Construction of Gravel Roads
Construction of Gravel Roads
material
Hard variety of crushed stone or gravel of specified
gradation is used. However softer varieties of stones may
also be utilized. There are no specifications for the materials
rounded stones and river gravel are not preferable as there is
poor interlocking.
Construction procedure
ii. Location the center line and road edges are marked on
the ground along the alignment, by driving wooden pegs,
reference pegs are also driven to help in following the
desired vertical profile of the road during construction.
The spacing of the reference pegs depends on the
estimated length for road construction per day.
iii. Preparation of Subgrade
Site is cleared and fills and cuts are completed. Trench is
formed to the desired depth of construction, the width of the
trench is made equal to that of carriageway. The trench is
brought to the desired grade and is compacted.
iv. Pavement construction
Crushed gravel aggregates are placed carefully in the trench
so as to avoid segregation aggregates are spread with greater
thickness at centre and less towards the edges so as to obtain
the desired camber. The layer is rolled using smooth wheeled
roller starting from the edges and proceeding towards the
centre with an overlap of at least half the width of roller in
the longitudinal direction.
Some quantity of water may also be sprayed and rolling is
done again so that the compaction is effective. The
camber is checked and corrected from time to time a
template or camber board.
v) Opening to traffic a few days after the final rolling
the road is opened to the traffic.
CONSTRUCTION OF WATER BOUND MACADAM ROADS (WBM)
10.0 90-100
4.75 10-30
150microns 0-8
4.75 85-100
150microns 10-30
Construction procedure for WBM
Material Required
The material required for construction is stacked on the
road side. Samples from the stacks are collected and their
grading are examined with regard to specifications. It is
recommended to provide 20 percent extra broken stones on
volume basis. Thus for one kilometer length per meter
width and for one centimeter thickness, the aggregates
required would be 6/5x1000x1/100=12 cubic meters. The
quantity of screenings required is about 30 cubic meters per
10 square meter area.
Construction steps
1. Preparation of Subgrade: the site is cleared and
either a trench is cut to the required camber or earth
bunds are made in order to provide a confinement to
the loose aggregates for compaction by rolling. The
week spots are corrected and rolled before the coarse
aggregates are placed.
2. Pavements construction this is done in following
stages.
a) Lateral Confinement : suitable bunds are provided
on both sides along the edges so as to confine the
aggregates while spreading and rolling.
b) Spreading of coarse aggregates: the coarse aggregates
are spread upon the prepared surface from the sack piles
on the road side. The thickness of each layer should be
such that the compacted thickness normally does not
exceed 7.5 cm .The aggregates are spread evenly to the
required profile by using templates placed across the road
about 6 meters apart. The surface is checked from time to
time ensuring the proper grade and camber.
Dry Rolling : After spreading the coarse aggregates, the
same are compacted to a full width by rolling. For this
purpose, a three wheel power roller of 6 to 10 tones
capacity or tandem roller or equivalent vibratory roller is
used