100% found this document useful (1 vote)
951 views2 pages

Grounding Installation Inspection and Test Plan ITP

The document provides a 16 item inspection and test plan for grounding installation. It lists the activities to be inspected, the relevant specifications and documents, and who is responsible for inspection. Items include verifying that the grounding electrode system and conductors are installed according to specifications, that resistance tests are done, and that grounding connections are tight and protected as required. Upon completion of work, the quality manager will review the quality control package and submit it.

Uploaded by

tristan guarino
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
951 views2 pages

Grounding Installation Inspection and Test Plan ITP

The document provides a 16 item inspection and test plan for grounding installation. It lists the activities to be inspected, the relevant specifications and documents, and who is responsible for inspection. Items include verifying that the grounding electrode system and conductors are installed according to specifications, that resistance tests are done, and that grounding connections are tight and protected as required. Upon completion of work, the quality manager will review the quality control package and submit it.

Uploaded by

tristan guarino
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Grounding Installation Inspection and Test Plan (ITP) Page 1 of 2

Division/Department: Engineering
Discipline:

Customer: INSPECTION AND TEST PLAN for: Grounding Installation


Contract Number: Work area: (Insert work area)
Contract/Project Name:
Legend I – Inspect R – Review W - Witness
M - Monitor H – Hold Point
Item
Activity Specification/ Responsibilit Verifying Inspection Requirements
Numb Comments
er Description Code Reference y Documents Meade Customer Rep Owner Rep
Document Review of Applicable Procedures,
1
Specifications, Drawings, Contract Documents
Verify the electrical systems that require grounded
2 neutrals are installed/tested in accordance with
specifications and drawings
Verify Grounding electrode system materials are in
3
accordance with specifications and drawings
Verify Grounding electrode system installation in
4
accordance with specifications and drawings
Verify Grounding electrode system is tested in
5
accordance with specifications and drawings
Verify buried/above ground grounding system
conductors between equipment and grounding
6
electrode system are installed, routed in accordance
with specifications and drawings
Verify Buried Grounding cable taps and splices are
exothermically welded or connected with an approved
7
mechanical connector, and coated in accordance with
specifications and drawings
Verify Grounding conductors between equipment and
8 grounding electrode system are resistance tested in
accordance with specifications and drawings
Verify Grounding conductors are protected by conduit
9
sleeves where required
Verify Grounding connections tight, and are per
10
specifications
11 Verify Rebar Grounded per specifications
Verify Ground conductors installed in duct banks per
12
specifications
Verify DCS grounding is in accordance with
13
specifications and drawings
Verify electrical equipment grounding is visible in
14
accordance with OSHA
Production to inform QC of near completion of work
15 scope prior to demobilization for final
acceptance/walkdown
Compile and Review of completed QC package and
16
submit

Version: Revision Date: Description of Change:


1.0 1/1/2013 Original Issue
This document is controlled electronically on the Meade Intranet. Printed or electronically transmitted copies are uncontrolled.
Grounding Installation Inspection and Test Plan (ITP) Page 2 of 2
Division/Department: Engineering
Discipline:

Name Position Signature Date

**** Site Project Manager/Forman Designee:

**** Quality Manager/Designee:

Customer Quality Approval or Job Rep:

Version: Revision Date: Description of Change:


1.0 1/1/2013 Original Issue
This document is controlled electronically on the Meade Intranet. Printed or electronically transmitted copies are uncontrolled.

You might also like