Risk - Management Presentation
Risk - Management Presentation
Table of Contents
Risk Management
III Procedure IV Tools & Practices
Types of Risks
› Macroeconomic
› Political Issues
› Legal Issues › Debt and interest rates
› Terrorism › Financial management
› Natural disasters › Asset losses
› Goodwill and amortization
› Accounting problems
Hazard
Financial
Internal & External Risks
Internal Risks
External Risks
Strategic Operational Enablers
Regulatory
Strategic Planning Processes Financial
Economical
Ethics & Values Business Interruption Technology
Socio- Political
Product Design System/ Software Manufacturing All Other Project Management Quality
Product Performance Data Accuracy Assembly Consumer service Teamwork Quality system
Your text here Your text here Your text here Your text here Your text here Your text here
Your text here Your text here Your text here Your text here Your text here Your text here
Your text here Your text here Your text here Your text here Your text here Your text here
Identification of Risk Categories
Customer Demand
Risk Subcategory Funding Capacity Capacity Availability
Retention Shortfall
Likelihood 2 3 3 4 5 5
Risk level
Profitable Growth
Low Price
Leverage Technology
Medium
This slide is 100% editable. Adapt
it to your needs and capture
your audience's attention.
Low High
This slide is 100% editable. Adapt This slide is 100% editable. Adapt
it to your needs and capture it to your needs and capture
your audience's attention. your audience's attention.
Stakeholders
Engagement
Risk Appetite
High
Likelihood
Risk Tolerance
Insignificant fall <7% schedule 7-10% schedule 10-15% schedule 15-20% schedule
Schedule in schedule slippage slippage slippage slippage
Insignificant scope Minor areas of Major areas of Reduction Project end item
Scope decrease scope affected scope affected unacceptable is useless
Only demanding
Barely noticeable Reduction requires Reduction Project end item
Quality degradation
applications are
approval unacceptable is unusable
affected
Risk Tolerance
Impact
Business continuity
problems Supplier default
IT problems
Product or
Loss of key partnerships
service quality
Poor project
management
Likelihood
Risk Management
Procedure
Procedure for Managing Risks
Very
› Major uncertainties remain › Performance, quality, cost or safety impacts Low Med High
High
High (5) › No or little prior experience or data resulting in major redesign and program delay
› Infrastructure and/or resources not in place
Very Show
1 3 5 R
High stopper
5
risk
› Infrastructure in place but under-resourced schedule adjustment
Proceed w/
Med 3 9 15 Y
3
caution
› Few uncertainties remain › Performance, quality, cost and safety
Low (1) › Significant experience and data exist requirements met within planned schedule
› Infrastructure in place and fully
Low 1 3 5 G No concern
1
Risk Scoring System
Consequences Likelihood of Occurrence Likelihood of Detection
1. No. direct effect on operating service level E. Probability of once in many years A. Detectability is very high
2. Minor deterioration in operating service level D. Probability of once in many operating months B. Considerable warning of failure before occurrence
3. Definite reduction in operating service level C. Probability of once in some operating weeks C. Some warning of failure before occurrence
4. Source deterioration in operating service level B. Probability of weekly occurrence D. Little warning of failure before occurrence
5. Operating service level approaches zero A. Probability of daily occurrence E. Detectability is effectively zero
Risk Assessment (Cont.)
Consequences
Likelihood 1 2 3 4 5
A. Almost Certain - - - - -
B. Likely - - - - -
C. Possible - - - - -
D. Unlikely - - - - -
E. Rare - - - - -
Proposed risk
Type of Existing risk treatment Additional Target Person
Outcome Rating treatment actions to
Risk actions in place Resources Date Responsible
mitigate risk
Detailed
Performance Proper assessment of John
Strategic risk 2 understanding Your text here 31/4/2018
Deterioration underlying strategies Smith
of the market
Detailed
Performance Proper assessment of John
Strategic risk 2 understanding Your text here 31/4/2018
Deterioration underlying strategies Smith
of the market
Detailed
Performance Proper assessment of John
Strategic risk 2 understanding Your text here 31/4/2018
Deterioration underlying strategies Smith
of the market
Detailed
Performance Proper assessment of John
Strategic risk 2 understanding Your text here 31/4/2018
Deterioration underlying strategies Smith
of the market
Risk Identification
Time Cost
› Schedule overruns › Budget Exceeded
› Tasks omitted from Schedule › Unanticipated
› Opportunity to compress › Expenditure
Schedule
Resources
Communication Identify › Team is under-resourced
› Materials shortage
› Poor communication Risks › Machinery unavailable
(Stakeholder dissatisfaction) › Industrial Action
› Positive & timely › Skills gap
communications (positive
publicity)
Environmental
Scope
› Bad weather results in re-work
› Scope creep › Weather delays progress
› Scope poorly defined › Adverse effects occur
› Project changes poorly › Environmental approvals not
managed complied with
Risk Identification
How Long Can You Contingency in case
Impact of Doing Without? Vulnerabilities?
Do Without? of a disaster?
30 days before
Raw Materials None until on hard exhausted Single supplier relationship Search for alternatives supplier
new deliveries
Transportation 30 days in
No suppliers, No deliveries Location, design of entrance None
System 2 days out
Vendors
4 hours No call center Mercy of vendor Being in-house
(Sourcing)
Risk Analysis – Complex
Control Measures Risk Analysis Additional Control Risk Analysis (with additional controls)
Description of Risk (Detail any existing Controls)
(Detail additional to be
C L Risk Rating implemented Controls) C L Risk Rating
Likelihood
Medical Possible Event might occur at some time (10years) Likely M(B4) S(B3) H(B2) H(B1)
Major Warning
treatment Possible L(C4) M(C3) S(C2) S(C1)
Minor non Unlikely/ Event expected to occur only in
Minor First aid compliance Rare exceptional circumstances (20+ years) Unlikely Rare L (D4) M(D3) M(D2) S(D1)
Risk Analysis – Simplified
Impact to Priority
Risk Items (Potential Future Problems Likelihood of Risk
Project if Risk (Likelihood *
Derived from Brainstorming) Item Occurring
Item Does Occur Impact)
Risk Matrix
High Risk
Possible
Medium Risk
assessment to define the level of High Risk
Low Risk
risk by considering the category of
probability or likelihood against
the category of consequence
severity. This is a simple
mechanism to increase visibility of
Rare
risks and assist management Low Risk
decision making. Low Risk Medium Risk
Who is
Risk Event Response Contingency Plan Trigger
responsible
2 Factory Availability Cost Overruns Stakeholder trip to China High Dave Add notes here
10
11
Risk Item Tracking
Monthly Ranking
Risk Items Risk Resolution
This Month Last Month # of Months
Impact &
Probability Qualitative
Analysis Analysis
Risk Mitigation
Strategies
Risk Impact & Probability Analysis
Impact Cost Time Quality
Require some additional Slight slippage against key Failure to include certain
Low funding from Institution milestones or published targets ‘nice to have’ elements
Requires Significant additional Delay affects key stakeholders – Significant elements of scope for
Medium funding from Institution loss of confidence in the project functionality will be unavailable.
Technical Risks 1
• Emphasize team support and avoid stand-
alone project Structure
• Increase project manager authority
• Improve problem handling and communication
• Increase the frequency of project monitoring
2 Cost Risks
• Increase frequency of project monitoring
• Improve communication, project goals
understanding, and team support
• Increase project manager authority
Schedule Risks 3
• Increase the frequency of project monitoring
• Select the most experienced project manager
Risk Mitigation Plan
Project Risk (Threat & Opportunity) Matrix: Any Risk with a probability of over 80% will be treated as a fact and will be addressed in the Project
Management Plan and not in Risk management. Risk Threshold( which risks move forward) in the process and which one will be
Quantitative Risk Analysis
Cost Risk
Borrow money from
Find a partner to
ABC 5/31 Cost High .80 4 3.20 help share costs
the bank or investor
Insufficient funds to to fund the effort
support the bid
Schedule Risk
Borrow additional Hire additional
BMC 6/1 Sched. Low .55 4 2.20 proposal staff from proposal staff or
Insufficient resources another division consultants
to finish work on time
Risk Score values are between Risk Impact values are between
1-4 (with 4 being the highest risk) or red, yellow, green, blue. 1 (insignificant) - 4 (Unable to meet objectives)
34
Email: [email protected]