The document provides a 16 item inspection and test plan for grounding installation. It lists the activities to be inspected, the relevant specifications and documents, and who is responsible for inspection. Items include verifying that the grounding electrode system and conductors are installed according to specifications, that resistance tests are done, and that grounding connections are tight and protected as required. Upon completion of work, the quality manager will review the quality control package and submit it.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100%(1)100% found this document useful (1 vote)
951 views2 pages
Grounding Installation Inspection and Test Plan ITP
The document provides a 16 item inspection and test plan for grounding installation. It lists the activities to be inspected, the relevant specifications and documents, and who is responsible for inspection. Items include verifying that the grounding electrode system and conductors are installed according to specifications, that resistance tests are done, and that grounding connections are tight and protected as required. Upon completion of work, the quality manager will review the quality control package and submit it.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2
Grounding Installation Inspection and Test Plan (ITP) Page 1 of 2
Division/Department: Engineering Discipline:
Customer: INSPECTION AND TEST PLAN for: Grounding Installation
Contract Number: Work area: (Insert work area) Contract/Project Name: Legend I – Inspect R – Review W - Witness M - Monitor H – Hold Point Item Activity Specification/ Responsibilit Verifying Inspection Requirements Numb Comments er Description Code Reference y Documents Meade Customer Rep Owner Rep Document Review of Applicable Procedures, 1 Specifications, Drawings, Contract Documents Verify the electrical systems that require grounded 2 neutrals are installed/tested in accordance with specifications and drawings Verify Grounding electrode system materials are in 3 accordance with specifications and drawings Verify Grounding electrode system installation in 4 accordance with specifications and drawings Verify Grounding electrode system is tested in 5 accordance with specifications and drawings Verify buried/above ground grounding system conductors between equipment and grounding 6 electrode system are installed, routed in accordance with specifications and drawings Verify Buried Grounding cable taps and splices are exothermically welded or connected with an approved 7 mechanical connector, and coated in accordance with specifications and drawings Verify Grounding conductors between equipment and 8 grounding electrode system are resistance tested in accordance with specifications and drawings Verify Grounding conductors are protected by conduit 9 sleeves where required Verify Grounding connections tight, and are per 10 specifications 11 Verify Rebar Grounded per specifications Verify Ground conductors installed in duct banks per 12 specifications Verify DCS grounding is in accordance with 13 specifications and drawings Verify electrical equipment grounding is visible in 14 accordance with OSHA Production to inform QC of near completion of work 15 scope prior to demobilization for final acceptance/walkdown Compile and Review of completed QC package and 16 submit
Version: Revision Date: Description of Change:
1.0 1/1/2013 Original Issue This document is controlled electronically on the Meade Intranet. Printed or electronically transmitted copies are uncontrolled. Grounding Installation Inspection and Test Plan (ITP) Page 2 of 2 Division/Department: Engineering Discipline:
Name Position Signature Date
**** Site Project Manager/Forman Designee:
**** Quality Manager/Designee:
Customer Quality Approval or Job Rep:
Version: Revision Date: Description of Change:
1.0 1/1/2013 Original Issue This document is controlled electronically on the Meade Intranet. Printed or electronically transmitted copies are uncontrolled.