0% found this document useful (0 votes)
211 views

Pile Cap - Mo Civil Engineering

Accept All The document discusses the process of constructing a pile cap, which is used to transfer loads from a superstructure to piles. It involves excavating around piles, cutting pile heads, placing blinding concrete with waterproofing, installing reinforcement with proper cover, and erecting formwork before casting concrete. The pile cap distributes loads from the structure to the piles below.

Uploaded by

indrajit sodha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
211 views

Pile Cap - Mo Civil Engineering

Accept All The document discusses the process of constructing a pile cap, which is used to transfer loads from a superstructure to piles. It involves excavating around piles, cutting pile heads, placing blinding concrete with waterproofing, installing reinforcement with proper cover, and erecting formwork before casting concrete. The pile cap distributes loads from the structure to the piles below.

Uploaded by

indrajit sodha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

12/23/21, 11:45 PM Pile Cap - Mo Civil Engineering

Mo Civil Engineering Menu

-20% -40% -40% -40% -40% -20% -40%

Pile Cap
Pile cap used to transfer the loads from superstructure to the piling. The pile cap is thick concrete mat rests on
piles. It is part of the foundation and used to distribute the loads over the piles. Piles used when the soil bearing is
not enough to carry loads of the structure.

Figure 1 

Excavation around piles: After 7 days of the casting of the pile the concrete will gain approximately, 70% of it
is compressive strength. The soil around piles will be removed to the required levels and dimension that
allows construction of the pile cap. A step shall be made if the excavation is more than 1.5 m to prevent soil
collapse.

We use cookies on our website to give you the most relevant experience by remembering your preferences and repeat visits. By
clicking “Accept All”, you consent to the use of ALL the cookies. However, you may visit "Cookie Settings" to provide a controlled
consent.

Cookie Settings Accept All

https://mocivilengineering.com/pile-cap/ 1/8
12/23/21, 11:45 PM Pile Cap - Mo Civil Engineering

Figure 2

Pile head cutting: Concrete will be removed up to cut off level. If concrete under the cut off level is unsound.
It shall be removed, and the pile will be repaired. Pile must be free from cracks and unsound concrete.

Figure 3 

Blinding concrete: after completion of concrete cutting for piles. Blinding concrete shall be cast. Following points
illustrating the procedure for pile cap blinding concrete.

We use 1. cookies
Soil shall be removed
on our website to and leveled
give you to the
the most formation
relevant level.byThe
experience formationyour
remembering for preferences
blinding concrete shall
and repeat be By
visits.
clicking “Accept All”, you
compacted consentand
properly to the use offor
tested ALLfield
the cookies.
densityHowever,
test. you may visit "Cookie Settings" to provide a controlled
consent.
2. Two layers of polyethylene sheet will be laid above the formation layer.
3. Settings
Cookie Now you can cast
Accept All the blinding concrete. The thickness and dimension should be matching to shop drawing.

https://mocivilengineering.com/pile-cap/ 2/8
12/23/21, 11:45 PM Pile Cap - Mo Civil Engineering

4. Termination grooves (2×2 cmxcm) shall be provided to blinding concrete to terminate the waterproofing for
pile cap and blinding concrete.
5. The blinding concrete will be cured for a minimum of 24 hours.

Figure 4

Waterproofing for blinding concrete:

To prevent groundwater ingress from the pile cap bottom. It is recommended to waterproof pile cap blinding,
especially in areas of the high water table and harsh environment. The sequence of waterproofing is as follow.

1. To obtain strong adhesive, it is essential to clean the blinding concrete thoroughly from any dirt or debris.
2. A chamfer shall be cast around piles head to provide a smooth transition between piles head and pile cap.
3. The surface of blinding concrete shall be painted with primer. Primer shall cover the area evenly.

We use cookies on our website to give you the most relevant experience by remembering your preferences and repeat visits. By
clicking “Accept All”, you consent to the use of ALL the cookies. However, you may visit "Cookie Settings" to provide a controlled
consent.

Cookie Settings Accept All

https://mocivilengineering.com/pile-cap/ 3/8
12/23/21, 11:45 PM Pile Cap - Mo Civil Engineering

Figure 5

Protection of waterproofing

Waterproofing shall be protected to avoid damages during the construction process. The protection depends on
the alignment of waterproofing.

1. Screed: screed will be provided for horizontal waterproofing such as blinding concrete waterproofing. To
protect the waterproofing from any damage during fixing reinforcement and shutter for pile cap.
2. Protection board: This board will be used for vertical waterproofing such as waterproofing for pile cap.

Figure 6

Reinforcement fixing for pile cap

Pile cap reinforcement shall be fixed as per approved drawing. At the field, the designer will provide you with the
shop drawing for each structural element. These drawing shall consider as a guide. However, there are some
important points. Enough cover block should be provided to maintain the required cover. Maintaining the needed
cover is very important, and ignoring cover requirement can lead to reducing structure durability. Importance of
cover can be briefed in the following points:

1. The concrete cover will form a barrier between reinforcing steel and corrosive agents such as chloride.
2. Protect reinforcing steel from concrete carbonation. Concrete carbonation can cause steel corrosion.
3. Fire Protection: concrete cover will protect the steel from fires and prevent steel melting.
4. Enough chairs shall be provided to maintain reinforcement rigid and avoid movement and deformation
during concreting.
5. Dowel (starter) bars shall be provided for pier column. Dowel bars shall be adequately braced to avoid
movement during casting. Also, dowel bars shall be maintained vertical

We use cookies on our website to give you the most relevant experience by remembering your preferences and repeat visits. By
clicking “Accept All”, you consent to the use of ALL the cookies. However, you may visit "Cookie Settings" to provide a controlled
consent.

Cookie Settings Accept All

https://mocivilengineering.com/pile-cap/ 4/8
12/23/21, 11:45 PM Pile Cap - Mo Civil Engineering

Figure 7

Formwork installation for pile cap

1. The engineer will provide a detailed drawing for pile cap shutter and the required supports such as jacks, tie
road. At the field the fabricated shutter shall be identical to the provided drawing.
2. Corner chamfer shall be fixed on all side and top of shutter to provide a smooth edge.
3. The concrete cover should be maintained after fixing of the shutter as shown on the drawing.
4. The alignment and verticality of shutter shall be checked by the surveyor.
5. The kicker and shear key shutter for pier shall be fixed and location checked by the surveyor.
Thermocouples shall be fixed before the concreting of pile cap to measure the temperature difference
between top, middle, and bottom of pile cap concrete. Thermocouples used to monitor the differential
temperature between different concrete layers in case of mass concrete. The differential temperature
should be less than 20 C. If the differential temperature increased more than 20 C, this could cause tensile
stress more than concrete strength, which can lead to internal cracks.
6. Prior to the concreting the area should be clean and free from any dirt’s.

We use cookies on our website to give you the most relevant experience by remembering your preferences and repeat visits. By
clicking “Accept All”, you consent to the use of ALL the cookies. However, you may visit "Cookie Settings" to provide a controlled
consent.

Cookie Settings Accept All

https://mocivilengineering.com/pile-cap/ 5/8
12/23/21, 11:45 PM Pile Cap - Mo Civil Engineering

Figure 8

Concreting of the pile cap

Before the concrete pile cap area should be cleaned again. In the events of dust or sand accumulation. The blower
should be used to assure removing all dirt’s. If the temperature during casting of pile cap is high, then shutter shall
be sprinkled with water to prevent the plywood from absorbing concrete moisture. A sufficient number of
vibrators and a competent person should be present during the casting process to produce a dense concrete
surface free from honeycombs. Concrete shall be cured for a minimum period of two weeks. Concrete surface
shall be covered with a hessian sheet, and it shall be kept wet all time during the curing period.

Figure 9

Waterproofing for pile cap

Waterproofing of pile cap is similar to waterproofing of blinding concrete. The significant difference is the way of
protection for the waterproofing membrane. Protection board will be used for pile cap walls. But for pile cap top
screed
We concrete
use cookies willwebsite
on our be used to protect
to give you the the
mostwaterproofing membrane 
relevant experience by remembering your preferences and repeat visits. By
clicking “Accept All”, you consent to the use of ALL the cookies. However, you may visit "Cookie Settings" to provide a controlled
consent.

Cookie Settings Accept All

https://mocivilengineering.com/pile-cap/ 6/8
12/23/21, 11:45 PM Pile Cap - Mo Civil Engineering

Figure 10

Testing for Grouts for Post-tensioning Ducts


Concrete Cover

Leave a Comment

Name *

Email *

Website

Save my name, email, and website in this browser for the next time I comment.

We use
Postcookies
Commenton our website to give you the most relevant experience by remembering your preferences and repeat visits. By
clicking “Accept All”, you consent to the use of ALL the cookies. However, you may visit "Cookie Settings" to provide a controlled
consent.

Cookie Settings Accept All

https://mocivilengineering.com/pile-cap/ 7/8
12/23/21, 11:45 PM Pile Cap - Mo Civil Engineering
-20% -40%

report this ad

Recent Posts

Segregation of Concrete
Concrete Bleeding

Concrete Abnormal Setting

Silica Fume for Concrete


Prestressing Losses-Friction Losses

report this ad

We use cookies on our website to give you the most relevant experience by remembering your preferences and repeat visits. By
clicking “Accept All”, you consent to the use of ALL the cookies. However, you may visit "Cookie Settings" to provide a controlled
consent.

Cookie Settings Accept All

https://mocivilengineering.com/pile-cap/ 8/8

You might also like