Dole. Where shall I mail it?" Acting on instruction from Dole, his wife
replied, "He has moved. I don't know where he is." Pinsky arrived in Webster on Dec. 2 with a $750,000
check in his pocket. He inquired around the city and was told that Dole was last seen leaving town by bus
with a lot of camping gear. Pinsky, in hot and continuous pursuit, proceeded to the Dover County tract and
after searching through the forest finally found Dole in a secluded cabin on Dec. 6. Pinsky said: "Mr. Dole, I
believe. Here is your check, well within your Dec. 11 tax deadline." Pinsky tendered a $750,000 certified
check but Dole refused to accept it. Pinsky now consults your law firm. The senior partner instructs you to
"prepare a memorandum discussing the legal and equitable remedies Pinsky may have against Dole and the
Wilderness Society, and stating your best judgment of the likelihood of success concerning each possible
remedy." Write the memorandum.
XII. ANSWER TO QUESTION 1
Was there an acceptance while the offer was still in force? I am putting aside until later whether Dole's offer
was an irrevocable one. Assuming that the offer was not irrevocable, the question is whether Pinsky accepted
while the offer was still in force.
As a preliminary matter, it is not clear that Dole's offer of October 9th is sufficiently definite to give
rise to an enforceable contract upon Pinsky's tender of a check. The offer contemplates that Dole will give
Pinsky $6.75 million worth of credit, but does not specify when this large sum must be paid, nor how it is to
be secured. Nor does the offer specify a conveyance date. Thus a court might hold that even if we show that
Pinsky did accept before Dole revoked or the offer lapsed, there is no enforceable contract for lack of
definiteness. But I think we have a fair chance of showing that as of October 9th, the parties fully intended to
reach sufficiently definite terms upon Pinsky's tender of a check. The court might therefore be induced to
supply the missing terms with respect to time for full payment, conveyance date, security, etc.
Turning now to whether Pinsky did anything to accept while there was still a valid power of
acceptance, the general rule is that the offeror has the right to set the time as of which his offer expires. Thus,
Dole's October 9th offer created a power of acceptance which lasted no later than December 4th. It is possible
that we will be able to show that Pinsky's call to Dole's wife, in which he said that he had the check ready for
mailing, constituted an acceptance. However, in all probability Dole will successfully contend that only
receipt by him of the check, not a statement of Pinsky's readiness to send it, constituted an acceptance. Dole
could point to the general rule that gives the offeror the right to prescribe the exact means by which his offer
may be accepted.
It is also possible that Pinsky's act of showing up in Webster with the check constituted a sort of
"constructive" acceptance, in that he did everything in his power to give Dole a check at the place where Dole
was supposed to be. Again, however, I would imagine that a court would hold that no acceptance could take
place until Dole was actually given the check. We could argue that Dole's act of disappearing constituted an
intentional interference with Pinsky's right of acceptance, and that therefore Dole has no right to insist upon
the precise conditions of his offer (i.e., that the check actually be given to him in person.) However, since I
am now assuming that Dole's offer was revocable at any time, presumably Dole had the right to thwart Pinsky
by moving, just as he had the right to revoke the offer outright. This would be an indirect communication of
revocation.
We might try the argument that Dole in fact made two offers to Pinsky: one was the written offer,
which terminated on December 4th, and the other was an oral offer which by its terms was to last until
December 11th (Dole's tax deadline). Therefore, we would contend, the oral offer remained in force until
expressly revoked, and Pinsky's December 6th tender of a check was a valid acceptance of this offer. (Dole's
refusal to accept this check on the 6th probably would not be a revocation of the offer, since I think a court
would hold that the tender of the check was sufficient to accept.)
I think, however, that this "two offers" theory is unlikely to prevail. Even if we convince the court that
there were two offers, Dole will have a good chance of showing that the oral offer was revoked. An offeror
can revoke his offer by indirect as well as direct means. Restatement 2d, §43, states that "An offeree's power
of acceptance is terminated when the offeror takes definite action inconsistent with an intention to enter into
the proposed contract and the offeree acquires reliable information to that effect." Dole could argue that when
he went off into the wilderness without telling anyone of his whereabouts, and Pinsky learned of his having
done so, it should have been clear to Pinsky that Dole meant not to accept the offer.
In summary, unless we can show that Dole's offer was irrevocable, I think we will have a very hard
time showing that Pinsky accepted it while he still had a valid power of acceptance. I turn now to the
irrevocability question.
Irrevocability of the offer: There are a number of theories which we might advance to
establish that Dole's October 9th offer was irrevocable until Dffer was irrevocable until December 4th.
