PTC Overview and Policy Issues
PTC Overview and Policy Issues
Summary
The Rail Safety Improvement Act of 2008 (RSIA08) requires implementation of positive train
control (PTC) on railroads which carry passengers or have high-volume freight traffic with toxic-
or poisonous-by-inhalation hazardous materials. PTC is a communications and signaling system
that has been identified by the National Transportation Safety Board (NTSB) as a technology
capable of preventing incidents caused by train operator or dispatcher error. PTC is expected to
reduce the number of incidents due to excessive speed, conflicting train movements, and engineer
failure to obey wayside signals. It would not prevent incidents due to trespassing on railroads’
right-of-way or at highway-rail grade crossings, where the vast majority of rail-related fatalities
occur, and might not work well in some passenger terminal areas.
Under RSIA08, PTC is required on about 60,000 miles of railroad track. The Federal Railroad
Administration (FRA) estimates full PTC implementation will cost approximately $14 billion.
Progress among railroads in installing and operating PTC is mixed: a few large freight and
commuter railroads show substantial progress while many others show much less progress.
Federal funding provided thus far includes about $2 billion in loans and grants, mostly for
commuter lines. After freight and commuter railroads raised concerns about their ability to meet
the December 31, 2015, deadline in RSIA08, Congress extended the deadline by three years to
December 31, 2018, or up to two years beyond that for certain qualifying railroads (P.L. 114-73).
A July 2018 FRA report indicates that possibly all railroads will seek to qualify for an extension
beyond the December 31, 2018, deadline, mostly for completing testing of their PTC systems.
PTC uses signals and sensors along the track to communicate train location, speed restrictions,
and moving authority. If the locomotive is violating a speed restriction or moving authority, on-
board equipment will automatically slow or stop the train. A more expansive version of PTC,
called communications-based train control (CBTC), would bring additional safety benefits plus
business benefits for railroad operators, such as increased capacity and reduced fuel consumption.
However, CBTC is not currently being installed by any U.S. railroad, due to the additional cost
and the challenge of meeting implementation deadlines.
In addition to funding requests for maintaining the PTC systems, Congress may be confronted
with issues related to interoperability and barriers to market entry as railroads work toward
implementing PTC.
Contents
Introduction ..................................................................................................................................... 1
Rail Safety and PTC ........................................................................................................................ 1
Signal Systems .......................................................................................................................... 2
Rail-Related Fatalities ............................................................................................................... 5
Train Incidents and PTC Legislation......................................................................................... 5
The Basics of PTC ........................................................................................................................... 8
Implementation ...............................................................................................................................11
Overseas Experience ............................................................................................................... 12
Cost and Benefits........................................................................................................................... 12
Safety Benefits from PTC-Preventable Incidents ................................................................... 13
Policy Issues .................................................................................................................................. 14
Interoperability ........................................................................................................................ 14
Avoiding Barriers to Market Entry .......................................................................................... 15
PTC Requirements Within Passenger Terminals ..................................................................... 16
Figures
Figure 1. National Network of Class I Railroads ............................................................................ 2
Figure 2. Example PTC System Architecture .................................................................................. 9
Figure 3. Communication-Based Train Control (CBTC) .............................................................. 10
Contacts
Author Information....................................................................................................................... 16
Introduction
Following several high-profile train incidents, Congress passed the Rail Safety Improvement Act
of 2008 (RSIA08; P.L. 110-432), which mandated positive train control (PTC) on many passenger
and freight railroads by December 31, 2015. The law does not describe PTC in technical terms,
but defines it as a risk mitigation system that could prevent train incidents by automatically
stopping trains when a collision or derailment is imminent.
After freight and commuter railroads raised concerns about their ability to meet the 2015
deadline, Congress extended the deadline by three years to December 31, 2018, or up to two
years beyond that for certain qualifying railroads (P.L. 114-73). As of July 2018, it appears that all
railroads will seek qualification for extending the deadline.1
While PTC promises benefits in terms of safety, its implementation entails substantial costs and
presents a variety of other policy-related issues. These include the interoperability of individual
railroads’ systems, access to sufficient radio spectrum to support PTC, the possibility that PTC
could be a barrier to market entry, and the suitability of PTC to passenger terminal environments.
1 Federal Railroad Administration, Railroads’ Progress Toward Implementation of Positive Train Control Systems,
July 1, 2018, p. 4.
