Ivisan Estimates
Ivisan Estimates
UNIT COST
I EXCAVATION - 40,200.00 40,200.00 29.00 1,386.21
II BACKFILLING - 100,500.00 100,500.00 458.00 219.43
CONCRETE WORKS
A. FOOTING 164,368.00 49,310.40 213,678.40 18.91 11,299.76
B. WALL FOOTING 109,495.00 32,848.50 142,343.50 26.00 5,474.75
C. TIE BEAMS 269,550.00 80,865.00 350,415.00 29.00 12,083.28
D. GROUND SLAB 117,990.00 35,397.00 153,387.00 24.00 6,391.13
E. RC COLUMN 651,474.00 195,442.20 846,916.20 30.00 28,230.54
F. SECOND FLOOR BEAMS 432,083.00 129,624.90 561,707.90 24.00 23,404.50
III G. ROOF BEAMS 180,608.00 54,182.40 234,790.40 24.00 9,782.93
H. ROOF BEAMS FOR STAIRS 140,020.00 42,006.00 182,026.00 22.00 8,273.91
I. SLB FOR STAIR COVER 120,744.00 36,223.20 156,967.20 8.00 19,620.90
J. TOOPINGS FOR GROUND FLOOR 34,460.00 10,338.00 44,798.00 9.75 4,594.67
K. TOPPING FOR 2ND FLOOR 35,100.00 10,530.00 45,630.00 10.00 4,563.00
L. SECOND FLOOR SLAB 425,915.00 127,774.50 553,689.50 186.00 2,976.83
M. ROOF DECK FLOOR SLAB 425,915.00 127,774.50 553,689.50 186.00 2,976.83
N. TOPPING FOR STAIR COVERING SLAB 38,840.00 11,652.00 50,492.00 11.00 4,590.18
O. STAIRS 120,000.00 36,000.00 156,000.00
MASONRY WORKS -
A. EXTERIOR WALLS @ H=1.5m 83,252.00 24,975.60 108,227.60 127.72 847.38
B. EXTERIOR WALL @ H=1.5m 126,510.00 37,953.00 164,463.00 185.00 888.99
C. INTERIOR WALL @ H=1.5m. 30,985.00 9,295.50 40,280.50 65.22 617.61
IV D. INTERIOR PARTITION @ HT. ABOVE 1.5m 61,720.00 18,516.00 80,236.00 140.21 572.26
E. 2ND FLOOR EXTERIOR WALL 74,760.00 22,428.00 97,188.00 159.00 611.25
F. 2ND FLOOR INTERIOR PARTITION 62,890.00 18,867.00 81,757.00 133.00 614.71
G. PARAPHET WALL 78,672.00 23,601.60 102,273.60 169.63 602.92
H. SEPTIC TANK 35,000.00 10,500.00 45,500.00
No. DESCRIPTION MATERIALS LABOR TOTAL AREAS/VOL. UNIT COST
CARPENTRY WORKS
A. DOORS (JAMBS ONLY) 31,500.00 9,450.00 40,950.00
B. WINDOWS - -
V
C. SCAFFOLDINGS 90,000.00 27,000.00 117,000.00
D. STAGING 80,000.00 24,000.00 104,000.00
F. STEEL FRAME DOORS - -
VI ELECTRICAL (ROUGH-IN) 40,000.00 12,000.00 52,000.00
VIII PLUMBING (ROUGH-IN) 30,000.00 9,000.00 39,000.00
-
-
4,091,851.00 1,368,255.30 5,460,106.30
BREAKDOWN OF EXPENDITURES:
MATERIALS COST 4,091,851.00
SUB-TOTAL 5,319,406.30
CONTENGENCIES 159,582.19
PREPARED BY: