7.2-Cut Over and Golive V1.0
7.2-Cut Over and Golive V1.0
CUT OVER
2
3
Cutover Planning
• For moving from old system to new ERP application, activities need
to be planned in minute details and transactions need to be stopped
in the old application for a brief period and moved to the new ERP.
• In the example, transactions in the old system is completed on 28th
and three days are planned to move the open items to the new
system before the changeover happens in the new system on 1st.
• A real-life cutover plan for a company having multiple factories and
distribution centers can be really complex.
3
4
4
5
GO LIVE
• The day a company moves from the old legacy system to the
new ERP application is called “Go Live” date.
• Ideally, a company should complete all its ERP project related
activities before going live, though in reality it is far from
truth and in most cases, projects go live with several open
issues.
• However, it is important that before “Go Live”, all critical
project activities are completed.
5
6
GO LIVE PREPARATION
• All configurations
• All developments
• All testing (Unit testing, integration testing, user acceptance testing)
• Trainings of core ream, power users and end users
• Data migration completed
• All authorizations are created and authorization testing completed
• In most ERP implementations, before going live, there will be a list of
6
7
Go Live Checklist
7
8
Summary
• Cutover and go live is the final stage of ERP project realization before the company moves to
the new system. These activities need lots of planning for smooth transition to the new
application.
• Cutover planning details on which date the transactions from the legacy application will
stop. Post this date, the selected transactions will happen in the new system. This activity
needs to be planned looking at criticality of transactions, i.e. ensuring as less downtime as
possible for critical transactions.
• Go live checklist is a ready reference document for all the points that need to be considered
before going live. Go live decision needs to be taken only when all these critical check points
show a green status. There
• can be few not so critical open points while going live that need to be closed within an
agreed time-frame.
• It is always recommended to have a third-party audit before going live.
8
9
THANK YOU