INTRODUCTION:
MARKET POTENTIAL:
4|P ag e
BASIS & PRESUMPTIONS:
(a) On Building @ 5%
(b) On plant and machinery @ 10%
(c) On office furniture and fixtures @ 15%
(d)On other fixed assets @ 15%.
5|P ag e
TECHNICAL ASPECTS:
POLLUTION CONTROL:
The process of manufacture does not generate pollution. However,
entrepreneurs are to contact State Pollution Control Board for
necessary guidance.
ENERGY CONSERVATION:
Maximum care should be taken while selecting the machinery and other
electrical equipment’s so as to ensure minimum power consumption.
7|P ag e
FINANCIAL ASPECTS:
8|P ag e
[B] Working Capital (Per Month)
(i) Staff & Labour
Personnel No. Rate(Rs.) Amount
Manager 1 40,000 40,000
Cutting Master 1 20,000 20,000
Skilled Worker 5 15,000 75,000
Pressman 1 10,000 10,000
Unskilled 1 8,000 8,000
Worker
Total 1,53,000
9|P ag e
Total Recurring expenses (per month)
Staff & Labour 1,53,000
Raw Material 1,80,000
Utilities 16,000
Other contingent expenses 15,800
Total 3,64,800
FINANCIAL ANALYSIS