If we can succeed with any of these arguments, I think we will then be able to convince the court that Dole's
running off into the wilderness was an interference with Pinsky's right to exercise his option, and that Pinsky
should be regarded as having validly exercised the option by arriving in Webster with the check. (If the offer
was irrevocable, Dole should not have the right to get around its irrevocability by making it impossible for
Pinsky to accept.)
One theory is that the October 9th offer was a validly binding option contract. Restatement 2d, §87(1)
(a), makes an offer irrevocable as an option contract if it "is in writing and signed by the offeror, recites a
purported consideration for the making of the offer, and proposes an exchange on fair terms within a
reasonable time." The difficulty with this provision is that Dole's October 9th document does not recite a
purported consideration. Therefore, unless the jurisdiction in which Pinsky sues has a statute or case law
analogous to the UCC "firm offer" provision, §2-205 (by which a merchant's signed offer to sell that states
that it will be kept open for a certain time is irrevocable, even without consideration), I don't think a
conventional option contract theory will work. We might conceivably be able to show that Pinsky's act of
surveying was of benefit to Dole, and bargained for by him, and was therefore consideration for the option.
But since there's a good chance that the court will find that Dole didn't care whether Pinsky surveyed or not,
and that there was therefore no consideration for the option, I think this whole "binding option" contract
theory will probably go down the drain.
A more promising theory is that Dole's offer was for a unilateral contract, and that when Pinsky
began to perform the requisite act of acceptance (i.e., the tender of a check), the offer became temporarily
irrevocable. See Restatement 2d, §45. To win with this theory, we would have to convince the court that from
the time Pinsky got to Webster, he was engaged in the act of tendering the check (and not merely preparing
to tender the check.) If we can establish this, we have a good chance of getting the court to follow
Restatement §45, and Pinsky will be able to get the full expectation measure of damages.
Promissory Estoppel: If all of the above theories fail, I think we can at least let Pinsky get his
$100,000 in surveyors' fees, by use of the doctrine of promissory estoppel. Restatement 2d, §87(2) provides
that "An offer which the offeror should reasonably expect to induce action or forbearance of a substantial
character on the part of the offeree before acceptance and which does induce such action or forbearance is
binding as an option contract to the extent necessary to avoid injustice." This provision does not require that
the offer have been supported by consideration, and seems to fit Pinsky's situation to a "T." Dole certainly
knew that Pinsky planned to spend money on surveyors' fees.
The reason that this promissory estoppel theory is less than completely satisfactory is that, as the Restatement puts it,
enforcement will be given only "to the extent necessary to avoid injustice." I'm afraid that the court is likely to award
Pinsky only his $100,000 in fees, and not to give him the "benefit of his bargain" (i.e., the profits he could have made
from Pinsky World, or even the $2.5 million profit he could have made by reselling the land to the wilderness group.) It's
possible that we can convince the court that "justice" requires giving Pinsky at least this $2.5 million turnaround profit,
but I wouldn't count on it.
Specific Performance Against Wilderness Society: If we can establish, by one of the above theories,
that there is a valid contract between Pinsky and Dole, we might be able to get the court to order specific
performance, in the form of a decree ordering Wilderness Society to convey the land to Pinsky (and a
collateral decree ordering Dole to return the money raised to purchase the land for donation to the Society). In
support of this request for specific performance, we can point out that the Wilderness Society people are not
bona fide purchasers, but in fact had knowledge of the offer to Pinsky. But as a practical matter, I don't think
we're likely to find a judge who would be willing to turn this land over to a developer like Pinsky, rather than
keeping it in its natural state. Specific performance is a remedy very much left to the trial court's discretion,
and I wouldn't get our hopes up about it. I think the best we can hope for is a breach of contract verdict
against Dole, with damages of the $2.5 million profit that Pinsky could have made by selling the land to the
Wilderness people. If we can come up with some very specific figures showing how profitable Pinsky World
would have been, maybe we can get some damages for these lost profits as well, but I'm afraid they will be
held to be too speculative unless Pinsky has previously operated a similar business.
XIII. QUESTION 2
The General Construction Co. of Memphis, Tennessee decided to build for itself a new headquarters building
of an original and striking design. It secured much publicity in journals read by architects and builders by
printing artists' sketches of the building, located at a dramatic site at a bend in the Mississippi river. In the
publicity was included the announcement of a self-imposed deadline for completion, a deadline that was very
short by usual standards of the construction industry for a building of that size.
The Frank Corporation is a steel fabricator that buys steel ingots and transforms them into structural
steel. On September 1, 2006, the General Construction Co. and the Frank Corporation executed a written
contract under which Frank undertook to fabricate and deliver the structural steel called for by General's
specifications, which were made part of the contract. The contract provided a delivery schedule with five lots
to be delivered as follows: