0% found this document useful (0 votes)
35 views2 pages

Toaz - Info Network Diagram Exercises PR

The document provides instructions and details for four network diagram exercises. Exercise 1 asks to draw a network diagram with activities A through G and their predecessors. Exercise 2 provides activities A through H with durations and predecessors to draw the diagram, determine the critical path, and project duration. Exercise 3 similarly provides activities A through H and Exercise 4 provides activities A through I to draw the diagram, find the critical path, and duration.

Uploaded by

Naqi Ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views2 pages

Toaz - Info Network Diagram Exercises PR

The document provides instructions and details for four network diagram exercises. Exercise 1 asks to draw a network diagram with activities A through G and their predecessors. Exercise 2 provides activities A through H with durations and predecessors to draw the diagram, determine the critical path, and project duration. Exercise 3 similarly provides activities A through H and Exercise 4 provides activities A through I to draw the diagram, find the critical path, and duration.

Uploaded by

Naqi Ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

NETWORK 

DIAGRAM EXERCISES:

Exercise 1

Draw the following Network Diagram:

Activity Predecessor(s)
A -
B -
C A
D B
E D
F C
G E,F

Exercise 2

Draw the Network Diagram and determine the Critical Path and duration of
the project (in days).

Activity Details Duration (days) Predecessor(s)


A Dig Holes 3 -
B Buy Wood 2 Dig Holes
C Buy Gate 1 Dig Holes
D Erect Fence 3 Buy Wood
E Buy Paint 1 Buy Gate
F Erect Gate 1 Erect Fence, Buy
Paint
G Paint Fence 2 Erect Gate
H Paint Gate 1 Paint Fence

Exercise 3

Draw the Network Diagram and determine the Critical Path and duration of
the project (in days).

Activity Duration (days) Predecessor(s)


A 2 -
B 2 A
C 4 A

Prepared by: D.Calderwood


D 1 B
E 3 C,D
F 2 C,D
G 4 E
H 5 F,G

Exercise 4

Draw the Network Diagram and determine the Critical Path and duration of
the project (in days).

Activity Duration (days) Predecessor(s)


A 2 -
B 3 -
C 4 A,B
D 5 C
E 2 D
F 3 D
G 4 E
H 2 F
I 2 G,H

Prepared by: D.Calderwood