2 U.S. Department of Transportation, “National Transportation Statistics,” http://www.bts.gov/publications/
national_transportation_statistics/html/table_01_01.html.
3 See CRS Report R42512, Passenger Train Access to Freight Railroad Track, by John Frittelli.
4 Cambridge Systematics, National Rail Freight Infrastructure Capacity and Investment Study, Final Report,
Source: Cambridge Systematics, Inc., National Rail Freight Infrastructure Capacity and Investment Study,
September 2007.
Notes: This map shows the Class I railroads in the United States. Not all lines shown are subject to the PTC
implementation mandate.
Signal Systems
For safety purposes, train dispatchers and signals along the track provide the engineer with the
authority to travel on a certain track segment to prevent collision with other trains. Some long
stretches of track in remote areas use only one main line without any signalization. This is called
“dark territory,” comprising about 40% of the North American rail network.5 In this case,
railroads rely on communications with dispatchers to provide authority. Dispatchers are also
responsible for assigning priority when more than one train requires use of a particular segment
of track.
On signaled track, track is separated into blocks by trackside or overhead signals that indicate to
an engineer whether the train can proceed (and at what speed) or must stop before it enters the
next block. Given the long stopping distance required by trains, a prior signal actually informs the
engineer about the indication on the next signal. This system is called automatic block signal
(ABS), and is generally the most sophisticated signal system used by freight railroads where PTC
has not been installed. Since 1947, it has been required for freight trains traveling 50 or more
miles per hour (mph) and passenger trains traveling 60 mph or more.6 Railroads have different
5 Institution of Railway Signal Engineers, Introduction to North American Railway Signaling (Omaha: Simmons-
Boardman, 2008), p. vii.
6 Codified today at 49 C.F.R. 236.
operating rules regarding how and under what circumstances the conductor must call out signals
to the engineer.
Intercity and commuter passenger trains often incorporate additional features in their signal
systems. A “cab signal” system relays external signal information to control displays inside the
engineer’s cab via an electric current that travels along the rails and is picked up by a receiver on
the locomotive. The cab signal is helpful when fog, sun, or track curvature hinders or delays
visual sighting of wayside signals. It also increases track utilization, as the engineer can adjust
train speed in between signals. An “automatic train stop” (ATS) or an “automatic train control”
(ATC) system can override the engineer’s control of a train if a wayside signal indication is not
acknowledged by the engineer. These devices are installed along the tracks, and trip a train’s
brakes when an engineer fails to respond to a wayside signal. Cab signals, ATS, and ATC were
developed beginning in the early 1900s, and have been required by federal regulations since 1947
for passenger trains traveling over 79 mph (see text box).
7 69 I.C.C. 258 (Order No. 13413), “In the Matter of Automatic Train-Control Devices,” decided June 13, 1922.
8 268 I.C.C. 547 (Order No. 29543), “Appliances, Methods, and Systems Intended to Promote Safety of Railroad
Operation,” decided June 17, 1947; 12 Federal Register 4683, July 15, 1947.
9 268 I.C.C. 552.
11 Railroad Accident Report, Head-on Collision between Penn Central Trains N-48 and N-49 at Darien, CT, August 20,
1969 (NTSB/RAR-70/03).
12 NTSB Recommendation R-70-20.
13 Office of Technology Assessment, Automatic Train Control in Rail Rapid Transit, May 1976.
14 NPRM, 48 Federal Register 11882, March 21, 1983; Final rule, 49 Federal Register 3374, January 26, 1984.
15 National Transportation Safety Board, Office of Public Affairs, “NTSB unveils new ‘Most Wanted List,’” press
Rail-Related Fatalities
Most rail-related fatalities are caused by pedestrians trespassing on railroad tracks or motor
vehicles being hit at grade crossings. Train derailments and collisions, which PTC is designed to
prevent, cause relatively few fatalities. Over a 10-year period ending in February 2016, there
were 7,695 rail-related fatalities: 58% were due to trespassing (4,458 fatalities), 37% occurred at
grade-crossings (2,838 fatalities), 2% were railroad workers (181 fatalities), and 1% were railroad
passengers (75 fatalities). Only a portion of these passenger deaths were due to train derailments
or collisions.20
Although preventing grade-crossing incidents is not specifically addressed in the PTC mandate of
RSIA08, this could be achieved technically within the PTC framework by installing sensors at
crossings that would engage the brakes of an oncoming train if a crossing gate is not working
properly or if a vehicle is detected on the tracks.21 While this may require further investment on
the part of the railroads and may not be implementable by the deadline, it may offer more
significant gains in terms of safety than train collision prevention alone. Once PTC is
implemented, Congress has requested the FRA to study the effectiveness of PTC technology in
preventing grade-crossing incidents.22
16 NTSB, Safety Recommendation R-97-9 through -21, August 28, 1997; see also Safety Recommendation R-97-013.
17 Safety Recommendation History, NTSB Safety Recommendation R-97-013.
18 U.S. Congress, House Committee on Appropriations, Conference Report on the Consolidated Appropriations
Resolution, to accompany H.J.Res. 2, 108th Cong., 1st sess., 2003, H.Rept. 108-10 (Washington: GPO, 2003), pp. 1286-
1287.
19 Letter from Betty Monro, Federal Railroad Administration Acting Administrator, to Senator Robert Byrd, August 17,
2004, http://www.fra.dot.gov/downloads/safety/ptc_ben_cost_report.pdf.
20 Two percent (143 fatalities) occurred for other reasons. FRA safety data (as of February 2016);
http://safetydata.fra.dot.gov/officeofsafety/default.aspx.
21 Fred Coleman III, Ronald W. Eck, and Eugene R. Russell, “Railroad-Highway Grade Crossings,” TRB Conference
23 “Train Crash’s Roots Run Deep; Decades-old Decisions by Metrolink Gambled on Passenger Safety, According to
commuter train engineer—it is believed he missed a red signal while texting. PTC was
specifically identified by the NTSB as a technology that could have prevented Chatsworth and
other similar incidents by providing a safeguard against human error.24
The Chatsworth accident on September 12, 2008, expedited the legislative process, and the bill
mandating PTC was signed into law October 16, 2008, as the Railroad Safety Improvement Act
of 2008 (RSIA08). RSIA08 requires “each Class I railroad carrier and each entity providing
regularly scheduled intercity or commuter rail passenger transportation” to implement PTC on all
segments or routes of railroad tracks that (a) carry frequent passenger or commuter service, or (b)
carry more than 5 million gross tons of freight per year and also are used for transporting toxic-
by-inhalation hazardous materials (TIH).25 At the time the law was signed, this mandate covered
approximately 70,000 miles of railroad track.
During the FRA rulemaking process, it became apparent that rail companies could change the
routes of trains carrying TIH to avoid the PTC requirement on some track segments. A Senate bill
was introduced to forgo mandatory PTC implementation on lines that will not be transporting
passengers or hazardous materials by the end of 2015.26 This was estimated to eliminate the PTC
mandate on 10,000 of the 70,000 track-miles initially covered. The bill was not enacted, but the
FRA approved such a change in its amended final rule, effective July 13, 2012.27 The American
Short Line and Regional Railroad Association proposed several changes to the FRA final rule,
including eliminating the PTC requirement for trains traveling less than 20 miles on PTC-
required track and extending the deadline for Class II and III railroads to employ PTC-equipped
locomotives until 2020. The FRA approved these changes in an amended final rule.28
In the 112th Congress, bills to delay the PTC implementation deadline were considered in both
houses of Congress. As approved by the Senate, the Moving Ahead for Progress in the 21st
Century Act (MAP-21; S. 1813) would have allowed the U.S. Department of Transportation
(DOT) to extend the December 31, 2015, deadline for any railroad in one-year increments until
December 31, 2018, if it deemed full implementation infeasible and if the railroad had made a
good-faith effort to comply. The bill would have allowed use of Railroad Rehabilitation and
Improvement Financing (RRIF)29 for PTC implementation. The American Energy and
Infrastructure Jobs Act of 2012 (H.R. 7), which was adopted by the House Transportation and
Infrastructure Committee but was not approved by the House of Representatives, would have
extended the deadline for PTC implementation to December 31, 2020, and would have allowed
railroads to adjust TIH routes until 2020 to reduce the extent of track affected by the PTC
mandate. The bill also would have allowed railroads to implement alternative strategies on track
that does not transport passengers where the “alternative risk reduction strategy that would reduce
the risk of release of poison- or toxic-by-inhalation hazardous materials to the same extent the
risk of a release of poison- or toxic-by-inhalation hazardous materials would be reduced if
positive train control were installed on those tracks.”30 While the provision would have allowed
24 National Transportation Safety Board, Collision of Metrolink Train 111 With Union Pacific Train LOF65-12
Chatsworth, California, RAR 10/01, September 12, 2008.
25 P.L. 110-432, §104.
27 Federal Railroad Administration, “Positive Train Control Systems Amendments (RRR),” 76 Federal Register 52918,
August 24, 2011. See also 78 Federal Register 5767, January 28, 2013, and 79 Federal Register 49693, August 22,
2014.
28 Federal Railroad Administration, “Positive Train Control Systems,” 75 Federal Register 2704, January 15, 2010.
29 Railroad Reinvestment and Improvement Funding (RRIF) provides direct federal loans and loan guarantees up to a
total of $35 billion to improve or develop new rail equipment and facilities and refinance outstanding debt.
30 H.R. 7, §8401, p. 805.
flexibility on the part of the railroads, alternative safety measures might interfere with the goal of
interoperability and could raise costs for smaller railroads that might need to conform to multiple
safety systems. The final version of the 2012 surface transportation bill, signed by President
Obama on July 6, 2012, as P.L. 112-141, did not change existing law concerning PTC.
The derailment of a Metro-North commuter train in the Bronx, NY, on December 1, 2013,
renewed calls for PTC implementation. Four passengers died and 60 to 70 passengers were
injured in this derailment. The train traveled at 82 mph over a straight section of track with a 70-
mph speed limit, but then derailed as it entered a curve with a 30-mph speed limit. According to
one report, although this section of Metro-North’s network was equipped with a cab
signal/ATS/ATC system, Metro-North’s version of this system was designed to prevent collisions
with other trains, and did not restrict speeds when no other trains posed a danger (as was the case
with the derailed train). In other words, the backup safety signal system was designed strictly to
ensure train separation and did not include a speed control element. Other commuter railroads
(New Jersey Transit and Southeastern Pennsylvania Transportation Authority, for example), as
well as Amtrak on the Northeast Corridor, had a system that would have restricted train speed in
this instance.31 The FRA ordered Metro-North to add speed control to its signal system and to
station a second crew member with train control duties at certain locations until it did so.32
The commuter rail incidents at Chatsworth, CA, and the Bronx, NY, revealed significant
disparities among signal system capabilities deployed by commuter operators. While these two
incidents intensified calls for PTC installation, neither railroad had fully deployed long-standing
signal technology that could also reduce the risk of collisions and derailment.
On May 12, 2015, an Amtrak train derailed at a curve in Philadelphia, killing eight passengers.
The train was travelling at 106 mph, while the curve had a speed limit of 50 mph. The NTSB’s
May 2016 report determined that the engineer had been distracted by dispatch calls about a
nearby train being hit by projectiles and likely thought the train had traveled beyond the curve,
where the speed limit is 110 mph.33 The NTSB noted that PTC would have prevented this
incident. Amtrak had not installed automatic train control technology on this portion of track
based on a risk analysis. It has since installed PTC on all segments of the Northeast Corridor that
it owns, including the segment on which this incident occurred.
At an NTSB forum on PTC held February 27, 2013, BNSF Railroad, Amtrak, the Alaska
Railroad, and Metrolink Commuter Railroad were identified by an FRA official as the only
railroads that were perhaps on schedule to meet the December 31, 2015, deadline.34 One topic of
discussion at the forum regarded the allowances the FRA was making in implementing PTC
because of the deadline.35 The complexity of testing the numerous subsystems, spectrum
availability in urban areas, and “back office” software interoperability were some of the
difficulties that the railroads identified.
The Positive Train Control Enforcement and Implementation Act of 2015 (P.L. 114-73), enacted
October 29, 2015, extended the deadline for PTC implementation from December 31, 2015, to
31 “Spuyten Duyvil: Why? A Safety Expert Weighs In,” Railway Age, December 5, 2013.
32 FRA, Emergency Order 29, Notice No. 1, December 6, 2013.
33 http://www.ntsb.gov/news/events/Pages/2016-Amtrak-BMG.aspx.
34 NTSB, Forum—Positive Train Control: Is It on Track?, February 27, 2013. Witness presentations and a webcast of
December 31, 2018. The three-year extension was thought necessary after most freight railroads
and commuter railroads stated that they would not be able to meet the 2015 deadline.36 Congress
also allowed the 2018 deadline to be extended up to another two years, provided that a railroad’s
modified implementation schedule was approved by the FRA and it had installed all the necessary
PTC hardware and acquired the necessary radio spectrum by December 31, 2018. Two accidents
resulting in passenger fatalities, the December 18, 2017, derailment of an Amtrak passenger train
near DuPont, WA, on track owned by the regional transit agency, and the February 4, 2018, crash
between an Amtrak train and a stationary freight train on South Carolina track owned by CSX
Corp., occurred in locations where PTC installation was in progress but the system was not yet
operational.
36 Government Accountability Office, Positive Train Control: Additional Oversight Needed as Most Railroads Do Not
Expect to Meet the 2015 Implementation Deadline, GAO-15-739, September 4, 2015.
37 49 C.F.R. §236.
38 Federal Railroad Administration, The North American Joint Positive Train Control (NAJPTC) Project, Research
Positive Train Control Development Plan (PTCDP), Union Pacific Railroad, Norfolk Southern Railway, and CSX
Transportation, Inc., FRA-2010-0060-0002, June 1, 2011.
40There are many ways of designing the system architecture to support PTC communication. In the context of railroad
operations with dispatchers, a system architecture with central control is the most plausible design.
incidents. Braking distance can be several miles for large freight trains and is dependent on
factors such as train speed, reaction time, wheel-rail friction, brakes wear, track conditions, track
grading, mass, and mass distribution of the train.41 All these variables are processed with a
complex braking algorithm designed to ensure an emergency stop prior to a collision without
excessive speed restriction leading to inefficient operation.
Source: Federal Railroad Administration, Research Results, North American Joint Train Control (NAJTC)
Project, April 2009.
Note: Two-way data communication and computer-aided dispatch are the primary subsystems that distinguish
full CBTC from PTC.
The greater capability of CBTC makes it suitable for very high speed passenger lines, and CBTC
is being instituted on some European rail lines for that reason. It has also been adopted by New
York City Transit and the Southeastern Pennsylvania Transportation Authority. CBTC also has the
potential to allow for driverless trains. However, the system requires seamless communication
coverage along the entirety of PTC-equipped track, as temporary communication loss can pose
safety risks. The need for constant communication also requires significant investment in either
radio towers or fixed transponders. These requirements raise the capital cost, making CBTC more
expensive than an overlay-type system.
The CBTC system potentially offers greater business benefits to railroad operators than an
overlay-type system. For example, the real-time, two-way communication of train locations
combined with speed restrictions and moving authorities can lead to more efficient scheduling,
increased capacity, and fuel savings. Nonetheless, U.S. railroads appear to have concluded that
41 David Barney, David Haley, and George Nikandros, “Calculating Train Braking Distance,” This paper appeared at
the 6th Australian Workshop on Safety Critical Systems and Software (SCS ‘01), Brisbane, 2001, pp. 23-29,
http://129.96.12.107/confpapers/CRPITV3Barney.pdf.
the advantages of communication-based train control are not worth the additional cost of
installing it at the present time.
It is important to note that both overlay-type systems and CBTC systems are designed principally
to reduce collisions between trains. The systems do not address intrusion into railroad right-of-
way. Currently, there is no requirement that they be capable of detecting and notifying trains
about crossing-gate failures, vehicles blocking tracks, or trespassers. However, such capabilities
could be incorporated into PTC systems in the future.
Implementation
Based on progress reports submitted by railroads to the FRA, the FRA surmises that only four
railroads (BNSF and Union Pacific, and the Los Angeles and Philadelphia area commuter
railroads) will likely have fully installed the necessary PTC equipment by the end of 2018, but
even these railroads would likely need an extension because other railroads operating over their
lines would not be fully PTC-compliant.42 As of June 30, 2018 (latest data available), PTC was
operating on 66% of the freight route miles required to have PTC and 2% of the passenger
network.43 PTC was installed and operable on 93% of the freight locomotives and 73% of the
passenger locomotives. Among the larger commuter railroads, the FRA deemed that Caltrain,
Maryland Area Regional Commuter, and New Jersey Transit were at risk of not qualifying for a
deadline extension because these railroads had installed less than 90% of the PTC hardware
required (as of June 30, 2018).44
Most of the current PTC projects rely on fixed transponders in conjunction with GPS with one-
way information communication to the trains to fulfill the baseline PTC requirements. Only a few
systems involve two-way communication with real-time information and computer-aided
dispatch. The smaller railroad companies and commuter lines, in most cases, are relying on the
Class I railroads to implement PTC before investing in their own systems due to the high risk and
the cost of developing their own systems.
