CSS Training Manual 18 Days Mon 2/8/21 Wed 25/8/21

This document outlines an 18-day project to create a CSS training manual. It involves research, outlining, development, editing, review, and print phases. Key tasks include investigating software, interviewing subject matter experts, writing 10 lessons, creating graphics, conducting two quality reviews, and printing the final manual. The project has 18 tasks assigned to various writers, editors, artists, and other roles and is scheduled to be completed between August 2nd and 25th, 2021.

Uploaded by

Syazwan Hafidzi
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views

CSS Training Manual 18 Days Mon 2/8/21 Wed 25/8/21

This document outlines an 18-day project to create a CSS training manual. It involves research, outlining, development, editing, review, and print phases. Key tasks include investigating software, interviewing subject matter experts, writing 10 lessons, creating graphics, conducting two quality reviews, and printing the final manual. The project has 18 tasks assigned to various writers, editors, artists, and other roles and is scheduled to be completed between August 2nd and 25th, 2021.

Uploaded by

Syazwan Hafidzi
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name Duration Start

July 2021 Finish Predecessors August 2021 September 20


27 30 2 5 8 11 14 17 20 23 26 29 1 4
0 CSS Training Manual 18 days Mon 2/8/21 Wed 25/8/21
1 Research Phase 13 days Wed 4/8/21 Fri 20/8/21
2 Investigate the Software 5 days Fri 13/8/21 Thu 19/8/21 Writer 1[50%],Writer 2[50%]
3 Search the Web 1 day Fri 20/8/21 Fri 20/8/21 2 Writer 1,Staff Assistant 1
4 Interview Subject Matter Experts 2 days Wed 4/8/21 Thu 5/8/21 Writer 1[50%],Project Manager 1[50%]
5 Outline Phase 2 days Mon 2/8/21 Tue 3/8/21
6 Draw Content Outline 1 day Mon 2/8/21 Mon 2/8/21
7 Present to Publisher 2 days Mon 2/8/21 Tue 3/8/21 Project Manager 1[50%],Travel Expenses[$1,000.00]
8 Review Outline 1 day Mon 2/8/21 Mon 2/8/21 Editor 2
9 Development Phase 10 days Tue 3/8/21 Mon 16/8/21
10 Write Lesson 1-5 5 days Tue 3/8/21 Mon 9/8/21 8 Writer 1
11 Write Lesson 6-10 5 days Tue 3/8/21 Mon 9/8/21 10SS Writer 2
12 Create Graphics 5 days Tue 10/8/21 Mon 16/8/21 11 Artist 1
13 Edit Phase 1 day Thu 12/8/21 Fri 13/8/21
14 Check for Grammar Inconsistencies 1 day Thu 12/8/21 Fri 13/8/21 12FS-50% Editor 2,Editor 1
15 Review Phase 5.5 days Fri 13/8/21 Fri 20/8/21
16 Quality Review 1 2.5 days Fri 13/8/21 Tue 17/8/21 14 Editor 1,Editor 2
17 Quality Review 2 3 days Wed 18/8/21 Fri 20/8/21 16 Editor 2
18 Print Phase 3 days Mon 23/8/21 Wed 25/8/21 17

Task Split Duration-only


Critical Task External Tasks Manual Summary Rollup
Milestone Project Summary Manual Summary
Project: CSS Training Manual Summary Group By Summary Start-only
Date: Fri 10/12/21
Rolled Up Task Inactive Task Finish-only
Rolled Up Critical Task Inactive Milestone Progress
Rolled Up Milestone Inactive Summary Deadline