In the United States, precursors to full PTC capability were developed voluntarily prior to the
2008 mandate. Development of radio-based CBTC systems and coordinated wayside systems
used to locate and communicate with trains began in 1983. Although systems developed by the
Association of American Railroads and Burlington Northern Railroad achieved technical success,
both systems were functional only in fully signalized territory and were deemed not economically
viable to deploy on a nationwide scale.
In 1991, Amtrak adopted an automatic train control (ATC) system along the tracks it owns in the
Northeast Corridor. That system, as discussed above, repeated signalization in the cab and
required the train engineer to acknowledge and enforce the speed limit given by the signals to
reduce human error. That system was later upgraded with the Advanced Civil Speed Enforcement
System, using transponders to send signals to trains and to enforce speed restrictions and stop
42 Federal Railroad Administration, Railroads’ Progress Toward Implementation of Positive Train Control Systems,
July 1, 2018, p. 4.
43 For railroad implementation status and plans, see https://www.fra.dot.gov/ptc.
44 Federal Railroad Administration, “FRA Publishes Railroads’ Quarter 2 PTC Data,” https://railroads.dot.gov/
newsroom/fra-publishes-railroads-quarter-2-ptc-data.
Overseas Experience
Passenger train incidents overseas with train control systems already installed may provide
lessons for implementation of PTC in the United States. After a deadly commuter train derailment
in Japan in 2005, an audit found that the maximum speed calibrated on many curves to trigger the
automatic train control system had been set too high to prevent derailments.48 After 40 passengers
were killed in a train collision in China in 2011, it was discovered that its train control system had
not been sufficiently tested.49 Investigations following an overspeed incident in Spain in 2013 that
killed 79 passengers found that the train control system had been turned off on a second set of
locomotives because it was not functioning properly.50 Similarly, the train control system had
been turned off on a German commuter locomotive so that it could make up time, which is
believed to have contributed to its collision with another train in February 2016.51
45 James Hoelscher and Larry Light, “Full PTC Today with Off the Shelf Technology: Amtrak’s ACSES Overlay on
Expanded ATC,” Proceedings of the 2001 AREMA Conference, Chicago, IL, 2001, http://www.arema.org/files/library/
2001_Conference_Proceedings/00022.pdf.
46 Federal Railroad Administration, “Positive Train Control Overview,” press release, February 2, 2009, p. 1,
http://www.fra.dot.gov/rrs/pages/fp_1265.shtml.
47 William Vantuono, “Two new technologies ready to roll,” International Railway Journal, vol. 48, no. 4 (April 2008),
pp. 26-28.
48 Knight Ridder Tribune Business News, “JR West’s new ATS had flaws that would not slow speeding trains,”
November 1, 2005.
49 International Railway Journal, “Wenzhou Crash Report Blames Design Flaws and Poor Management,” February
2012.
50 International Railway Journal, “ETCS: A Crucial Factor in Santiago Accident Inquiry,” April 7, 2015.
51 BBC, “Germany Train Crash: Controller Distracted by Computer Game,” April 12, 2016.
52 Frank D. Roskind, Positive Train Control Systems Economic Analysis, Federal Railroad Administration, FRA-2006-
The four largest railroad companies account for almost all of the estimated 60,000 miles of Class
I track that fall under the PTC mandate. In 2017, CSX estimated its cost of installing PTC to be
$2.4 billion, of which $1.8 billion had been expended through 2016, while as of 2018 Union
Pacific estimated its total cost for PTC to be $2.9 billion, of which $2.3 billion had been spent by
the end of 2016.54
Smaller freight companies often share track with the Class I railroads. While this presents
interoperability challenges, there is opportunity to use the PTC type approvals from the larger
companies’ development efforts to save cost. This is also the case with shared passenger rail in
the Northeast Corridor. Despite this advantage, the infrastructure cost alone for just two of the
five largest transit agencies operating on the corridor, Metro-North in the New York area and the
Southeastern Pennsylvania Transportation Authority in the Philadelphia area, has been estimated
at $350 million and $100 million, respectively.55 As the FRA has stated (see text box), the
expense of PTC could constrain commuter rail development, diverting commuters to less safe
forms of transportation.
Commuter railroads’ cost for installing PTC is likely to be borne primarily by state or local
governments. However, the federal government has provided assistance. This includes a $967
million RRIF loan to the Metro-North and Long Island commuter railroads for PTC
implementation,56 $382 million in combined RRIF/Transportation Infrastructure Finance and
Innovation Act (TIFIA) loans to the Massachusetts Bay Transportation Authority, $199 million in
FY2017 in the FAST Act (P.L. 114-94, §3028), and $250 million in grants provided in the
Consolidated Railroad Infrastructure and Safety Improvement (CRISI) program (funding is not
restricted to just commuter railroads). In March 2018, the DOT Inspector General issued a report
reviewing how railroads had spent federal funding provided for PTC implementation.57
Some shippers believe that since the majority of the investment in PTC will come directly from
the railroad companies, these costs will likely be passed to customers. They expect price increases
due to the cost of PTC implementation, especially if the rail companies are unable to realize
business benefits from the new systems. The Chlorine Institute, a trade organization representing
the chlorine industry, expects the railroad companies to raise costs disproportionately for
shipments of toxic-by-inhalation hazardous materials (TIH), as concern about the safety of TIH
transport is perceived as a source of the PTC mandate.58
54 CSX Corporation, Form 10-K for the fiscal year ended December 30, 2016, p. 5; Union Pacific, “Positive Train
Control,” https://www.up.com/media/media_kit/ptc/about-ptc/ (accessed February 6, 2018).
55 Jeff Stagl, “PTC: Railroads, suppliers still have a ways to go to meet the 2015 positive train control mandate,”
57 DOT IG, “Federal Funding Support for Positive Train Control Implementation,” March 28, 2018.
58 The Chlorine Institute, Inc., “Chlorine Institute Asks Federal Rail Administration to Reconsider Positive Train
Control Rule Due to Faulty Cost-Benefit Analysis,” press release, March 16, 2010, http://www.chlorineinstitute.org/
files/PDFs/2010-03-16%20-%20CI%20PTC%20petition.pdf.
59 Frank D. Roskind, Positive Train Control Systems Economic Analysis, Federal Railroad Administration, FRA-2006-
fatalities and injuries, equipment damage, track damage, off-track damage, hazardous material
cleanup, evacuations, wreck cleanup, loss of freight, and freight delay. According to a 1999 FRA
estimate, between 1987 and 1997 an annual average of 7 fatalities, 22 injuries, $20 million in
property damages, and evacuations of 150 people due to potential hazardous material release
could have been prevented by PTC.60
Although many serious incidents due to error by train engineers or dispatchers could be prevented
by PTC, PTC is expected to prevent less than 2% of the approximately 2,000 railroad collisions
and derailments that occur annually. The majority of these 2,000 incidents occur in rail yards and
are generally less severe than PTC-preventable incidents.
While the costs and safety benefits are projected with some confidence, there is disagreement
regarding the potential business and social benefits of PTC. This makes a full cost-benefit
analysis of PTC-related issues difficult. Business and social benefits are expected to come from
increased railroad efficiency, reductions in logistical costs, and diversion of freight from truck to
rail. However, these benefits are predicated on the functionality of full computer-based train
control and not PTC alone. Computer-aided dispatch has the potential to increase capacity and
reduce fuel consumption. This can reduce railroad operating costs, lead to faster, less expensive
delivery, and induce demand from truck freight. This then may lead to social benefits such as
reductions in fuel consumption and truck accidents.
The FRA projects $4 billion in potential annual business benefits a decade after full PTC
implementation. The overlay system without CBTC capability currently planned by the railroads
is expected to offer little or no business benefit to the railroads. A possible exception is the role
PTC could have in discussions about the appropriate size of train crews. The Class I freight
railroads generally run trains with two-person crews, but PTC might facilitate one-person crews.
However, the FRA has recently proposed a rule requiring two-person crews.61 The social benefits
of the overlay system are likely to come largely from the anticipated reduction in incidents.62
Policy Issues
Interoperability
The freight rail transportation network has two primary components: the track and the freight
service. In some cases, the service is provided by the same company that owns the track.
However, since shippers’ needs do not correspond to railroads’ track ownership, freight operators
trade trackage or haulage rights and share revenue from the shipper. FRA regulations require that
railroads’ PTC systems be interoperable so that any train operating on PTC-equipped track can
communicate with the host railroad’s PTC system.
Prior to RSIA08, several railroad companies were developing communication-based train control
independently for their own business reasons, and were not concerned about interoperability. The
federal mandate has required changes in these plans in the interest of interoperability. UP, CSXT,
and NS have received FRA “type approvals” for Interoperable Electronic Train Management
60 Railroad Safety Advisory Committee, Federal Railroad Administration, Implementation of Positive Train Control
Systems, Report, August 1999, https://rsac.fra.dot.gov/meetings/19990908.php.
61 81 Federal Register 13918, March 15, 2016.
62 Frank D. Roskind, Positive Train Control Systems Economic Analysis, Federal Railroad Administration, FRA-2006-
Systems (I-ETMS) in which the PTC system itself is approved for development.63 This makes it
likely that the systems installed by these railroads will be highly compatible. BNSF, which has a
precursor ETMS system in place, has type approval for that system, which is to be updated to I-
ETMS when software becomes available.
Interoperability issues pertain to passenger service as well. In the Northeast Corridor, Amtrak
operates on Amtrak-owned track and track owned by regional transit authorities and vice versa.
Amtrak began PTC development prior to RSIA08 and has provided the PTC standard and type
approval for transit authorities utilizing the corridor. The freight companies and Amtrak are now
working to ensure interoperability between their respective systems.
In Europe, achieving interoperability in train control systems has been a decades-long challenge
among the different national railroad passenger networks attempting to cross borders.64
63 Letter from Jo Strang, FRA Associate Administrator for Railroad Safety/Chief Safety Officer, to Jeff D. Young et al.,
Union Pacific Railroad Assistant Vice President, Transportation System, August 26, 2011, FRA Type Approval (FRA-
TA-2011-02) for the Interoperable Electronic Train Management System (I-ETMS).
64 International Railway Journal, “ETCS Progress Still Dogged by Challenges,” March 30, 2016; European
Commission Staff Working Document, “Delivering an Effective and Interoperable European Rail Traffic Management
System—the Way Ahead,” November 14, 2017; https://ec.europa.eu/transport/sites/transport/files/swd20170375-ertms-
the-way-ahead.pdf.
65 Federal Railroad Administration, “Positive Train Control Systems Amendments (RRR),” 77 Federal Register 28285,
accommodate short line railroads, but in some cases may be reluctant to allow short line trains on
their networks.67 The president of the American Short Line and Regional Railroad Association
issued the following testimony to the Surface Transportation Board:
Differential pricing of certain routes or products by class I carriers ... ha[s] eliminated
marginal customers who may be a small railroad’s only source of business on its line,
effectively putting the small railroad out of business. Some small railroads who want to
provide service to new customers meet resistance from connecting carriers whose
marketing plans are inconsistent with the small railroad’s proposed business.68
At this point, concerns that PTC could create barriers to railroad competition are hypothetical, as
no specific complaints are known to have been presented to the FRA or to the Surface
Transportation Board, which oversees certain rail competition issues.
Author Information
John Frittelli
Specialist in Transportation Policy
Acknowledgments
Former CRS Research Associate Jeffrey C. Peters made significant contributions to this report.
Disclaimer
67 CRS Report RL34117, Railroad Access and Competition Issues, by John Frittelli.
68 Richard F. Timmons, STB Ex Parte No. 677: Common Carrier Obligation Hearing, American Short Line and
Regional Railroad Association, Testimony of Richard F. Timmons, Washington, DC, April 25, 2008, p. 2.
69 49 C.F.R. §236.1019 (b).
70 NTSB Board Meeting, “2 Bumping Post Collision Investigations,” February 6, 2018; https://www.ntsb.gov/news/
events/Pages/2018-DCA17SR001-BMG.aspx.
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other
than public understanding of information that has been provided by CRS to Members of Congress in
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or
material from a third party, you may need to obtain the permission of the copyright holder if you wish to
copy or otherwise use copyrighted material.